100% found this document useful (2 votes)
3K views

SATIP-H-100-01 Rev 8

This document outlines the inspection plan for painting liquid coating systems on industrial facilities. It details 7 steps in the project including document review, material receiving, application, and pre-commissioning. For each step, it identifies the quality procedures and records to be used, and assigns inspection responsibilities to either the contractor or Saudi Aramco. General notes provide guidance about surveillance, witnessing, and holding points for QA/QC inspections.

Uploaded by

SajjadPervaiz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
3K views

SATIP-H-100-01 Rev 8

This document outlines the inspection plan for painting liquid coating systems on industrial facilities. It details 7 steps in the project including document review, material receiving, application, and pre-commissioning. For each step, it identifies the quality procedures and records to be used, and assigns inspection responsibilities to either the contractor or Saudi Aramco. General notes provide guidance about surveillance, witnessing, and holding points for QA/QC inspections.

Uploaded by

SajjadPervaiz
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

SAUDI ARAMCO ID/PID FORM REV 7 - 010109 Rev 8 COS 30-June-14

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Paint Application of Liquid Coating Systems (Industrial Facilities) SATIP-H-100-01 31-Dec-14 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

1.1 Coating Procedure SAIC-H-2023 RH RH

Coating Personnel Qualification &


Certification Card
SAIC-H-2010
1.2 a) Blaster RH RH
b) Paint applicator
c) Crew supervisor

2.0 MATERIAL RECEIVING

Verification and Visual Inspection of


2.1 SAIC-H-2024 SAIC-H-2024 H W
Paints and abrasives
Storage and Handling of Paints and
2.2 SAIC-H-2025 SAIC-H-2025 H W
Abrasives

2.3 Equipment Inspection SAIC-H-2026 SAIC-H-2026 H H Use SATR-H-2006

3.0 APPLICATION

Inspection of Surface Preparation & Prior


3.1 to Application of liquid coating systems SAIC-H-2027 SAIC-H-2027 H W Use SATR-H-2006
(New Installations)

In-Process Inspection of Primer Coat OR


3.2 SAIC-H-2028 SAIC-H-2028 H W Use SATR-H-2006
First Coat Application

Inspection of Primer Coat prior to top


3.3 SAIC-H-2029 SAIC-H-2029 H W Use SATR-H-2006
coating

In-Process Inspection of Intermediate


3.4 SAIC-H-2030 SAIC-H-2030 H S Use SATR-H-2006
and/or Top Coat Application

Inspection of Top Coat Application


3.5 SAIC-H-2031 SAIC-H-2031 H W Use SATR-H-2006
(Dry/Cured Coating)

Inspection of Repair/Touch-up of
3.6 SAIC-H-2032 SAIC-H-2032 H W Use SATR-H-2006
Coatings

Page 1 of 4
SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

Paint Application of Liquid Coating Systems (Industrial Facilities) SATIP-H-100-01 31-Dec-14 MECHANICAL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. & Activity Code PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Safety Color coding and Stenciling of


3.7 SAIC-H-2033 SAIC-H-2033 W W
Identification on Equipment/piping

4.0 PRE-COMMISSIONING

Final Coating Inspection/ Punchlisting


4.1 SAIC-H-2034 SAIC-H-2034 H W Use SATR-A-2011
(Contractor)
Mechanical Completion Punch listing
4.2 SA-6133 H
(Saudi Aramco)

GENERAL NOTES

1 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
2
representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
3
attendance.
4 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Page 2 of 4
DISCIPLINE:

MECHANICAL
CONTRACTOR/SUBCONTRACTOR

REMARKS

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Use SATR-H-2006

Page 3 of 4
DISCIPLINE:

MECHANICAL
CONTRACTOR/SUBCONTRACTOR

REMARKS

Use SATR-A-2011

GENERAL NOTES

Construction Organization
in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization

in advance. Inspection or test shall not be carried out without the QA/QC organization representative in

en the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
Review of Documents
Review and Approval of Documents
100% Contractor Inspection

Page 4 of 4