SSB 3 (Eng)
SSB 3 (Eng)
Prepared By
International Resources Group
New Delhi-Washington, D C
August, 1998
For
USAIDIIndia
Mr N V Seshadri
Collaboratrng lnstirzitzons Center for Naval Analys~sCorporatton Consewatlon Internattonal KNB Englneerlng and
Applied Sc~encesInc Keller-Bl~esnerEng~neertngResource Management Internat~onalInc
Tellus Instltute Urban Institute and World Resources Instltute
SUBSTATION
PREVENTIVE MAINTENANCE MANUAL
(FINAL DRAFT) I Ij
Prepared by The
The development work and complet~onof t h ~ Substat~onPrevent~veklanual was funded bv the Unlted States Agency for International
Develonment (USAID) under an Intcrnat~onnlRasources Croup (IRg) contract w ~ t hUSAID \rllss~onto Indla Contract NO OUT-PACE-I- "
804-96-00002 00 The vlelvs and statements conta~~iedIn the Jlanual are based on lndustrv standard practices USAID published documents
+
n nn .rn I "rn nat ntnn In 1 .r C 4 I n
~ n r rnl rpnr hol I t n hn r a l mhln m n I thprhnr
TABLE OF CONTENTS
I
Page
I
No
Vll-I
VII INCORRECT CONNECTORS REPLACEMENT
The IRG team vrsrted a number of substatrons In an effort to rdentrfy the probable
cause of the large number of HV substat~onpower and d~strrbutrontransformer
farlures A presentation was grven to the Chairman and the Members of the Board
on June 18, 1998 The results of the IRg rnvest~gatronsrndrcated the need to
Increase the marntenance qualrty, review and upgrade system protect~on practrces
used on the HV substatrons and on the d~strrbut~ontransformers
Page 2 Of 2 2
HSEB SUBSTATiONS STATUS
A HSEB SUBSTATIONS
At the present tlme the Haryana Electrtclty Board (HSEB) operates and rna~ntainsall
transrnlsslon ilnes and substations that transfer the electrtcal energy from the generatron
resources to the load centers of HSEB This temporary cond~tlonwill be changrng in the
near future when the HSEB IS divrded into a Generation Company, a Transrnlssion
Company and about three Dlstrrbution Companies The operat~on and maintenance
procedures presented here~nare based on the assumpt~onthat each company will have
access and be responsible for the operation and maintenance of their own substations
TABLE I f I
SYSTEM VOLTAGE LEVELS AND QUANTITY
OF SUBSTATIONS AND DISTRIBUTION TRANSFORMERS
SYSTEM VOLTAGES (KV) SUBSTATIONS
D~strrbut~oTransformers o n 11 kV feeder s I I
99,524
/
/I Totals 99,942 11
B IDENTIFY SOURCE OF LOSSES
The marn source of power losses at the substatron IS In the power transformer and auxrlrary
equ~prnent However, there is another source of power losses rn a substatron whrch IS
usually the result of poor connections between the bus and lrne conductors, drsconnect
swrtches, crrcuit breakers, reclosers, and fuse cutouts There are at trmes podrly desrgned
and/or deficient rnstallatrons, and/or use of lengthy and undersized jumpers, use of non
appropriate connectors to ensure a solid connect~on, and the makrng of connections
between copper and aluminum and other materral without the use of appropriate blmetal
connectors The splrcing of non-allke metals results in galvanrc corrosron that eventually glves
rise to a htgh power loss splrce The continues use of non-essent~alequipment (fixed or
rotat~ng)also leads to power losses whrch are not acceptable to HSEB
The Thermov~sionscanner is used to detect electric power system components that are
operat~ngat temperatures above their normal desrgned thermal capacity The use of a
Thermovisron scanner by substation marntenance personnel permits to determine the
locatron of 'hot spots' orconnections that are operating at abnormally high temperatures
The locatron of the source of power losses must be rdentlfied prior to the development of
any actron plan to reduce them The basic approach is as follows
Once the losses and their sources are identrfied from the above tests and corrective
measures implemented to reduce these losses Perform the followrng evaluatron to
quantrfy the technrcal and economlc benefits
Page 2 of 6 'I'
HSEB-Preventive Maintenance Manual
Chapter II - HSEB Substations Status
- - - -- - -
D CONNECTORS
To reduce the power losses at the substation, the correct connector for the applrcatlon
must be used
3 The correct metallic bolts must be used wrth bolted connectors Applrcatron of
the correct torque value must follow the manufacturer instruct~ons
4 The correct size connectors must be used for the equrpment termination being
connected
5 The correct contact pressure must be reached by using either the correct bolt
torque, or correct gun and cartrrdge for wedge connectors, or correct crrrnper
and dies for crlmped connectors
Page 3 of 6 ,
- -t
HSEB-Preventive Ma~ntenanceManual
Chapter II - HSEB Substat~on Status
E TRANSFORMER COOLING
All substation transformers have an oil and air (OA) ratlng for a winding temper;ature rise
of 65C above the 30C ambient with natural air-cooling Some transformers have an
additional 25 per cent Increase In thermal capac~tyover the OA rattng through the use of
forced coollng air fans The additronal coolrng capacity is derived from the use of cooling
fans use to limit the windrng temperature from risrng above the 65 OC design temperature
If the transformer IS carrying a load that is lower than the normal transformer OA ratlng,
the operation of the fans IS not requlred If fans are turned on manually and kept on
running cont~nuously,this 1s a waste of electrrcal energy and should be eliminated by
turn~ngoff the fans
It appears that ~ngeneral, the HSEB has available at therr substation transformers that
were purchased with a variety of different tap changers to maintaln bus voltage wlthin the
prescribed operating criterra
There are existing transformers with load tap changers which are defective and are either
frozen on a particular tap pos~tionor whlch can not be operated onto a tap setting under
no-load conditrons
It IS necessary that load tap changers be rnalntarned perrodlcally to ensure that adequate
voltage levels are rnalntained at the substation's 11 kV bus Incorrect tap setttngs may
have detrimental effects on power factor, voltage and correspond~nglyon power losses
G CONDUCTOR SlZlNG
Jumper and bus conductors must be adequately sized for the main transformer load~ng
Alumlnum jumpers are used to connect equipment terminations that are almost always
made of copper
Not using bimetallic connectors to connect the aluminum jumper to the copper termlnatron
pads of the equipment results ~n high power losses belng generated due to incorrectly
appl~edconnectors
Page 4 of 6
9
HSEB-Preventive Maintenance Manual
I Chapter I1 - HSEB Substatrons Status
I H CONTACT RESISTANCE
I
