Solution Review Problems of Chapter 17 PDF
Solution Review Problems of Chapter 17 PDF
1. For the following network diagram, determine both the critical path and the expected
project duration. The numbers on the arrows represent expected activity times.
Solution:
Expected
Path Path Time
124689 41
125689 48
125789 55*
13789 40
2. Chris received new word processing software for her birthday. She also received a
check, with which she intends to purchase a new computer. Chriss college instructor
assigned a paper due next week. Chris decided that she will prepare the paper on the
new computer. She made a list of the activities she will need to do and their estimated
times.
Write Paper
Grammar ck
Submit paper
b. AON diagram
3. For problem 1, determine the following quantities for each activity: the earliest start
time, latest start time, earliest finish time, latest finish time, and slack time. List the
critical activities, and determine the expected duration of the project.
Solution:
Summary:
Activity ES EF LS LF Slack
1 0 5 0 5 0
2 5 23 5 23 0
3 5 18 20 33 15
4 23 26 37 40 14
5 23 33 23 33 0
6 33 37 40 44 7
7 33 44 33 44 0
8 44 53 44 53 0
9 53 55 53 55 0
LS LF
ES EF
37 40
23 26
4 40 44
5 23 33 37
5 23 3
2 23 33 6
18 23 33 4
0 5
0 5
44 53 53 55
5
10 44 53 53 55
5
1 20 33
5 18
33 44 89 92
33 44
13
3 11
4. The project manager of a task force planning the construction of a domed stadium had
hoped to be able to complete construction prior to the start of the next college football
season. After reviewing construction time estimates, it now appears that a certain
amount of crashing will be needed to ensure project completion before the season
opener. Given the following time and cost estimates, determine a minimum-cost
crashing schedule that will shave five weeks off the project length. Note: No activity
can be crashed more than two weeks.
Solution: B
14
A K
12 9
Start
End
C M
10 G 3
D 15 N
P 8
17 11
E
H
18
F 8
12 J
I 12
7
Activity c c f f e,p
Crashed
Cost $5,000 5,000 12,000 15,000 36,000
Cum. Cost $5,000 10,000 22,000 37,000 73,000
5. A construction project has indirect costs totaling $40,000 per week. Major activities in
the project and their expected times are shown in this precedence diagram:
Weeks Crashed
Path 0 1 2 3 4 5 6
12571113 35 wk. 34 33 32 31 30 29
1381113 32 32 31 30 29
1391213 20
146101213 33 33 32 31 30 29
Summary:
Project Cum. wk. Cum. Crash Indirect Costs Total Cost
Length Shortened Costs ($0000) ($000) ($000)
35 0 0 35(40) = 1,400 1,400
34 1 15 34(40) = 1,360 1,375
33 2 33 33(40) = 1,320 1,353
32 3 58 32(40) = 1,280 1,338
31 4 96 31(40) = 1,240 1,336
30 5 139 30(40) = 1,200 1,339
29 6 185 29(40) = 1,160 1,345
1,400
Total
Cost
($000)
1,300
0 30 31 32 33 34 35
Product Length
(wk)
6. Chucks Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a
contract with a mysterious New York lawyer (Mr. T). Relevant data are shown below.
The complication is that Mr. T wants delivery in 32 weeks or he will impose a penalty
of $375 for each week his yacht is late. Note: No activity can be crashed more than
two weeks.
7 4 8 6
L M P Z
Start 9 125, - 300, 350 5 -, - 7 90, - En
K Q Y d
410, 415 5 6 200, 225 85, 90
N J
45, 45 50,-
Project duration = 39 wk
Project Shorten Crash
length activity cost
39 wk 0
38 Z 90
37 N, L 170 = (125 + 45)
36 Q 200
35 Q 225
34 M, N 345
Stop here; additional crashing will cost more than the $375 weekly penalty.