How To Generate S Curve From Primavera-P6
How To Generate S Curve From Primavera-P6
1. Establish WBS
2. Adding activities, Activity codes, Activity sequencing
3. Define resource dictionary
4. Assign activity resource and budgeted quantity man hour
5. Save as a baseline schedule
6. Record the actual status when the actual works are done and schedule it based on report date
This post demonstrates how these curves are produced by using Excel export data from Primavera-P6.
And you might need to look at spreadsheet information such as Cum Budged Units and Cum Actual Units in
order to analyze periodic data .That means cum Budgeted Units and Cum Actual Units from the Spreadsheet
Fields are also displayed to calculate weekly or monthly progress S-curve and histogram data.
2. And then you will see the Columns window. In the selected options box, Activity ID, Activity Name, Resource
ID Name, Start and Finish columns are shown by default.
3. Select Actual Units and Budgeted Units from units group in the available options box, then click the
forward arrow diagram to show actual units and budgeted units as shown in figure below.
B-2) To View Cum Budgeted Units and Actual Units Columns in Spreadsheet Fields
1. Click on the layout area and select Resource Usage Spreadsheet as shown in figure below.
2. Point the mouse to anywhere on the resource usage spreadsheet field area or click on Display button to view
the desired columns. Go to Spreadsheet Fields >> Customize as shown in figure below.
Click the forward arrow button to select Cum Actual Units and Cum Budgeted Units as shown in figure below.
In case you wish to view Early Curve and Late Curve, then select the Cum Remaining Early Units and Cum
Remaining Late Units.
4. Finally, you will see the resource usage spreadsheet field showing cum budgeted units and actual units
fields and data that can be exported to Excel Spreadsheet by copy and paste option.
5.Things that we should have done before export P6 data to excel are resource grouping and time scale format.
Resource grouping represents what you want to report or analyze. Group the resource as total when you want
to see overall summary data only. To view Group and Sort window, go to View >> Group and Sort
by >>Customize. In Group and Sort window, mark on Show Grand Totals and Show Summaries Only to see
overall summary data. See figure below.
7. Export the P6's Spreadsheet Data to Excel; now, you are ready to export P6's S curve/Histogram data to Excel
spreadsheet. Select on the shading area and select all. And then copy and paste the data to excel. See figure
below.
8. Suppose the exported data is as shown in figure below. As we set Cum Budgeted Units and Cum Actual
Units in the spreadsheet option field, you will see Cum Budgeted Units and Cum Actual Units data through the
project start to the end date.
Note: In order to get these data, activity resource, Budgeted Units and Actual Units must be assigned to each activity.
Data Date
To create progress S-Curve and weekly progress histogram chart, populate the progress data. Then finally you
will get the S-curve and histogram curve showing progress data and bar chart.