A Proposed Methodology For Quantifying The Environmental Impacts of Structural Elements of Standard Bridge Designs
A Proposed Methodology For Quantifying The Environmental Impacts of Structural Elements of Standard Bridge Designs
AbstractThis paper proposes a methodology to account for the abiotic resources, ocean acidification, eutrophication, global
environmental sustainability aspect of standard bridge designs in warming, ozone depletion, and photochemical oxidant
the Philippines. Through the methodology, the authors quantified formation.
the environmental impacts of bridges at their pre-construction
stage. The final output of the methodology is to produce an By means of quantifying the said impacts, bridge proponents
Environmental Impact Score (EIS) to aid proponents in ranking
may be guided with numerical values that would help in
the environmental performance of one bridge to another. By
conducting a Life Cycle Inventory Assessment (LCIA) and assessing the environmental implication of the project. By
producing an EIS, structural engineers will be able quantify the quantifying environmental impacts, structural engineers may
environmental impacts of different bridge structural systems and in reduce the impacts of a bridge early on in the design stage.
turn apply sustainability in the decision making of future bridge
projects.
II. METHODOLOGY
Keywords Analytical Hierarchy Process; bridges; environmental
impacts; environmental sustainability; Life Cycle Impact A. Bill of Quantities of Bridges
Assessment; structural systems The methodology begins with the acquisition of bridge
plans containing the bill of quantities of materials. Copies of
I. INTRODUCTION the as-built structural plans were furnished by the Bridges
Management Cluster of the Department of Public Works and
The Philippines is at its peak of construction and is Highways (DPWH) Unified Project Management Office
currently developing its road network system. Factors such as (UPMO) of the Philippines.
safety, serviceability, and economy have been considered in
bridge designs however proponents have fallen short in The study assessed eighteen (18) bridge plans located in
incorporating the environmental aspect of these designs. The Region IV-A of the Philippines. The bridge plans obtained
role of a structural engineer continues to be redefined with the included five (5) types of structural systems, namely,
introduction of variable construction methods and design reinforced concrete deck girder (RCDG), prestressed concrete
factors. In light of the nations response to climate change, the deck girder (PCDG), reinforced concrete slab (RCSL),
inclusion and consideration of potential environmental effects reinforced concrete box culvert (RCBC), and Steel girder.
by bridge components and elements are deemed relevant in the These are five (5) of the most common structural systems seen
initial design and conception of the structure. in the DPWH inventory of bridges. Figures 1, 2, and 3 are
photos of some of these structural systems.
Using the Life Cycle Impact Assessment (LCIA) database
Ecoinvent v3.1, the study introduces a methodology that
allows the conversion of construction materials used in the
bridge design into equivalent impacts namely consumption of
Sustainable Built Environment Conference (SBE2016)
July 13-15, 2016, Acacia Hotel, Alabang, Muntinlupa City, Philippines
Substructure:
B. Ecoinvent v3.1 Database
The next step was to convert the amount of materials into Reinforcing Steel 17,502.416 x 0.0099196 173.617
its equivalent effect to the environment. The Ecoinvent v3.1 Concrete Class A 108.804 x 0.6582100 71.616
database provided the researchers with materials found in the
Concrete Class B 0 x 0.6582100 0
bill of quantities of each bridge. The researchers used the
CML 2001 method, which provided various impact categories. Structural Steel 0 x 0.0034700 0
Each construction material corresponded to specific Total: 245.233
environmental impact equivalents. Table I enumerates the
Total
different environmental impacts along with their Super and 565.557
corresponding units. Sub
Sustainable Built Environment Conference (SBE2016)
July 13-15, 2016, Acacia Hotel, Alabang, Muntinlupa City, Philippines
At this point, the bridges analyzed still cannot be compared chemical engineers from the academe of the De La Salle
because that they differ in size. To eliminate this University, structural engineers from the Bureau of Design
inconsistency, the deck area of each bridge was used to sector of the DPWH, environmentalists from the Department
calculate the environmental impact equivalents per deck area. of Environment and Natural Resources (DENR), and
For example above, the sample bridge has a deck area of contractors to participate in the assessment of the weighting
189.84 sq. meters. As presented in Equation (1), the total factors. Figure 4 displays the percentages of weighting factors
environmental impact equivalent was divided by the deck area obtained from the AHP.
to produce an impact per square meter value.
C. Normalization
The different units of each of the environmental impact
potential posed as a challenge because it is impossible to
combine values with different units. This problem was aided
by means of the normalization process. In order to combine
the equivalents of the environmental impact potentials, the
highest equivalent in each category (ARDP, AP, EP, GWP,
POCP, and ODP) became a basis for all other values. The
smaller values were divided by the highest value in each
Fig. 4. Weighting Factors
category and would produce a ratio that could be combined
with normalized values from the other categories. Table III
shows an example of the normalization process with a highest E. Environmental Impact Score (EIS)
value of 6.278 that was used to normalize all the other values. The EIS was obtained by calculating the sum of all the
environmental impact potentials (as seen in Equation (2)).
