Quality Assurance Checklist (2) : Process Guideline
Quality Assurance Checklist (2) : Process Guideline
QUALITY ASSURANCE
CHECKLIST (2)
FOR HOUSE CONSTRUCTION IN DISASTER-PRONE AREAS FOR
CONTENTS
Page
A INTRODUCTION 2
B PRE-PLANNING 2
D SITE ORGANIZATION 9
G PAINTING WORK 16
I ELECTRICAL WORK 25
This document is intended mostly to help building Health and safety are factors that must be pursued with as
contractors and site supervisors to maintain reliable much vigour as other management objectives. Ensuring the
standards in order to ensure that the final product would be well-being and safety of all workers or visitors at
of durable quality. It is hoped that users of this information construction sites will improve performance; minimize
will contribute to the construction of houses that will accidents and illness which in turn will reduce disruption of
successfully withstand any adverse weather and even work as well as consequent expenses.
disasters such as cyclones, floods and earthquakes. By
carefully implementing the guidelines provided in this The following checklist is prepared so that building
document, users of this information who are engaged in the contractors and supervisors can make sure that essential
construction process will enhance their abilities and steps are taken to ensure maintenance of quality control
reputation in addition to ensuring that occupants of the throughout the building process.
buildings would be satisfied with the buildings performance
after occupation. This document has been prepared also to Note: In checking out the Yes/No response to each
serve the interests of persons who would occupy the question, it is important that if the answer is No, follow-up
houses constructed and those financing the construction corrective action is needed.
as stakeholders who must be concerned about achieving
quality in the final product. B: PRE-PLANNING
PLANNING AND SITE ORGANIZATION PRELIMINARY ASSESSMENT OF PROJECT
Careful forethought and planning are required for sound Have you?
site organization. Consideration must be given to the
efficient use of available space at the site during building Carefully studied the architectural and structural
operations in order to ensure that all building activities move drawings
smoothly with minimal interference or delay. The proper Yes __ No __
choice of suppliers and subcontractors plays an
important part in achieving desired quality and efficiency.
Carefully studied the terms of the contract, the To determine personnel requirements:
Specifications and Bill of Quantities BOQ* (* i.e. list of
materials with corresponding quantities required for Have you?
work items)
Drawn up a schedule of personnel required for carrying
Yes __ No __ out the project to completion (See specimen schedule of
Noted any discrepancies or items that are not clear to personnel annexed)
you in the architectural and structural drawings, Yes __ No __
Specifications and BOQ
Yes __ No __ DETERMINE TIME FRAME FOR COMPLETING
PROJECT
Requested clarification on items unclear to you in
drawings and other documentation from the architect Have you?
and engineer and client.
Checked the Bar Chart s time periods for completing
Yes __ No __
each activity in sequence, taking into account holidays,
Made sure that information provided in the drawings and inclement weather and other common factors that cause
other documentation is adequate, also that the terms of delays and determined the feasibility of completing work
the contract are acceptable for proceeding with on schedule
preparatory work for construction at the proposed site
Yes __ No __
Yes __ No __
CHOOSING SUPPLIERS AND PURCHASING
Prepared a Bar Chart (See specimen bar chart
MATERIALS
annexed) that lists the sequence of building activities
with corresponding time periods for completing each
Quality and conformity to the specifications should be the
activity, taking into account holidays, inclement weather
primary consideration and not the cheapest price when
and other factors that are likely to cause delays.
choosing suppliers and materials.
Yes __ No __
Whenever and whatever the contractor aims to purchase, s/he
DETERMINE REQUIREMENTS should aim to buy:
PLANT/EQUIPMENT, MATERIALS, AND PERSONNEL
the right quality
To determine plant/equipment and materials requirements:
at the right time
Have you? the right quantity
from the right source
Studied the plans and specifications in relation to the
phases of construction shown in the Bar Chart at the right price
Yes __ No __
Have you?
