Prince2 Process Model
Prince2 Process Model
PROGRAMME MANAGEMENT
PRINCE2 PROCESS MODEL Corporate advice
Initiation Project Closure
notification and decisions notification
authorization
www.forsa-advies.nl
- Daily Log Prepare the Risk Management Strategy Stage Boundary - Issue Register
- Quality Register
UPDATE
Prepare the Quality Management Strategy Prepare planned - PID
- Project Plan - Business Case
Prepare the Configuration Management Strategy Plan the next stage closure
- Benefits Review Plan - Project Plan
CREATE Prepare the Communication Management Strategy Produce an Exception Plan Prepare premature - Issue Register
- PID Set up the project controls Stage boundary Update the Project Plan CREATE closure - Configuration Item
UPDATE:
- Risk Management Strategy Create the Project Plan approaching Update the Business Case - (next) Stage Plan Hand over products Records
- Project definition
- Quality Management Strategy Report stage end - Product Descriptions - Benefits Review Plan
- Business Case Refine the Business Case Evaluate the project
- Configuration Management Strategy - End Stage Report
- Communication Management Strategy
- Project approach Assemble the Project Initiation Documentation - Lessons Report Recommend project CLOSED
- Project Management closure - Risk Register
- Project controls - Follow-on action
Team Structure recommendations - Issue Register
- Project Plan Stage boundary
- Role descriptions - Exception Plan - Quality Register
- Tailoring of PRINCE2 approaching Project end - Daily Log
- Daily log
- Risk Register approaching - Lessons Log
- Lessons Log
- Quality Register
- Configuration Item Records OBTAIN:
- Issue Register
- Benefits Review Plan
Controlling a Stage - Acceptance Record
Authorize Work Packages Capture and examine issues and risks Take corrective action
Review Work Package status Review the stage status Escalate issues and risks
Legenda Receive completed Work Packages Report highlights
Management products
that need to be updated,
approved, obtained or
submitted New risk Completed
Authority to deliver CREATE UPDATE: - Quality Register Work Package
Newly created products
a Work Package - Work Packages - Stage Plan (current stage) - Work Package
UPDATE- Quality Register - Highlight Report - Configuration Item Records - Lessons Log New issue
- Configuration Item Record(s)
- Team Plan - Issue Report - Risk Register - Issue Report
An event or decision
- Checkpoint Report - Exception Report - Issue Register - Daily Log
triggering another process
or to inform corporate or
DELIVERY
programme management
CREATE
- Team Plan
An activity - Checkpoint Report Managing Product Delivery
APPROVE Accept a Work Package Execute a Work Package Deliver a Work Package
- Work Package
OBTAIN
- Approval records
SUBMIT
PRINCE2 is a registered trade mark of AXELOS. - new issue
Reproduced under licence of AXELOS. (R) 2013-2015, - new risk
Forsa Advies. All rights reserved. QRC-UK 1.3
7 Themes : describe aspects of projectmanagement that must be addressed continually by the Project Manager
en
ity expectations
Im
figure 8.2
Risk cause
tify
figure 7.2 en figure 7.3
Acceptance
criteria Communicate
May result in Risk event
Project Product Quality Quality
Management
Pla
Description components Which may effect Risk effect
Quality
es
Strategy s
As
n
Planning figure 8.4 PRINCE2 is a registered trade mark of AXELOS. Reproduced under
Product Quality criteria licence of AXELOS. 2013-2015, Forsa Advies. All rights reserved.
Descriptions and tolerances www.forsa-advies.nl
PRINCE2 product
based planning
Risk response categories
technique Quality methods Threat responses Opportunity responses The six tolerance areas by level
Quality Avoid Exploit Project level Stage level Work Package Product level
Tolerances areas
responsibilities tolerances tolerances level tolerances tolerances
Reduce (probability and/or impact)
Fallback (reduces impact only) TIME
Quality Register Enhance
Transfer (reduces impact only, and often only the +/- amounts of time on target Project Plan Stage Plan Work Package NA
financial impact) completion dates
Product
PRINCE2 quality Quality COSTS
Project Plan Stage Plan Work Package NA
review technique Share +/- amounts of planned budget
Quality and Control
approval records SCOPE
Accept Reject Permitted variation of the scope
Accceptance records of a project solution, e.g. MoSCoW Project Plan Stage Plan Work Package
figure 8.4 NA
figure 6.1 prioritization of requirements (Must (note 1) (note 1) (note 1)
have, Should have, Could have, Wont
have for now)
CHANGE PROGRESS RISK
Advantage Impact of Limit on the aggregated value of
gained implementation DELEGATING TOLERANCE AND REPORTING
The configuration management procedure Specialist work aligned to technical stages threats (e.g. expected monetary value Risk
ACTUAL AND FORECAST PROGRESS Stage Plan Work Package
typically comprises five core activities:
to remain less than 10% of the plans Management NA
Reduced costs/ (note 2) (note 2)
PROJEC T
budget); and limit on any individual Strategy
planning time/risks Corporate or programme threat (e.g. any threat to operational
identification Cost/duration of management Management stage 1 Management stage 2 Management stage 3 Management stage 4 service)
control More benefits option
status accounting Project QUALITY
verification and audit Risk of option Project progress/
Etc. tolerances exceptions Defining quality targets in terms of Project Product NA NA Product
Specification
ranges, e.g. a product that weighs Description (note 3) (note 3) Description
300 g +/- 10 g
figure 9.2
ISSUE AND CHANGE CONTROL PROCEDURE Project Board
Overall Peripheral BENEFITS
design Detailed design design
Project Board/Change Authority Defining target benefits in terms of
Stage Stage progress/ ranges, e.g. to achieve minimum cost Business Case NA NA NA
Request for advice Request for advice/Exception Report tolerances exceptions savings of 5% per branch, with an
Built facility
Capture Examine Propose Decide Implement average of 7% across all branches