I W~thage and many interrupting operations with cumulat~veeffects, thrs contact resistance
could increase, thus generat~ngI'R losses under heavy load cond~tlons
This contact resrstance should be measured perrodrcally and compared to the
I manufacturers designed values to ensure that they are w~thlnthe tolerance allowed by the
- manufacturer If they are out of tolerance then the breaker/recloser should be taken out of
( service and the contacts cleaned in accordance with the manufacturers 0 & M procedures
before putt~ngthe equrpment back agaln rnto servlce
-
Typlcal resistances are of the order of 2 30 micro-ohms Srmrlarly, fuse cut-outs and
disconnect switches have mating parts and sliding contacts which, if allowed to
deteriorate, can give rrse to high resistance values
I- Checking for "Hot spotsJ with a scanner at the t~meof the substatron peak load, alerts the
I
users that the particular piece of equrpment needs to have its contact surface cleaned srnce a
h~gherthan normal resrstance IS building up due to corrosron, oxidation, pittlng, etc
I If, however, the equipment is modrfied or its connections are altered and not in
accordance with the manufacturers recommendatrons, 'hot spots' are to be expected
Many trrnes this improvisation has been found to be the source of hot spots A typical
I example is the replacement of fuse barreis and K type fuse links wrth wire hand wound
across the terminals of the link connections Electrrcally this provides continurty to the
I system but from an economic standpoint thls IS a source of very h ~ g hpower losses, as h~gn
contact res~stancesare created
It is an excellent engineering practice to use the manufacturers desrgned equipment for the
I applicatron 1t was rntended for Temporary solution or rmprovisatron must not be allowed to
become a permanent condrtion as these give rise to expensive power losses that must be
avorded by HSEB
Page 5 of 6
i0
HSEB-Preventwe Maintenance Manual
Chapter I1 - HSEB Substations Status
J PROTECTION COORDINATION
A vrsual inspectron of the drstr~butlonsystem lrnes end drstrrbutron trans for me;^ that
HSEB do not use them at all It appears that through trme thrs has become an standard and
expensrve practlce resulting rn many feeder outages and transformer faliures Usually the fuses
on a dlstrlbutron lrne have to be coordrnated wrth the recloser, relay, or another fuse at the 11
kV substat~onsrde HSEB needs upgrade the entire protectlon system by utrlrz~ng fuses,
lrghtnrng arresters, breakers at every substation and to perform coordrnatron studres to
determine relay settrngs and fuse types to prov~decoordinated protection to the HSEB
system Proper system protectlon coord~natlonw~llensure that the operat~on of fuses, located
downstream on a glven feeder, w~llnot take out the ent~refeeder andlor substat~on
The benefit of adequate system coordlnatlon IS that only the faulty sectton IS out of service
and only a few consumers are affected
Also, ground fault relayrng of the substatrons should be set hrgh enough so as not to
cause tr~pprngat the substat~on,for unbalanced loads due to rncorrect balanc~ng,or for
trlpprng of srngle phase lrne transformers whrch would cause a dynamrc unbalance
Ground fault relaylng at the substation IS generally set above 100 amps
K GROUNDING
All equrpment tanks, neutral conductors, etc should be adequately grounded rn accordance
wrth rndustry standard pract~ces Hrgh ground resrstance In neutral conductors could
generate hrgh losses when the unbalanced currents flow In the neutral conductor
Also drsconnectron of neutral grounds dependrng on where they occur could cause
float~ng neutral voltages whrch could glve rrse to hrgh over voltages durrng unbalanced
loadrng condrtions
BASE LOSSES
It should be noted that good plannrng, desrgn, or maintenance couldn'telrmrnate all losses rn
a substatron Every prece of equrpment, conductor and connector has rts own rnherent losses
As an example, the marn transformer has "No load losses" and "load losses" These are
specrfred and predicted by the manufacturers durrng the development of transformer destgn
drawrngs and specrficatrons Transformers can be purchased wrth power losses that are
lower by wrrtrng specifications w~thlow loss lrmrts that are st111wrthin desrgn constrarns
although the HSEB may have to pay a h~gherrnrtral prrce However, over the economlc lrfe of
the transformer thrs hrgher prlce transformer IS the best economlc chorce for the HSEB
Page 6 of 6 I
(
PREVENTIVE MAINTENANCE PROGRAM
DEVELOPMENT
A GENERAL
B DATA COLLECTION
The first consideration IS to design the program to meet the needs of the Haryana
State Electricity Board Develop a manual that IS as simple as possible The starting
polnt IS to perform an evaluation of needs The following questions must be answered
If it is found that the available staff IS not sufficient to marntarn the equ~pmentor their
qual~fications are below requirements, then HSEB has to evaluate the economlc
benefits of add~ngqualified staff to meet PM objed~ves Once the answers to these
questtons have been obtarned then the overall program development can begrn
There will be need to spend only three to four hours per equipment item to compile all
necessary data Thrs includes reading the matntenance operator's manual, developing
and writing the program, and ordering recommended spare parts The PM
requirements remaln the same and only the equipment data needs to be compiled to
ensure an adequate PM program
HSEB-Preventrve Ma~ntenanceManual
-
Chapter Ill Preventive Ma~ntenanceProgram Development
1 Forms
Once all data has been accumulated, an equrpment numberrng system must
be developed The system may use srx-digit numbers (for example, 0021-21)
The fist four drg~tsrndrcate the equrpment type, the fifth and srxth
d~gitsrdent~fythe items - motor, corl or relay - ~neach category Such a
numbering system should be used throughout the program to ~dentrfyand
catalog materrals In addrtron to the equ~pmentdata, rnformatron about spare
parts and assembly list~ngsIS included on the lower half of Form I
Page 2 of 12
D
HSEB-Preventive Ma~ntenanceManual
Chapter I11 - Preventwe Ma~ntenanceProgram Development
EQUIPMENT DATA RECORD
Equ~pment Equ~prnentNo I
Model no
Vendor
I
I
Volts
Others
Techn~cal
I~stlng I reference
I I
I I
I
I
I I
I
I
I
I
4
Page 3 of 12
HSEB-Preventrve Maintenance Manual
Chapter Ill - Preventrve Ma~ntenanceProgram Development
FORM 3
EQUIPMENT-GUIDE LIST
IDENTIFY EACH PIECE OF EQUIPMENT IN THE ELECTRICAL OR MECHANICAL
SYSTEMS BY NAME, NUMBER AN D LOCATION
Equ~pment Equ~pmentNo
Number Location
HSEB-Preventive Maintenance Manual