Double checked the accuracy of the Bill of Quantities
Made sure that an experienced and knowledgeable
Yes __ No __
purchasing officer has personally visited the premises of
Listed the materials required at each successive stage the suppliers and has established the reliability of each
of construction (See specimen materials schedule supplier and the quantity of the materials that are to be
annexed) purchased from them
Yes __ No __ Yes __ No __
Established the time limits for commencing and Have you briefed the chosen supervisor thoroughly on
completing the elements in the subcontract work, all aspects of his/her responsibilities
based on the general programme, and commitment to
Yes __ No __
complete work on schedule, as well as the penalty to
be imposed due to delay in completion Explained clearly the time frames set for each item and
phase of work
Yes __ No __
Yes __ No __
Arranged for supervisors by the client or clients
representative Have you clearly explained the terms of engagement
and obtained the supervisors agreement to the stated
Yes __ No __
terms
Made sure that worker safety and welfare arrangements
Yes __ No __
are satisfactory
Yes __ No __ C : HEALTH AND SAFETY AT THE WORK
Obtained agreement on the subcontractors liability for SITE
damages to third parties and insurance cover
The physical well being and safety of workers on site as well
Yes __ No __ as safety of visitors to the site should be of primary concern to
the contractor and implementation of a project. An accident
OVERSIGHT OF DIRECT LABOUR* (*Labour prevention programme should be established to minimize the
employed directly by the main contractor or number of accidents that can happen on a building site. All
house owner) workers should be briefed on safety standards and
measures to be taken to handle accidents. Good
Have you?
housekeeping on a construction site is very important if
accidents are to be avoided. Good housekeeping on a
Given a clear description of the work to be done,
construction site includes the following:
including the work of making good the work of previous
trades*(*construction work items done by others earlier)
1. Keeping the site tidy
that have been affected by the work of the workmen
2. Quickly clearing away debris that can be hazardous to
Yes __ No __
persons moving around the site
Made clear the terms and conditions of engagement
3. Removing nails from used timbers
Yes __ No __
4. Making sure that nails, broken glass and other harmful
Established time/s to start work items and time limits for objects are not left lying around
completion of work
5. Making sure that each worker is personally responsible
Yes __ No __ to clean-up as well as make good whenever needed
after an item of work is completed.
SITE SUPERVISION
6. Making sure that live power lines with unprotected joints
Have you? and exposed wires are not allowed to be used or left
exposed in a way that may cause harm to persons
Chosen and appointed an experienced and 7. Making sure that materials are stacked in a manner that
competent supervisor to oversee the work done by would not cause harm to persons
personnel who are to carry out all types of building
activity on the site 8. Making sure that any live flames are not left untended if
they are used at all for a purpose
Yes __ No __
9. Making sure that pits or excavations are clearly Make sure that protective gear and equipment are
identified and protected so as not to cause injury to used such as gloves, eye shields for welders, safety
people by using marking tape, danger signs or red flags helmets, safety belts, face masks etc.
as appropriate
Make certain that workers at site are given clear and
10. Making sure that plastic or polythene sheets are not specific instructions on proper posture when lifting
used as temporary floor covering in locations especially heavy items and methods of moving and handling
where ladders are used because such coverings are too materials (See Manual Handling of Materials and
slippery and dangerous Equipment 1 & 2).
11. Making sure edges of covering material on the floor are
well tucked in so as not to cause persons to trip Advanced foot &hand
Slipped disc
Hold load close to
body
Body weight
+ Hernia
Poor balance
+ Arm well down
Object weight
=
Effect
Excessive
Muscular effort
Manual Handling of Material & Equipment -1 Position of Arms when carrying object
application of a scientific method of handling and lifting collection of water within or very near the proposed
material known as human kinetics. Human kinetics makes building area during and after construction is completed
the most efficient use of the body and limbs as levers and a
Yes __ No __
source of power without the need for use of brute force.
Efficient use of the body requires taking care to adjust and LOCATING OF SERVICES ON SITE
position the body before manually handling or lifting objects
(See Manual Handling of Material & Equipment 1 & 2). Have you located on site the following?
The Basic principles of manual handling Area for storage of cement, aggregate, sand, timber,
steel, bricks, stones
Obtain a proper hold of the item being handled
Yes __ No __
Maintain a straight back
Concrete mixer and concrete mixing platform
Position the feet correctly for balance
Yes __ No __
Make powerful use of leg muscles and body weight
Lock-up store for equipment and tools with necessary
Responsibility of supervisors and training racks, bins etc.
