Project Parameters Control Panel: Pre-Define Input Parameters
Project Parameters Control Panel: Pre-Define Input Parameters
Control Panel
Project Name New Project Pre-Define Input Parameters:
Project Manager Manager's Name PROJECT DEFINITION GO
Totals - - -
Task Description Staffing Timing (Dates) Progress Completion
ID0 Phase Description Productivity Start End Units Capex Date
Totals 0%
? Create Schedule Export Sheet
Day Beginning:
TASKS
FULL-TIME HOURS
Scheduled
Completed
Operating Costs
Capital Costs
Total Costs
New Project project status report as at
(Start date: , Earned Value analysis denomination: $0)
Earned Value Analysis ? Performance Measurements ? Variances ? Indices ?
Unit Type BCWS BCWP ACWP Cost Schedule CPI SPI
Totals - - - - -
60.0%
40.0%
20.0%
0.0%
1-Jan-13
Date
PREPARATION PROJECT DEFINITION ANALYSIS DESIGN DEVELOPMENT TESTING
Perform feasibility s Define Project Document high-
Document cur Build IT Infrastructu Build test pa
Perform risk & impa Document project definition r Document highDefine proc Build prototype Perform syst
Document business Document project plan Document detaDefine organDesign physical prot Perform integ
Document umbrella Document quality plan Document detaDefine locat Build physical proto Perform user
Obtain interim fundi Document resource terms of reference Define data Test physical protot Perform regre
Project definition approved Define applicImplement prototyp Review imple
Agree Contract Define techniMarket and approve prototype
Document vendor/client contract Current stat Prototype authorised
Document futBuild database
Define proc Develop database
Define organProduce database design
Define locat Build database
Define data Build database testing routines
Define applicPerform database unit testing
Define techniDevelop data migration
Future state Produce data migration design
Perform detaBuild data migration components
Define organBuild data migration testing routi
Define devel Perform data migration unit testi
Define testi Database development complete
Define imple Build application software
Define accepDesign software configuration
Define operaInstall and configure software components
Build software testing routines
Unit test software components
Software development complete
Build technology hardware
Design hardware configuration
Install and configure hardware components
Build hardware testing routines
Unit test hardware components
Hardware development complete
Build Business Infrastructure
Build business processes
Document detailed process model
Document detailed procedures
Unit test processes and procedures
Process development complete
Undertake communications
Document communications plan
Communicate organisational changes
Communicate system changes
Measure communications effectiveness
Communications plan implemented
Undertake training
Document training procedures & handbook
Perform organisational training / re-skilling
Measure training effectiveness
Traininng complete
Build physical locations
Produce physical location design
Purchase / build locations
Unit test locations
Location development complete
IMPLEMENTATION ACCEPTANCE REVIEW CLOSE-DOWN OPERATIONAL SUPPORT *
Schedule implementationPerform final user Document poDocument project Manage operational schedule (faci
*
Implement IT Infrastruct Perform final operational accep Release resources Manage availability *
Implement data migratio Signoff implementation completPerform contract c Manage capacity *
Perform data extraction routines Manage performance *
Perform data scrubbing & migration routines Manage backup and recovery *
Perform data loading routines Manage disaster recovery *
Check data validity Manage against SLAs *
Implement application software Manage security *
Distribute and install application software Manage data *
Test installed application software Manage on-going training *
Implement technology hardware Support solution (1st/2nd/3rd le*
Distribute and install technology hardware *
Test installed technology hardware *
Implement Business Infrastructure *
Implement processes *
Distribute process & procedural documentation *
Check distribution complete *
Implement organisational changes *
Undertake actual org. changes *
*
*
*
e software components *
*
*
*
*
*
e hardware components *
*
*
*
*
*
process model *
*
and procedures *
*
*
*
isational changes *
*
ations effectiveness *
an implemented *
*
procedures & handbook *
nal training / re-skilling *
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
*
Color PROJECT PHASES PUBLIC HOLIDAYS
PREPARATION
PROJECT DEFINITION
ANALYSIS
DESIGN
DEVELOPMENT
TESTING
IMPLEMENTATION
ACCEPTANCE
REVIEW
CLOSE-DOWN
OPERATIONAL SUPPORT
E-MAIL TEXTS
Sending Task List to participants: