Capturing Lessons Learned Final PDF
Capturing Lessons Learned Final PDF
Learned
Throughout a projects life cycle, we learn lessons and discover opportunities for improvement.
As a key part of The Nature Conservancys Conservation by Design principles, documenting
lessons learned helps a project team discover both strengths and weaknesses. It provides an
opportunity for team members and/or partners to discuss successes during the project,
unintended outcomes, and recommendations for others involved in similar future projects. It
also allows the team to discuss things that might have been done differently, the root causes of
problems that occurred, and ways to avoid those problems in later project stages.
Disseminate
past lessons
or best
practices
Define the
Lessons Reuse lessons
learned
learned
repository
project
Applying
Knowledge
Collection of
Review for
lessons and
applicability
practices
2. Collect
The collection process involves the capture of information through structured and unstructured
processes such as project critiques, written forms, and meetings. The collection of lessons may
come from as many sources as an organization is willing to solicit. Lessons learned can be based
both upon positive experiences that achieve organization goals, and on negative experiences
that result in undesirable outcomes. For some projects, a collaborative lessons collection
process can be as or more important as documenting the lessons.
4. Store
The storage aspect of lessons learned usually involves incorporating lessons into an electronic
database for future sharing and dissemination. Information should be stored in a manner that
allows users to identify search lessons by keyword.
5. Disseminate
The final element, and the most important, is the dissemination of lessons learned, since
lessons are of little benefit unless they are distributed and used by people who will benefit from
them. Dissemination can include the revision of a work process, training, and routine
distribution via a variety of communication media. Lessons can be pushed, or automatically
delivered to a user, or pulled in situations where a user must manually search for them.
Approach 1. Integrated
The simplest approach is to incorporate lessons learned early, regularly, and consistently
through regular project reporting, or within the context of the initial management plan.
Capturing lessons learned would be part of the regular annual or semi-annual reporting cycle
and may even be embedded in the initial project management plan. Table 1 outlines this
integrated approach. One major advantage of this method is that there need not be a separate
and often costly lessons learned project with an outside leader or team, but instead the process
is embedded within the project plan, and is carried out by the project manager or internal
designee. This approach is far less resource-intensive.
Table 1. Simplified, integrated process for capturing lessons learned from project onset
Step 1 Project manager meets with staff every 3-6 months to identify and discuss top key
lessons. (The timing of this process can be tied with specific reporting
requirements or be done more or less frequently if desired.)
Step 2 Project manager or assignees synthesizes discussion and enters summary points
into the case study format (see below).
Step 3 Project manager or assignee submits/synthesizes lessons (in case study or other
formats) in semi-annual and annual progress reports.
*
Step 4 Central lessons learned coordinator disseminates lessons, either through regularly
updated website or internal newsletter, or holds annual workshop on top lessons
learned for sharing between projects. Coordinator might also identify similar
projects that can most benefit from specific lessons shared and facilitate short
workshop.
*
More detail is provided on these steps below.
Approach 2. Post-Facto
The more detailed, complex approach is one which requires a thorough examination of the
project post-facto. This is sometimes done in projects reactively or as an afterthought when
project managers realize things could have been done differently. However, many organizations
who have invested heavily in a project over a long period of time, or who are interested in
replicating similar projects are willing to spend the time and money necessary to improve
future efficiency. While more resource-intensive, this approach offers the benefit of bringing
project members and partners together for an extensive look into the operations, successes,
and shortcomings of the project. Table 2 outlines a process for capturing lessons learned in a
thorough manner at the end of a project. The steps can be modified or rearranged to meet the
projects needs; however it is good practice to follow a methodical approach. The next section
provides further detail on steps in this approach, such as identifying the project team, and
choosing a lessons learned writer/leader, data collection method, and dissemination strategy.
Table 3 outlines the pros and cons of each method.
Approach 3. Combination
While it is preferred to begin with the integrated approach wherein lessons learned are part of
the initial project plan and team members meet regularly to capture lessons learned, it is also
helpful to bring together key partners and stakeholders with the project team and the end of or
during a project. This allows for a broader analysis and may help to build a sense of
collaboration and communication within the partnership or group responsible for project
implementation. Table 3 outlines how this combined approach may unfold.
