Operations Manual-Ktps, Version02
Operations Manual-Ktps, Version02
OPERATIONS MANUAL
(Version-01)
INDEX
Chapter-I
Auxiliary electrical equipment shall be suitable for Operation on the following supply
system:
(a) For motors rated above 175 : 11000V, 3 phase, 3 wire, 50 Hz medium KW
resistance earthed AC 33000V, 3 phase, 3 wire, 50 Hz medium resistance earthed AC (up
to 1500 KW)
(b) For motor control center: 415V, 3 phase, 3 wire solidly earthed AC
(c) For motor rated 175 kW and : 415, 3 phase, 3 wire solidly earthed AC below
(e) AC control & protective : 110 V resistances. The single-phase 110V devices AC
supply shall be derived by Contractor by providing 415V/110V control transformers of
adequate rating with MCCB / MCB on both the primary and secondary sides.
(f) Uninterrupted power supply: 230 V, 1 phase, 50 Hz, 2 wire AC supply from UPS
system for I&C (including indicator recorders) and UCMS only
(g) Space heaters (for motors : 240V, 1 phase, 2 wire, 50 Hz AC system rated 30 KW
and above) with effectively earthed neutral. The power supply shall be derived by
CONTRACTOR by providing 415V / 240V transformer of adequate rating with MCCB /
MCB on primary / secondary sides.
(h) Solid state controls (including : 24V DC, 2 wire (24 V DC derived from UPS
solenoid valves) supply)
(i) Solid state controls (including : 24 V DC, 2 wire (24V DC derived from UPS
solenoid valves) supply).
(j) Lighting fixtures; and space : 240V, 1 phase, 2 wire, 50 Hz system heaters in
panels
(k) The above voltages may vary as follows: All devices shall be suitable for
continuous operation over the entire range of voltage and frequency indicated below
without any change in their performance.
Coal Analysis:
Chapter-II
PRE-TREATMENT PLANT:
The raw water passes through motorized butterfly valve to Cascade Aerator to
Stilling Chamber through Parshall flume (Flow Measuring Element) to Flash Mixer
(Retention Time of 1 minute). The flash mixer is having slow speed agitator with baffles
and the drainage is connected to the sludge sump. One no. clari-flocculator is arranged
with rake mechanism and telescopic type continuous sludge discharge arrangement. The
clari-flocculator outlet is connected to Rapid Gravity Filters (RGF). Four (4) numbers
RGFs (each of 600TPH capacity) with roof over filter beds for the dual media filtering
material with valve chambers are available. The RGFs outlet pipes are connected to
filtered water reservoir. Chlorination facility is available for raw water and potable water.
Details of PTP:
Water Pumps:
CT(W) Make up Pumps
Numbers : Three (2W + 1S)
One number Condensate Storage Tank (CST) of capacity 500 m3 is also located
besides the DMWDT and is the suction for Two numbers Emergency Hotwell Make up
Pumps of 150 TPH capacity each and Two numbers Boiler Fill Pumps of 150 TPH
capacity each.
To prevent microbiological fouling in the circulating water pits and in the entire
CW system, a chlorination plant is provided in a separate building near the CWPH to
dose chlorine into the pump suction pits on a continuous basis, to operate the cooling
tower at minimum COC 4 or higher and to prevent buildup of suspended solids a
chemical dosing system consisting of Biocide, anti-scalent and corrosion inhibitor are
provided along with Sulphuric acid dosing system to control the PH of circulating water
and maintain m-alkalinity in the range of 150 to 200 ppm. 12 nos. chlorine cylinders each
of capacity 900 Kg are available at chlorine plant. 1 No. Bulk Acid (98% H2SO4) storage
tank of 12 m3 along with 5 m3 acid measuring facility are also available in the plant
Safety Warning: - In case of chlorine leak, run away from the location in the
direction of wind flow shown by the wind sack.
4 nos. each of capacity of 19500 m3/Hr. CWPs to cater the cooling water
requirement of Condenser of main Turbine as well as 2 Nos. Drive Turbines of BFPs are
available in the CWPH. The shaft bearings are of less rubber type with flushing grove and
forced water lubricated type. The CW system at VI stage is in closed cycle from
Condenser to Cooling Tower through CW Pumps with filter water as makeup and the
system is having natural draught Cooling Tower. Stop log gates and coarse screens are
available at the upstream of the CW Pumps. The Stop log assembly units and screens
shall be lifted /lowered with a speed of 1 to 2 m/min. under balanced conditions of load
only. The coarse screening is designed for 50% choking condition.
Details
Total No.of Pumps : Four (3W+1S)
Pump capacity : 19500 m3/Hr (TPH)
Type of Pump : Vertical Mixed flow
Motor rating : 1600 KW (115% of duty point)/
11 KV
Auxiliary Cooling Water (ACW) system supplies water required for plate heat
exchanger (PHE) of SG,TG and other unit auxiliaries. This system comprises of 3 Nos.
ACW Pumps of 2200 m3/Hr capacity, two working and one as standby. These pumps are
available in CWPH adjacent to CW Pumps.
Details
Total No. of Pumps : Three (2W+1S)
Pump capacity : 2200 m3/Hr (TPH)
Type of Pump : Vertical Mixed flow
Motor rating : 375 KW/ 3.3 KV/
Fore-bay level settings:
Normal : 90.2 msl
High : 90.5 msl
Very Low : 88.7 msl (all CWPs trip)
Very Very Low : 88.5 msl (all ACWPs trip)
One natural draught cooling tower with cooling water basin is available and outlet
channel from the basin is connected to the Fore bay of CW Pumps sump together with
sludge removal sump along with valve pit are also available. Cooling Tower (CT) shell is
of hyperbolic paraboloid shape. The CT basin is designed for a water depth of one meter
from normal water level with a free board of 0.3 m above maximum water level , the CT
basin is divided into two equal parts by water tight RCC partition for the cleaning and
maintenance of one half while the other half is in service. Arrangements for water
drainage are also provided. The cold water from the CT basin flows by gravity to open
approach channel leading to the Fore Bay. The cold water channel is provided with
independent stop logs and screens. In accordance with official regulations, aviation
warning lights are installed along the perimeter of the tower opening. The drift loss will
be around 0.005% of the mass of water circulating.
Details:-
Height of the Cooling Tower : 163 mtrs.
Type of Cooling Tower : Counter flow, splash bar type
Cooling range : 10.33 deg.C
Designed wet bulb temp. : 28 deg.C
Approach : 5 deg.C
Fill type : splash bar type (PVC)
Nozzles, orifices, splash cups : PVC
Drift eliminators
The plant waste water treatment is carried out in ETP with maximum recovery and
minimum discharge i.e. to achieve zero discharge. The following lines connected to ETP:
1. Boiler Blow Down: Power cycle blow down is collected through pipes in local
boiler blow down (BBD) sump. This blow down is pumped to Common
Collection Sump (CCS1).The average flow rate may be around 20 m3/Hr.
2. Transformer Area Oily Waste: The effluent generated in the event of fire,
subsequent water spray and leakage of oil from the transformer etc. are collected
in CCS2 through drain channels. Oil is pumped to Corrugated Plate Interceptor
{(CPI) 1 No., 20 PH capacity} and skimmed oil will be collected in drums and the
left out oily water is pumped back to CCS. Treated water after CCS flows to clari-
flocculator.
3. Oily Waste Water from TG/Boiler Area: Oily waste from TG/Boiler area is
collected through drain channels in collection sump located in Boiler area and
treated in CPI separator and clear water flows to CCS3.
4. Wash Water from TG/Boiler Area: The effluents from floor washing in TG/Boiler
area contain suspended solids are collected in a Boiler area sump for further
process
5. Cooling Tower Blow Down: The excess blow down from the CT is collected in
CCS.
6. Fly Ash Silo Area: Wash water from ESP area and Ash Silo area are collected in
local sumps and pumped to CCS for treatment.
7. Clari-flocculator: A Lamella Clarifier of 450 m3/Hr capacity is provided to
remove TSS. Clear water from clarifier is let to clarified water sump by gravity.
8. Filters: Four (3W+1S) Dual Media Filters each of 150 m3/Hr capacity are
provided with back wash and air scouring facilities. The filtered water passes
through filter membrane to achieve SDI less than 3 before feeding to RO module.
9. Ultra filtration Modules: Four (3W+1S) UFMs each of 150 m3/he capacity with
90% recovery are provided reduce the SDI less than 3. The ultra filtered water is
stored in an intermediate storage tank and pumped to RO modules later.
10. Reverse Osmosis (RO) Modules: Four (3W+1S) RO modules each of 150 m3/He
capacity with 80% recovery are provided. The UF water is pumped by means of
RO feed pumps through micron cartridge filters and high pressure pumps to RO
modules to De-gasser system and stored in de-gassed water storage tank. The
permeate water is pumped to CT basin for CW makeup.
Note: The reject water is collected in sump and used for dust suppression,
floor washing and green belt development etc.
Chapter-III
Details:
Belt conveyors : 13A/B to 17A/B
Twin stream conveyor of 1200 TPH
Capacity
Belt weighers : 2 Nos. on 13A/B
Traveling trippers : 4 Nos. 1200 TPH (each on 16A/B
and 17A/B)
Maximum belt speed : 3 m/s
Belt Width : 1400 mm
Trough angle : 35 deg.
Crisscross feeding
Arrangement (A->B, B->A) : Available at TP-U and TP-V only
No of plies in a conveyor : Four plies
Belt type : Synthetic fabric of nylon/nylon,
polyester/polyamide
18 433.78
19 476.02
20 518.26
21 560.30
21.8 594.30
22 610.40
23 618.40
24 650.00
The existing 2 Nos. HFO tanks each of capacity 4525 KL are used for the storage
of HFO. The existing 1 No LDO storage tank of capacity 750 KL is used for the storage
of LDO. 2 Nos HFO pumps and 2 Nos. LDO pumps are available. HFO pressure of 8
Kg/Cm2 shall be maintained when the guns are in service, at that pressure an average
consumption of HFO is 2.5 KL/gun Hr.
Ash Handling System includes Bottom ash handling system, coarse ash handling
system (Economiser Hoppers) and fly ash system (APH hoppers, In-Duct hoppers, ESP
hoppers and Stack hoppers). Bottom ash is collected in the water impounded bottom ash
hopper and conveyed to ash slurry sump through jet pumps and further pumped to Hydro-
bins or to stage-V slurry sump using ash disposal pumps. Coarse ash from the Eco.
Hoppers is extracted by means of flushing with LP water and the slurry is conveyed to
BAH. Fly ash is extracted through vacuum and conveyed to intermediate fly ash (IFA)
Silo or to Remote fly ash (RFA) Silos through pressure conveying system using Transport
Air Compressors (TACs).The fly ash collected in the IFA Silo is disposed in wet form
through HCSD system to existing ash pond. Fly ash collected in RFA Silo is disposed in
dry form through Trucks.
Chapter-IV
PROXIMATEANALYSIS
Fixed carbon : 28.7%
Volatile matter : 28.3%
Moisture : 9.0%
Ash : 34%
Grindability Index : 52.HGI
Size of coal to mill : 25 mm
UTIMATE ANALYSIS
Carbon : 46%
Hydrogen : 2.70%
Sulphur : 0.50%
Nitrogen : 1.49%
Oxygen : 6.2%
Moisture : 9.0%
Ash : 34%
STEAM GENERATOR
Single Drum, controlled circulation, radiant, single reheat, dry bottom, two pass,
balanced draft, out door, sub critical conventional boiler.
Two stream air and flue gas system.
Steam capacity :1625 T/Hr.
Main steam parameters : 175 bar / 540C.
Reheat parameters : 43 bar/540C.
Drum pressure : 193 bar.
Gas temp leaving furnace : 1389C.
FG Temp at AH outlet : 125C.
Gross efficiency : 89.02%.
BCWP`s (3) Motor capacity : 350KW, 3.3 KV
Residence time for fuel particles in the furnace 3 secs.
Furnace volume : 14,272 M
Furnace Protected area : 7610 M
Fuel Heat input : 1181.9 X 10Kcal/hr
Water Wall Soot Blowers (WWSBs) : 88
Long Retractable Soot Blowers : 44
(LRSBs)
MILLS:
Stack
1 No. Stack of height 275M.
Single refractory flue
Stack comprises RCC shell, stair cases, lift, aviation lamps, FG sampling &
analyzer equipment etc.
Soot Blowers:
The unit is having three types of soot blowers. They are 88 numbers Water Wall
Soot Blowers (WWSBs), 44 numbers Long Retractable Soot blowers (LRSBs) and 2
numbers Air Heaters Soot Blowers (AHSBs). 88 numbers of WWSBs are distributed in
four elevations each with 22 numbers one below Windbox and three elevations above
windbox as follows. The steam for soot blowing is taken from the outlet header of
Divisional Panelette. Operating pressure is 25KSc and the temperature is 250-300 deg.C.
A pressure of 25Kg/Cm2 is maintained via a control valve and all the drain valves are in
open condition till the steam in the line reaches above 250 deg.C. A safety valve is
provided in the line with suitable setting. Drain lines, four from WWSBs, 2 from LRSBs
and 2 from AHs, are connected IBD flash tank (IBDFT).