Yes __ No __
Supervisors must ensure that safe handling practices are
used by the staff at all times as well as making sure that the Steel bending bench
staff are coached or trained in adopting safe handling Yes __ No __
practices. When loads are too heavy for reasonable manual
handling mechanical devices must be used. Workers should Temporary toilet/s for workers (if no off site toilet is
not be asked to handle items that are too heavy or to carry available)
heavy loads over any distance. Yes __ No __
Proper training can only be given by practical demonstration A place where a First Aid kit can be accessible to all
and supervised practice using material encountered on the workers on site
job. All members of the staff must be given needed training. Yes __ No __
A site office with racks for documents and basic furniture
D : SITE ORGANIZATION
Yes __ No __
PREPARATION OF THE SITE
Have you?
Fig 3
Have you? Used the centre lines to establish the side limits of
excavations for wall foundations as per
Established centre lines of principle walls and architectural/structural drawings (See fig. 4)
identified these with pegs and chords (See fig. 4)
Yes __ No __
Yes __ No __
Fig 5 -Foundation
Trenches
ade sure that the masons, working stone and brick work,
have followed the guidelines listed in the above-named
Quality Assurance Checklist 1)
Yes __ No __
Made sure that plasterers and tilers have properly
followed the guidelines listed in the above-named
Quality Assurance Checklist 1)
Yes __ No __
Ring beams and other beams in superstructure Made sure that door and window or other openings on
Yes __ No __ external walls are positioned at least 2 0away from
corners of walls or other adjacent openings. This
Floor slabs
requirement applies in all buildings located in
Yes __ No __ disaster-prone areas (See Fig. 10)
Yes __ No __
Fig 9- Positioning door openings The reason for preserving and finishing timber
CARPENTRY WORK (Refer also Quality Assurance 1. T. O. (Tar oils) of which the best known is creosote
Checklist 1) 2. O. S. (Organic Solvent), with dissolved chemicals
3. W. B. (Water Borne), which consists of salts dissolved in
Have you?
water, giving it a toxic solution free of deposit.
Made sure that the carpenters, roofers, and joiners have
Organic solvent types are very effective for the treatment of
properly followed the guidelines for fabrication and fitting
decay and insect attack, having good penetrating properties.
doors and windows and timber framed roofs listed and
Water borne types are often used for pressure treatment of
illustrated in the above-mentioned Quality Assurance
timber and this type can be used internally and externally,
Checklist 1.
although some tend to leach away when soaked with water.
Yes __ No __
The application of preservatives to timber in conditions 4. Paint on one or two layers of undercoat. Apply the
where highly complex pressure and vacuum treatments are undercoat evenly to the surfaces, brushing out the paint
not easily available, Steeping is the best practice for practical to avoid any runs.
purposes; this involves submerging the timber in cold
5. When the undercoat is dry, rub down the surface with
preservative for periods varying from a few days to a few
fine-grade sandpaper.
weeks. Small section timber will require only a few hours, but
the longer the treatment the greater the penetration. 6. Wipe clean the sanded surface and brush on the top
Dipping consists of submerging the timber in a bath of coat. Allow the paint to dry in as dust-free conditions as
preservative small items for a period of 10 seconds, to a possible.
minimum of 3 minutes for structural timber.
Varnishing and Staining wood
Brushing-on or using a coarse spray is the least effective
method. It is the only way of treating timber after it has been Varnishes give coatings as durable as oil-based paints, and
installed or fitted. Understandably not all surfaces of the are available in matt, satin, and gloss finishes. Pigmentation
timber would be exposed to receive the preservative. changes the colour of wood. Staining produces a more
However, a good measure of protection can be given to the effective tone than varnishing. The procedure for varnishing
timber if the application of preservative is carried out carefully and staining wood is as follows:
using plenty of preservative.
1. Prepare the wood for vanishing (See preparation of
Any timber that is cut after the preservative has been timber for finishing)
applied should have all the new exposed surfaces 2. Sand and fill to create a smooth surface.
liberally treated before the timber is covered or installed.
