TPB 100 Method of Statement
TPB 100 Method of Statement
No. 17-2, Jalan USJ 10/1E, UEP Subang Jaya, 47620 Subang Jaya, Selangor Darul Ehsan.
Tel : 03-5631 6282 Fax : 03-5632 6282
1. SCOPE
1.1 This procedure refers to the installation of Jack-In piles only
2. EQUIPMENT
Jack-In Machine
2.1 System Used : Gripped System
2.2 Maximum Pile Size : 150mm ~ 250mm Square, 150mm ~ 250mm diameter
2.3 Maximum Jacking Force : 100ton
Other Equipment
2.1 Air Compressor/ Diamond Cutter
2.2 Welding Set
2.3 Generator Set
4.1 All handling and lifting will be at the designed lifting points and support points.
During pitching and installation the verticality of the pile will be continuously monitored and plumbed to ensure
the pile is centrally in line with the pile axis to receive the ram to prevent pile whip, twist or rotation.
Each pile shall be clearly marked with red ink at 300mm intervals along its length to enable the jacked In
pressure/force to be.recorded at every 300mm depth of pile penetration.
The pile will be extended by butt-welding the steels plate on the pile heads. On completion of welding the slag will
be chipped off and wife brushed to receive bitumen or anti rust paint.
The vertical support structure of the jack-in machine is plumbed to ensure vertically by means of a spirit level or
plumb line. This is achieved by adjusting the four stabilizers. Pile shall be lifted and inserted into the equipment by
crane. The pile shall be position into the grip of the equipment and gripped the pile body. Once the pile vertical and
in position, jacking commences.
During the pile installation, the hydraulic pressure of main jacks is measured by the pressure gauge, and the
corresponding pile penetrations are recorded by the site staff at regular intervals. The pile may be extended by means
of welding. Except for pile jointing, each pile is jacked in continuously until the required resistance or penetration
is reached.
The required resistance is normally twice the pile working load, or higher of the jack supervising engineer so desired.
The corresponding pressure in the main jacks and the penetration are recorded.
The portion of the installed piles which is above ground may be cut to enable movement of rig.
CITY PILING SDN BHD ( 671791-U )
No. 17-2, Jalan USJ 10/1E, UEP Subang Jaya, 47620 Subang Jaya, Selangor Darul Ehsan.
Tel : 03-5631 6282 Fax : 03-5632 6282
The jack-in force is determined by the engineer. Once the required pressure corresponds to the required jack-in
force is indicated in the pressure gauge, the pressure is held for 30 seconds. The set criteria is that the same
required pressure is achieved consecutively for two times, each time held for 30 seconds and each settlement
should not exceed 15mm.
CITY PILING SDN BHD ( 671791-U )
No. 17-2, Jalan USJ 10/1E, UEP Subang Jaya, 47620 Subang Jaya, Selangor Darul Ehsan.
Tel : 03-5631 6282 Fax : 03-5632 6282
5. SAFETY
5.1 Statutory safety requirements (General Duties of Employees, Section 24, Occupational Safety and Health Act, 1994)
Site specific safety requirements, as set out in the contract; and the main contractor's Environment, Safety. Health
and Security Plan.
Hazard Precautions
Sinking 1. Ensuring ground is reasonably level.
2. Ensure equipment is level
3. Use matting if ground is soft
4. Do no attempt to track across water ponded area.
Pile falling during pitching 1. Use approved and tested wire ropes.
2. Double loop of wire rope around the pile to avoid slipping (pile surface is smooth)
3. Do no drag the pile more than 12m from the jack-in cylinder
4. Stay away from pile during dragging and pitching.
Others 1. Operator should always view at the worker working at the grip clamp and only
grip the pile where operator is free from clamp
2. Ensure no worker is under the object when being lifted.
3. Regular checking of lifting cables.
5. CUTTING OF PILES
The work involve cutting of piles with mechanical driven diamond cutter at high speed. The risks and precaution are as follows:
Hazard Precautions
Stuck by flying material 1. Stay at least 4m during cutting.
Dust 1. Operator must wear dust mask
Cut by cutter 1. Only experienced worker is a allowed to work
Falling of piles 1. If piles above cut off level are more than 4m high, it should be supported
by crane or clamped by the equipment.
CITY PILING SDN BHD
DTZB100 HYDRAULIC STATIC PILE DRIVER
CITY PILING SDN BHD
Item Parameter
Forward 9.2m/min
Backward 18.1m/min
Stepping Speed
Left 9.2m/min
Right 18.1m/min
HY80Y-RP
Hydraulic pump model
HY63Y-LP
Y225S-4-V1 (37W
Vertical)
Motor Model
Y180M-4-V1 (30KW
Vertical)
Voltage 380V
Frequency 50HZ
YCW - 3x32 +
Power cable
2 x 16