WWSBs:
L/S F/S R/S Rr/S
18-26 1-6 7-11 12-17
40-44 23-28 29-33 34-39
62-66 45-50 51-55 56-61
84-88 67-72 73-77 78-83
And 89 to 104 envisaged but not provided.
LRSBs:
105 to 162. Out these envisaged only 44 are provided at Super Heaters zone barring 145
to 162 (except 153 and 154).
AHSBs:
AH-A 163
AH-B 164
In ASLD scheme 24 numbers noise pick ups have been arranged at various locations. If
noise range crosses 20dB, it shows a red indication on bar graph and at 16dB alarm
appears, in case of steam leak. The arrangement of ASLDs on boiler is as follows:
1 LS 57.9m 13 RS 70m
2 Front 57m 14 LS 70m
3 LS 20m 15 LS LTSH Upper 66m
4 LS Top of WB 16 Upper LTSH LS 58.1m
5 RS Top of WB 17 Eco. Upper LS 51.2m
6 Near FTP LS 51.7m 18 Eco. Lower LS 44.3m
7 RS 20m 19 RS LTSH Upper 66m
8 LS Top of WB 20 Upper LTSH RS 58.1m
9 RS Top of WB 21 Eco. Upper RS 51.2m
10 Near FTP RS 51.7m 22 Eco. Lower RS 46.3m
11 RS 57.9m 23 RS 66.4m
12 LS 66.4m 24 RS 70m
Economiser System
Sl.
Description Material Design Temp.
No.
Coils SA 210 Gr A1 326
1. Economiser
Headers SA 106 Gr C 398
Circulating System
Sl.
Description Material Design Temp.
No.
1. Drum SA 299 368
Tubes SA210 Gr C 398
2. Water Walls
Headers SA 299, SA106 Gr C 370
Re-heater System
Sl.
Description Material Temp. Range
No.
Performance requirement
60% TG 80% TG SG
for constant pressure TG MCR
MCR MCR MCR
operation
Steam quantity leaving final
34 T/hr 886.48 1185.60 1496.84 1625
super heater outlet
Steam quantity leaving final 1391.1
35 T/hr 812.99 1071.63 1333.99
re-heater outlet 6
Steam generator efficiency
36 % 89.20 89.10 88.98 89.02
based on the GCV of the fuel
Combustion air requirement 446.2 =
37 Kg/s 270.8 353.3 488.7
(without leakage) 1605TPH
38 Drum pressure Bar (a) 175.0 181.3 189.3 193.13
Feed Water Pressure at
39 Bar (a) 178.0 184.7 193.5 197.6
economizer inlet
Gas temperature leaving
40 Deg. C 1396 1413 1409 1389
furnace
41 Feed water temperature
a) Entering economizer Deg. C 230 243 254 255
COAL MILLS
59 Type of coal mills XRP 1003
60 Number required 7 (A,B,C,D,E,F,G)
61 Mill inside condition Pressurized
62 Capacity T/hr 65 (with 9% moisture & 52 HGI)
Output per mill at specified input
63 T/hr 54.0
size & moisture
Minimum stable load without oil
64 40% TGMCR
support
COAL FEEDER
105 Type Gravimetric
106 Model Size:36 inches
107 Capacity T/Hr 76
108 Speed rpm 0.8 to 8.0
109 Belt Width mm 1168 4
110 Accuracy of measurement % 0.5
111 Type of control -processor based
Chapter-V
STEAM TURBINE
STEAM TURBINE
Sl.
Particulars Units Technical Particulars
No.
Reheat condensing with
regenerative feed water
heating including de-
aerating feed water heater.
1. Type of steam turbine
Provision of de-aerating
condenser in lieu of de-
aerating feed water heater is
not acceptable.
a) Constant pressure
above 95% TGMCR
2. Operating mode b) Sliding pressure
between 40% TGMCR
and 95% TGMCR
100% TG MCR gross output at the generator
terminals requirements:
500 MW, without exceeding
3. a) Guarantee condition with 3% makeup and
governing valves opening
including auxiliary steam requirements for the
by 95%.
plant, temperature.
a)Steam pressure at HP
turbine 170 kg/cm2 (a)
Turbine generator steam parameters at STG b) Steam temperature at HP
4.
stop valves turbine: 5370C
c) Steam temperature at IP
turbine: 5370C
3000 rpm, directly coupled
5. Turbine speed
to electric generator
Redundant (Digital)
6. Type of governor Electro-hydraulic with
back-up facility.
Two cooling water passes.
Bottom mounted single
shell with divided water box
7. Type of condenser
to facilitate unit operation
with one half under
maintenance.
Oxygen in condensate at hotwell outlet
8. with 3% make-up from 30% TG MCR to
cc/litre Not to exceed 0.03
TGVWO
STEAM TURBINE & ACCESSORIES
Maximum continuous rating at generator
9. MW 500
terminals (MCR)
10. Turbine rated speed 3000
Chapter-VI
GENERATOR
TRANSFORMER YARD
4 Nos (3 Nos. working + 1No.spare) single phase, oil cooled 207 MVA,
21/400KV Generator Transformers
1 Nos. 50MVA, 220KV, /11KV,Station transformer. ST-6A
1 Nos. 80 MVA, 400/11 KV, 3 winding station Transformer.ST-6B
2 Nos. 25 MVA, 21 KV/11.50 KV unit transformers.
2 Nos. 12.5 MVA,11/3.6 Unit Auxiliary Transformers.
2 Nos. 16 MVA, 11/3.6 Station Auxiliary Transformers.
ST-6B
1 spare bay
Sl.
Description Unit Particulars
No.
GENERATOR
1. Type and model number THDF 115/59
(a) Gross power output at TGVWO condi-tion with 3%
2 makeup and design cooling water temperature and rated power
MW 524.204
factor.
MW 500
(b) Max. continuous rating
MVA 588
3. Rated terminal voltage KV 21
4. Rated stator current Amps 16166
5. Rated frequency Hz 50
6. Rated power factor 0.85 lag
7. Rotor current at MCR Amps 4040
8. Maximum permissible variation range in:
a) Rated terminal voltage % 5
b) Rated frequency with/without time limits % 5
9. Synchronous speed rpm 3000
10. Number of phases No. 3
11. Generator efficiency at:
a) 100% load % 98.64
b) 75% load % 98.62
c) 50 % load % 98.41
Minimum guaranteed short circuit ratio corresponding to
12. 0.48
maximum capability
13. Designation for method of cooling as per IS / IEC standards ICW37H71
Basic impulse insulation withstand voltage of stator winding KV
14. (4 Ur + 5)
with respect to earth (peak)
15. Maximum permissible capacitive loading at full load MVAR 160
16. Permissible tolerance on all guaranteed reactance values % 15
Guaranteed temperatures at rated hydrogen pressure and max
17.
inlet cooling water temp. at rated load
o
a) Stator windings C 120
o
b) Stator core C 120
o
i) In contact with insulated winding C 120
o
ii) Not in contact with insulated winding C 120
o
c) Rotor windings C 105
Class F with
temp rise limited
18. Class of stator winding insulation
to class B
values
Sl.
Description Unit Technical Particulars
No.
ROTOR WINDING PARTICULARS
Class F with temp rise limited
19. Class of field winding insulation
to class B value.
GENERATOR MISCELLANEOUS
PARTICULARS
Noise level in free field / semi-reverberant
20.
conditions
a) No load dB (A)
As per MOEF guidelines.
b) On load dB (A)
EXCITATION SYSTEMS
21. Excitation System Parameter
Type of excitation system offered, Brushless
22. Brushless
essential.
a) Nominal field voltage Volts 340
b) Ceiling / Field forcing voltage Volts 680
c) Minimum and maximum field current 1378A - min
Amps
with generator at 100 % load 4040A - max
23. Brushless Excitation System
Ratings:
(a) Continuous max. Output kW 1375
(b) Rated voltage Volts 340
(c) Rated Current Amps 4040
(d) Rated full load speed Rpm 3000
(e) rated frequency Hz 150
(f) Ceiling voltage Volts 680
(g) Response ratio S Greater than 2.0
Voltage Regulator and Accessories
24. Type and quantity Digital Voltage regulator
25. No. of auto & manual channels Two Auto + Two manual
26. Guaranteed sensitivity 0.5% (accuracy)
27. Range of voltage level setting
- Auto Auto - 90 to 110% of Ugn
- manual Manual - 0 to 110% of Ifn
No critical speed shall fall within
28. Critical speed
6% of the rated speed
HYDROGEN COOLING SYSTEM
29. Type & total number of coolers provided Nos. Shell & Tube type-4 Nos
Number of coolers required in simultaneous
30.
use at MCR Nos. 4
Load that can be carried with one cooler out
31.
of service MVA 392
Current and kVA rating of generator at 15396 A / 588 MVA at 105% rated
32. Amps
voltage above 100% voltage
DIGITAL AUTOMATIC VOLTAGE REGULATOR
5% of rated voltage in auto
33. Accuracy of voltage regulation %
channel
34. Response time ms <20
35. Operating frequency range Hz 300 5%
Sl.
Description Unit Technical Particulars
No.
1. Generator Transformer
2. Type Outdoor, single phase, 50Hz
3. Applicable standard IS: 2026
4. Quantity 4 Nos. (3+1 spare)
5. Full load rating MVA 207
6. Rating of each windings MVA HV = 207, LV = 207
7. Rating of no load voltage HV / LV kV 400/3/21
8. Rated frequency Hz 50
9. System earthing on HV side Solid
10. Type of tap changer- off circuit/on load OFF Circuit
110% continuous,125% for 1
11. Overfluxing capacity
minute,140% for 5 second
Impulse withstand voltage of winding
12. KVp 1425/125
HV/LV/HV neutral
Maximum temperature rise at full load with
13.
100% coolers:
o
(a) Oil C 50
o
(b) Winding C 55
Efficiency at
14. (a) full load 99.77 apprx.
(b) 75% load 99.79 apprx.
15. Off Circuit Tap Changer
16. Rated Voltage Volts 60,000
17. Rated Current Amps 1,200
No. of cooler banks and capacity of each
18. 2X100%
cooler bank
Guaranteed No load current
At 100 % - 80 Amps
19. When excited from LV side at 100% and
Amps At 110% - 170 Amps
110% rated voltage
Max. Flux density when rated and 110%
20. Wb/m2 1.9
ratedvoltage
Vacuum withstand capability main tank, mm of
21. Full Vacuum (except Conservator)
radiators and accessories Hg.
Station Transformer-1
24. Type 3-winding, 3 phase, outdoor
25. Full load rating MVA 80/40-40
26. Rated no load voltage HV/LV KV 400/11.5-11.5
Rating of different cooling methods 60% / 80% / 100%
27.
ONAN/ONAF ONAN/ONAF/OFAF
At 80 MVA base HV-LV1 &
28. Impedance value % HV-LV2: 19%
LV1-LV2: 34% (min)
29. Rated frequency Hz 50
Winding connection of different windings
30. YNynyn0
and vector group
System earthing
31. (a) HV HV Solidly earthed
(b) LV LV through NG resistor
32. Type of tap changer OLTC
33. Tapping range and number of steps -12.5% to + 7.5% (17 steps)
Maximum temperature rise at full load with
100% coolers: o
34. C 50
(a) Oil o
C 55
(b) Winding
35. Applicable standard for bushing IS 2099
36. No load loss kW 69 max
37. Load loss kW 305 max.
38. Cooler loss kW 8 max
39. Efficiency @pf=1
(a) At full load % 99.5 apprx.