3. Brush away the dust and wipe the surface with a lint-
Even when timber is to be painted, it is important that the free cloth dampened with white spirit.
timber be treated prior to painting. 4. Rub in the varnish with a lint-free cloth by dabbing the
varnish into the surface of the wood, working in the
The preparation of timber for finishing direction of the grain.
Any sand papering should be done in the direction of the 5. Allow the first coat of varnish to dry for up to 12 hours,
grain. The grade of paper should be varied from medium to depending on the temperature and the type of coating.
fine as the surface is gradually cut down to become shiny and 6. Lightly rub the surface with sandpaper.
clean (totally clear of dust)
7. Remove the dust by cleaning the surface with a dusting
The normal method of painting timber brush and remove any remaining dust with a lint-free
cloth dampened in white spirit.
The painting process, whether it is to be a gloss or matt finish,
8. Follow the manufacturers instructions; apply each coat
can be divided into six stages:
with a clean brush. Rub the surface lightly after each
coat of varnish has dried.
1. Lightly sand any rough edges or surfaces on new wood.
Remove dust by wiping the sanded areas with a lint-free
Linseed oil finish
cloth dampened in white spirit. Knots in wood can be
sealed with shellac or knotting. 1. Lightly sand the surface of timber using No. 100 sand
2. When the knotting is completely dry, apply a wood paper, thereafter with 120 sand paper
primer. Brush the primer well into the wood and allow to 2. Dip a rag (folded into a small compact bundle) in linseed
dry. oil and apply evenly on the timber surface (a brush may
3. Smooth the surface by rubbing lightly with fine be used instead of a rag). A suitable stain can be mixed
sandpaper.
in with the linseed oil to obtain the desired colour. This Qualities: Difficult to saw when fresh. Seasons well if
may be repeated to obtain the desired colour converted green. Logs tend to split at ends if left unconverted.
Very durable especially in contact with water.
3. Allow time for the linseed oil to dry in a dust-free
environment Hora
Do not use varnish on surfaces of woodwork that are The painting process
expose to the sun as varnish soon burns and fades in
sunlight. Paint one room at a time
Smooth and dry all surfaces to be painted and clean the
Always use good quality paints and brushes to obtain a
room of all debris and dust
quality finish.
Start first with the ceiling. Time it so one whole surface
Choosing a painting tool :The use of brush or roller for can be finished in one operation. Start from the light
painting is optional for water based paints. A good roller will source and work away from it in order to clearly see
usually cut the time it takes to paint a room, giving it a more what is and what is not painted.
finished result with less effort than a brush. The use of a roller
Next paint the walls.
to paint is a recommended alternative. A roller tray (metallic
preferred to plastic) is needed for use with a roller, also a Finally paint the woodwork.
roller pole that can be extended for painting ceilings. Brushes If painting over an existing dark coloured surface, two
of smaller sizes are needed for painting recessed surfaces undercoats may be needed before applying the top
and rebates that cannot be painted easily with a roller. Never coat.
use rollers for oil-based paints.
Painting walls
Care of tools
When painting walls with a roller or brush paint in
Rollers: Always thoroughly wash roller and roller trays after blocks. Work from right to left if you are right handed or
use with water based paints. Flick the roller sharply out-of- vice versa if left handed. When using a brush, work in
doors until no more water sprays from the surface. Then peg horizontal strips beginning parallel with the ceiling and
the roller on a line and leave to dry for a few hours. Keep the moving downwards.
roller in a bag that will prevent it from getting dusty.
Start the first bay (top corner) moving horizontally
Brushes: When using oil based paints, such as gloss or towards the opposite corner, applying paint as in the
undercoat, wash the brush in a suitable cleaning liquid previous bay.
(turpentine or thinner). Do not allow paint to dry on a brush Blend each new section with the previous one by lightly
after it is used. Clean it soon after it is used. This practice will working back towards it when laying-off. Always work
ensure longer use of the brush. Flick the brush sharply out-of- new into old to avoid marking the drying paint.
doors until no water sprays off the bristles. Dry the brush with
waste cloth or rag. Store brushes by hanging them upside Continue in this manner across the surface to the end,
down from a hook with the bristles effectively kept free from and then begin a new row of bays below the first.
dust. Continue this process for succeeding rows of bays.
