25 - Transformer Core and Frame Check List

1) The document is an electrical checklist for testing the transformer core and frame of a combined cycle add-on project in Assiut, Egypt. 2) It outlines 7 items to check, including visual inspections, pressure gauge checks, impact recorder functionality and data reviews, and megger tests between the frame, core, and body to ensure insulation values are above minimum accepted levels. 3) Sign-offs are required from material engineers, vendors, quality control engineers, and UPEEC staff to verify all electrical checks are completed satisfactorily.

Uploaded by

Mena Kamel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views

25 - Transformer Core and Frame Check List

1) The document is an electrical checklist for testing the transformer core and frame of a combined cycle add-on project in Assiut, Egypt. 2) It outlines 7 items to check, including visual inspections, pressure gauge checks, impact recorder functionality and data reviews, and megger tests between the frame, core, and body to ensure insulation values are above minimum accepted levels. 3) Sign-offs are required from material engineers, vendors, quality control engineers, and UPEEC staff to verify all electrical checks are completed satisfactorily.

Uploaded by

Mena Kamel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Electrical Check list

Trans. Core and frame Test


Project : ASSIUT COMBINED CYCLE ADD-ON IIR

Module: Manuf.

Item Check activities Ok N.A


1 check visual and paint damages due to transportation
2 Check the pressure gauge to verify positive pressure
3 Verify that the impact recorders battery is still charged and the unit is functional (if Required)
4 Review the impact recorder data; Impacts of 3G or less
5 Impact recorder serial number =
6 Megger test the core and core frame (core-form) at 500Vdc.
Tester model : Tester Serial No. Due Date for Calibration:

Phase ident. Test volt Min. accepted value Result (M) Accepted
Frame & Core 500 Vdc 50 M ohm
Body & Core 500 Vdc 50 M ohm
Frame & Body 500 Vdc 50 M ohm

7 Check Local panel internal wiring and components

Remarks

Company Name Signature Date


Material engineer (OCI)

Vendor (HYSONG)

QC Engineer (OCI)

UPEEC

ACCPP-OC-QA-CKL-E-0025
Rev 00 Page 1 of 1