No. of cooler banks and capacity of each
40. 2x50% Radiator bank
cooler bank
Guaranteed No load current
41. When excited from LV side at 100% and
110% rated voltage Amps <1%
Max. Flux density when rated and 110%
42
rated voltage Wb/m2 1.9 (Max)
Vacuum withstand capability of main tank, mm of
43 Full vacuum except Conservator
radiators and accessories Hg
Capability of transformer to remain in
44 operation from hot conditions after failure Min As per IS: 6600
of forced cooling with full load
Station Transformer-2
45 Type 3-winding, 3 phase, outdoor
46 Full load rating MVA 50/40/30
47 Rated no load voltage HV/LV KV 220/11.5
Rating of different cooling methods 80% / 100%
48
ONAN/ONAF OFAF/ONAF/ONAN
BTS
5% over the maximum SC fault
86 SC current rating
current on the bus
87 Short time current withstand duration seconds 1
88 Continuous current rating of the buses 20% over the maximum bus load
89 Type of CBs SF6 / Vacuum
Chapter-VII
TDBFP A PROTECTION
MD BFP C Protections
MILLS
I. Permissive:
1. Seal air header DP adequate >250mmwcl.
2. Pulveriger ready.
3. Pulveriger OFF.
4. Ignition permit available.
5. Switch gear available.
II. First outs
1. Loss of PA/FD Fans.
2. MFT
3. Mill Lub oil system.
4. Pulverige discharge valve not open.
5. Ignition Energy req. not available.
6. Electrical Trip.
7. SA Hdr/Pul/ DP low <200mmwcl.
8. Loss of primary air <500mmwcl.
9. Pulveriger start fail.
Feeders
I. First Outs
1. Pulveriger OFF
2. No coal flow trip.
3. MFT.
4. Elevation No ignition Energy.
5. Feeder not remote.
6. Feeder Seal air valve not open.
FD fan
1. Post purge fan trip from FSSS.
2. FD Fan-A motor bearing temperature very high. 105C0
3. FD Fan-A motor winding temperature very high. 105C0
4. ID Fan-A & B OFF.
5. FD Fan A&B ON and ID Fan A OFF.
6. FD Fan A ON and O/L damper close.
7. FD Fan A On and LO pressure very low.
PA fan
1. PA Fan-A lub oil pressure very low and PA Fan-A ON MFT OPTD.
2. PA Fan-A 3motor bearing temperature very high. 105C0
3. PA Fan-A motor winding temperature very high. 105C0
4. PA Fan-A motor bearing vibration very high. Both FD Fan OFF.
5. PA Fan-A ON and discharge damper closed.
BCW Pumps
1. Motor cavity temperature very high >66 degC
2. Discharge valve system- 1 N opened.
3. Discharge valve system -2 N opened.
Chapter-VIII
1. Load : 505 MW
2. Frequency : 50.01 HZ
3. Turbine Speed : 3005 RPM
4. Coal flow : 244 TPH
5. M.S Pr L/R : 174/174 Kg/Cm
6. M.S Temp L/R : 539/539 C
7. HRH Pr. L/R : 44.7/44.5 Kg/ Cm
8. HRH Tem L/R : 535/536 C
9. CRH Pr. L/R : 47.4/47.4 Kg/ Cm
10. CRH Temp L/R : 347/346
11. Aux. PRDS Pr/Temp : 17/210
12. Vacuum : -0.92 Kg/Cm
13. Seal steam Pr/Temp : 325mmwcl/290 C
14. CEPs disc. Flow : 1445 TPH
15. CEP HDR Pr : 23.44 Kg/Cm
16. CWP I/L temp : 28C
17. CWP O/L temp : 37C
18. ACWP disc Pr : 3.5 Kg/Cm
19. DMCW disc Pr : 7.5 Kg/Cm
20. Hot well level : 15.6 MM
21. LP exhaust temp : 43C
22. HPT Blanding Pr : 170 Kg/Cm
23. Shaft expansions
(HPTF / IPTR /LPTR) : 17.7/14.29/21.33 mm
24. Axial shift : 0.08/0.04/0.08 mm
25. Differential expansion (HP / IP) : -0.34/3.24 mm
26. Over all expansion (HP / IP) : 18.9/11.30 mm
27. Turbine BRGs VIB : 1. 18/20 2. 15/10 3. 21/23
4. 41/32
5. 14/64 6. 22/40 7. 19/30
28. Turbine shaft VIB : 1.213/97 2.151/77 3.92/64
4.35/57
5.35/75 6.62/74 7.53/60
29. MS flow : 1583 TPH
30. HP Bypass down steam temp L/R : 262/262C
31. EX5 Pr / temp : 24.6 Kg/Cm/ 412
32. EX4 Pr / temp : 6.69 Kg/Cm/ 292
33. EX3 Pr/temp : 3.13 Kg/Cm / 203
34. EX2 Pr/temp : 0.63 Kg/Cm / 118
SL.
NO. DESCRIPTION NORMAL ALARM TRIP
<6.3 mm/s 9.9mm/sec
1 FD FAN MOTOR VIBRATION PEAK 6.3 mm/sec (>10sec.)
2 FD FAN BEARINGTEMPERATURE 95 C0 105 C0
<6.3 mm/s
3 PA FAN MOTOR VIBRATION PEAK 6.3 mm/sec 9.9 mm/sec
4 PA FAN BEARINGTEMPERATURE - 95 C0 105 C0
PA, FD FAN MOTOR
- 95 C0 105 C0
5 BEARING+WINDING
12.6 mm/s
6 PAFAN, FD FAN BEARING VIBRATION <6.3 6.3 mm/s peak peak
7 DP ACROSS SCANNER AIR FILTER (Low) 10mmwc <5 * -
DP ACROSS SCANNER AIR FILTER
8 (High) 10 MM Wc >15 * -
9 DP SCANNER AIR TO FURNACE (Low) <125*
12 HFO PUMPS SUCTION STRNR DP (High) 0.1 >0.15 -
HFO PRESSURE PUMPS I/L COMMON
13 LINE (Low) -0.1 -0.15
14 HFO PRESSURE AT PUMPS I/L (Low) -0.5 -0.5
15 HFO PRESSURE AT PUMPS O/L (Low) 30 KG/CM2 29 KG/CM2
16 HFO PRESSURE AT PUMPS O/L (Low) 30 KG/CM2 28.5
TEMPERATURE BEF. OPERATING
17 FLOOR STRAINER OK 130c0 <90 C0
18 PRESSURE BEF. OPERATING FLOOR OK 23 KG/CM2 <23 KG/CM2
19 DP ACROSS OPERATING FLOOR (High) 0.15 >0.3
20 HFO HDR. PRESSURE (Low) 17.5 4.5 KG/CM2
21 HFO HDR. PRESSURE (2/3) (Low) 17.5 4. KG/CM2
22 HFO HDR. TEMPERATURE (Low) <95 C0
23 HFO HDR. TEMPERATURE (2/3) (Low) <85 C0
ATOMISING STEAM HDR. PRESSURE
24 (Low) 7.5 KG/CM2 <4.0
ATOMISING STEAM HDR. PRESSURE
25 (2/3) (Low) 7.5 KG/CM2 <3.5KG/CM2
Chapter-X
ID FANS INTERLOCKS
ID FAN A
START PERMISSIVES
1. Inlet Guide vane position minimum.
2. Hyd. Coupling scoop position minimum.
3. SAPH A/B Running and inlet / outlet dampers open & any FD discharge damper
open.
4. Hyd. Coupling oil pump ON and pr. Adequate. > 1.2 kg/cm.
5. Inlet / outlet dampers fully closed.
6. Hyd. Coupling oil level normal.
7. Hyd. Coupling oil temp. at cooler inlet normal.<95c
8. Hyd. Coupling oil temp. at cooler outlet normal.<65c
9. Temp. of Motor, Fan &8H.C. bearings are normal.<80c
TRIP CONDITIONS
1. Any hyd. coupling temp very high. >85c
2. Hyd. Coupling oil temp at cooler inlet very high. >100c
3. Hyd. Coupling oil temp at cooler outlet very high. >75c
4. Fan /motor bearing temp. Hi Hi>85c
5. Hyd. Coupling oil pressure lo lo <0.5 kg/cm.
6. Discharge dampers / gate does not open fully within specified time. 3 min after the
fan start.
7. Post purge furnace pressure hi/lo from FSSS.
8. Electrical protection Trip
9. Emergency PB pressed.
FD FAN A
START PERMISSIVE
1. Blade pitch position min.
2. Control oil pressure adequate >8 kg/cm.
3. Lub oil pressure adequate >0.5 kg/cm.
4. Any ID fan running AND no FD fan running
-OR-
Two ID fans running
5. Discharge damper fully closed.
TRIP CONDITIONS
1. No ID fan is running.
2. Fan / motor bearing temp. Hi Hi >85c.
3. Discharge damper does not open fully within specified time after 2 min starting
fan.
4. Post purge furnace pr. Hi / Lo from FSSS
5. FD fan B running. ID fan B running on BUS B & running ID fan A trips.
When the selector switch is in Auto. The oil pump starts under the following conditions.
PA FAN A
START PERMISSIVES :
1. F.D fan A or B running but PA fan B not running or both FD fan A & B running.
2. Blade pitch position minimum.
3. Outlet damper fully closed.
4. Start permit from FSSS
TRIP CONDITIONS
When the selector switch is in Auto the oil pump start under the following conditions.
1. Pump selected to LEAD pump start when fan start command is give.
2. Start by (LAG) pump starts when fan is running and control <6 kg/cm oil
pressure is low.
3. LAG pump starts when fan is running and LEAD pump trips.
TRIP CONDITIONS
AUTO START
ID FAN INTERLOCKS
1. Conditions existing when the unit is shut down and prior to starting of ID fans.
a. ID fan `A` & ID fan `B` off.
b. Regulating damper of fans A&B fully open.
c. Inlet gates of fans A&B open.
d. Outlet gates of fans A&B open.
e. The regulating dampers & VFD control will be on manual control during
shutdown, and impulse from furnace draft control to regulating damper of ID fans
disconnected.
f. Lube oil pumps of ID fans off.
Starting ID Fan `A` (ID fan `B` is off)
(a). ID fan `A` shall be prohibited from starting till the following conditions are satisfied :
i. Flue gas path available.
ii. Regulation dampers of Fan A in minimum position.
iii. Outlet gate of Fan A closed.
iv. Inlet gate Fan A closed.
v. Fan/Fan motor bearing temperature not very high.
vi. Motor winding temperature is not very high.
vii. One of the air heater is running with its inlet and outlet dampers kept open.
ix VFD system per missives satisfied (Refer clause 7.0)
x. VFD system `channel 1 ready` or `channel 2 ready` signal available (one
contact for
each channel).
xi. VFD system `channel 1 start permissive` or `channel 2 start permissive
available
from VFD system.
(b). The starting of ID fan `A` shall be done in following sequence
i. VFD system channel 1 start command starts fan `A` and runs up fan A to
minimum speed.
ii. When fan `A` reaches minimum speed. Impulse for VFD channel 2 start is
given by operator.
When ID fan `A` is started (ID Fan B is off ), impulses shall be given for.
iii. Opening the inlet gate and outlet gate of fan A.
iv. Connecting the regulating dampers / VFD control of Fan A to the auto control.
v. Closing the inlet gate and the outlet gate of ID fan B and bringing the
regulating dampers
to minimum Position.
Starting of ID fan B
a. ID fan B shall be prohibited from starting unless the following conditions are
satisfied :
i. Outlet gate of fan B is closed.
ii. Inlet gate of fan B is closed.
iii. Regulating damper of fan B is in minimum position.
iv. Fan/Fan motor bearing temperature not very high.
v. Motor winding temperature not very high.
vi. Lube oil system per missives satisfied .
vii. VFD system `auxiliary supplies healthy` permissive satisfied.
viii. VFD system `channel 1 ready` or channel 2 ready` .
ix. VFD system `channel 1 start permissive` or channel 2 start permissive
available.
i. VFD system channel 1 command start fan `B` and runs up fan `B` to
minimum speed.
ii. When fan `B` reaches minimum speed, impulse for VFD channel 2 start is
given by operator.
iii. When ID fan B is started, impulses shall be given for:
iv. Opening the inlet gate and outlet gate of fan B after the motor reaches the
prescribed speed.
v. Connecting the regulating damper and VFD control fan `B` to auto control
vi. Permission to start other FD fan.
General
a. Variable frequency drive
i. Individual start/stop push buttons shall be provided in UCB/CRT for each
VFD channel.
ii. Source breakers of VFD system have to be closed from plant I&C system
only if source
breaker close permissive is available from VFD system.
iii. The signal interface drawing of VFD system supplier shall be referred to
for preparation
of interlock schemes.
b. Fan outlet gate
If one ID Fan is started when the other ID Fan is of, the outlet gate of starting fan
shall be opened with starting of the fan to reduce the load of electrically operated
gate.
When starting the second fan the respective outlet gate shall be opened after the
fan reaches minimum speed
FD FAN INTERLOCKS
Conditions prior to starting FD Fans
a. FD Fan A and FD Fan B off.
b. Fan impellers tilted to maximum opening.
c. Outlet dampers are fully open.
d. Fan impeller regulator disconnected.
e. Lube oil pumps of FD fans off.
Starting FD Fan A
a. FD fan A shall be prohibited from starting until the following conditions are
satisfied.
i. ID Fan A or ID Fan B is on.
ii. Fan A damper in the minimum position.
iii. Outlet damper or fan A in closed position.
iv. Fan / motor bearing temperature not very high.
v. Motor winding temperature not very high.
vi. Lube oil system permissives satisfied.
b. when FD fan A is started impulses shall be given for.
i. Outlet damper of fan A to opened after the motor reaches rated speed.
ii. The outlet damper of FD fan B close & impeller blades of fan B to be
driven to minimum position.
iii. Connecting the impeller of fan A control drive to auto control.
Tripping of FD A
a. FD fan A shall trip automatically under the following conditions.
i. FD fan bearing temperature too high.
ii. FD fan A motor bearing /winding temperature too high.
iii. Both ID fans trip.
iv. Post purge fan trip.
v. Vibration level fan or motor very high. For fan, trip shall be initiated with
a delay of 10 minutes during starting and running of fan.
vi. Lube oil pressure of FD fan A too low.
b. when FD A trips impulses shall be given for.
i. Disconnecting the impeller control drove from auto control system.
ii. Bringing the impeller of fan A to the maximum position.
iii. Bringing the impeller of FD fan B to the maximum position.
iv. Opening the outlet damper of FD fan B.
v. To open the emergency scanner air damper.
vi. Boiler tripping.
vii. The outlet damper of FD fan A shall remain open.