Dont go back to areas that have been completed, as
Use of tools the drying paint will no longer be workable and will be
easily damaged.
Before using a new brush soak it thoroughly in cold water.
With the brush still wet take it to a dry, rough wall surface or Painting exterior surfaces
corner of a wall and flick the brush back and forth until the
brush is quite dry. Repeat this process of wetting and drying When painting exteriors, follow the sun. Allow it to dry
the brush to shed any loose bristles. and warm the surface and then proceed to paint in the
shade.
Load the brush by dipping the tips of the bristles into the paint.
Do not allow the paint to reach the upper part of the brush. Painting with a brush (See Painting Basics 1 & 2)
Dab off excess paint by pushing the bristles against the inside
of the paint container to prevent dripping when applying.
Painting basics 2
H : PLUMBING AND SEWERAGE WORK Made sure that all pipe joints are fitted as per
manufacturers instructions so as to be leak-free
PLUMBING AND SEWERAGE (See Section
Yes __ No __
Standard Requirements for Plumbing and
Sewerage Works) Made that ends of PVC pipe surfaces for joining are free
from grease and dust before application of solvent prior
Have you? to joining pipes.
Yes __ No __
Chosen a qualified and experienced plumber to carry
out the plumbing work needed for the building Made sure that a period of two hours is allowed before
pressure testing is done on non-threaded PVC pipes
Yes __ No __
that have been joined by solvent
Issued the needed drawings and specifications to the
Yes __ No __
plumber and clearly explained what is required for
carrying out the plumbing work Made sure, when joining threaded PVC pipes that a thin
layer of thread-sealing tape is wrapped around the
Yes __ No __
external thread and screwed completely (not
Made sure that the PVC pipes used for plumbing and excessively) into the internally threaded pipe.
sewerage are new, of good quality, without defects or
Yes __ No __
deformities and manufactured by reputed
manufacturers. Made sure that rodding eyes have been provided at
bends and branches according to standard plumbing
Yes __ No __
requirements.
Made sure that PVC pipes are stored and stacked in a
Yes __ No __
manner that will protect them from damage and
exposure to sunlight. Made sure that standards for connecting waste lines to
stacks are followed (See Plumbing Basics 1 & 3)
Yes __ No __
Yes __ No __
Made sure that toilet fixtures are positioned to allow
space for movement around and between them (See Made sure that wash basins, showers/baths and sinks
Plumbing Basics 1) or other fixtures are fitted with correctly sized waste
lines and depths of water seal traps (See Plumbing
Yes __ No __
basics 3)
Made sure toilet fixtures such as wash basins, showers,
Yes __ No __
sinks, taps, water closets etc. are fitted at the specified
heights (See Plumbing Basics 2). Where provision is Made sure that PVC pipes that penetrate masonry or
required for disabled users; have the positions and concrete external walls are placed within a steel pipe
heights for such items been adjusted accordingly with two rubber sealing rings to prevent entry of water
(See Basic Dimensional Information for Wheelchair into the building (See Plumbing Basics 2)
Users 2)
Yes __ No __
Made sure that the flushing systems in water closets
Made sure that joints for pipes (plumbing and
operate efficiently
sewerage) are not made within walls all joints are
Yes __ No __ fitted externally
Made sure that valves, meters and taps used are new Yes __ No __
and of good quality
Yes __ No __
Made sure that all the above-ground pipes are secured Made sure that the standard gradients for below-ground
against axial thrust by using correctly sized fixing pipes are strictly followed when they are laid
clamps where pipes change direction
Yes __ No __
Yes __ No __
Made sure that proper bedding method is used for
Made sure that pipe clamps are used as supports at a below-ground pipes especially in soft soils, and standard
distance of ten (10) times the pipe diameter. lean concrete bedding in stable soils as specified (See
Plumbing basics 4)
Yes __ No __
Yes __ No __
Made sure that water seal traps are provided in
drainage systems and water seals retain a minimum Made sure that below ground pipes are well supported
seal under test and working conditions for each at joints, bends and junctions by providing suitable
appliance (See Plumbing Basics 3) supports and abutments (See Plumbing basics 4)
Yes __ No __ Yes __ No __
Made sure that ventilation is provided where needed to Made sure, when laying pipes in steep terrain, that