Chapter Ill - Preventive Ma~ntenanceProgram Development
C CREATING THE PREVENTIVE MAINTENANCE MANUAL
Upon the completion of the collection of all equipment data, a computenzed Ftabase
is built and use as the baas for the development of the various preventive
maintenance activitres The system lists what maintenance checks must be performed
on the equipment It also Indicates what tools and spare parts are required
FORM 4 - Thrs Form 4 is the PM MANUAL It IS the heart of the program It contarns a
one-line summary of each PM requirement for each piece of equ~pmentThe manual is
arranged in numerrcal sequence This manual supplies all information necessary to
schedule preventive maintenance, order replacement parts, record equipment hrstory,
and analyze equipment conditions
Included in each section are the PM summary sheets, equrpment data records, and
equ~pmenth~storyrecords In front, an index l~stsall equipment In numerical order All
forms are filed in sequence under the equipment number, beginnrng with 0001
FORM 4
PREVENTIVE MAINTENANCE MANUAL
I Equipment
Equipment no Location
-
I
I
I
I
I
I
1
Page 5 of 12
HSEB-Preventwe Maintenance Manual
Chapter Ill - Preventive Ma~ntenanceProgram Development
D EQUIPMENT HISTORY
FORM 5 The equipment history record, Form 5, is the last page of each sectron
Entnes on thrs Form should include all repairs, overhauls, modifications, and other
non-PM-related funct~onsperformed on that piece of equ~pment Descriptions should
include parts, labor, and dates Thrs record serves as guide to accurately estirnatlng
the need for future repairs of overhauls It marntains the equ~pmenthistorical records
that glve all ~nformat~on repairs to equipment It can point out recurrent problems and
warn of a sertous breakdown Again, the data on these Forms 1s input to the computer
to contlnue the data base development
FORM 5
EQUIPMENT HISTORY RECORD
Equ~pment Equrpment no
I I
I
I
I
I
I
I 1
I
I
I
I
1
I
I
E SCHEDULING
Once the basic information has been collected, maintenance schedules are developed for
each piece of equipment instructing the staff as to when and what type of
ma~ntenancethey are to perform The computerized printout of each schedule IS issued
and each maintenance crew can then transferred to larger forms designed so they may
Page 6 of 12
HSEB-Preventive Maintenance Manual
Chapter Ill - Preventwe Ma~ntenanceProgram Development
be placed on convenrent buHeting boards alongsrde each other This arrangement
allows reading honzontaily across one line at a t~me,assunng ease In schedulrng
Suggested sizes of schedules are yearly, 20 x 28 In, quarterly, 44 x 28 rn , weekly,
24 x 28 In Space is provided for 50 equipment items Addrtronal schedules may,be
used if necessary
FORM 6 The five year schedule, Form 6 , should be filled out first, coverrng
all requirements except weekly Once all equipment numbers and names
have been filled, the scheduling should begin with the first Item Refer to the
PM manual and make the approprrate assignments In each of the four
blocks, each block represents one quarter of the year Quarterly checks are
entered first Semiannual requirements are next and will be scheduled rn two
of the blocks Annual requirements are scheduled last
2 Yearly Schedule
FORM 6
YEARLY SCHEDULE
J
Begrnnrng Year
FORM 7 Thrs Form 7 allows the development of the quarterly schedtde startrng at
the first block Each of the 13 blocks represents 1 week of the quarter At the top of
each column, the date of each Monday of the quarter should be entered
Informatron for the quarterly schedule IStaken from the yearly schedule and the
PM manual Each of the 13 blocks represents 1 week of the quarter
FORM 7
QUARTERLY SCHEDULE
Quarter Year
I I
I
I I
HSEB-Preventwe Maintenance Manual
Chapter III - Preventive Marntenance Program Develo~ment
4. Monthly Schedule
FORM 8 Form 8 ISused beg~nnrngw~ththe first week and the tirst equrpment
Item, schedule all monthly asslgnments Each equipment item will be scheduled three
trmes per quarter Because there are 13 weeks per quarter one segment w~ilhave a 4-
week interval Scheduling w11l depend on how much t~meIS
for preventwe ma~ntenance, but try to schedule jobs evenly
throughout the month Otherwise, the crews will be performing all the jobs in
the first week of every month The only t~rnea problem may occur IS if an
assrgnrnent must be rescheduled, and there may not be sufficient time to
accompl~shit
After the monthly assignments have been scheduled, the quarterly, semi-
annual, and annual assrgnments should be added Consult the yearly schedule
for those assignments included in the quarter berng scheduled Refer to PM
manual and schedule simrlar types of assrgnments for the same week
FORM 8
MONTHLY SCHEDULE
Month Year
.
I
I
I
1
Page 9 of 12
HSEB-Preventive Ma~ntenanceManual
Chapter Ill
5
- Preventwe Maintenance Program Development
Weekly Schedule
FORM 9 The weekly schedule, Form 9, IS the workrng document for prevent~ve
marntenance An extra column of blocks may be added to ~ncludethe name of
the person respons~blefor a partrcular prece of equrpment
The schedule should have all dally and weekly assrgnments, rf required It
can be covered w~thplastlc so that addlt~onalschedulrng can be done
w~tha grease pencri From week to week, srmply wrpe rt clean and,
reschedule from the quarterly
To set up the schedule, transfer all ass~gnmentsfrom the applrcable week on the
quarterly schedule and enter the date of Monday of the current week rn the top
space An X should be drawn through ass~gnrnentsas they are completed
Assrgnments that are not completed should be c~rcledAt the end of the week, all
completed assrgnments should be noted on the quarterly schedule Unfinrshed ones
should be circled and entered rn the next weekly block The weekly schedule IS filled
out after the yearly and quarterly has been completed It w~ll serve as the workrng
document for prevent~vema~ntenance
FORM 9
WEEKLY SCHEDULE
Week
Equrpment No Equrpment Mon Tue WedThurs Frl 1 Sat
I I
I
I I 1 I I
I I
I
I I I
I I I I I
I I
I I
I
I I I
Page 10 ot 12 2/
HSEB-Preventive Ma~ntenanceManual
Chapter Ill
F
- Preventwe Ma~ntenanceProgram Development
POINTS TO REMEMBER
Shortly before the end of the year, a new yearly schedule should be generated Any
improvements rn schedulrng, such as rearranglng assrgnrnents and dates, should be
lncorporated at this t~me
The PM IS most effective when jobs are scheduled and completed on an evenly
distrrbuted basis Monthly assignments should be completed 4 weeks apart, and so on
Completron of assrgnments on trme is rmportant In assurrng unrformrty of equrpment