PA FAN INTERLOCKS:
Conditions prior to start up
a. PA fan A and PA fan B off.
b. Outlet dampers of fan A and fan B closed.
c. Regulating vanes of fan A and fan B in closed position.
d. Regulating vane regulator disconnected.
e. Lube oil pumps of PA Fan off.
Starting PA fan A
a. PA fan A shall be prohibited from starting until the following conditions are
satisfied.
i. Regulation vanes of PA Fan A in the minimum position.
ii. Outlet damper of PA fan A in closed position.
iii. Anyone FD fan is on.
iv. Purge complete.
v. PA fan and fan motor bearing temperature not very high.
vi. Motor winding temperature is nit very high.
vii. Lube oil system permissives satisfied.
b. When PA fan A is started, impulses shall be given for:
i. Opening the outlet damper of PA Fan A.
ii. Connecting the regulating vanes of PA fan A to auto control.
iii. Bringing the regulating vanes of PA fan B to the minimum position.
iv. Closing the outlet damper of PA fan B.
v. Permission to start any three coal elevation through FSSS.
Tripping of PA fan A
a. PA fan A shall trip under the following conditions:
i. PA fan A bearing temperature too high.
ii. PA fan A motor bearing /winding temperature too high.
iii. Boiler trips.
iv. Vibration level of fan or motor very high. For fan, trip shall be initiated
with a delay of 10 minutes during starting and running of fan.
v. Lube oil pressure of PA fan A too low.
b. When PA fan A trip, impulses shall be given for :
i. Opening the outlet damper of PA fan B after the motor reaches rated speed.
ii. Connecting the regulating vanes of PA fan B to auto control.
iii. Permission to put in service remaining coal elevation through FSSS.
GENERAL
i. If one PA Fan is stated when the other PA Fan off, the outlet gate of starting
fan shall be opened with starting of the fan to reduce the load of electrically
operated gate.
ii. When starting the second fan , the respective outlet gate shall be opened after
the fan reaches full speed.
Chapter-XI
TG SIDE PROTECTIONS
d) IPT rear Brg. Temp. bottom front Ch1 >1300C, 2/4 Logic. >1000C
e) LPT rear Brg. Bottom front Temp. Ch1 >1300C, 2/4 Logic. >1000C
f) Gen. Brg. Temp. TE Ch1 >1300C, 2/4 Logic. >1000C
g) Gen Brg. Temp. EE Ch1 >1300C, 2/4 Logic. >1000C
h) Exciter Brg. Temp. Ch1 >1300C, 2/4 Logic. >1000C
on MOT level
< -150mm (1050mm from top)
Note: normal level - 0.0mm
14 Fire Prot. Optd. (900mm from top) < -50mm
15 UCB/UCP EPB optd. -
16 ATRS shut down CMD -
17 Emergency PB-HMI. -
** Difference (Condenser Actual Pr. Condenser calculated pr. As per curve) < 0,
i.e. actual condenser pressure falls below calculated value
CW PUMPS
ALARM
S.No TRIP CONDITION TRIP SETTING SETTING
0.9 KG/CM2
1 DISCHARGE PRESSURE V. LOW >90 sec
4.0 KG/CM2
2 DISCHARGE PRESSURE V. HIGH >90 sec
3.0 KG/CM2 >10
3 DISCHARGE HDR PRESSURE V. HIGH sec
SUMP LEVEL V.LOW (for cascade tripping of all
4 CWPs) 88.5 MSL 88.7 MSL
5 MOTOR WINDING TEMP. V. HIGH >140 0C >110C0
6 MOTOR BEARING TEMP. V. HIGH >95 0C >85C0
7 PUMP BEARING TEMP V. HIGH >95 0C >85C0
8 PUMP ON & DISCHARGE VALVE NOT OPEN
TDBFP-A/B
Trip Set Normal
S. N. Description Value Alarm Value working Value
< 2.0
1 Lube oil header pressure very low (2/3 logic). 1 KG/CM2 KG/CM2 2.5 KG/CM2
2 Exhaust. Steam temperature very high (2/3 logic). 1200C 850C 50-600C
> 11.2, < 4.5 7.0 - 9.0
3 Live steam pressure very high (2/3 logic). 12.5 KG/CM2 KG/CM2 KG/CM2
>-0.60 (-) 0.87
4 Exhaust steam pressure very high (2/3 logic). -0.4 KG/CM2 KG/CM2 KG/CM2
5 Gov. oil (Control Oil) pressure very low (2/3 logic) <4.5 KG/CM2 <6.5 KG/CM2 ~7.5 KG/CM2
+0.7/-0.7 +0.5/-0.5
6 Axial displacement very high (2/3 logic). KG/CM2 KG/CM2
Turbine Vibration high
8 G.B. O/P Vibration very high.5 sec. delay. 174 119 45
9 G.B. I/P Vibration very high.5 sec. delay. 174 119 45
11 Turbine F.J.B. Vibration very high, 5 sec. delay. 174 119 45
12 Turbine R.J.B. Vibration very high, 5 sec. delay. 174 119 45
6000 Mech.
10 Over speed (2/3 logic) (rpm) 6300 Elect. 4000 - 5800
13 D/A level very low (2/3 logic). -1510 0
7 Turbine Eccentricity High. <300 rpm - > 137 45
Temperature very high.
14 G.B bearing temperature, 1/6 Logic 1200C > 1050C 600C
a ) G.B. IP FJ temperature 1200C > 1050C 600C
b) G.B. IP RJ temperature 1200C > 1050C 600C
c) G.B. IPTBTM1 (IP Shaft) 1200C > 1050C 600C
d) G.B. IPTBTM2. 1200C > 1050C 600C
e) G.B. OP FJ temperature. 1200C > 1050C 600C
f) G.B. OP RJ temperature. 1200C > 1050C 600C
Turbine bearing temperature very high >2 sec.,
15 Logic
a) TB Act. temperature 1200C > 1050C 600C
b) TB Nact. temperature 1200C > 1050C 600C
c) TBFJB temperature 1200C > 1050C 600C
d) TB RJB temperature 1200C > 1050C 600C
16 B.P. bearing temperature very high Logic
a) B.P. bearing temperature D.E. side 950C 900C 650C
b) B.P. bearing temperature N.D.E. side 950C 900C 650C
CEPs
Trip Set Normal
S. N. Description Value Alarm Value working Value
<18KG/CM2
>10sec.
1 Pump ON & discharge pr. low 21 KG/CM2 28 KG/CM2
2 Hotwell level low -1955mm -250mm 0
<300 TPH
>10sec
3 Flow through CEP low
4 Thrust brg temperature very high Logic >1050C 1000C 800C
5 Motor brg temperature very high Logic 900C >2sec
850C 700C
>1300C
>2sec
6 Motor wdg. temperature very high 2/6 Logic 1250C 1000C
7 Suction valve not open
8 Emergency stop P.B.
Chapter-XII
ELECTRICAL PROTECTIONS
CLASS A
1. Differential protection:-
CLASS B
1. Fire failure 40G
2. GT HV WT1 R/Y/B 30GTA R/Y/B
3. GT LV WT1 R/Y/B 30GB R/Y/B
CLASS C
1. Negative phase sequence protection 46G.
2. Generator Back up impedance stage I 21G.
3. Gen. under frequency 81G3.
4. Pole slip protection 78G
5. GT standby earth fault stage I 51NGT
1. GT Over fluxing:
The iron core of the GT carries the flux to produce required E.M.F. If there
generator, GT becomes over saturated resulting in high magnetizing current. This is
turn leads to high iron losses which will increase the winding temp. of the
transformer. Since core can be damaged because of the over heating, protection has to
be provided against it. The flux is dependent on ratio of voltage and frequency.
The condition of over fluxing could arise in case the voltage at the machine
terminal rises or its frequency drops or both occurring simultaneously. Practically this
condition will arise. If the machine AVR misbehaves there by unduly increase the
voltage even when the gird frequency is low.
Setting for relay is V/f = 1.18 P.U, i..e 20% higher than rated V/f ratio.
Alarm is set. at 5secs and trip 2secs. V/f relay also generator AVR Raise
block.
rotational speed there by inducing double frequency current. As a result, eddy current
produces are very large and cause severe heating of the rotor winding particularly
damper windings.
For any current conditions in the three phases, the amount of unbalance can be
determined from the values of the negative sequence components of current by the
method of symmetrical components.
( 46GA, 46GT time delay 5sec.)
A direct short circuit between different phase with or without ground fault of the
winding causes a severe fault current to flow inside the affected machine and cause
highly extensive damage. As a result, there is a distinct difference between the current
at the neutral and terminal ends of the particular winding. This difference is detected
by the differential relay.
The current entering and learning the protection object is determined by current
transformers and compared by relays by means of a differential circuits
If the differential current exceeds a set percentage of the current flowing in the
protected object, the relay pick up.
If is set to operate current 5% of 5A.
The 400kv busing of the generator transformer are connected to the switch yard
by double moose conductor over head line. Any fault occurring on these lines is
detected by over head line differential protection.
0.1A with stabilizing resistor of 685 ohm. It picks upto 100A fault current .
UT`s are connected directly to the stator windings, so it has been provided
with a based differential so it has been provided with a based differential protection is
a similar circulation current scheme.
The H.V winding of the generator transformer is star connected and the neutral is
solidly earthed. The protection is meant for complete protection of HV winding of
generator transformer. The delta side of the generation transformer is considered as a
part of the generator and its earth fault would cause earth fault current to flow towards
the generator neutral and be detected as generator earth fault (64GT).
Chapter-XIII
D.G set
1. Check the D.G set physically for oil level, cooling water, battery voltage
1. Ensure electrical supply to C.W P& ACW pumps and other associated axillaries are
available
2. Ensure that all line clears (LC) are returned. All men and materials removed from
equipment and site
3. Ensure all soot blowers are in home position
4. Ensure RAW, fire fighting system is available for service
5. Get clearance in chimney from boiler maintenance wing for start up of boiler
operations
6. Start new pumps by checking permits & first outs, kept the other pump in Auto
Stand by
7. Start TG DMCW and SG DMCW pumps, check the pressures and kept the other
pump in Auto standby
8. Start SAC and IAC and check the service and instrument air pressure adequate i.e.
>6.5 kg/cm2
9. Fill the deareator with boiler fill pump make ready the chemicals to be mixed in
deareator
10. Start the MDBFP by checking all permits and kept in recirculation mode.
11. Start the dosing pump for adding chemicals to the MDBFP suction
12. After getting required chemical values start filling of drum. Check the drum level
Hydro Step & transmitters. Check for all control and Instrumentation system are
available for service
13. Start boiler circulating water pumps, observe and maintain drum level
14. Check MOT level and control fluid tank levels
15. Check CW duct filling .If not filled start filling by opening ACW to CW
interconnection valve
60. Check load reference set point more then 20 MW and less then 35 MW depending
upon main steam pressure.
61. Adjust the Voltage so that incoming and running Voltages values are same.
62. Adjust the turbine speed so that synchroscope is slowly rotating in clock wise
direction showing incoming frequency is slightly higher than gird.
63. Switch ON Auto synchronizer after two mimintes Generator breaker closed.
64. Immediately raise the load with help of speed reference upto 25MW.
65. Close HP/LP Bypass valves.
66. Slowly change speed control mode to load control mode.
67. Close all the drains which were opened during rolling.
68. Check the generator slot core, exciter air and hydrogen cold gas temperatures.
69. Check that pressure limiter valve slowly increase also ensure that load reference set
point is higher than the actual load valve.
70. Slowly increase Boiler firing with help mills and increase the load depending upon
main steam pressure
71. Raise the HP bypass pressure set point to about 180kg/cm 2 and temperature set point
to about 3400c to avoid HP bypass opening on auto.
Check the following conditions exist immediately after the unit tripping.
Generator / Field Breaker are tripped.
UAT`s Supply to unit buses are tripped and station supply takes over
automatically.
Generator AVR trips to manual mode.
All the turbine stop valves are closed.
CRH NRV at HPT Exhaust closed.
Turbine trip oil, Aux. Sec. oil and secondary oil pressure became zero.
All the feed water heaters Extraction Block valves are closed automatically.
Drain before HP control valves are closed.
Verify
Main turbine Aux. oil pump1 starts automatically. (if SLC is on).
Turbine gate valve gearing is opened automatically at 210 rpm (if SLC on ).
JOP1 start automatically if at 510rpm if SLC is on.
Turbine gate valve gearing is opened automatically at 210rpm ( if SLC is on).
Drum, SH / RH pressures rise on interruption of steam to turbine.
HP /LP bypass open , if on auto with proper set points.
Condenser vacuum breaker may open if tripping is because of fire protection or
axial shift.
SH/RH attemperation block valves are closed if spry control valves are less than
5% open.
Drum level may sink.
All mills & feeders with both PA fans tripped.
HFO trip valve may close as per oil gun logics.
Furnace vacuum dips to very low value due to implostion.
All wind box dampers open up after unit tripping.
Stop one set of ID /FD fans to avoid forced cooling of the boiler. Stablise &
Maintain the draught & air flow.
