Construction Work Program Sample Ms Project
Construction Work Program Sample Ms Project
k -1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19 Week 20
T T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S SMT T F S
0 SCLBH-ACCOMODATION BLOCK 122.75 Thu 3/28/13 Fri 8/9/13
days
2 Mobilisation and site clearance 2 days Thu 3/28/13 Fri 3/29/13 Mobilisation and site clearance
7 Back and Murrum filling 4 days Fri 4/12/13 Wed 4/17/13 Murrum filling and compaction
9 Blinding and laying DPM & Slab formwork 1 day Mon 4/22/13 Tue 4/23/13 Blinding & DPM & Slab formwork
10 Casting slab concrete 3 days Tue 4/23/13 Thu 4/25/13 Concrete slab casting
13 Beam steel work 5 days Mon 5/6/13 Fri 5/10/13 Beam steel work
14 Beam form work 4 days Thu 5/9/13 Mon 5/13/13 Beam form work
15 Casting beam concrete 4 days Mon 5/13/13 Fri 5/17/13 Casting beam Concrete
16 walling above beam 3 days Tue 5/21/13 Thu 5/23/13 Walling above beam
20 Fabrication of windows abd doors 21 days Tue 4/30/13 Wed 5/22/13 Fabrication of windows and doors
24 Plumbing & mechanical installations 20 days Tue 4/16/13 Wed 7/17/13 Plumbing & mech Installations
25 Electrical installations 9.56 days Fri 5/31/13 Thu 7/18/13 Electrical Installations
30 Ceiling timber framing & fixing boards 20 days Mon 6/17/13 Tue 7/9/13 Ceiling timber framing
Project: SCLBH-ACCOMODATION BL Task Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary Group By Summary Deadline
Date: Fri 4/12/13
Page 1