upkeep
H FAILED-PARTI EQUIPMENT REPORT
Thrs form includes the equrpment name and number, the farlure, and rts cause On
the lower portron of the form, a descrrptlon of the corrective actron and a lrst of parts
used for the reparr should be included
I SPARE PARTS
Page 11 of I 2 27J
HSEB-Preventive Ma~ntenanceManual
Chapter Ill - Preventwe Maintenance Program Development
After the system has been in operation for a time, manv recurrent ~robiernsw~llbe
noted and adequate parts support w~llbe available A penodtc review of the faded-
part/equipment reports may define some potentrai problem areas
I
FAILED-PARTIEQUIPMENT REPORT
I
I Date W O No
Act~ontaken
Parts List
Part Name Part No Comments
I
Date Repaired
Page 12 of 12
I
Single-phase transformers
Three-phase two-w~nd~ngtransformers with and w~thoutburred
tert~arres
Three-phase three-wrnding transformers
Three-phase autotransformers with and without burled
tertrarres
Page 2 of 3 'd
HSEB-Preventwe Maintenance Manual
Chapter IV - Transformer Impedance Test
Page 3 of 3
J
SWlTCHGEAR INSPECTION
AND TEST PROCEDURES
TABLE 4 I
Page 2 of 3 @
HSEB-Preventive Ma~ntenanceManual
Chapter V - Swltchgear Inspect~onAnd Test Procedures
TABLE 4 2
I
FIELD OVERPOTENTIAL TEST VOLTAGES* /
Rated kV Max~mum
8 25 19 5 27 8
ME1 15 0 27 0 37 5
(Metal-Enclosed Interrupter 15 5 37 5 52 5
Sw~tchgear) 25 8 45 0 +
38 0 60 0 +
0 76 16 23
MEB 50 14 3 20 3
(Metal-Enclosed Bus) 15 0 27 0 37 5
25 0 45 0 +
35 0 60 0 +
+ Consult Manufacturer'sSpeclficatlons
*Derived from ANSIIIEEE C37 20 2 and C37 20 3
Page 3 of 3
THERMOVISION SCANNER
I
TO IDENTIFY "HOT SPOTS" I
6 When a hot spot In located, zero In on the hottest area, and set
the record and ~ t stemperature In memory
8 When all the scannlng has been completed and checked from
drfferent angles and recorded In the memory turn the camera
off Disassemble any assembled components, and return all
components to thelr orlglnal cases for transportat~onback to
the shop
Standards To Be 1 The Images and data must be sharp and clear, especrally those
Observed readlng high temperatures
Page 2 of 3
31
HSEB-Preventwe Maintenance Manual
Chapter VI - Thermovls~onScanner To ldentlfy "Hot Spots
Devrat~onfrom None
Standards
Necessary 1 Scann~ngOperator must be fully conversant wrth th$operatrng
Knowledge and manual for the scanner being used and must know how to
Skills cailbrate the scanner for the arnbrent cond~tions
2 S~ncethe Scannrng Operator will be worklng In hrgh voltage
substations, all safety work practrces, clearances, etc must be
known and observed A mrnrmum of two operators work~ng
together for each scanner IS recommended
Page 3 of 3
32.
INCORRECT CONNECTORS REPLACEMENT
5
Page 3 of 4
HSEB-Preventwe Ma~ntenanceManuai
Chapter VII - Incorrect Connectors Replacement
Knowledge And catalog appl~cation/select~onguide
Skt 11s 2 Be famrl~ar with the requirements of connectors and
configuratrons
3 Have vendors'representatwe confirm the selection you have
made for the application you need
4 Be familrar with cable and wire sizes, NEMA hole spacing,
and bolt slzes, torque requirements
5 Be able to ident~fytermrnals of equipment whether they are
copper (or anodrzed cooper), Aluminum, Galvanrzed steef or
ACSR Thls can be done by performing the followrng tests
Scratch test for copper - brrght red when scratched
Magnetrc test for steel vs Non-rnagnet~cfor stainless
steel
Light werght, s~lvercolor for Aluminum & non-magnetic
Page 4 of 4
Purpose Substatron equrpment IS scanned to detem~neequrprnent and
components operating at temperatures above their designed
temperature rlse ratlngs These locallzed hrgh temperature zones
are referred to a s "hot spots" The reasons for the "hot spots" are
then determrned and corrective actions rdentrfied and
rmplemented to reduce t h e high I2R losses Corrective actions
may include the replacement of faulty equlprnent
Procedure 1 The thermal vrsron scan of the substation may rndicate that specrfic
equ~prnentis the source of the hot spot on the scan
2 The causes of the hot spot must be determ~nedfirst It could
be one or more of the following
a H ~ g hcurrent flow above thermal lrmits overload~ngclrcu~ts
b Poor contact connectors
c Incorrect connectors
I Incorrect size and configuratron
Page 2 o f 3
3f
HSEB-Preventrve Marntenance Manual
Chapter Vlll - Replacement of Faulty Equ~pment
4 Be fam~liarwith the metals used in the connectron of the
I
equipment and with the type of connectors needed to ~nclude
I
the replacement equipment in the circuits
Page 3 of 3
REDUNDANT EQUIPMENT
AND JUMPERS REMOVAL
Purpose Non-essentral equrpment that may have been left In the crrcult
for a number of reasons generates hot spots at each corroded
or hrgh resrstance connect~on Since these connectlons are not
requrred because the equrprnent can already be removed from
service, these addrtronal I2R losses can be eliminated For
servlce contrnurty however, the removed equlpment must be
replaced with a jumper The jumper and rts connectors must be
surtably srzed and selected so as to cause the mlnlmum of I2R
losses
Procedure Redundant equlpment rn the crrcurt ~fnot actually contrrbutrng to
Deviatron from 1 If there are trme constraints on the replacement, and the
Standards correct connectors are not immediately available, the
addition of another connector In the jumper circult is
allowable to achieve the necessary connector configuration
However, this is only allowable ~f the overall resistance of
0 05 ohms IS not exceeded
Page 2 of 3
HSEB-Preventwe Marntenance Manual 3
Page 3 of 3 fk
CHANGING TRANSFORMER
NO-LOAD TAPS MANUALLY
-
Knowledge and transformerwindrngs
2 Be fam~l~arw~thcorrect operat~onof rnsulatron megger
and be able to evaluate resuits
Page of 2 2 qf
/
The following are the conditrons that have been found durrng the
HSEB-Preventive Maintenance Manual
Chapter XI - Transformer Cooling Systems
substatron performance evaluatrons conducted In the field
Sample c a s e s
OA rat~ng
but hrgher
than Case
2a
Case 3 >OA 30C >95"C >65OC ON
Ratlng
Case4 >OA 40C >95"C >65"C ON
ratlng
Page 2 of 3
4
6
HSEB-Preventive Maintenance Manual
Chapter XI - Transformer Cooiing Systems
It can be seen from the above Table that the dec~s~onwhether to
turn the fans ON or OFF depends on whether the 011temperature
IS above or below 65C To allow 'forrnaccuracles, etc use 60C ori
temperature as the cnterra instead of 65C
Devratlons from 1 If load changes occur very rapldly in the one-hour perrod, around
Standard Peak trrne, ~t may be beneficla1 to check the oil temperature
gage more frequently durrng thrs perrod and operate the fans
accordrngly
Page 3 of 3 q?
