Project: 2 Storey Residential: Site Preparation

This document outlines the tasks and schedule for a 2 storey residential construction project. It includes site preparation such as clearing, fencing and utilities installation. It then details the excavation, concrete works, steel reinforcement, masonry, carpentry, plumbing, electrical, roofing, finishing and project turnover. A Gantt chart is provided showing the tasks, predecessors, duration and costs.

Uploaded by

Neil Steven Tan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views

Project: 2 Storey Residential: Site Preparation

This document outlines the tasks and schedule for a 2 storey residential construction project. It includes site preparation such as clearing, fencing and utilities installation. It then details the excavation, concrete works, steel reinforcement, masonry, carpentry, plumbing, electrical, roofing, finishing and project turnover. A Gantt chart is provided showing the tasks, predecessors, duration and costs.

Uploaded by

Neil Steven Tan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

PROJECT: 2 STOREY RESIDENTIAL

SITE PREPARATION
EVENTS ACTIVITIES PREDECESSOR/S DURATION ACTUAL/NORM ACCELERATIN
AL COST G COST
A CLEARING OF SITE 0 1
B PURCHASE OF INITIAL 0,H 7
MATERIALS
C TEMPORARY E 1
UTILITIES AND
SHELTER
D SURVEYING(BEARING B 1
LOCATIONS)
E FENCING OF SITE B,D 1
F MOBILIZATION B,D 5
G STAKE AND B,C 1
BATTERBOARDS
SITEWORKS
H EXCAVATION OF G 3
FOOTINGS
I SOIL POISONING G 3
J GRAVEL BEDDING I 2
K BACKFILLING V 3
L COMPACTING K,V 5
STEELWORKS/REINFORCEMENT (GROUND FLOOR)
M CUTTING,BENDING,T G 3
YING,LAYING,
(FOOTINGS)
N CUTTING,BENDING,T H 3
YING,LAYING,
(COLUMNS)
O CUTTING,BENDING,T J,W,D 3
YING,LAYING,
(BEAMS)
P CUTTING,BENDING,T H,U 3
YING,LAYING,(SLAB)
SECOND FLOOR (FRAMING)
Q CUTTING,BENDING,T Y 3
YING,LAYING,
(COLUMNS)
R CUTTING,BENDING,T J,W,D 3
YING,LAYING,
(BEAMS)
S CUTTING,BENDING,T J,W,D 3
YING,LAYING,(2ND
FLOOR SLAB)
STAIRS
T CUTTING,BENDING,T X 2
YING,LAYING
ROOF BEAMS AND GIRDERS
U CUTTING,BENDING,T X 2
YING,LAYING

CONCRETE WORKS (FOOTING)


V SEIVING,PROPORTIO M,J 3
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
COLUMNS(GROUND FLOOR)
W SEIVING,PROPORTIO U,L,N 3
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING

COLUMNS(SECOND FLOOR)
X SEIVING,PROPORTIO H,R,G 3
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
BEAM AND SLAB
Y SEIVING,PROPORTIO S,R,H 3
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
STAIRS
Z SEIVING,PROPORTIO H 2
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
ROOF BEAMS AND GIRDERS CONCRETING
A SEIVING,PROPORTIO U,H 2
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
SLAB ON GRADE
B SEIVING,PROPORTIO P 2
NING,MIXING,POURIN
G,MOIST CURING,
CONVEYING
MASONRY
GROUND FLOOR
D CHB LAYING AND E 6
MORTARING
SECOND FLOOR
E CHB LAYING AND Y 6
MORTARING
CARPENTRY
G DOOR AND WINDOW E 2
FRAME INSTALLATION
H SHAPING AND I,I,J,T 1
PASTING OF
FORMWORKS
I REMOVING OF J,W,D,X 1
FORMWORKS
J ASSEMBLING OF 0,K, 1
SCAFFOLDING
K DISASSEMBLE OF Y 1
SCAFFOLDS
L INSTALLING OF P,M,N,Q,X 3
DRYWALL BOARD
M CUTTING OF LUMBER AF,O,AM,R,AK,Q,B 3
N TREATMENT OF M,L,O,Q,AC 3
LUMBER
O FRAMING OF CEILING AC,M 2
P WALL FRAMING N 2
Q CEILING BOARD AF,P,AM,N 3
INSTALLATION
R INSTALLING FASCIA AG 2
BOARDS
PLUMBING WORKS
S PLUMBING SUBSLAB H 2
T PLUMBING H
ROUGHING-IN
U INSPECTION S,T 1
ELECTRICAL WORKS
V SET ELECTRICAL W 1
BOXES
W INSTAL ELECTRIC AD 1
SERVICE PANEL
X SET ELECTRICAL Y 1
FIXTURES
Y SWITCH AND PLUG V 1
Z ELECTRICAL X 1
INSPECTION
PAINTING FINISHES
AA START ALL INTERIOR AB 3
PAINTING
AB START ALL EXTERIOR Z,AI,AK 3
PAINTING
ROOFING AND TINSMITHING WORKS
AC JOINERY OF RAFTERS Z 4
AND CEILING JOIST
AD INSTALL ROOF AC,M 2
SHEATHING
PLACE FLASHING
INSTALL GUTTERS
AF INSTALL AJ 3
DOWNSPOUTS
FINISHING
AG DOORS AND Y,Z, 2
WINDOW HARDWARE
AH BATHHARDWARE AI 2
AI PLASTERING OF ML,AI,AK 5
WALLS
AJ INSTALL OF CEILING N 2
EAVES
AK INSTALLATION OF N,Q,X,Y,Z 3
DOORS
INSTALLATION OF
WINDOWS
AL INTERIOR TRIMMING Z,AI,AK 2
AM GROUTING OF FLOOR AG 3
TILES
AN INSTALL AL,AI 2
CABINETRIES
AO CLEANING AN,AI 1
PROJECT TURNOVER