1. Take ACW, DMCW, CEP and MDBFP ( BFP C) pumps and maintain drum
level .
2. Take APH, ID Fans & FD Fans, increase the secondary air flow more than
680TPH.
3. Ensure all purge prmissivess are available and give push to purge command after
5 min. Boiler MFR gates reset. The first cause of Unit Tripping gates reset.
4. Ensure deaeretor pressure is maintain at 3.5 kg/cm and Auxiliary steam pressure
is maintained at 14 kg/cm .
5. Establish condenser vacuum 0.90 kg/cm.
6. Reset generator trip relay and turbine trip with the help of Starting device is
brought to 0% and observe trip oil pressure comes to 6.8 kg/cm (approx.).
7. Light up the Boiler with `CD` and EF elevation oil guns.
8. Ensure that minimum stable fire is established in the Boiler.
9. Open the following drain valves. (As per requirement)
Turbine can be rolled to rated speed either by ATRS rolling or manual rolling through
Electro Hydraulic Governor.
Degree of super heater of main steam before HP By pass is more than mid metal
temperature of H.P control valves/
Raise the starting Device above 42% and then to 56%/
1) Verify that all ESVs have opened.
2) Verify that drains before HP control valves are in auto and valves have
opened.
3) Put seal steam controller on auto.
4) Verify that the following generator conditions are fulfilled.
a) The degree of superheat of main steam before turbine is more than 50C.
b) M.S. temperature before turbine is more than either midwall temperature of
HP casing or simulated mid section temperature of HP shaft.
c) HRH temperature before turbine is more than simulated mid section
temperature of IP shaft.
During the warm up and hot start up of the turbine, observe the following parameters.
Differential Expansions.
Axial Shaft
Temperature difference between top and bottom of the HP/IP casing.
Bearing temperature and vibration.
Steam parameters.
TSE margin recorders for the following components HPS/HPC/IPS.
Operating parameters of condensing system.
Operating parameters of turbine oil& control fluid systems
Maintain MS temperature and pressure at turbine inlet as per start up curve.
HYDRAULIC ROLLING
Procedure 1
1. Initial speeder gear - 60 to 65%.
2. Isolate EHTC Hydraulic levers.
3. Generate Trip oil pressure by raising SLLD.[ SLLD bring it to 0 % to raise
trip oil pressure and then rise SLLD till STOP valves open about 35 to 36 %].
4. Observe the TSI parameters at Critical speeds 860, 1300 to 1500, 2400 to 2600.
5. Open and observe the SLLD about 35% Stop valves opened.
At about 42.4 % speed start raising and maintaining at 350RPM. Kept under
soaking to get the X-Ctiterias.
6. After fulfilling the X-Criterias raise the turbine speed by increasing the SLLD.
While raising the speed observe the dN/dT. Maintain it around 600RPM / Min and
should not less than 108RPM/min.( SLLD 60.3% 2900RPM Sec. oil HP :
4.34 ,Sec oil IP : 4.54,Aux sec :3.71)
7. Try to reduce speeder gear and observe the slightly change in turbine speed. That
means speeder gear is controlling speed. After ensure that, slowly increase SLLD
to 100% and leave it.
8. Match the turbine speed with grid frequency by controlling the speeder gear. Raise
the inching time of Speeder gear from 2sec to 4sec.
9. Synchronize the Unit by Manually.
10. After synchronization immediately raise the load up to 50MW to prevent low
forward power trip.
11. After reaching load 100MW change over the control from speeder gear to SLLD
care fully and raise speeder gear to 100%. Reduce speeder gear inch time from
4sec to 2sec.
12. Then control the load by using SLLD by observing the MS pressure.
Procedure 2
1. Check EHTC hydraulic levers are closed or not. If not closed, close the levers.
2. Increase speeder gear Inch. Time from 2sec. to 4sec. and keep the speeder gear at
20%.
3. Reduce the SLLD to 0% to turbine trip reset and slowly raise. At about 35% stop
valves open. At bout 42% speed starts raising. At around 48% speed will maintain
at 360RPM.
4. After fulfilling all X -criterias , raise SLLD slowly and check speed upto 2600
RPM
5. Then raise speeder gear and check speed is raising. Slowly raise the speed with
speeder gear to grid frequency.
6. Immediately after synernization, raise speeder gear fastly to load the generator.
After raising load about 50 to 60 MW slowly reduce the SLLD and check for
taking over of control and raise speeder gear to 100%. Reduce speeder gear inch
time from 4sec to 2sec.
7. Then control load with SLLD based on MS Pr.
***Raise the speed set point so as admit steam to the turbine &start rolling.
Raise the speed to 360rpm for warming up the casing.
Verify that gate valve gearing has closed.
Close all the drains valves as mentioned earlier for warm up of steam lines.
While admitting steam to the turbine, ensure that permissible wall temperature of
limit curves are not exceeded
AT 3000rpm
Verify that the following conditions are fulfilled.
1) Both AOP`s are off.
2) HRH temperature before LP bypass than IP shaft mid metal temperature.
3) Cold Hydrogen gas temperature is less than 45C
4) Main Exciter hot air temperature is less than 45C.
5) Cold primary water temperature is less than 50C
6) Cold primary water flow through bushing is more than 0.37 dm /sec and windings is
more than 13.3 dm /sec.
7) Differential temperature between primary water & Hydrogen is more than 1C.
Main steam temperature can be raised at the rate 1.6C up 485C and at the
rate of 0.6C above 485C till it reaches 540C.
1. Cut the mills from top up to C-mill one by one and reduce the load depending
upon the MS pressure.
2. At load 300MW, take MDBFP-C and kept in recirculation mode.
3. Take oil support in AB elevation.
4. Reduce the load along with Firing.
5. Change over the APRDS from CRH to MS.
6. At around 80kg/cm pressure, take the HPBP in to manual and open about >2%.
Oberve the opening of LPBP.
7. At 150 MW Trim device kept in Trim.
8. Trip the Turbine at 50MW load.
9. Observe the Turbine speed. At around 2850 RPM AOP starts in AUTO. Other
wise start the AOP manually.
10. Observe the Turbo supervisory parameters.
11. Observe the Turbine speed, At around 510 RPM JOP starts in AUTO. Otherwise
take manually.
12. It is recommended to maintain seal steam till 300RPM.
13. Observe the turbine speed, At around 210RPM Barring gear valve opened in
AUTO.
14. Observe the Turbine speed and is maintaining constantly around 110 RPM.
15. Observe LP exhaust Temp is maintaining around 45 C.
16. Kill the vacuum by switching OFF Vacuum Pump and Open Vacuum Breaker.
17. After reaching Vacuum -0.3Kg/cm2 Cutoff the seal steam by closing Seal steam
valve and open leak steam valve.
18. Exhauster Fan stopped and I/P isolating valve closed.
Chapter-XIV
The turbine is equipped with electro hydraulic governing system to facilitate the
operation of the turbo set in an inter-connected grid system. Three numbers of digital
speed measuring probes are installed in bearing house. The EHG system consist the
following control loops.
1) Speed control loop: The speed controller essentially compares the speed
reference generated by the speed reference limiter circuit and actual speed
of turbine and accordingly provides an out put for the valve lift controller.
The speed reference is generated by the speed reference limiter control
loop. The desired reference speed valve can be set remotely from control
desk of manually at the cabinet.
DN/DT Monitoring is provided to avoid rolling of the turbo-set at
or near critical speed. The acceleration of the set is monitored in the range
700RPM to 2850RPM. In case dn/dt goes below set valve the speed set
point is rolled back to the soaking value and set also.
2) Load control loop: The load controller receives the reference load signal
from the loaf reference limiter and also from the frequency controller
depending upon the frequency of the grid. These two signals are summed
in the load controller and the net value deriver for controlling the valve
position. The droop characteristics of the frequency controller can be
varied from 2.5 % to 8% in steps of 0.5%.
3) Pressure control loop: The pressure controller controls the turbine load
w.r.t the main steam pressure deviation and prevents a pressure drop, eg:
during a quick load increase. The to operational modes are
a) Initial Pressure control: Operation of the initial steam
pressure controller initiates the unloading of the set in the event of
initial steam pressure falling below a preset value. The unloading
of the set continues proportional to the available pressure the
loading of the set begins only if the firing rate in the boiler is
HG TO EHG TRANSFER
1. See the MS pressure set point and actual pressure deviation shall be less and in
negative side.
2. See that tacking device in OFF condition. It should be in OFF condition.
3. In this condition, plunger coil in OFF condition. Switch ON plunger coil.
4. Raise the load ref. set point to increase the EHTC position set point to 100% and
check the feed backs 1&2.
5. If everything is OK, parallel the EHG and HG Isolation manual leavers on
governing rack. Check the sec.oil pressures of HPCV & IPCV.
6. Then slowly reduce the load ref. set point (point by point) and observe the E/H
converter output and position feedbacks, load variation. When load variation
observed, start raising SLLD slowly and observe load, there should not be any
change in load. Raise the SLLD up to 85%.
7. Then put the tracking device ON. Then control the load by changing load ref. set
point.
The unit load demand is fed to Boiler master to generate Boiler demand i.e Air & Fuel
requirement and to Turbine control to sat Turbine demand i.e MW.
The control system envisages following modes of operation that are selectable manually.
1. Coordinated Mode : - In this mode both Boiler master and Turbine control are put in
`Auto` and unit load demand is fed to both Boiler and Turbine to compute their individual
load demands. The load demand signal will be added by Throttle pressure difference
before going to EHG & Boiler master.
2. Boiler Follow Mode : - In this mode Turbine takes load and the boiler follows. It is
adopted when Turbine control is in manual. The Turbine seta the MW load and boiler
controls throttle pressure as a follower. The load demand signal will go directly to EHG.
3. Turbine Follow Mode : - In this mode boiler takes load and the Turbine follows. It is
adopted during Runback situation. The boiler controls MW while the Turbine maintains
throttle pressure. The load demand signal will be added by throttle pressure difference
before going to EHG.
4. Manual Mode : - In this mode both boiler master and turbine controller are switched
over to manual and unit is controlled manually.
6. Run Down / Run Back : - `Run down` is switched ON automatically when the
process error i.e Feed water, Airflow etc. becomes excessive and the control element goes
to maximum position making process uncontrollable. Under the situation, unit load
demand is reduced to a valve as permitted by the process to get over the blockage.
Similarly `Run back` is initiated automatically in the event of tripping of unit auxiliaries
i.e BFP, IDF etc. to match unit demand with reduced unit capability.
`Up/ Down directional blockings` are introduced whenever process error i.e. Feed water ,
Air flow etc. becomes high or associated control element goes to maximum position to
hold the unit load demand till such time the process recovers. Under generator circuit
breaker OPEN and turbine trip the unit is run under house load operation.
The objective of this control system is to maintain the drum level to the normal water
level of the drum at all loads. At lower loads (<30%), the start up feed control valve will
be used as final control element and at higher loads, speed control of Boiler feed water
pumps will be used. Drum level is measured by 3transmitters through temperature
compensated constant head unit. The pressure compensated drum level signal may be
selected by Mid value Auto selection (MVAS) circuit of control.
Low Load:- The drum level measured signal is compared with the drum level set point.
The error signal will have a proportional, integral and differential action is the single
element controller. This controller out put will be the position demand signal for the start
up feed control valve.
High Load:- At higher loads the start up control valve shall be closed. The steam flow
shall be measured . In order to prevent sudden response due to drum swell and shrink on
load change, a time cog unit shall be included in the steam flow signal. Temperature
compensated feed water flow signal is computed by according feed water flow at
economizer inlet and super heater spray water flow. The error signal produced between
drum level measured signal and drum level set point shall have proportional integral and
differential action in the three element drum level controller this will be added with steam
flow signal which is the feed water flow demand signal (set point). This will be compared
with the feed water flow in the feed water controller. Deviation it any will have a
proportional and integral action in the feed water controller. This controller out put will be
the designed speed signal for the individual Boiler feed water pumps speed control
system. Position indicator is provided for the motor driven BFP hydraulic coupling scoop
position indication and speed indicator is provided for turbine drive BRP speed
indication.
Chapter-XV
EMERGENCY OPERATION
1.
Pilot oil pressure low alarm will appears.
2.
Standby AOP will start on AUTO.
3.
HPT front bearing vibration become high.
4.
TG bearing vibration high ( >35 microns).
5.
ABS shaft vibration BRGI casing front & BRG rear
increases.
6. Speed controller output will go to maximum.
7. MW goes up due to control valve opening.
8. Turbine rpm indicator will show gradual fall.
9. Speeder gear become ineffective.
NOTE : Prolonged operation under this condition is not recommended
1. Start permissive for all CEPs will go Motor cooling water flow LO.
2. All CEP bearing temperature start rising.
3. DM water pump discharge pressure decreases.
4. If DMCW pump A trips : DMCW pump A motor current decreases to Zero
DMCW pump A motor status become trip DMCW pump A motor trip.
5. If DMCW pumps B trips : DMCW pump B motor current decreases to Zero
DMCW pump B motor status becomes trip DMCW pumps B motor trip.