FORMATION OF "DRIP LOOPS'' I
I
/
IN VERTICAL JUMPERS
Procedure When vertrcal jurnpers are changed, the measurement for the new
jumpers should include an easy 'S'drip loop before connectrng the
terminal bush~ngsof the equ~pmentto the bottom of the jumper
This type of "drrp loop" is required on all vert~caljumpers that
terminate on outdoor c~rcuitbreakers, reclosers, autornat~cvoltage
regulator etc
1 Select the material and cross section of the new jumpers for
the requrred current carryrng capac~ty
2 Remove all sources of energy from the equipment to be
worked on
3 Apply safety grounds, ground clusters and ground charns to
safely isolate the equ~prnent
4 Remove "old" jumpers
5 Measure length of "old" jumpers but add an extra length of 2
feet to form the "drip loop"
6 Prepare connectron between jumper and the
equ~pmentand select the correct connector
7 Make the connectton of the vertrcal jumper to the equipment
at the bottom end Form a "drip loop" with the slack in the
jumper so that rainwater will run down the jumper and run off
the jumper at the lowest potnt preventing it from flowing Into
the equ~pmentconnector at the end of the jumper
8 Complete the top connection of the jumper
9 Check for continu~tyand proper connections
10 Remove safety grounds
HSEB-Preventive Maintenance Manual
Chapter Xll - Formation Of "Drip Loops" On Vertical Jumpers
Standards
Necessary 1 Famrirarrty wrth makrng jumpers connectrons
Page 2 of 2 (4
XI11 INSPECTING & TESTING LARGE
I TRANSFORMERS I
applicable
4 Verify removal of any shipping bracing after final placement
recommended by manufacturer
9 Ver~fyproper equ~pmentground~ng
Efectr~calTests 1 Perform insulatron-resrstance tests, winding-to-w~nding, and
alarm functions
6 Verify proper core groundrng rf accessible
applrcable
Test Values 1 Insulat~on-res~stanceand absorpt~ontest Test voltages
Page 2 of 5 51
HSEB-Preventive Maintenance Manual
Chapter Xlll - Inspecting And Testing Large Transformers
be rnvestigated
TABLE 13 I
LIQUID-FILLED TRANSFORMER INSULATION POWER FACTOR VALUES
Tetrachlor- H ~ g hF~rePornt
011 S111cone ethylene Hydrocarbon
New Power Transformers 0 5% 0 5% 3 0% 0 5%
New D~str~but~onTransformers 1 0% 0 5% 3 0% 1 0%
Page 3 of 5 5p
HSEB-Preventive Maintenance Manual
Chapter Xlll - lnspect~ngAnd Testing Large Transformers
I
TABLE 13 2
INSULATING LIQUID TEST VALUES
H~ghMolecular Tetrachlor-
above 34 5 kV
20 PPM
Maxrmurn
15 PPM
Maxrmurn
Page 4 of 5 53
HSEB-Preventwe Maintenance Manual
Chapter XI11 - lnspect~ngAnd Testing Large Transformers
TABLE 13 3
TRANSFORMER INSULATION-RESISTANCE TEST VOLTAGES
Recommended
M~n~mum M ~ n ~ m ulnsulat~onm
Transformer dc Resistance In Megohms
Cod Rating Test Voltage L~qu~d-F~lled D~Y-TYP~
TABLE 13 4
TRANSFORMER INSULATION RESISTANCE
Temperature Transformer
"C OF
011 Dry
Page 5 of 5
XIV UTILIZATION OF FUSES, CUTOUTS
AND LIGHTNING ARRESTERS'
'
r At present lightning arrersters are not used on dlstribut~on
transformers and/or capac~torsand at some substatrons large
Current HSEB power transformers Thls equ~pment IS not protected agalnst
Pract~ceon system surges or I~ghtn~ng
L~ghtn~ng
Arresters The continuous sudden changes In system configuratron
resulting from the number outages caused by overloaded
feeders, I transformer failures, and other causes, create large
over voltages Thrs high over voltage travels along the hrgh
and/or low srde of overhead lines connected to transformers or
capac~torsThe effect upon the equipment IS to puncture or
damage the internal ~nsulationof t h e equ~pmentthat may failed
lmmed~arelyor that eventually will fail
HSEB-Preventive Maintenance Manual
-
Chapter XIV Utilization of Fuses Distr~butionCutouts
and Lightning Arresters
Fuses Purpose Fuses are relat~ve inexpensive protect~on dev~ces connected
between transformers, capacitors or other equ~pmentand the high
and low-tension d~stnbut~onsystems Fuses are used to prevent or
lrmit the damage to equipment due to overfoads or short c~rcuits
The fuses remove the transformer or capacitor out of servlce
before the occurrence of damage to the equ~pment
Fuse Operation When the current through the fuse IS excessive the resistance
Curve magnrtude of a fault current and the tlme required for the fuse link
to open the crrcurt The greater the current, the faster the fuse
melts and the shorter the t~mefor it to blow
D~strrbutron Distr~butroncutouts provrde a hlgh-voltage rnount~ngfor the fuse '
Cutouts element used to protect the drstr~butionsystem or the equ~pment
connected to it Distrrbutron cutouts are used with rnstallat~onof
transformers, capacrtors, cable c~rcuitsand sectronalrzing points
on overhead lines
There are varrous types of cutouts, enclosed, open and open ltnk
r
St I n s r e ~ l ~ o ~11~111to bc Insp-cl~anNote A c t ~ o nrequired
- ~nspec~eki
-
Freqllcl~c y
- -----
-- Rea~orl s
I hlonlhly
1 hlontbly
I
Check for leakage of oil Stop any leaks from
drain oft valve, gas-
3 hfontllly hets and tank leaks etc
Check for colollr of s~llca Recondltlon o r
gel and reactlvat~ng,rf nece- replace,as nece-
4 Monthly ssary ssary
Check L As and jumpers
for t~ghtness
5 Monthly Fuses Check for cont~nulty,tlgh- Replace old fu-
(HT & LT) tness and correct r a t r n g ses with new
'.
