Is 401 Project Management Lecture Four - "Project Cost Management"
Is 401 Project Management Lecture Four - "Project Cost Management"
Project Integration
Scope
Time
Cost
Quality
Human Resources
Communication
Risk
Procurement
Stakeholder
T. Abady, DWU 2017 3
Todays Topics
Between 2004 and 2012, cost overrun has increased from 56% to 59%
So they replaced that measure (on target) with a measure of customer perceived
value. This resulted in a 7% decrease in the rate of successful projects.
In other words, despite how much money was invested in software development,
customers were not always satisfied about the value of software features as many
features were either not used or irregularly used.
T. Abady, DWU 2017 6
Eg. Consider a commerce application that you estimate will increase revenues of K 100 million
company by 10 %. If company gains K2 for every K 100 it generates in revenue, this means you have
made a profit margin of 2%. If company looses K2 for every K 100, there is a -2% profit margin.
Development $ 500,000.00 - - - -
Implementation $ 700,000.00 - - - -
Correction costs
The costs for correcting an error grow exponentially with project progress. Not Spend
enough effort in early stages!
Further points
Direct vs. indirect costs
e.g Direct cost of people working full-time, equipment purchased
e.g Indirect cost of electricity, cost of water etc...
Sunk costs
e.g money spent in the past projects. Should be forgotten.
Learning curves
e.g involves production in large quantities. In the selling of 2000 gadgets, the cost of
selling the first 100 gadgets will be used to cover the production cost of the item.
Once the first 100 gadgets are sold to make up for the total production cost, then the rest
can be sold at the real price.
Reserves / contingency
e.g allow for situations that are partially planned for. Training of staff members, recruitment
T. Abady, DWU 2017 10
Cost Management
Resource Planning Cost Control
Budget updates
Cost Estimation
Cost estimates
Support. details
Cost mgmt. plan
Cost Budgeting
Cost baseline
T. Abady, DWU 2017 11
Cost Estimation
Outputs
Cost estimates (rough budgetary definite)
Supporting details (rules, assumptions, tools & techniques used)
Cost management plan (describes how cost variances will be
managed)
Techniques
Top-down (= analogous) estimation: uses actual costs of similiar
projects
Bottom-up estimation: estimate individual work items and sum them
up (time-expensive)
Parametric modelling: uses project characteristics (parameters) in a
mathematical model
T. Abady, DWU 2017 12
Cost Estimation
Typical Problems with IT Projects
Cost Budgeting
Task
Allocating the estimated project costs to individual tasks
Inputs
WBS & project schedule
Cost estimates
Output
Cost baseline, i.e. time-phased budget, used for performance monitoring
T. Abady, DWU 2017 16
Controlling Costs
you can determine how well the project is meeting its goals
The planned value (PV), formally called the budgeted cost of work scheduled
(BCWS), also called the budget, is that portion of the approved total cost estimate
planned to be spent on an activity during a given period
Actual cost (AC), formally called actual cost of work performed (ACWP), is the
total of direct and indirect costs incurred in accomplishing work on an activity
during a given period
The earned value (EV), formally called the budgeted cost of work performed
(BCWP), is an estimate of the value of the physical work actually completed
EV is based on the original planned costs for the project or activity and the rate at
which the team is completing work on the project or activity to date
T. Abady, DWU 2017 19
Rate of Performance
Figure 7-5. Earned Value Chart for Project after Five Months
T. Abady, DWU 2017 24
Chapter Summary