Course Note
Course Note
[D31VR]
Authors:
G Bowles and J R Kelly
1: Clients
1.1 Introduction
1.2 Glossary
1.3 The construction client
1.4 Questions
i
4: RM and the Project Life Cycle
4.1 Introduction
4.2 Learning outcomes
4.3 The project life cycle
4.4 VM, RM and the project life cycle
4.5 Relationship between VM and RM in the project life
cycle
4.6 Strategic Risk
4.7 Tactical risk
4.8 Risk- time, cost and quality
ii
7.4.2 Risk identification
7.4.3 Risk Analysis
7.4.4 Risk Response
7.4.5 Risk monitoring and control
7.5 The combined value and risk management workshop
iii
12: Strategic Development of Public Private Partnership
Projects
12.1 Introduction
12.2 Glossary
12.3 Key principles of PPP
12.4 Output service specification
12.5 Strategic project procurement and risk pricing
12.6 Key risks in the project life cycle
12.7 Reading
12.8 Questions
iv
Overview of the Course
Value Management (VM) and Risk Management (RM) have been combined
in this course to demonstrate the power of using an informed team under the
direction of a skilled facilitator to recognise and either solve (value
management), or account for (risk management), problems occurring on
construction projects in their various stages. VM and RM are
complimentary disciplines which have been described as being 2 sides of
the same coin. They are complimentary in their objectives, in that improving
value in a project can only be achieved if the risk associated with it is
balanced and manageable. They are also complimentary in methodology, or
process, terms. The implementation of value management and risk
management, in a practical sense, is very similar for each.
Both systems require:
v
course recognises the strengths of the various value systems world-wide but
particularly examines the methodologies of North America and the UK.
vi
the motivation to build or surrounding strategic issues. In this context VM
studies use Function Analysis (FA) and other problem solving tools and a
multidisciplinary design team to suggest alternative elements, materials and
components, as well as making small revisions to the project concept to
improve VFM. RM is a means of improving project performance by
reducing exposure to the many possible risks, threats and hazards that
threaten good project performance. Good project performance is achieved if
the building or other facility is delivered on time, within budget and to the
stipulated quality standards necessary for a happy client and construction
team.
vii
Aims and Objectives
The aim of the value management aspect of this course is to introduce the
concept of value management and critically appraise its application to the
strategic and tactical decisions taken in construction value management in
USA and UK. With regard to the former the course will promote a better
understanding of project definition and how it supports the objectives of the
client organisation. On the latter, it will promote a good understanding of
construction value management as applied to the design of elements and
components.
The aim of the risk management aspect of the course is to introduce the
student to risk and uncertainty in the context of the construction project and
develop an understanding of some common approaches to managing and
mitigating the risks that its participants are exposed to.
viii
1: Clients
1.1 Introduction
This unit contains information about the construction client, their
characteristic structures and their approach to construction projects. The
questions at the end of this unit are intended to promote further reading and
analysis.
1.2 Glossary
It is quite common for some of those interest groups which can be defined
to be part of the client body to have no representation in the decision
making unit, and it is also quite common for the power within the decision
making unit to be unequally shared. The function of the project sponsor is to
overcome these deficiencies by representing the views of those not
represented. The client project manager is often a feature of large
commercial organisations that regularly procure from the construction
industry. In this situation it is less common to have a project sponsor.
In text question
Investment Decision
Maker
Project Board
Project Owner (may not be require:
advisory only)
Project Manager
(generally external consultant)
Investment Decision
Contractor Suppliers
Maker
In text question
What are the difficulties associated with clients that are made up of a
large number of stakeholders?
1.4 Questions
Question 1 Describe a system for categorising construction industry
clients.
2.1 Introduction
The aim of this unit is to review the background to value management and
outline its application to the construction industry.
Cost which provides neither use, nor life, nor quality, nor
appearance, nor customer features.