6. If DMCW pump C trip : DMCW pump C motor current goes to zero DMCW
pump C motor status become trip DMCW pumps C motor trip.
7. DM water pump discharge pressure decreases.
8. All bearing temperature will rise, Hydrogen gas, PW, exciter hot air temperatures
increases. Unit may trip on any of the above temperature high protection.
Emergency 7 : FAILURE OF + 24 V DC
CAUSE : REASON NOT KNOWN
Identification :
NOTE : a). Confirm the starting of EOP. Trip the Turbine in case restoration of
24v
1. DP across FD fan A/B lube oil filter becomes H1 ( > 1.2 Kg/cm) with a short
delay.
2. Annunciation FD fan cont/lube oil press low comes in (<0.8 Kg/cm)
3. FD Fan A/B lube oil pressure becomes low
4. FD Fan A/B bearing temp monitor shows increasing valve as the temperature
increases gradually with a time delay of 6-8 minutes.
5. Annunciation FD fan / motor bearing temperature high comes on after
sometime.
6. FD fan lub oil pressure adequate permissive lamp will go off
7. FD fan A/B Motor/ fan brg temperature high comes in (>90/105c)
1. The ctrl oil drops below 1.8Kg/sq cm. This causes the lead pump to
take auto start red ON lamp comes, green OFF lamp goes off.
2. ID fan control/lub oil pr continues to drop, the permissive lamp
hydraulic coupling oil pr adequate goes off at pr less than 1.2
Kg/cm)
3. ID fan vibration high alarm also comes
4. ID fan control oil pr low annunciation appears ( <0.8 kg/cm)
5. Running ID fan A HC oil pr low alarm appears
6. ID fan trips on hydraulic oil pr low protection bkr trip white lamp
appears ( <0.5 Kg/cm)
7. ID fan tripped/start failure annunciation appears
16. Flue gas pressure at RAPH inlet gradually decreases to normally value
17. Furnace pressure gradually decreases to normal value.
Chapter-XVI
2FA
2FB 11KV Station switch board OBB Control Supply-1
2FC 11KV Station switch board OBX Control Supply-1
2FD 3.3KV Station Aux. switch board OCA Control Supply-1
2FE 3.3KV Station Aux. switch board OCB Control Supply-1
2FF Station Transformer-1 CCC Supply
2FG Station Transformer-1 RTCC Supply
2FH Emergency Lighting
7FA Spare
7FB EOP
7FC TDBFP-B EOP
7FD Spare
1RA
1RB Fire Water MCC-1
1RC ID FO-1
1RD SSS-1
1RE TG AC MCC-1
1RF TG vent MCC-1
1RG BOP-1
2R
2RA TDBFP-A EOP
2RB Spare
2RC PTP-1
2RD Silo,Hydrobin,PMCC
2RE SAT-1
2RF ETP-1
2RG Spare
3R
3RA SOP
3RB 11kv - 11BA-1
3RC 11BB-1
3RD UAT-1
3RE 11CB-1
3RF USS-1
3RG Boiler MCC-1
3RH Turbine MCC-1
3RI EMC-1
3RJ D Pass Control Supply
4R
4RA ATRS-SGC Turbine& SLL Drain
4RB ATRS-SGC Oil Supply Hp Controls Fluid
4RC Sol Valve-3 TDBFP-A
4RD Sol Valve-4 TDBFP-A
4RE Sol Valve-5 TDBFP-A
4RF Sol Valve-6 TDBFP-A
4RG Sol Valve-7 TDBFP-A
4RH Sol Valve-8 TDBFP-A
4RI Load shedding relay & Auto synchroniser
4RJ GCP-GRP Control supply
4RK MSSV left
5R
5RA Nil
5RB
5RC
5RD
5RE
5RF
5RG Alarm module
5RH Incomer from AHP-6R4
6R
6RA Sol valve-1 TDBFP-B
6RB Sol valve-2 TDBFP-B
6RC Sol valve-3 TDBFP-B
6RD Sol valve-4 TDBFP-B
6RE Spare
6RF Jacking oil pump-2
7R
7RA OBA-2
7RB OBB-2
7RC OBX-2
7RD OCA-2
7RE ATRS
7RF BTS-1 Source-2
7RG SH electric Relief valve left
7RH GCP & GRP
7RI DAVR
7RJ VFD control for ID fan
7RK Scanner Air fan DC motor
8R
8RA 11BB-2
8RB OCB-2
8RC ST-280 MVA CCC supply
8RD ST-2 RTCC supply
8RE SAT-2 CCC supply
8RF TG AC MCC CS-2
8RG ID & FO MCC
8RH UAT-CCC supply (UAT-2)
8RI ESP Board CS-2
8RJ D Pass
8RK AHP & CHP Control supply-2
8RL FSSS
9R
9RA Sol valve-8 TDBFP-B
9RB C-Pass-1
9RC USS-2
9RD B Pass
9RE Boiler MCC-2
9RF Turbine MCC-2
9RG EMC Control supply-2
9RH ECP-2
9RI
9RJ
9RK
9RL
Annexure-I
MDBFP-C
Make :- BHEL
Specification :- IS325
Frame :- 11F7842
Duty :- Continuous
KW :- 10,000
RPM :- 1,495
Stator Volts :- 11,000
Rotor Volts :- ------
Temp Rise :- 70oC
Insulation Class :- F
Phase :- 3
Freq :- 50 HZ
Connection :- Stator Rotor :-
Amb-Temp :- 50oC
Stator Amps :- 605A
Rotor Amps :- -----
Rotor type :- SQ Cage - Rotor
DE Bearing :- 220X140
NDE Bearing :- Q220X140
Deg.Of Protection :- IP 55
Serial. No :- 46244A 421-41-01
Division :- Bhopal
Year :- 2009
Weight :- 23,000Kg.
Make :- BHEL
Specification :- IS-325
Frame :- ILA7904-4
Duty :- Continuous
KW :- 2650
RPM :- 1494
Stator Volts :- 11,000
Rotor Volts :- ------
Temp rise :- 70oC
Ins Class :- F
Phase :- 3
Frequency :- 50HZ
Connection :- [STAR]
Amb- temp :- 50oC
Stator Amp :- 152 A
Rotor type :- Cage type
DE Bearing-1 :- NU 236m
DE Bearing-2 :- 6236 C3
NDE Bearing :- NU 232 m
Deg-of Protection :- IP 55
Division :- Bhopal
Year :- 2008
Weight :- 3500 Kg
Cooling Code :- IC 0151
Make :- BHEL
Frame :- 11 A 7714 68
Duty :- Continuous
KW :- 1025
Stator Volts :- 3300 V
Stator Amps :- 229 A
Rpm :- 993
Phase :- 3
Frequency :- 50 HZ
Insulation Class :- F
Specification :- IS 325 1996
Connection :- [STAR]
Amb temp :- 50oC
Deg.Of Protection :- IP 55
DE Bearing-1 :- NU 230 m
DE Bearing-2 :- 6230 C3
NDE Bearing :- NU 226 m
Year :- 2009
Weight :- 7550 Kg
Division :- Bhopal
Rotor type :- SQ-Cage
ID FAN-A/B
FRAME. : ILA4344
Phase/freq : 3ph/50HZ
Stator Voltage : 2X2300V
Stator amps : 4X461
EDCC amps : 291A
rpm : 505
Connection : STAR
Type : synchronous motor
Rating : 3000KW
Make:- BHEL
Frame :- ILA 7636 6
Duty :- Continuous
KW :- 525
Stator Volts :- 3300 V
Stator Amps :- 130 A
Rpm :- 985
Phase :- 3
Frequency :- 50HZ
Insulation class :- F
Specification :- IS 325 1996
Connection :- [STAR]
Amb temp :- 50oC
DE Bearing-1 :- NU 228 m
DE Bearing-2 :- 6228 C3
C.E.P:- 11A,11B&11C
Make:- BHEL
Frame :- 1LA7634-4
Duty :- Continuous
KW :- 900
Stator Volts :- 3300V
Stator Amps :- 194A
Rpm :- 1486
Phase :- 3
Hz :- 50
Insulation class :- F
Specifications :- 1s : 325-1996
Connection :- [STAR]
Amb-temp :- 50oC
Deg- of Protection :- IP55
DE Bearing :- 6226 C3
NDE Bearing :- 7322 B
Year :- 2009
Weight :- 5500Kg
Division :- cage
SGDMCW PUMP-A/B
FRAME. : ILA7500-4
Phase/freq : 3ph/50HZ
Stator Voltage : 3300V
Stator amps : 229
rpm : 1483
Connection : STAR
Type : induction motor
Rating : 150KW
TGDMCW PUMP-A/B/C
FRAME. : ILA7500-4
Phase/freq : 3ph/50HZ
Stator Voltage : 3300V
Stator amps : 55
rpm :1479
Connection : STAR
Type : induction motor
Rating : 250 KW
Annexure-II
Annexure-III
1. TURBINE INFORMATION
Casing:
The casing serves to contain and support the stationary and rotating parts of the
turbine. The casing has been horizontally split in the plane of the shaft centerline.
The vertical joint is made up permanently at the factory. The upper half of the
casing contains the high pressure steam chest, the steam admission valve seats and
the upper halves of the diaphragms.
The casing supports have been designed to minimize effects of thermal expansion
and hold the turbine in axial alignment.
Shaft Packing:
Shaft packings are provided at both ends of the turbine casing where the rotor
passes through it. These packings are of the metal labyrinth type and they are piped
to and work in conjunction with the steam seal system to minimize leakage of
steam from or air into the turbine case along the shaft.
Each labyrinth ring is composed of four spring loa ded, butt jointed segments
which are recessed into bores of the labyrinth housings or turbine casing.
Oil Guards:
Shaft oil guards serve to prevent leakage of oil from the bearings along the shaft.
The horizantally split oil guards are fitted into grooves in the lower bearing
brackets and the bearing bracket caps.
Diaphragms:
The diaphragms, mounted in grooves in the turbine casing act as partitions to
divide the turbine into separate compartments for each stage. They contain
stationary nozzles which direct the steam into the following rotating stages. Each
diaphragm is horizontal split through the plane of the shaft centerline.
A drain hole is drilled through the bottom of each diaphragm to remove any
condensate.
Stage Packing:
To minimize steam leaka ge between turbine stages where the shaft passes through
each diaphragm, labyrinth type metal packing is used. These stage packings each
consist of a number of segments. The segments are mounted in grooves in the
inner periphery of the diaphragms.
Main Bearings:
The main bearings supporting the rotor, are of the babbit-lined, multiple tilting pad
type. The bearings are similar in construction and are pressure lubricated.
Thurst Bearing:
The rotor is axially positioned by a double acting thurst bearing of the multiple-
shoe, self-aligning and equalizing type. This thrust bearing is mounted in the front
bearing pedestal next to the radial bearing.
Rotor:
The turbine rotor consists essentially of a shaft with wheels and blades, coupling
hubs, a thurst collar and a spur gear used for the electronic governor and used for the
tachometer. The spur gear has been mounted to the turbine rotor on high pressure
end.
Turning Gear:
An electric motor driven "B.H.S." turning gear type RDV-2 is furnished for
turning the rotor at a speed of 100 rpm upon start up and after stopping the turbine,
in order to maintain an equal heat distribution in the turbine rotor. For manual
operation, the free end of the electric motor has been provided with a square. A
ratchet wrench that fits on this square, can be used for manual turning. The
turning gear can only be started when the turbine is at stand still.
a) Automatic start - When the turbine is tripped, the turbine is at stand still
and the disconnect coupling is at disengaged position, the release solenoid is
shortly energised. This releases the swinging arm from the latch. The pinion will
come down on the toothed wheel rim, which is mounted on the turbine shaft.
When the pinion and toothed wheel rim engage, (detected by a limit switch) the gear
motor will be started. When the pinion and the toothed wheel rim do not engage
within a set time, operational mode will change from "automatic" to "off". One must
then locally engage the mentioned gears by slight turning of the hand wheel of the
electric motor. Now press push button "on" to start turning gear.
b) Start by push button command - This start is similar to the automatic start
except that the disconnect coupling is not nece ssarily disengaged position.
c) Automatic stop at starting the turbine - When the turbine gear is driving the
turbine rotor the forces on the teeth of the pinion and the toothed wheel rim are
directed such that engagement is positively maintained. Now when turbine is
started and speed increases, the turbine will have the tendency to drive the
turning gear. Due to this the forces on the teeth of the pinion are in such
direction as to disengage the turning gear. This causes an immediate and
automatic release of the pinion from the toothed wheel rim through the lift of the
swinging arm. This a rm catches a latch and remains in disengaged position.
Disengagement of the gear is detected by a limit switch which causes the E-motor
to be switched off. The turning gear can also be stopped by:
instrumentation, will measure the shaft vibration and total run out and will give
an electrical alarm signal, when the vibration level rises above a preset value.
Speed Indicator:
The turbine is provided with an electric speed indicator consisting of a gear, a
probe, a transmitter and an indicator. The probe is mounted on the front bearing
housing and it senses the rotation of a gear with 60 teeth. The gear is mounted
on the turbine shaft. The probe produces a pulse every time a tooth passes through
its magnetic field. These pulses are converted into a "mA" signal that is fed into the
indicator.