Table 4. Combined process for capturing lessons learned throughout project duration.
Step 1 Project manager meets with staff every 3-6 months to identify and discuss top key lessons.
(The timing of this process can be tied with specific reporting requirements or be done more
or less frequently if desired.)
Step 2 Project manager or assignees synthesizes discussion and enters summary points into the case
study format (see below).
Step 3 Project manager or assignee submits/synthesizes lessons (in case study or other formats) in
semi-annual and annual progress reports.
Step 4 An annual and/or end of project facilitated group discussion FGD involving key partners and
stakeholderspossibly facilitated by TNC, partners, or by third party (depending on how the
institutional arrangement of the project and the conditions of the relationships). A survey can
be added for partner participants attending the discussion to capture their views of the
lessons learned.
Step 5 Key lessons are summarized and distributed to all who participate in the group.
Step 6* Central lessons learned coordinator disseminates lessons, either through regularly updated
website or internal newsletter, or holds annual workshop on top lessons learned for sharing
between projects. Coordinator might also identify similar projects that can most benefit from
specific lessons shared and facilitate short workshop.
In identifying the project team, it is important to build initial engagement from all key players
who will be involved in advance of the project. Include the project manager, the project team,
and the key stakeholders in the lessons learned exercise. Select staff with specific expertise or
knowledge of the project and other needed skills, such as communication and writing.
There are a few different approaches in selecting a lessons learned leader. We suggest picking
someone with good or at least some familiarity with the larger organizations goals and process
but not someone directly involved in the daily operations of the project. There is certainly
something to be said for having an outsider that is an expert in capturing lessons learned lead
the process. The outsider obviously will have no knowledge of the project and thus no inherent
biases. However, the downsides to this approach are that there may be less buy-in from the
project team members, stakeholders or partners may be less willing to share information with a
stranger, and some insider information may be lost in the process. One alternative to this
approach is to pair the expert with the project manager or another insider heavily involved in
the project. Then the two could work as a team to lead the process and hone the lessons
learned. Another alternative, as suggested above, is to have the project team itself identify and
develop the lessons learned through an iterative, adaptive process throughout the life of the
project.
See Appendix 2 for a detailed analysis of the purpose, advantages, and disadvantages for
different data collection options (e.g., surveys, interviews, workshops, reviews).
Multiple resources exist for creating questionnaires and surveys, and designing interview
questions. One free, user-friendly survey website is SurveyMonkey.com
(www.surveymonkey.com), which offers advice for question design and also offers basic data
analysis and display options. This document provides excellent guidance on conducting a survey
and designing a questionnaire - http://www.statpac.com/surveys/surveys.pdf.
Whatever method you are using, concentrate on obtaining information in four general areas:
1. What went well?
2. What didn't go well or had unintended consequences?
3. If you had it all to do over again, what would you do differently?
4. What recommendations would you make to others doing similar projects?
You can include other more detailed questions in your survey or interview, such as:
The guidelines below are modified from the book "Learning to Fly - Practical knowledge
management from leading and learning organisations")1, and set out ten key steps to
facilitating a lessons learned review.
1. Call the meeting. If conducting a post-facto process, hold a face-to-face meeting as soon as
you can after the project ends, within weeks rather than months.
2. Invite the right people. The project leader needs to attend, as do key members of the
project team. If a similar project is already underway, then there is great value in the new
project team attending - a "customer" for the knowledge.
3. Appoint a facilitator. Identify a facilitator who was not closely involved in the project. The
facilitator should be someone who can ask questions from an independent, but non-
threatening standpoint. This isn't an audit, it's an investment!
4. Revisit the objectives and deliverables of the project. Ask "what did we set out to do?" and
"what did we achieve?"
5. Go through the project step by step. Revisit the project plan and identify any deviation from
plan. Where were the delays, and what went ahead of schedule? What changed and why?
6. Ask what went well? Ask "what were the successful steps towards achieving your
objective?" and "what went really well in the project?"
Ask a "why?" question several times. This is vital, and will get you to the root of the reason.