2.2 Terminology
The terms most commonly used are value management and value
engineering. In a construction context, value management is generally
considered to relate to the business activity of the client and spans
individual projects. Value engineering relates to studies undertaken on
specific projects between the completion of the sketch design and the
completion of construction work on site. These studies tend to be
technical in nature dealing with elements, components and construction
process. See figure 2.1.
a b A B C D E F G H J K L M c d e
Project Client Inception Feasibility Outline Scheme Detail Production Bills of Tender Project Site Completion Feedback
1st use nth use demolition
awareness develop- proposals design design information quantities action planning operations
ment
In text question
This service is achieved through the application of the job plan described
below. At the core of a value management service is the identification of a
function which is defined as:
Client needs, which are the fundamental requirements that the project
must possess to serve the clients basic intentions. Needs should not be
seen solely in terms of utility as the client may have a need for a
flamboyant statement or a need for a facility or a part of a facility
which heightens the clients esteem.
Project constraints are those factors that will impose a discipline upon
the design, for example, the shape of the site, planning requirements,
regulations, etc.
Time for design and construction as well as the anticipated period for
which the client will have an interest in the building.
Research has also shown that original suggestions are as likely to come
from those inexpert in a subject as from those who are expert. For
example, the interior design consultant may come up with a good original
suggestion for the solution to a structural function. One reason put
forward for this is that the consultant will not be constrained by
professionally determined technical rules or education.
In text question
At the end of the development stage the team will again consider the
worked up ideas and all those which either cost more than the original or
are found to reduce quality are rejected.
Question: Briefly outline the value management job plan stating the
objectives of each stage. Consider the resources that would
be required for a workshop.
The exercise would address the definition of the various functional spaces
required by the client and performance specification of the spaces in terms
of area and height, adjacency, IT and other technical requirements, quality
and the heating, ventilation, lighting and sound environment to be
maintained.
In text question
2.6 Conclusion
This unit has outlined the basic principles of the generic job plan and has
indicated the stages in construction to which this may be applied. Further
units in this course will outline the tools and techniques appropriate to the
use of the job plan at the elements and components stages.
Think about a university department at the spaces level. What are the
different types of functional spaces required by the university and its
users?
Consider a project that you are familiar with. Do you believe the finished
product would have been different if VM had been applied?
3.1 Introduction
This unit introduces the concepts of risk and risk management. A number
of definitions and perspectives on risk are examined, both generally and
relating specifically to project management. Risk within the context of the
construction project is developed. The distinction between risk and
uncertainty is explained, highlighting that risk on a construction project is
not so much about the possibility of certain events occurring, but more
fundamental is about the very circumstances that surround typical
construction projects throughout their lifecycle- from inception to
completion.
In text question
In text question
that are delivered late and/or over budget for which one or more parties
has suffered. However, the qualifier primarily hints that there are
consequences and effects of risk other than negative ones which is
consistent with the strictly correct definitions of risk.
In text question
This view is very similar to that above, although in addition to risk being
associated with a specific cause (event) or condition- a set of
In text question
Discussion and debate on how risk should be perceived has also been
ongoing by practitioners and academics in the field of project
management. Hillson (see supplementary reading) states that risk can have
a range of effects on the achievement of project objectives, from the total
disaster to the unexpected welcome surprise, but is in no doubt that
common usage of the word risk sees only the downside. The negative
connotations are reflected in traditional definitions of the word, both in
standard dictionaries and more technical definitions, but some
professional bodies and standards organisations have gradually developed
their definitions of risk to include both upside and downside. Some
definitions have the nature of the effect as undefined and could therefore
implicitly encompass both positive and negative effects. Others are
explicit in naming both opportunities and threats within its definition of
risk.
In text question
In text question
The terms risk and uncertainty are often used together and sometimes
considered to be interchangeable and synonymous. The concepts are very
close and, for the purposes of construction risk management, some writers
tend not to differentiate between them. However there is a distinction to
be made as explained above, and recent research on project risk
In text question
Spectrum of Risk
Note that only the last item really relates to specific events or conditions
as referred to in the earlier definitions of a risk. The other sources of
uncertainty arise from a lack of understanding of what is involved and are
less obviously described as threats or opportunities.
In text question
HIGH HIGH
+ Challenger + + + Architects
Innovator +
Contractors
Developers
+ Practicaliser
Risk
Modifier
+Synthesiser Risk
+ M&E
taking + taking + Electrical contractors
+ Planner contractors
+ Repeater +
+ Dreamer Quantity
surveyors
+Engineering
consultants
LOW LOW
4.1 Introduction
This unit explains the project life cycle in terms of its two main phases-
the initial strategic phase where the project is being defined, and the
tactical phase which follows and is concerned with delivery. The
application of VM and RM throughout these phases of the project life
cycle is discussed. Good project performance is achieved if the project
which best meets the client needs is correctly and clearly identified in the
former phase, and efficiently delivered in the latter. Whilst both VM and
RM have a role to play throughout these phases, the nature of its practice
and the benefits accrued change as the project evolves.
A comparison of the various project life cycle frameworks shows that the
timing and responsibilities for the various design and construction
activities involved may vary, the way the various participants are brought
together may differ, and the number of steps detailed and terminology
used varies. However, fundamentally they all exhibit a number of
common features which see the project go through a strategic definition
phase followed by tactical delivery phase. This distinction is explained in
the next section.
Completion
Feedback
In text question
What are the 2 main phases that make up any project life cycle?
Business
project Investment/development appraisal
Project brief
Decision to build
Bidding
Construction
time
Breaking the project down into its strategic and tactical phases that
constitute the PLC, both VM and RM have a role to play throughout,
though their relative importance in contributing to good project
performance varies. Generally VM is the dominant discipline in the earlier
stages and RM in the latter as explained in the following section. Figure
4.2 illustrates how the project develops from concept through to
construction. From a VM perspective this is described by Kelly and Male
as Levels 1 to 4; dealing with concept, spaces and elements and
components issues. VE is the part of VM which considers specific aspects
relating to the design and construction of the technical solution, and would
be practiced at the tactical phase of the project. Clearly, with both VM and
RM, the nature of the study, the information being reviewed and the
In text question
VM and RM
VE
Definition Delivery
carried out as part of VM rather than a stand alone risk study. A major risk
at the outset stems from not properly scoping or defining the project
precisely what VM is intended to address. Naturally then, most effort and
attention is given over to VM at the early project stages. It is only as the
project progresses and the design and logistics of its delivery become an
issue that RM as a separate and defined activity comes into its own. The
diagram below illustrates how the boundaries between the disciplines of
VM and RM are blurred at the outset, becoming more distinct and
definable as separate entities as the project progresses. In short VM has its
major role at the earlier stages of a project (particularly the strategic
phase) whilst RMs major role is in the latter delivery stages.
In text question
Definition
(strategic)
VM and RM RM
VM
blurred
(VM dominant)
VM and RM Delivery
VM RM
distinct (tactical)
(RM dominant)
time
In text question
In text question
At what point in the PLC has the clients value system been
formed?
The tactical phase commences as the design gets underway following the
decision to build. The design teams task is to interpret and transmit the
brief into a technical design solution that meets the clients defined
strategic objectives. Throughout the sketch and detailed design stages of
the various packages the client and design team will work toward
progressing the design and exercising cost control with the aim of
finalising decisions on design, specification and cost for every aspect of
the project. This has to be done timeously to meet the clients programme
and within cost constraints for the project. The numerous activities,
involving many disparate but interrelated activities, have to be effectively
coordinated and controlled for success- typically a major project
management challenge.
The overall objectives are to deliver the project on time, within budget and
to the required quality as defined in contract documentation. This is to the
benefit of all parties concerned, irrespective of how risk is apportioned
under the contractual provisions that bind them together. Contributing to
these objectives is largely a function of effective project management for
the client, design team, contractor, subcontractor and suppliers. Clear lines
of communication, strong leadership, supervision and decision making
will help ensure effective co-ordination and execution of all the works on
site. However this particular phase, unlike the previous, also involves
exposure to hazards. This is the particular class of risks that result in
physical damage, injury or death rather than just commercial loss, should
they occur. The building site and erection of the works is a particularly
hazardous environment and the UK industry has a poor safety record
compared to that of other UK industries and indeed European construction
industries.
