This weekly progress report provides updates on the Lake Victoria Water Supply and Sanitation Program Phase-II construction project. According to the report, the overall progress of the project is 46% complete as of the week of November 14-20, 2016. Specific items like the school toilet main buildings and external drainage are both 97% complete, with no additional progress made during the reported week.
This weekly progress report provides updates on the Lake Victoria Water Supply and Sanitation Program Phase-II construction project. According to the report, the overall progress of the project is 46% complete as of the week of November 14-20, 2016. Specific items like the school toilet main buildings and external drainage are both 97% complete, with no additional progress made during the reported week.
Project: Lake Victoria Water Supply and Sanitation Program Phase-II
Contract No: MWAUWASA/LVWATSAN-II/EAC/W/2014/004 th th Week from 14 November 2016 -20 November 2016 Week No. 60 Overall Progress 46% ITEM NO DESCRIPTION UNIT RATE Previous Comulative This week Progress Commulative E01 SCHOOL TOILET MAIN BUILDINGS 97% 0% 97% E01.1 EARTHWORK 100% 0% 100% Excavation works will include cart away, loading of surplus excavated 100% 0% 100% E01.1.1 Excavate oversite average 150mm deep to remove vegetated soil, convey 100% 0% 100% E01.1.2 Excavate foundation trench commencing at stripped level and not 100% 0% 100% E01.1.4 Extra over for the excavation in rock formations (PROVISIONAL SUM) 100% 0% 100% E01.1.3 Earth backfilling well rammed and consolidated around foundations 100% 0% 100% E01.1.4 Allow for planking and strutting to uphold the sides of excavations. 100% 0% 100% E01.1.5 Allow for keeping excavations free from water 100% 0% 100% E01.1.6 Apply 200mm blinded hardcore bed 100% 0% 100% E01.2 CONCRETE WORK 100% 0% 100% E01.3 BLOCK WORK 100% 0% 100% E01.5 JOINEY WORK 100% 0% 100% E01.6 FINISHING 100% 0% 100% E01.7 PAINTING AND DECORATION 100% 0% 100% E01.9 WASTEWATER INSTALLATIONS 100% 0% 100% E01.10 WATER SUPPLY INSTALLATIONS 100% 0% 100% E01.11 PROTECTION OF BUILDING AGAINST TERMITES 100% 0% 100% E02 EXTERNAL DRAINAGE 97% 0% 97%