Don't take the initial response at face value. Often people don't even realise what the
underlying reason behind a success or failure is.
7. Find out why these aspects went well, and express the learning as advice or guidelines for
the future. This is a key point. Try to avoid expressing lessons learned in a passive, past
tense, such as: "Project Foxtrot completed ahead of schedule because the project team
remained in-tact throughout the design and execution stages".
1
By Chris Collison and Geoff Parcell, www.chriscollison.com/l2f/ year?
A Guide to Capturing Lessons Learned Page 7
The lesson will be far more accessible to others if it is expressed as:
"On time-critical projects, ensure that the project team remains consistent throughout the
design and execution stages of the project. This will eliminate any learning-curve issues due
to the take-on of new staff".
As the facilitator, acknowledge feelings and press for the facts. Ask "what repeatable,
successful processes did we use? and how could we ensure future projects go just as well,
or even better?
8. Ask "what could have gone better?" Ask "what were the aspects that stopped you
delivering even more?" Identify the stumbling blocks and pitfalls, so they can be avoided in
future by asking "what would your advice be to future project teams, based on your
experiences here?"
9. Ensure that participants leave with their feelings acknowledged. Ask for "Marks out of ten"
and "What would make it a ten for you?" to access residual issues.
10. Record the meeting. Use quotes to express the depth of feeling. Express the
recommendations as clearly, measurably and unambiguously as possible, using the
guideline format explained in point 7. Take a photograph of the project team, and ensure
that you record contact information (e-mail and telephone) to make follow-up
conversations easy for anyone reading he lessons learned. Ensure that you circulate the
write-up around the participants for comment, and permission to use specific quotes before
sharing more widely.
Once you have captured lessons learned, make sure they are easily referenced by other project
teams. Keep them in a location where they can be easily found and searched maybe a project
portal or intranet site. Start every project by accessing past project lessons learned. Track
improved effectiveness and efficiencies on projects based on applying the lessons learned from
past projects. In this way, the lessons learned from past projects help to increase the success of
future projects. Make a component of every project a requirement to review the lessons
learned from past projects. Strive to create a set of enabling conditions that foster an
organizational culture of capturing and adapting behavior based on identified lessons learned.
Include the project manager, the project team and the key stakeholders in the lessons
learned exercise.
Conduct the wrap-up lessons learned exercise soon after the project ends to get the
most effective input from people.
Recruit a lessons learned facilitator who is not closely connected to the project.
Prepare for the exercise by meeting with the project manager.
Review project material such as previously gathered lessons learned material and the
final Quality Assurance report to get a sense of project issues and successes.
Conduct the session in a comfortable setting.
Set ground rules and timelines for discussion.
Concentrate on obtaining information in four general areas:
o What went well?
o What didn't go well or had unintended consequences?
o If you had it all to do over again, what would you do differently?
o What recommendations would you make to others doing similar projects?
Focus on behaviors or tactics that were successful or problematic, rather than people
who were successful or problematic.
Guard against a bias towards negative or positive comments.
Ask questions to get balanced input.
Accept input after the session from individuals who prefer to remain anonymous.
Provide the project manager with a complete, unedited listing of input from the lessons
learned exercise.
Analyze the raw material for future use.
Document lessons learned in a positive way that promotes their use as best practices.
Include lessons learned documentation in the post-implementation review for the
project.
Has the facilitator reviewed the final quality assurance report or other project material,
including previously gathered lessons learned information?
Has input been received in the key project areas?
Has input been documented as received in the session and provided to the project
manager?
Has material been analyzed and documented for follow-on use?
Has an archive location, such as a lessons learned database or library been established?
2
From Gantthead.com
A Guide to Capturing Lessons Learned Page 11
Appendix 2
Data Collection: Methods and Sources3
3
From The Partnering Initiative, The Case Study Toolbook, 2005
A Guide to Capturing Lessons Learned Page 12
A Guide to Capturing Lessons Learned Page 13
Appendix 3
Options for Disseminating Lessons Learned4
4
From The Partnering Initiative, The Case Study Toolbook, 2005
A Guide to Capturing Lessons Learned Page 14