Breakable Diaphragm:
A breakable diaphragm has been installed on the top of the exhaust casing. It
consists of a rupture disk clamped between flanges. The disk will burst if the
turbine exhaust gauge pressure will rise to 0.5 bar. Exhaust steam will pass then
to atmosphere, reducing the excess exhaust pressure.
These valves are opened during starting to remove any accumulation of condensate
and they are closed when the equipment is in operation.
2. PUMP INFORMATION
General:
The pump is a multi-stage type having all impellers mounted in series and facing in
the same direction. Liquid enters the suction nozzle, passes through the impellers
and leaves through the discharge nozzle at opposite end of the casing. Each
impeller operates within a diffuser which converts velocity to pressure. This
process is repeated in the successive stages, each stage adding an increment of
pressure. Discharge pressure is admitted to areas between inner and outer casing
thus utilizing hydraulic forces to maintain sealing of individual stage joints and of
the internal joints between the inner a nd outer c asing.
Outer Casing:
The outer casing is a forged cylindrical shell or barrel, which has nozzles to conduct
the pumped fluid to and from the inner casing and rotor.
Inner Assembly:
The inner assembly consists of diaphragms, diffusers and a rotor which are
assembled together to form a single assembly. The inner assembly is positioned
into the outer casing by a cylindrical fit and held in that position by bolts.
Inner Casing:
The inner casing portion of the inner a ssembly consists of a combination of chrome
steel diaphragms & diffusers. These form the hydraulic passages between successive
stages.
Rotating Element:
The rotor basically consists of several impellers, a thrust collar, shaft sleeves and
a balance drum mounted on the chrome steel shaft.
End Head:
The end head closes the outer casing a fter insertion of the inner assembly. The end
head supports the outboard seal housing and the outboard bearing housing.
Gaskets:
The joint between the end head and outer casing is the sole high pressure outside
joint in the pump. This joint contains a confined flexitallic gasket which has been
compressed by the heavy alloy steel bolting which secures the end head to the
outer casing. This flexible gasket assures proper sealing even during transient
temperature changes. There are no gaskets used at the internal high pressure joints
nor at the inter stage joints.
the bore of the balance sleeve, acting as a pressure reducing bushing between the
pump discharge and pump inlet pressures. The water, which leaks past the balance
drum, is returned to the pump suction. The diameter of the balance drum and the
pressures acting on it are such that an axial force is produced on the rotor,
which counteracts the axial force caused by the impellers. For design reasons the
axial force of the impellers is not fully counteracted by the down force for the whole
of the working area of the pump. Therefore a double acting thrust bearing has been
installed which takes up the resultant axial force. The stationary balance sleeve is
bolted to the end head and sealed by a confined flexitallic gasket. The rotating
balance drum is mounted with a shrink fit on a tapered portion of the shaft using a
hydraulic tool. This type of mounting securely locks the balance drum against
rotational and axial movement. In addition the drum is held in place by a retaining
ring fitted in a groove in the shaft and shouldered against the drum. An "O" ring
and a back-up ring are fitted in the balance drum bore to prevent leakage of
hydraulic pressure oil when mounting or dismounting the balance drum.
Main Bearing:
The rotor is supported by Glacier Babbitt lined, multiple tilting pad type bearings.
The pads of each bearing are fitted into slots in a two-piece bearing housing and are
located by screws. The horizontal split bearing housing is mounted in a bore in
the bearing bracket. The bearing housing is prevented from rotation by a pin.
Pressure lubrication is employed. Oil piped from the lubrication system flows to the
bearings through passages in the bearing brackets. This oil passes out through the
individual bearing drain.
Thrust Bearing:
A thrust bearing, consisting of a rotating collar, which is mounted on the pump
shaft and operating between two identical thrust elements, is provided to maintain
the axial position of the rotor under all operating conditions. This bearing is
located in a thrust bearing housing formed by the bearing bracket at non driver side.
The bearing is lubricated by oil from the main oil system. The oil is led into the
thrust bearing through holes in the bearing bracket and is sprayed between the
shoes and the thrust collar at the leading edge of each pad. On reaching the collar,
it turns outward between the shoes and escapes around the collar. The thrust
bearing cleara nces are such that during normal operation there is an oil film on
both sides of the collar, between the colla r and the thrust faces. Thermocouples
are installed in some of the thrust bearing shoes to measure the bearing
temperatures.
Warming-Up System:
Warming-up system has been installed on the pump to keep the temperature
differance between the discharge end and the suction end below 250 C. Normally
the pump is warmed up with the discharge line closed and the suction line open.
Then the warm-up liquid is admitted to the pump through the warm-up
connection and out through the suction nozzle. Thermocouples have been
installed on the suction and discharge end which provides, together with a
temperature switch, control signals for a motor operated valve in the warming-up
supply line.
3. OIL SYSTEMS
The oil unit supplies lube oil to the turbine, main pump, coupling, Tacke gearbox,
BHS turning gear and the booster pump. It also supplies oil to the governing oil
system of the turbine. The oil reservoir supplies the oil required to operate the
systems. Condition of the oil should be checked at least twice a year.
Lubrication System: Lubrication oil is supplied from the main oil reservoir. This
reservoir is a
fabricated steel tank having a maximum operating capa city of about 4050 liters
and a stand still capacity of 4500 liters, the tank scale is about 45 liters to a cm
height. The tank is fitted with a deaeration tray to prevent foaming of oil
entering the tank through the filler pipe or draining back to the tank from the oil
system. A level glass is mounted on the side of the tank. The reservoir is equipped
with a tank drain, an oil filter cap, two motor driven oil vapour extractors and
low & high level a larm switc hes. The AC electric motor driven main oil pump is an
"Allweiler" pump designed to deliver 855 l/min. at a gauge pressure of 15kg/cm2.
The AC electric motor driven auxiliary oil pump is identical to the main oil
pump. It will take over the oil supply if the main oil pump fails for any reason or
when the control oil gauge pressure drops to 7 kg/cm2 or when lube oil gauge
pressure drops to 1.6 kg/cm2.The oil system is also provided with a DC electric
motor driven emergency lube oil pump which will start if the lube oil gauge
pressure drops below 1.2 kg/cm2 for any reason. The main and auxiliary oil pump
discharge lines are fitted with relief valves, set at gauge pressure of 16 kg/cm2 to
protect the pumps from damage due to excess pressure. Pressure indicators are
installed on the discharge lines to determine the output pressure of the pumps and
pressure switches are installed to start the standby pump if the discharge pressure of
the running pump drops to a gauge pressure of 7 kg/cm2. The relief valve behind
the emergency oil pump is set at a gauge pressure of 5.2 kg/cm2.After passing
through check valves, the oil is directed to a three-way transfer valve. This valve
permits passage of oil to either or both of the oil coolers, where the oil is cooled if
necessary to the proper operating temperature of 400 C. Thermometers are fitted at
the inlet and discharge of the coolers, so that the operation of the coolers can be
checked. A temperature switch has been installed on the cooler outlet line for
giving an alarm when the oil temperature is too high. The switch has been set at
500 C. After passing from the discharge of the coolers, the oil is piped to a duplex
oil filter. The filter is fitted with a pressure differential indicator and a pressure
differential switch which will give an alarm signal at too high pressure
difference, setting 0.8 kg/cm2. Before switching over a filter or cooler, make sure
that the filter or cooler, that will be taken into service, is filled with oil and vented.
From the filter, the oil at a ga uge pressure of 10 kg/cm2, is piped to the turbine
control oil system and, via orifice and check valve, to the bearings of the turbine
and the pumps, to the turning ge ar, to the coupling between the turbine and the
main pump and to the gear box. Several switches have been installed on the oil
system. An oil separator has been installed on the oil unit. This separator
should be in operation as long as the oil unit is in operation.
Control System:
Oil at a gauge pressure of 10 kg/cm2 is delivered to the turbine control system.
This system is described in the next section.
4. CONTROL SYSTEM
(Please refer CONTROL OIL DIAGRAM BFP TURBINE in schematic diary for
the various valve numbers & solenoids mentioned in this chapter.)
The turbine electronic controller provides electical outputs to position the steam
admission valves. The electrical signals are converted to mechanical movements by
a proportional electric/ hydraulic/mechanical actuator. The mechanical output of
this actuator will position the control linkage of a hydraulic relay valve power
servomotor. The servomotor positions the steam admission valves. The admission
valves are designed so that the HP valve opens after fully opening of the LP
valves. The turbine drives the booster pump and the main boiler feed pump. At
normal operation the turbine speed will be controlled by signals from the boiler
control system. The controller can be devided into three parts, namely:
commands raise/lower to the "digital ramp position control" in order to maintain the
required feed water needs.
A bumpless automatic transfer is provided to return from "position control"
to "speed control". This basically operates as follows:
After a "request mode transfer" is given by push button command, the speed
set point will automatically be set such that the output of the speed governor
equals the output of the position control. This is done by a window comparator
that compares the output of the speed governor with the output of the position
control and gives raise lower signals to the "digital speed reference". When the
output of the speed governor equals the output of the position control the transfer
from "position control" to "speed control" takes automatically place, the
automatic tracking of the "digital speed reference" stops and the automatic tracking
of the "digital ramp position control" for normal operation starts again. Thus the
position control follows the speed governor output again.
At frequencies below 350 Hz (equals to 350 rpm) the signal from the speed
pickup is insufficient to drive the speed sensor. This means that below this speed
the control system is in "position control" mode. Consequently the turbine is
started up using the position control and when the turbine speed is above 500
rpm the system is transferred to the "speed control" mode.
Speed Reference: The speed set point is provided by a "digital speed reference".
The "digital
speed reference" can be operated manually by push button raise/lower or by the
analog 4-20 mA feed water control signal (or automatically, when changing from
"position control" to "speed control" mode, as described above). When the feed
water control signal sets the speed set point, raise/lower signals are given to the
"digital speed reference" by a window comparator that compares the output of
the "digital speed reference" with the feed water control signal. The speed range
that can be set manually by push buttons is 500 rpm to trip speed. The speed
range that can be set by the feed water control signal is 2000 rpm to max.
continuous speed. Upon loss of the feed water control signal (signal being far
below 4mA) the speed setting automatically switches to manual.
Power Supplies:
The speed governor is powered by power supply 1 or 2. At failure of one power
supply the speed governor remains in operation. The position control is powered by
power supply 3. Consequently the powers for the speed governor can be
switched off for repairs of the speed governor while the turbine remains in
operation by means of the position control during operation.
The three independent overspeed switches receive power from all 3 power
supplies. This means that these overspeed switches are always powered when the
turbine is in operation. The switches have been set at 5925 Hz(rpm).
Servomotor:
The function of the servomotor is to open or close the turbine steam admission
valves in response to governing demands. It consists of a pilot valve and a power
piston (the power piston's stem is connected to the valve lifting lever) a hydraulic
amplifier which also consists of a pilot valve (which is connected to the output shaft
of the Woodward actuator) and a power piston. The power piston of the hydraulic
amplifier acts to position the servomotor pilot valve. The operation of the
servomotor is as follows: Assume that the pilot va lve of the hydraulic amplifier is
moved downward by the Woodward actuator. Oil will be admitted at the bottom
side of the amplifier's power piston causing the piston to move upward. The pilot
valve of the servomotor will also be moved upward and oil will be admitted to the
top side of the main power piston and oil from the bottom side is ported to drain.
This strokes the main power piston downward, thereby opening the steam admission
valves. When the power piston move, the pilot valves will be returned to their
central position by the action of the respective external feedback linkages. Limit
switches have been installed for valve position indication and they will give a
reset condition signal to the reset system when the valves are closed.
Tripping System:
Automatic tripping is accomplished by turbine overspeed, too high bearing metal
temperature, too high axial displacement and too low lube oil and/or trip oil
pressure. Under all these actions the turbine trip solenoids will be activated and
trip oil pressure is released to drain, allowing the steam trip valves to close, thus
shutting off the steam flow to the turbine and causing the turbine to shut down. At a
trip of the turbine, also the turbine control valves will be closed through a contact
that causes the Woodward actuator to run to the closed position.
Trip Valves:
The high pressure, and low pressure steam inlet lines are provided with a trip
valve. These valves will immediately shut off the steam supply to the turbine
when a turbine trip occurs. These valves are opened by the trip oil pressure and
will be closed by spring force if the trip oil pressure drops below a certain value.
The va lves are provided with an electronic exercise system for checking the
functioning of the electronic overspeed trip system and the freedom of the trip
valve moving parts during operation. This system consists of a signal generator,
several relays and switches and solenoid valves. The system functions as follows:
By pushing the "TEST" knob circuit 1,2 or 3 the output of the signal
generator is supplied to the speed switch 1,2 or 3 of the Woodward. At the same
time, solenoid 307 will be switched into the test position and will prevent the
turbine from tripping when solenoid valve 308 is energized (opened). Increase the
output of the signal generator, upon reaching the trip frequency, solenoid valve 308
will be energized and oil is drained from the trip valve cylinder causing the piston
to move in the valve closing direction by spring force. The piston stops
automatically as soon as the piston closes drain hole. This position will be
indicated by the lamp "Trip valve test position". Decrease the output of the
signal ge nerator and release the "Test" knob.
