Construction Work Program Sample Ms Project

This document contains a Gantt chart that outlines the tasks, durations, start dates and finish dates for a construction project to build accommodation blocks over 122.75 days from March 28, 2013 to August 9, 2013. Key tasks included mobilization, substructure work like excavation and concrete pouring, wall and frame construction, roofing, installation of windows and doors, mechanical and electrical installations, plastering, ceiling, flooring, painting, site cleaning and handover.

Uploaded by

Mwesigwa Daniel
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views

Construction Work Program Sample Ms Project

This document contains a Gantt chart that outlines the tasks, durations, start dates and finish dates for a construction project to build accommodation blocks over 122.75 days from March 28, 2013 to August 9, 2013. Key tasks included mobilization, substructure work like excavation and concrete pouring, wall and frame construction, roofing, installation of windows and doors, mechanical and electrical installations, plastering, ceiling, flooring, painting, site cleaning and handover.

Uploaded by

Mwesigwa Daniel
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start Finish

k -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20
T T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S
0 SCLBH-ACCOMODATION BLOCK 122.75 Thu 3/28/13 Fri 8/9/13
days

1 MOBILISATION 2 days Thu 3/28/13 Fri 3/29/13

2 Mobilisation and site clearance 2 days Thu 3/28/13 Fri 3/29/13 Mobilisation and site clearance

3 SUBSTRUCTURE 26.56 days Thu 3/28/13 Thu 4/25/13

4 Trench excavation 5 days Thu 3/28/13 Tue 4/2/13 Trench excavation

5 Strip Concreting 2 days Tue 4/2/13 Thu 4/4/13 Strip Concreting

6 Plith Walling 5 days Mon 4/8/13 Fri 4/12/13 plinth Walling

7 Back and Murrum filling 4 days Fri 4/12/13 Wed 4/17/13 Murrum filling and compaction

8 Hardcore placement 4 days Wed 4/17/13 Mon 4/22/13 Hardcore placement

9 Blinding and laying DPM & Slab formwork 1 day Mon 4/22/13 Tue 4/23/13 Blinding & DPM & Slab formwork

10 Casting slab concrete 3 days Tue 4/23/13 Thu 4/25/13 Concrete slab casting

11 WALLING AND FRAME 22.13 days Tue 4/30/13 Thu 5/23/13

12 General walling 15 days Tue 4/30/13 Thu 5/16/13 General Walling

13 Beam steel work 5 days Mon 5/6/13 Fri 5/10/13 Beam steel work

14 Beam form work 4 days Thu 5/9/13 Mon 5/13/13 Beam form work

15 Casting beam concrete 4 days Mon 5/13/13 Fri 5/17/13 Casting beam Concrete

16 walling above beam 3 days Tue 5/21/13 Thu 5/23/13 Walling above beam

17 ROOF CONSTRUCTION 21 days Thu 5/16/13 Fri 6/7/13

18 Roofing 21 days Thu 5/16/13 Fri 6/7/13 Roofing

19 WINDOWS AND DOORS 32.63 days Tue 4/30/13 Tue 6/4/13

20 Fabrication of windows abd doors 21 days Tue 4/30/13 Wed 5/22/13 Fabrication of windows and doors

21 Fitting Windows 4 days Mon 5/27/13 Thu 5/30/13 Fitting Windows

22 Fitting Doors 5 days Thu 5/30/13 Tue 6/4/13 Fitting Doors

23 MECHANICAL INSTALLATIONS 86.06 days Tue 4/16/13 Thu 7/18/13

24 Plumbing & mechanical installations 20 days Tue 4/16/13 Wed 7/17/13 Plumbing & mech Installations

25 Electrical installations 9.56 days Fri 5/31/13 Thu 7/18/13 Electrical Installations

26 PLASTERING 8 days Fri 6/7/13 Mon 6/17/13

27 Internal plaster 8 days Fri 6/7/13 Mon 6/17/13 Internal plaster

28 External finishes 4 days Wed 6/12/13 Sat 6/15/13 External finishes

29 CEILING 20 days Mon 6/17/13 Tue 7/9/13

30 Ceiling timber framing & fixing boards 20 days Mon 6/17/13 Tue 7/9/13 Ceiling timber framing

31 Floor 5 days Tue 7/9/13 Sat 7/13/13 Floor Screeding

32 Painting 21 days Sat 7/13/13 Tue 8/6/13 Painting

33 SITE CLEANING 2 days Tue 8/6/13 Thu 8/8/13 SITE CLEANING

34 HAND OVER 1 day Thu 8/8/13 Fri 8/9/13 HAND OVER

Project: SCLBH-ACCOMODATION BL Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline
Date: Fri 4/12/13