ones of right
capacr t y
6 L'onthly G 0 Slv~tch Check for pasitron/spark-
Ing of G 0 switch blades
7 Monthly - Check diaphragm for cra-
cks
BEST AVAILABLE COPY
-. ,-. 11) Check w~ltercontent ln v a l ~ ~ etso
8 Monthly Insulation 11ie 011 water corlt
Relstance 111) JU case c~ucckle lest
Compare ~ l t hvalues at red i n case
9 Quatterly Bushlogs & ~ I I O ~ ~ Sdele1 lora~lol~,colll lmlnal
the tlme of comrnlss~on~ng
nrclng herns 1) Replace these perform dl-electrtc str- Llie 7 /F wl
Check for chlpped and
broken bushlngs rf necessary eogth test ttself shou
11) Examltle & replace the Cleao off nil lvf iceep record of test put to de
damaged gaskets drrt, p ~ ~ ndt results at1011 an3
olher depos~ts out by nlea
danger plate sufic~en tprovrs~on of replace ba~bed of during driest part of e1rl11 rcslstel
c tc Bsrbed wire wlre, as neccss- year of (a) Neut- arc not more 1 1
ary '"1 of T/F (b) T/P body 2 ollms
11) Check for proper suppo- l'alnt & reprint and o t l ~ e rrnetal parts
rtrng of danger plate at the danger plate I c JI ~ g h l n ~ narrestorsg
suitable he~ght ~f defected,
1 ~Keep) record of test 11) In case of hlgll
13, Half ~ ,testlog 1) Observe coiour of the Perform crackle results values, recond
011 to have ldea of l t s test on the 011 Ion t l ~ erods dee
yearly cond~tlon, samples drawn er into ground ( by
from drain-of1 addrflon of w tcr
through plpe
ANNEXURE 'B'
I)
I-IOURLYJDAILY SCHEDULE
Two Consgr- Cl)ech for proper comu- Clean the lospe-
INSPECTION AND MAINTENANCE SCHEDULE FOR POWER T/F
}early \ator aicatlon of the conser- ctron glass so that
7 ank vator wlth TJF tank by o ~ love1 1s pro- -
d r a ~ ~ i some~ng all throb- perly visible SI. Inspecrlon Item to be Inspccllon notes Remarks
gh dram cff valve and Elo Frequency l~ispected
Complete overhaul of the 7 -do- 0 1 1 level Check for any leakage If low, br~ngit to
Once ~n in bush- the correct all
every- transformer mgs level
five years
8 -do- Rellef vent Check for cracked or Replace ~fcracked
Note , These charts should be displayed in the ofice
room of the Xen and SDO concerned d~aphragm broken or braken
-
-. hION1 HLY 9CKi D t J L E
9 Dally each For Inter- Check for ally sound or INSPECTlON AN D M41NTENARCE YCHTDULE FOR POWER
Slllft nal unusual excessive chatteting
10 -do- Heaters In For proper aorC~og, XI
Sr I n ~ l ~ c c ( l o l ~111 ms to be jnzpecllon Noles Reruarhs
No 1-1 equenc) rnepecled
Junction prov~ded I M o n l h l ~ Dellydl atlng I ) Check for condltlon/ I) Recondltloa/
11 --do - External Check v~suallyfor t~ghtness
br ea tl~er colour of S~llcaGel place, as nece
connectroo and spark~ng on Jumpers Ensure that alr pass- ary
(Leads/ Bushrngs etc on complete 11 ) 11) Make up 011
Jumpers) darkness age 1s free requlred
1111 Tlght 11d of the brea- 111)Do clean ng
12, -do- Bus bar & Check for any ddmage &
Cab1e slgns of overheatlag a t 1 her for alr t ~ g l ~ t r ~toes s the breathel
Boxes & thelr J O I ~ ~ S avoid eutry of rnolst nlr
IV) Clleck 011 level In ollcup
Cables
v ) Remove 011 from dash
N n t e These Charts sbould be displayed In the pot & pour 111 fresh 011
substations
where requ~red
2 lMonthly B t ~ ~ h l nandg E~afnln efor oracks, Palnt Clcan or rcplacc
gaskets ~ n dl1 t deposrts and gap
ceir~ngsCheck gasket for
leakage
3 -do- Cooler fqn Lubrlcate bearrugs, check Roplace burnt oi
and pump gear box Examlue cout- worn out contact.
bezrrngs acts Check manual control or otl~erpal ts
motors and ?nd ~r~tcrlocks
ope! ?tlng
mecban~sm
4 -do- On-load tap Lubrlcate beanngs. check Replace burnt or
chasger gear box 011 level and ex- worn out contacrs
dr lvlng drnlne contacts or other parts
mechanism:
I.
G 0
0 T3
I0
1 2 3 5
4
5 Qunr- ?hymo Check for its normal
terly Syphon work~ngorder
Fillera 1111 Specjfic I<eslstl v ~ t y =Above 10 x 10'"
011 11
15 Yetlrly 2 1 Yearly Dlverter Check for worn out con- Replace worrt
Fdundatron Check for cracks ~f any
or after switches {acts, Pllter 011 rrrcspective out parts,
d r d settl~ng,
10,000 for tap- of 011 test
16 --do - Buslllllgs 'Iestthe Lushrngs wlth a . .
Opera- changer
hrpot busllrng tester , ~ n d trons havlng non-
comparing wrth pre! lolls arcing sele-
figures ctor swrtch
17 -do- Temper- Pockets hcld~ng thermo- 011 to be reple- 22, Two 011conser- Internal lnrpectlon,
Should be tharo-
years vator ughly cleaned,
a ture meters sl~ouldbe cheched, nlshed,rf required 23 -do- Buchholz
lndrcatlon Mecehanlcal inspectroo Adlust Boat, swr
IS -do- D ~ atypel Check pointer for free- Adjust, r f requlr- relay tchest etc, as req-
uired -.
.-
19 -do- Palnt work Should be ~nspected Any patntlng or years or selector1 : ' 4 parts F~lttli011
retouch~agshould after swltch of .. . -
I I
i r . A -- I 47
I
20 -do- Conser- I)Check for proper corn- Clean the nspec- 25 7 t a 10 0v;rall 'it;spSct~on ~nciu! by holing
vator Tank mun~catlonof the conser- tion gass so that years ding' llft~h$%f: 'core and down *lth ~1e.u
vator w ~ t hT/F tank by so that oil level 1s cdl~ht 13!llf~d'
properly v ~ s ~ b l e
I
dry oil T~ghten
drarnlng some oil thro- I J I d
1
1.
1-
ugli dram off valve and all bolts, nuts toll
watchlng the 011 In clarnp~ngscrews.
Major overhaul (complcts)
gauge glass to drop of transformers. .I I,
-.