effectively maintain water seal of traps installed in the pipes be secured against sliding off by providing
building correctly positioned supports and that pipes are laid with
the sockets facing upwards (See Plumbing Basics 4)
Yes __ No __
Yes __ No __
Made sure that branch pipes to the stack are positioned
to prevent backpressure and blocks from occurring (See Made sure that soil that surrounds buried pipes are free
Plumbing Basics 1 & 3) of stones or other material that may cause damage to
the pipes
Yes __ No __
Yes __ No __
Made sure that branch discharge pipes are fully
accessible for clearing blockages Tested all sections of below-ground pipes for water
tightness by pressure testing before these are covered
Yes __ No __
Yes __ No __
Made sure that below-ground plumbing and sewerage
pipes are laid at the required depth as per standard Made sure, before pressure testing of pipes, that buried
regulations. pipes are covered with backfill to approximately 2 9
leaving uncovered space of 6 around joints and
Yes __ No __
junctions in order to load the pipes sufficiently
Made sure that the drain invert depth and radius
Yes __ No __
conforms to plumbing standards (See Plumbing Basics
3) Made sure that invert levels of manholes are as
specified in order to make sure that the sewerage
Yes __ No __
disposal works efficiently
Made sure that below-ground soil and drainage pipes
Yes __ No __
are not positioned too close to water supply pipelines
Made sure that the spacing of manholes are according
Yes __ No __
to standard regulations and drawings and specifications
Made sure that water pipelines are laid as remote as
Yes __ No __
possible from electrical cables, gas, waste water and
sewerage lines in conformity with local regulations Made sure that the septic tank is constructed strictly in
accordance with the given drawings and specifications
Yes __ No __
(sizes and depths) of chambers
Plumbing Basics 3
Plumbing Basics 2
Plumbing and sewerage pipelines shall be supported HELPFUL RULES OF THUMB IN PLUMBING DESIGN
and protected as per the manufacturers instructions as AND PLANNING
approved by the local authority.
At planning stage locate the appropriate manhole or
Pipes carrying off waste from water closets and waste
sewer outfall on the site plan in locations where there is
water from baths, wash basins and sinks to drains shall
a public sewerage system
be trapped immediately beneath such fixtures. Traps
shall have a minimum water seal of 2 (See Plumbing Where sewerage has to be handled within the site,
basics 3) and shall be ventilated wherever such determine invert levels of manholes and septic tanks.
ventilation is necessary to maintain water seal of the Septic tanks should be installed at depths that are
trap. Ventilating pipes shall be carried up vertically from clear of ground water table levels
the drain to a height of 2 0 above the outer covering
GENERAL
Yes __ No __
The circuit plan shall have branch circuits that serve
Checked if the following tests have been done easily defined areas or purposes. Each branch circuit
satisfactorily: should not be overloaded. Some heavy voltage
appliances may need dedicated circuits for themselves.
Insulation Resistance Test Yes __ No __
Earth Continuity Test Yes __ No __ PROTECTION OF CABLES
floor slabs and shall be mechanically continuous and The fan shall be positioned at a height that is in
watertight so that cables are fully protected. No conduit accordance with local regulations
smaller than (19mm)shall be used.
The down rod shall be of adequate mechanical strength
Cables buried in concrete shall have at least 1 3/8 and the internal diameter shall not be less than 5/8 (16
(35mm) depth of cover over its entire length. mm).
Conduits buried in plaster shall have at least 3/16 (
INSTALLATION OF ACCESSORIES
5mm) depth of cover throughout its entire length.
Below ground cables have to be laid at depths All switches, bell pushes and fan regulators shall be
designated by the local authority and excavations for fitted at a minimum height of 4 0 (1200mm) above
buried cables should be identified with marker tapes at finished floor level, unless otherwise specified in the
require depths. design (Provision for disabled persons to access
switches etc. would require height adjustments)
INSTALLATION OF CONDUITS AND CABLES
Switches for toilets and bathrooms shall be installed
outside the room and immediately adjacent to the
The conduits shall be fitted and completed before any
normal access door of the room, or a switch can be of a
cables are drawn in. Surface mounted conduits shall be
type operated by an insulated chord.
securely fitted to wall and ceiling surfaces.