TABLE III. NORMALIZATION OF ENVIRONMENTAL IMPACT POTENTIALS
former still produced the greatest EIS of 1.0 with its relatively Generally, RCBCs have relatively shorter span lengths
smaller deck area of 60.80 m2 (as seen in Table VII). This compared to other bridges. In addition, this type of bridge is
indicates that the deck area of a bridge is not directly structurally designed with no primary members supporting the
proportional to its EIS. superstructure. Since the loads are not distributed to any
supporting girders, serviceability requirement for deflection of
TABLE VII. EIS AND DECK AREA OF BRIDGES A AND C the bridge deck is larger. In theory, deflection is a function of
Average Normalized Environmental Impacts the elements moment of inertia. Increasing the thickness of
Bri- Deck the element would result to a larger moment of inertia, thus
dge ARD POC
Area
P
AP EP GWP
P
ODP EIS minimizing the resulting deflection on the structural element.
(m2)
The increase in thickness of the bridge deck would require a
A 60.80 1.000 1.000 1.000 1.000 1.000 1.000 1.00
larger volume of structural concrete and number of
128.0
C
4
0.708 0.594 0.709 0.705 0.711 0.705 0.69 reinforcements. This explains the larger EIS of an RCBC
because of the addition and use of more structural materials.
Figures 6 and 7 show the equivalent environmental impact
values for reinforcing steel and structural concrete of Bridges B. Case study on PCDG, RCSL, and Steel Girder
A and C. Superstructures
One of the major components in bridge design is the
presence of a superstructure. Most bridge superstructures
include girders responsible for the transfer of loads from a
bridges slab to the abutments or supports. In the case study
conducted, there were bridges with three configurations
namely, prestressed concrete deck girders (PCDG), reinforced
concrete slabs (RCSL), and steel girders.
Bridge N
Superstruc-
ture Reinforcing Concrete,
Prestressed Concrete
Steel, kgs m3
Reinforci
Concrete,
Deck Slab 16,092.551 93.109 ng Steel,
m3
kgs
DIaphragm 2,615.666 13.638 - -
Superstruc- Bridge M
ture Reinforcing Steel, kgs Concrete, m3
Deck Slab 31,324.00 172.04
Sidewalk 4,125.40 3.245 Fig. 8. Superstructure impact equivalents of PCDG, RCSL, and Steel Girder
bridges
Girder 3,291.90 20.808
Total 46,552 215.32 Based on this figure, Bridge P had the highest impact in
the categories of abiotic resource depletion, global warming,
and photochemical oxidant creation, but had significantly
TABLE X. STRUCTURAL ELEMENTS OF BRIDGE P (STEEL GIRDER) lower impacts in acidification, eutrophication, and ozone
Bridge P depletion, as compared to the other two bridges. The results
Superstruc-
ture Concrete, Structural indicate that Bridge M had higher impacts in all categories as
Reinforcing Steel, kgs
m3 Steel, kgs compared to the prestressed concrete bridge, Bridge N, despite
Deck Slab 17,352.01 87.748 - having a smaller deck area.
Sidewalk 2,590.517 23.12 -
The manufacturing of the materials used to construct the
Girder - - 93,842.98 components of Bridge P proved to have a greater impact due
to its contribution to the depletion of abiotic resources as well
Total 19,942.527 110.868 93,842.98
as the global warming. Given that the bearings of these
potentials were heavier than the rest based on the AHP, the
manufacturing of the structural steel of Bridge P led to a
It can be observed from these tables that the higher EIS. With regards to the difference of EIS of Bridge N
superstructures of the bridges have significantly different and M, the cause of Bridge M to have a higher EIS value than
types and amounts of materials. The bridge that used the most Bridge N was due to the larger amount of reinforcing steel
concrete for the superstructure was found to be Bridge N used for the structure. Tables VIII and IX show that the
(PCDG) while the bridge that used the most reinforcing steel reinforcing steel used by Bridge M amounted to 46,552 kgs
was Bridge M (RCSL). Bridge P (Steel Girder) has utilizes a while Bridge N had 42,601.35 kgs (21,808 kgs + 20,793 kgs).
large amount of structural steel as well as using reinforcing Applying the Ecoinvent factors will give a larger impact
steel and concrete for its girder and deck slab, respectively. equivalent for Bridge M. Using the deck areas for comparison,
In order to analyze the environmental impacts of the the smaller deck area of Bridge M, will definitely cause the
superstructures of these bridges, the same method was used in environmental impact equivalent per sq. meter to be higher
solving for all of the bridges EIS. The results of this process than that of Bridge N. The amount of concrete used in these
can be seen in Figure 8 (Note: GWP is in 100s and ODP is to bridges also had a significant difference, with Bridge M
be multiplied by 10-4.) (RCSL) having a higher amount of concrete used per sq.
meter, which also led to the increase in its EIS as compared to
Bridge N (PCDG).
Bridge P, which a large amount of structural steel generated system for a specific bridge. Although the results are bridge-
the highest EIS as compared to structures that use reinforcing specific, engineers will have a rationale of the expected EIS of
steel and concrete only. In terms of reinforced concrete, any proposed structural bridge design. This heightened
Bridge M, configured with a reinforced concrete slab, awareness of the environmental impacts of bridges will
produced a higher EIS due to the amount of reinforcing steel promote and advance the concept of sustainability.
used for its construction. Given these results, it is important to
take note that the configurations of the superstructures can
affect the environmental impact potentials that a bridge has. REFERENCES