I
to porcelain ~nsulater
and bearings, 2 -do- (111 Check for 011leakage and when
15 --do- Gear Boxes Check gears and bearings Flu- excessive the level be also checked
a
sh out oil grease dnd relubrlc- 3 -do- Earth Check that Earth connect~oos
ate,
Operating
conncctron are properly made
16 -do- Check working of motor and 4 -do- Jumpers Check that jumpers, nuts, bllts,
motor and mechanism, Nut Bolts clamps are properly tight and
mechanish
etc
17 -do-- Lochs & Check out locks and keys
5,
- do- are of proper s ~ z e
Secondary Check that secondary wlrmg 1s
inter -locks operate as rntended Check w~rlng properly made and routlog is
J
mechanical - interlocks, such as
-- --
-7
appll~able),~~* $
4 4
8 Aflnual We.llhcr
INSPE~TION~r MA~NTENANCESCHEDULEFOR See [bat ~ e ~ t b slledsr alld
s h e d s and hooks of o x ~ d efilrn arrestels
LIGHT NING ARRESTORS
flnoks are securely fastened III place,
repalnt ~f necessary
9 --do- Lllm and Check and trghtcn ll~le and
Ground gr~ull d counectlons check
11 Weekly Surge Note and record operation in-
connectloll ground lead for colros~onor
or at the Counter d ~ c a t o rreadlog dmag e below grourrd jlne
Check ground resistance See
that all leads are as short and
former
tripplug
direct as poss~ble
10 -do - bperatlon 1 o check the
2 Monthly Base & Usual ~ n s p e c t ~ tondetect cmck- tests (Surge- of 11ghtnrogarresters by M & p
working
Support mg settllng o r shlft~ngof base
! gcnhrat~ng d~vlslbns
or supper t S
Check that surge moultor is equlprnent
3 -do- Surge under pro-
Monltor properly connected and 1s in curement)
worklog order & shows a lea-
E (M k' P I J ~ b ; L l a&;tt
NOTE 1) and Hissat should prasu
kage current, I
,I I
Bulb or dry See that copper o x ~ d eor rtle- 22 Annual liydrot~le(erClieck cond~t~ollofbydrometer
I6 Half
yearly ihtlfier nium ~ e c l ~ l ielementsr are llot and tbermo- and l l ~ e r r n oter~~ ~ eC I I ~ C11,~-
element operatlog to0 hot, t h ~ s wlll melers drorl~etcrs and tberslome[ers
shorten then ltfe used for dally and n~outillv
-- -J
readlugs agalnst spare u n ~ t helds
17 -do- Rheostat Check that sl~dlngmecharl~sm of In reserve
the rheostat 1s tn order and
clean the sltdlog contacts, l f 23 -do- Sink, See tllat the sink, futlnels,
requ~red Check contact heat Funnel and fillers a n d othr dlst~lledwater
log and sprlng pressure
fillers and a c ~ handllng facll1[les kept
Check metalrc structureslparts c h ~ and in good useablc con-
18 Annual Battery located In the room for corro- dltlon
Room and
ventillatlon slon and clean and p a ~ n t as 24 -do- Water st111 Check st111for proper operatton
necessary, check ventllat~on and adequacy and purlty of
system fan etc for proper oper-
at~on,to make sure that no distlllcd water delivered 'See
explosive gases ate belog accu- (hat equipment 1s kept cleah
-
mulited m , b h ~ e room~ due to 25 Yearly or as - Complete overhaul or the
excessive gasslng ur poor ven- recommend- battery
, 1-
ttlattbn 11I ed by manu-
Inspect concrete base or wood-en facturer
19 -do- Base racks for deterroratlon Repa~rand
o r rack Note 1 illese cllarts should be displayed in the
r ,
rpaint
e p aas~'necessary ..-
n twith acid res~stdnt
Substation,
I Check base pad of shoet rubber,
'sahdor othi;dmaterlal for de-
20 -do- Casc Pad terrorat~onfrom a c ~ dor otherI
I causds
mechanism see that every t h ~ n g1s ~n worklog 34 -do- Adjustlnellt T l ~ egap may be checked and
o r d e r Check plns, bear~ngs of gap (for adjusted l o Ole repulred vnluc
and latch for wear, blndlng and MOCB) &
m i s a l ~ g n m e n t Clean aud other type
lubricate the movltlg parts Check l o clleck tile
presc~lbed
Iatch carefully to see that it IS Items by tllc
n o t becomrng worn so as to
nianufacturet
- -
unlatch from vibration or stick 35 --do- Wlrlllg Cbeck a n d trgllten wlnng
or fall to trlp Tsghterl bolts connect~ou connectron a t telnllnal polnts
28 -do- Trtpplng
and skrews
Observe oyeratlon during
I Inpect wrr~ngfor open clrcult.
short c ~ r c u ~andt dnlllnged
solenold ansulatron.
electrical t r ~ p p ~ n Seeg that full
1 -- -
- -- - 4 5
-- - - 2 3
1
- -_
1 2 3 - - ---- - - -_ _-__- ---- 5
.-..
46 ~rnu111y Rilaln Tfgllterl L ~ l ln l l l c I I I C ~ ull(l
52 fZl'flu3lly Llfl rods (Iliecl colltsct for kft rod$ rol
tcrmInals connect~ons Mcfinl\ll Julllt Guldcs b ~ a k mweaken~ng,or \irapplnp,
,,nd mating surr,icc, l f the\ 1~je ~11ld1~ul11ngout at e ~ l d s C I I ~ ~ ~
c r n n c c t l o i l ~beell 01 er Ilcated I~~I'LC~ crdcquacy of gurdcs
glorrnd cable lo see t h l t lt IS 53 -do O ~ ~ ~ r d t j l Checkl~: fur luoce l o c ~ . , ~se~t ~ ~ ~ ,
not loose or broken fells, sllafls SClcIY, keys, b ,trlngs bent rods
al'd bell o r tmlsted s11'1fts etc Clean
-dc- Ma~n Retllove the t a d s or dralll out
47 looseness
contacts 011. so that Ihe colltrlcts call be Ilft
jnspecleri drec ? cailtacts,
lough 1~1th n flne file Clleck
c o n f ~ c l svoltage drop with I
55 -do--
56
-do-
Annually Operatloo t ~ m e sat intervals, as system
j7 Annllally ['oslllon Chech t h a t ~ o s l t l o nlndlccttor 1, operation wrll permlt and may
~ n d ~ c ~ i ~properlyr ~ n d ~ c a t t ntheg bre'lher allcvlate the heatrng by w1p1.g
posluan Chech aperat~ngrods t h e o x ~ d efrom the contact
or levers fo r loose parts surfaces, as well as demonstrate
58 -do-- 1)nshpotS C i l ~ c h f o rproper settlng and that the breale r 1s in operating
63 --do- condltron
zdjust as l ~ ~ c e s s a r yClsnn o u ~ BusLog Check top seltrng & adjustments
and replen~sh 11quld In Irquld current a t terminal board to see
d'ishp?~~ transfa rmers that they agree wlth dtagrams
59 -do- Mecl~anrsm Check c l~dltronof metal and and potenllal Check lnsulat~onreslstance of
cablnets hdldwa~eRepaint as neceqsary dev~ces wirrng wlth devlces connected
See thdt doors gaskets are I
Check ratro & phase angle
ilght and properly excl~lcic adjustments, of potcntcal devlces if
dust and dlrt ch~nge ehay& been made in
60 Annunlly Paner lnspect fuses of clrcurt brenher secondary connectton and
Supply & In all power and control supply, burden Tlghten connections.
wlrlng crrcults Check u p ~nsulat~o n - --
a"" n=
!z
rn
z
~3hnz;t; C M O v ,
= a
EJEilC u
GgpEf=a J
gggasg $
" ",-
0-
- e g %g -
f!
