03.master List of Procedure YI-ID N
03.master List of Procedure YI-ID N
Form-002R01
Rev. No. : 01
Date : 04 March 2016
PT. YOKOHAMA INDUSTRIAL PRODUCT MANUFACTURING INDONESIA
30 Industrial Products PlantQuality Assurance section CH-AQ-011R01 Procedure Management of Measuring Instruments 1 1/6/2016 until termination
31 Industrial Products PlantQuality Assurance section CH-BQ-019 Procedure for Product Identification and Traceability 0 11/16/2015 until termination
Procedure for Nonconformance Products and
32 Industrial Products PlantQuality Assurance section CH-BQ-027R01
Materials Handling
1 1/25/2016 until termination
33 Industrial Products PlantQuality Assurance section CH-EQ-020 Procedure for Incoming Inspection 0 1/5/2016 until termination
34 Industrial Products PlantPlant Control section CH-BK-001R01 Order Receiving 1 5/2/2016 until termination
35 Industrial Products PlantPlant Control section CH-BK-002R01 Order Processing 1 3/15/2016 until termination
36 Industrial Products PlantPlant Control section CH-BK-003R01 Purchase Order Procedure 1 4/7/2016 until termination
37 Industrial Products PlantPlant Control section CH-BK-004 Material Requirement Calculation 0 12/7/2015 until termination
38 Industrial Products PlantPlant Control section CH-BK-005 Monthly Production Plan 0 12/7/2015 until termination
39 Industrial Products PlantPlant Control section CH-BK-006 Fender Product Serial Number 0 1/4/2016 until termination
40 Accounting Section CH-BH-002 Stock Taking Procedure 0 11/2/2015 until termination
41 HR & GA Section CH-EG-001 Procedure for Employee Evaluation System (C2S) 0 2/22/2016 until termination
42 Production Engineering Section CH-EE-100 Procedure of First Article Management 0 4/1/2016 until termination
43 Production Control Section CH-BK-007 Purchase Requisition Procedure 0 4/7/2016 until termination
44 Production Control Section CH-BK-008 Supplier Selection 0 4/7/2016 until termination
45 Production Control Section CH-BK-009 MH STS Product Serial Number 0 4/19/2016 until termination
46 Production Engineering Section CH-EE-001R01 Procedure for Cleaning Rubber 1 4/28/2016 until termination
47 Production Engineering Section CH-EE-002 Procedure for Bucket Cleaning 0 2/19/2016 until termination
48 Production Engineering Section CH-EE-003R01 Procedure for Re-Mixing 1 5/25/2016 until termination
49 Production Engineering Section CH-EE-004 Procedure for Re-Examination for Re-Mixing Rubber 0 3/21/2016 until termination
Compound
50 Production Engineering Section CH-EE-005 Control Plan STS Hose for Mass Production 0 3/28/2016 until termination