Check to see that the trip valve's piston returns to its normal position. Repeat
this procedure for the second trip valve. The above described test should be done
once a week. The oil cylinder of each trip valve is equipped with a relay valve which
opens a large flow area around it for fast tripping upon loss of trip oil pressure,
without using large oil lines. When the emergency system is reset, the relay valve
closes under influence of the trip oil pressure. On steam side the valves are fitted
with an integral steam strainer.
Overspeed Trip:
Besides the three electronic speed switches as described above, the unit is also
provided with a mecha nical overspee d trip. This device is a spring loaded
plunger set radially in the overspeed trip body. This body is mounted to the pinion
of the gearbox. At the designed tripping speed(5900 rpm) the centrifugal forc e of
the plunger overcomes the counteracting force of thr plunger spring, the plunger
moves outward and strikes the nut of the handtrip device causing trip oil pressure to
drain, which results in closing of the trip valves. For test purposes the overspeed trip
can be made to act at operating speed (without tripping the unit) by filling the plunger
with oil. To test the mechanical overspeed trip during operation handle as
follows:
1) While running the unit at 4700 50 rpm. push the test va lve 310 into
test position. This will prevent the turbine from tripping.
2) Open valve 301, Thus admitting oil into the overspeed plunger
causing the plunger to move outward.
3) Make sure that the plunger has struck the hand trip device nut. If
necessary readjust the overspeed trip device.
4) Close valve 301, wait a few minutes so that oil can leave the plunger
causing the plunger to retract.( TO AVOID DAMAGE TO THE
HAND TRIP DEVICE, DO NOT ATTEMPT TO RESET IT
BEFORE THE PLUNGER OF THE OVERSPEED HAS
RETRACTED.)
5) Reset the hand trip device.(TO PREVENT THE TURBINE FROM
TRIPPING, THE HAND TRIP DEVICE M UST BE RESET.
BEFORE RETURNING TEST VALVE 310 TO THE NORMAL
POSITION.)
6) Release test valve 310 so that it returns to the normal position.
The above described test should be done at lea st every two months. During
this test the mechanica l overspeed trip can not shutdown the turbine. The unit
however is still protected against overspeed by the overspeed switches which are
part of the woodward governor.
Handtrip Device:
This device is mounted on the gearbox at free pinion end. When the stem of this
device is moved by the overspeed trip plunger, it will be moved into the valve
body. This opens the valve and releases the pressure in the trip oil line, causing
the trip valves to close. The hand trip device can be manually reset, but normally
this will be done by the action of its solenoid 311. The solenoid is energised then
for some time to close the valve against spring force until it is held closed by trip
oil pressure.
BEFORE RESETTING THE HAND TRIP DEVICE, MAKE SURE THAT
THE OVERSPEED PLUNGER HAS RETRACTED. IF NOT, RESETTING
WILL CAUSE DAMAGE TO THE TRIPPING MECHANISM.
1) Make sure that the main steam block valves are closed.
2) Start the main or auxiliary lube oil pump and check the oil pressures.
3) Reset the trip oil system.
4) Trip the unit by releasing lube oil pre ssure.
5) Observe the action of the trip valves to see that they trip instantly With no
evidence of sticking or binding.
5. OPERATION
Normal Starting Preparations:
1. Energize all control and alarm circuits and verify their action.
2. Make sure that the HP trip valve is closed.
3. Make sure that the LP trip valve is closed.
4. Place the turbine controller in the position control mode.
5. Make sure that the output of the position controller is 0%.
6. Make sure that the gland steam condensor is ready for operation.
7. Drain condensate from the steam lines, turbine case and trip throttle valves by
opening their respective drain valves.
8. Check the oil level and the condition of the oil. Be sure, the oil is in good
condition, uncontaminated by water sludge or other foreign matter.
9. Start the main oil pump and vent the oil system thoroughly. Fill the stand by
oil cooler and filter. Start the oil vapour extractor of the oil reservoir.
10. Check the oil pressures. Lube oil gauge pressure should be 2 kg/cm2 at the
turbine. If necessary adjust relief valve 109. Control oil gauge pressure should
be 10 kg/cm2 at the turbine. If necessary adjust relief valve 108. Make sure
that the auxiliary oil pump and the emergency oil pump start at the correct oil
pressures.
11. Engage the coupling between the turbine and the main boiler feed pump.
12. Start the turning gear.
13. Open the turbine drains.
14. Start the steam supply to the turbine gland seal system. Gland seal steam
gauge pressure should be 0.1 kg/cm2.
15. Put the condensing system into operation.
16. Warm the boiler feed pump thoroughly by putting the warming up system in
the automatic mode, check to see that:
17. After warming up the pump, close the valve in the warming up supply line.
18. .Make sure that the drains of the pump case are closed and that the pump the
discharge valve is closed
19. Make sure that the valves in the gland seal water lines to the opened. main
pump and in the seal water lines to the booster pump are Vent the seal water
system and coolers thoroughly.
19. Make sure that the drain lines from the seal housings are open.
21. Open the valves in the recirculation line.
22. Fill the pump with boiler feed water, being sure pump is fully vented. Pump
may be filled from seal injection system, or through warm up connection.
23. Set control valves for the seal injection system (approximately 750degC.).
24. When the water pressure in the pump approximates the suction pressure,
open the valve in the suction line.
25. Make sure that the booster pump is ready to operate.
26. Thoroughly drain and preheat the steam supply lines.
27. Make sure that the turbine vacuum is below 0.3 kg/cm2 absolute.
28. Reset the turbine trip system and test the tripping mechanisms as described in
control section.
29. After testing the trip mechanisms, reset the trip system again.M ake sure that
the trip valves open.
30) When the lube oil temperature has reached at least 350degC., and the steam just
before the LP trip valve is at least 400degC. superheated, open the steam
admission valves (by raising the output of the position control) to bring the
turbine up to speed of about 1000 rpm so that the turbine may be heated
evenly.
NOTE: After a black out the turbine can be started with auxiliary steam of 16
bar and 2100degC. It must be ensured that no water, from the inlet piping, can
enter the turbine.
31) Operate at 1000 rpm for not less than a quarter of an hour. During the
warming up period listen care fully for any rubbing, unusual noise or
vibration. Also during the warming up period check oil pressures, oil
temperatures, oil flow to bearings and general me chanical performance of the
unit.
NOTE: If abnormal vibration, noise or any other erratic condition should
develop, shut the unit down immediately and investigate the cause.
32) Throttle all steam drain valves to a quarter turn open.
33) After the turbine has been thoroughly warmed (that means casing
temperature is within 500degC. from the steam temperature) and the vibrations
are normal, and vacuum is below 0.3 kg/cm2 absolute, increase the speed by
raising the output of the position control. Increase the speed in steps of 20
rpm/sec. The control system will a utomatically change over from position
control to speed control when the turbine speed reaches the minimum speed
setting of the digital speed reference.
CAUTION: Care should be exercised when the unit is accelerating or
decelerating through the critical speeds. Prolonged operation is
limited to speeds at least 10% removed from critical.
34) Increase the speed by means of raising the digital speed reference.
35) The boiler feed pump is discharging through the recirculation line. The unit
can be operated satisfactory under these conditions until the pump is ready to
be put on the line.
36) Check the operation of the oil system. The cooling water flow through the oil
cooler should be adjusted so that the temperature of the oil leaving the cooler is
500degC.
37) Check that the seal steam gauge pressure is 0.1 kg/cm2. Make required
correction.
38) Close the turbine drains except the drain behind the HP t rip valve. This drain
must always be open.
39) Open the pump discharge valve to put the pump on the line.
40) Increase the speed up to the minimum feed water control speed. At reaching
this speed, the feed water control signal will be balanced with the actual speed
setting. This balancing is completed when the feed water controller has no
intention to provide a raise or lower command to the digital speed reference.
The contact for remote speed setting can now be closed and the feed water
signal will provide raise and lower commands to the digital speed reference.
41) Check to see that the proper vacuum is being maintained on the turbine exhaust.
NOTE: - In Unit # 4,5 & 6 TDBFP B, a new controller has been installed &
commissioned under R & M. The operating procedure for this controller is as
follows:
1. After ensuring all permissive, give RESET c ommand.
2. After turbine RESET, for rolling the turbine give GOVERNOR START command.
3. After giving GOVERNOR START command give RAISE command for control valve
opening.
4. After attaining the turbine speed 1000 rpm SPEED CONTROL will be automatically active
(no need of REQUEST CHANGE).
5. After attaining the speed 1000 rpm, further give RAISE command till saturation
(until RAISE push button lamp glows). This will not affect control valve opening
or turbine speed.
6. After 1000 rpm turbine speed, control valve opening will be controlled by SPEED
SET POINT.
7. After 1000 rpm, by raising the SPEED SET POINT turbi ne speed can be increased for
required loading.
RUNNING - A least once every shift, the following log checks should be made:
1) Unit speed
2) Oil te mperature and pressure. The condition of the oil should be checked at
least every six months.
3) Bearing temperatures. The unit must be tripped when the bearing metal temperature
increases to 1200degC. The alarm setting should be adjusted at 50 C. above the
initial stabilised operating temperature.
4) Unit vibrations. Any sudden increase in vibration level must be investigated and the cause
corrected before operation is continued.
5) Seal steam pressure. Check to see that the gland steam system operates properly.
6) Exhaust vacuum.
7) Sealing water temperature. Make sure that the control valves of the seal water system are
set properly(approx. 750degC.).If the temperature of the booster pump sealing
water outlet, exceeds the normal va lue of 650degC., check the sealing chamber and
the cooling water supply to the sealing water cooler. If every thing is found o.k., inspect
the filters and coolers in the sealing water system. If the temperature of the main pump
seal water outlet, exceeds 800degC, check the sealing chamber, the water supply to
the se als and the seal water filters.
8) Pump inlet and outlet pressures and temperatures. Make sure that there always a
sufficient normal suction head is available, the pump may get damaged if the normal
suction head is too low. Therefore, pay special attention to the filters in the suction
piping. Also a pressure drop in the deaerator may lead to a loss of normal suction head.
For this reason the pressure drop must be restricted.
09) Pump flow.
10) Flow through the balance piping, kicker stage and bleed off line.
11) Under certain conditions, the temperature differentials of a running pump
may be higher than the differentials given for putting a cold or standby pump
on the line. This is permissible, only if the flow through the pump exceeds the
recirculation flow of the pump.
12) Test the electronic exercise system off the turbine trip valves once a week as
described in the control section.
13) Test the mechanical over speed trip device every two months as described in
the control section.
STOPPING
1) Decrease the speed until the minimum flow valve opens and the pump does not supply
feed water to the boiler any longer.
2) Trip the turbine with help of the hand trip device or with one of the other trip devices.
Make sure that the trip valves close instantly.
3) After turbine rotor comes to the rest, disengage the coupling between the main pump
and the turbine, and start the turning gear.
4) Open the turbine drains.
5) Break the turbine vacuum.
6) Stop the steam supply to the gland steam system.
7) The turning gear can be stopped when the turbine casing temperature is below 700degC.
8) The oil supply can be stopped when the turbine rotor is at stand still.
NOTE - If it should be necessary to restart the unit before it has cooled down, it
should be done in accordance with the start up curve.
Line up of TDBFP
Charging of Pump
1. Open all air vents - at booster pump suction strainer air vent,
booster pump top, main pump suction strainer air vent, line air
vent after main pump.
2. Open BFP suction valve slowly and let off air in the system & then
completely open the suction valve. Close all air vents.
3. Ensure Recirculation valve & its isolating valve open position
4. Ensure all isolating valves in Booster pump & main pump jacket
cooling water line & ensure TG DMCW cooling water line up
5. Ensure cooling water valves open to lube oil coolers
1. Start DC EOP and take one oil vapour extraction fan into service
2. After establishing lube oil header pressure & observe return oil
flow from all return lines
3. Start any one lube oil pump
4. Start JOP & observe rise in JOP pressure.
5. Stop DE JOP & kept its SLC in on position
6. Engage the main pump to the turbine through engage/disengage
solenoids after starting power pack.
7. Ensure main pump recirculation is in open position
8. Open Barring gear valve & observe speed rise of turbine to 320
RPM
Vacuum Pulling
ksc), the remote engage will go to off position and ensure this for
proceeding further.
5. Open the ESV tile and give open command, observe the raise of
startup oil pressure above piston and after some time trip oil
pressure below piston of stop valve develops and stop valve
slowly starts opening and the start up oil above the piston gets
de-pressurised.(Ensure the close feed back of control valve prior
to this step).
Speed raising and soaking of TDBFP at 1500 rpm & at 3000 rpm
1. Open the speed reference tile and give 1500 rpm, confirm it and
observe the speed raise & monitor the turbine vibrations, TSC.
2. Soak the turbine at 1500 rpm till the casing temperature reaches
150 degC. Raise the speed further to 3000rpm and soak it.
3. Load the TDBFP after crossing the casing temperature 220 degC.