*
m u - - 0
eo 2-2 a
Z
Z F o C
0 CI
g 0,
-rD E 0
D
cno= - a4
p e z 2
t u
r: z
$ 0-
3 I z,
>
n
- -
1 2
r- 3-4----5
Qu lrterly f'lult joint locatcrs
2uart crly 111)Cxccss~ved e p o ~ nfdustls~ lltl
coal and oilier pollullon should be made to
I V ) Kxcesslve rusting of fit~ngs detect over-heated
Joints
- do- Conduc- Check for the followlllg
IX )Broken conductor strands
tors and 1) Examrne,lf securely t~e dto tile x ) Nlchrng near insulator
earthw~re ~risuI~tor~polelcross-arm neck and/or nea'r conductor
11) Proper sag clamps
111) Proxlmlty of trees and other Tree branches X I ) B~ndingwtre has not
objects ~nclud~ngbuilding, witllln 1 8 m become loose in d open
etc from the l ~ n e X I I )M ~ d s p a njoints have n o t
on its ellller crached
slde should be XIII)
All joints and jumpers of
removed
alumtnlum cond~lctorshave
iv) Suffic~entclearance p;o dr chmps/jolniln ~
between conductor and slee6s
earthw~res, and also from
the ground 6 -do- Jumpers & Chec? for the following
I
level w ~ t ha
cross-arms by ne wones
one kg hammer i 11) Brlng In posltlon the
A clear r ~ n g
1s ladtcat~on slrpped cross- arms /
of healtliy clamps/br,lclngs
wood, w h ~ l e IU)Palnt the steel CI oss-arm
a hollow rrng and bractngs, etc, rf
IS a slgn of excess~velyrusted
decay Provlde 17 ( T h e Insulators and I) Clean and check for
butt j o ~ n t s ~nsulators fitt~ngs cracked/ chlpped am1
where decayed be checked punctured ~nsulators
wood IS
twice a year Replace,where necessary
removed
preferably 11 )
Examine for the surface Do not u
11) Ex,qmlne for burn~ngof before and contam~nat~on n n d cotton wnsl
wood at hardware after (monsoons) remove ~t by wrplng
qttachment pornts and \
with a soft cloth If the
recond~lron, where deposrt has set hard,
nccessary~ a weak acldrc solufron
I
Cyrneot Pole No detalled may be used.
mqlntepance required 18 Annually Conductors I) Tlghten loose blndlngs
1) Tlghten the loose stays and earthwlres and replace damaged
15 Annually Staya
11) Replqce the broken1 ones 1
damaged stays and stqy-
bows n) Examlne for corrosion 'at To avo]
I
1 2 3 4
- -
-- 5 - --
An~lually the ~ o l n fofs conductors corros~onthe Annually cldmps Tlghten dl1
with p 1 11 necessary
~nsulators 11) P a form impulse vollage Tl~ese tests
by means of spmkover test & leakage can be
btndlng wrrc of current test to hnow the performed by
the same metal condltlon of lhe arrestor, using Jlgh[n.
as that forn~rog 1 replace case of 1ng arrestor
the o u t c r strand
I unsrtlsfactory results testlog hlf
of the conductor developed by
311) Exanilne closely for C p R I ,
broken stra~ldspdrtrcu- Bnngalore o r
larly, at the clamps any other
and insulators due ava rlable
to vqbrai~onand repalr, Instruments
where necessary. To know the
IV) Examlne general c o n d ~ t ~ o n
condltlon of
of the conductor and the arrestor the
earthwlres, I e for klnks, test results be
crusl~edspots, overlunder compared
tenslonrng, ctc , and w ~ t h the s
tandardl
recondrt~on, where manufacturer's
necessary3 speclficat~ons
v) Examlne for any loosel
cracked joints of
conductors In the
.meggar
A1ternamay
t ively
be
used for
mldspan and recondrtlon, detectrng
faulty l~ghtnlng
where necessary arrestor
V I ) Examlne for s l ~ p p ~ nofg
ill) Keep records of test
conductors from the results
I
i INSPECTION cSr. ANNEXURE 'I'
MAINTENANCB SCHEDULE FOR
Annually iv ) Check and t~ghte nall I
L T LINE
ltne connectrons and I Sr brcquctlc) ol Equ~prnent/rterns Jtl~rect~orlNoic Aclroll Requrred/
cart11 leads
No l~ispect~o~l Lo be inspected liemarks
20 -do - 11 KV Cable 1) Clean and examltie for 1
and cable boxes damaged busblngs 1 2 3 4 :
Ill
22
I
I ) If the swltch with
-do ~ ~ t ~ - ~ l ~ m~belcnog~ d l t l othen antlcllmblng
devlces and devices s u c h as cover IS Intact
11) If the cable/sw~tcI~
barbed wrre, locks, etc ,
I
danger plales
etc paint and r e p r ~ n t the -
I
ruontng ho t
111) Broken cut-outs
danger plates if defaced'
NOTE * charis should be drsplnyed m the oEc e rooms of the Xen IV) Signs of over-heating/
burnlag on contacts
V) Proper slze of fuse
wrre -
I
-
I l ]If-VL,t l j I rpl,icc l l ~ eL T cable/
L 1 s?r~tchby h ~ g h e
l capdclty one, wherc n
e~e~sdry
1 1 ) i<epliice t l ~ ednn\ngecl
L T cable wlth uew
clue of the r1g11t
cnpaclty
111) f x Inllne the s\r ~ t c farl~
smoo t 11 opera1 J ~ J I
I V ) Replace the burnt f
cracked cut-outc
v) Recondltlon tile swltch
contacts
VI) Repltice the old filses
w ~ nbw~hone or rlght
c~lpaclty
V I I ) T~gbienall connections
V I I I ) Ensure that the lalet
of the cable ~ n t othe
swltch is plugged w ~ t h
plastjc con~pound to
avold entry o f rain
water Refill, where
necessary,
IX) Clean of thz cob-web
and other nests, etc ,
from the ~ n s t d eo f the
a) roles swltcll
4-One to two Same as recommended for
yearly b) Stays these item under Schedule
(Depending c ) Consuming for I3 7 Llne
upon the d) Conductor
volume of e ) Insulators
warh) f ) Connectar
g) Cable boxes
etc rooms of the Xen
NOTE These charts sl~ouldbe d~splayedIn Ille aflice
and SDO concerned,
----