All socket outlets except in a toilet, or kitchen shall be
No conduit smaller than (20mm) in diameter shall be
mounted at a minimum height of 6 (150mm) above
used as per standard regulations
finished floor level. Socket outlets in kitchens shall be
Conduits in floor slabs or columns shall be inspected mounted at a minimum height of 6(150mm) above
and approved before pouring of concrete or otherwise kitchen counter level unless otherwise specified.
covering up.
All socket outlets shall be of the shuttered type.
All cables and conductors used as fixed wiring shall be
In a room where a shower or fixed bath is installed, only
supported so that they are not exposed to undue stress.
a shaver socket is permitted to be installed.
Unbroken runs of conductors shall be used. Joints
All ceiling fans shall be fitted at a height where an
shall not be permitted in wiring between power control
average person with raised hands will not be able to
sources (Control switch or main switch) and any outlet
touch the blades of the fan.
point, light fixture, fan, etc.
All lamps with metal parts shall be earthed.
Diagonal runs of power cables shall not be permitted.
All branches shall be taken at right angles. Cables All cables should be PVC/PVC/Cu except earth wire
shall be kept clear of hot water or steam pipes etc. which could be PVC/Cu
During construction, where conduit is buried in the Cable description:
carcass of a building or in the ground, all open ends
PVC/PVC = PVC sheathed cables with copper
shall be temporarily plugged to prevent ingress of
conductor
foreign matter, moisture or water
PVC/Cu = PVC insulated copper conductor. E.g.
INSTALLATION OF CEILING FANS Earth cables
Lamps with fan circuits and 5 Amp socket outlets shall
The terminal block on the fan as well as the capacities
be with 1/1.13 cables and 7/0 67
shall be provided with removable covers
The fan hook shall be of adequate mechanical strength SUB CIRCUIT ARRANGEMENT
and the internal diameter shall not be less than 5/8
(16mm).
Circuit Type Number of points per MCB Made sure that stairs and ramps have adequate lighting
circuit rating
Yes __ No __
Lamp, fan, bell/s 08 06 A Made sure that the treads of stairs are not less than 12
(300 mm) wide
5 Amp socket outlet 02 10 A
Yes __ No __
15 Amp socket outlet 01 16 A Made sure that floor finishes in toilets are slip resistant
Have you?
Yes __ No __
Made sure that sizes and slope of access ramps
conform to standard specifications
Yes __ No __
Made sure that handrails are provided on both sides of
stairs
Yes __ No __
Made sure that stairs do not have open risers
Yes __ No __
Made sure that handrails at stairs and ramps extend
beyond the top and bottom ends.
Yes __ No __
Made sure that risers and treads in stairs are
consistently sized
Yes __ No __
Basic Dimensional Information For Wheelchair Made sure that heights of electrical switches and socket
User Access 2 outlets have been positioned for easy access by
wheelchair users
Yes __ No __
Made sure that grip bars have been provided in toilets
and bathrooms to enable disabled persons to use
facilities with ease
Yes __ No __
Provided handrails at the approved height along ramps
that are unprotected
Yes __ No __
Made sure that ramp and landing surfaces are slip-
resistant
Yes __ No __
Provided suitable barriers under stairways or other
protruding obstructions that persons with impaired vision
may not be aware of
Yes __ No __
Information sources:
Made sure that adequate clearance is allowed around
beds in bedrooms used by wheelchair users
Building and Social Housing Foundation (B+SHF) A
Yes __ No __ Practical Guide to the Construction of Low Cost Typhoon-
Resistant Housing. Building and Social Housing Foundation,
Made sure that adequate clearance is allowed around
UK, 1983
toilet fixtures for wheelchair users
Yes __ No __ Coburn A. Hughes R, Pomonis A, Spence R, - Technical
Principles of Building for Safety Intermediate technology
Made sure that all doorways and passageways are of
Publications, UK, 1995
adequate width to enable disabled persons using
wheelchairs to pass through comfortably
Yes __ No __
Annex 1
PROJECT REFERENCE
MATERIAL BREAKDOWN
Materials Nos. Bags Cubes Bars Kgs. L/ft Unit rate Total cost Due date
Rubble 8
Sand 3
Metal 3/4"
FOUNDATION
2
Cement 41
10mm bars 22
6mm bars 25
Bricks 400
Binding Wire 2
Bricks 1300
PLINTH - ROOF SOFFIT
Cement 35
Sand 3
Metal 3/4" 0
10mm bars 30
6mm bars 15
Binding Wire 1
1/2' Conduit pipes 15
Cement 50
Sand 2.5
FILLER SLAB ROOF
Metal 3/4" 3
12mm bars 2
10mm bars 65
8mm bars 40
6mm bars 5
Binding Wire 3
Rejcted calicut tiles 750
4"x 2" hard wood
2"x 1" hard wood
CALICUT TILE ROOF
1.5
Sand 2
Bricks 1000
Coloured cement 2
Cement 20
Sand 1
White cement 5
FINISHES
ITEM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1. Clearing site
2. Excavate top soil
3. Exc. Foundation
4. Steel to fdns.
5. Formwork to fdns.
6. Concrete to fdns.
7. Steel to columns
8. Formwk. To columns
9. Conc. to columns
10. Masonry to g/floor
11.Formwk.- plinth beam
12. Steel to plinth beam
13. Conc. To plith beam
14. Return fill & Ram
15. Hardcore fill
16. DPC & DPM
17. Bk. Wk.to floor
18. Masonry above floor
19. Formwk. to ring beam
20. Steel to ring beam
21. Concrete to ring beam
22. Fabricate roof trusses
23. Fix roof truss
24. Fix roof timber frame
25. Place roof tiles/sheets
26. Timber to gable ends
27. Form eaves
28. Fix ceiling boards
29. Floor finish
30. Fix door frames *
MATERIAL BREAKDOWN
Description Materials Nos. Bags Cubes Bars Kgs. Meters. Unit Total Due
Rate Cost date
FOUNDATION rubble 0 0 0
TO PLINTH sand 0 0 0
metal - 3/4'' 0 0 0
cement 0 0 0
10mm 0 0 0
6mm 0 0 0
bricks 0 0 0
binding wire 0 0 0
FROM PLINTH bricks 0 0 0
TO ROOF cement 0 0 0
SOFFIT sand 0 0 0
metal - 3/4" 0 0 0
10mm steel 0 0 0
6mm steel 0 0 0
binding wire 0 0 0
conduit 0 0 0
FILLER SLAB cement 0 0 0
ROOF sand 0 0 0
metal- 3/4'' 0 0 0
12mm steel 0 0 0
10mm steel 0 0 0
8mm steel 0 0 0
6mm steel 0 0 0
binding wire 0 0 0
CALICUT TILE 4"x2" hard wood 0 0 0
ROOF 2"x1" hard wood 0 0 0
(alternative) 2"x5" hard wood 0 0 0
MATERIAL BREAKDOWN
Description Materials Nos. Bags Cubes Bars Kgs. Meters. Unit Total Due
date
Rate Cost
3"x4" hard wood 0 0 0
8"x1" hard wood 0 0 0
roof tiles 0 0 0
ridge tiles 0 0 0
nails 0 0 0
FLOORING cement 0 0 0
metal - 1 1/2" 0 0 0
sand 0 0 0
bricks 0 0 0
black cement 0 0 0
FINISHING cement 0 0 0
sand 0 0 0
white cement 0 0 0
red cement 0 0 0
yellow cement 0 0 0
lime 0 0 0
2"x2"weld mesh 0 0 0
Process guideline
Practical Action Quality Assurance Checklist (2) Process guidelines
WORKMEN
Steel fixers 2 2 2 2 2 2
Concrete gang 3 3 2 2 3 3
Carpenters 2 2 2 2 2 2 4 4 4 4 4 4 4 2
Masons 3 3 2 2
Plasterer 2 2
Painters 4 4
Labourers 6 4 2 2 1 3 2 2 1 Supervsor - 20 weeks
Week Number 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
36