In text question
In text question
5.1 Introduction
It has been said that the construction industry is exposed to more risk and
uncertainty than perhaps any other industry. This unit examines the
features of the process and product of the construction industry that might
justify this status. It will also be shown that the amount of risk and
uncertainty is largely related to the amount of uniqueness inherent in
each project. Risks are either controllable or uncontrollable depending on
where in the project environment they stem from and elements of the
environment are explained. A checklist of typical sources of risk to be
found in many construction projects is presented.
If the above assertion is accepted there can be little argument that RM has
a very important part to play in project success. However, it is worthwhile
reflecting on this statement and the extent to which it is valid. In
particular, why is it that construction is so exposed to risk and what is it
about the industry that makes it so different from any other? The first part
of this unit discusses the characteristics of the construction industry and
its projects to give a greater understanding of the extent of risk and
uncertainty that prevails. Some recent initiatives that have been proposed
for the industry to offset some of the risk and uncertainty are then
discussed.
Project heterogeneity
There is likely to be truly different situations and circumstances that arise
from project to project, no matter how similar the buildings are that are
being compared. In this respect no two projects are the same (even
comparing, say, two identical house types). Where such heterogeneity
exists in the design, construction and management of projects there will
be, by definition, more uncertainty about the outcome of the events or
situations. Members of the project team are working in conditions of
greater uncertainty because of a lack of directly relevant past experience,
information, knowledge and understanding. Correspondingly there is a
higher degree of risk. It is more difficult to accurately forecast outcomes
relating to the time, cost and quality targets. A simple analogy is that if
you are asked to do a task which you have never carried out before, you
will be less confident in predicting the time and effort it takes to do this,
compared with a task you have carried out many times before.
Undoubtedly, any construction projects will have heterogeneous aspects
relating to its technical, managerial and commercial aspects.
In text question
Project homogeneity
Contrast the construction project with the product of a high volume
manufacturing process. In the latter case there is little variability to affect
the outcome. Quality control and productivity are much more predictable,
tightly defined and the process can be made to be very efficient. There are
no unknowns and there is little risk involved in the production process
(whether there is a market for the product is another matter- this would be
an example of an external commercial risk). Construction, however, is not
a manufacturing process and cannot achieve the same degree of certainty
and productivity associated with such a scenario.
From the foregoing we can see that the more homogeneity involved in the
process (design and construction activities) and the product (the technical
solution represented by the building or facility and its constituent parts),
the less uncertainty there is about the situation and therefore less risk
involved. Following this line it would be desirable for projects to be
In text question
Construction Materials
Many of the materials that buildings are constructed from are practically
universal and in some cases have been used for thousands of years. For
example, we know a great deal about the performance and properties of
materials such as concrete, slate, timber, stone and steel.
Construction Components
As well as many materials being used consistently throughout the
industry, standard designs and components have emerged more recently.
This reduces uncertainty by reducing design variables and simplifying site
and labour processes. The more standardisation that is practiced in
construction, the more the industry takes on the characteristics of a
manufacturing process.
Site Operations
Many site operations and activities of the construction process are also the
same from project to project, using specific types and capacities of plant
and labour operations. Site engineers and project managers use this
knowledge and experience in planning and co-ordinating the works.
In text question
Element specifications
Although buildings can be analysed in terms of a standard set of elements
as discussed above, the actual specification and design for each element is
wide and varied.
In text question
This view, and related proposals within the report, is not without
controversy though. The supply side of the industry- contractors, sub-
contractors, consultants, suppliers- who had little involvement in the
report, claim that Egan does not really understand construction and
many of the proposals are unrealistic. Undoubtedly though, from a risk
management perspective, more standard repeatable situations whether in
product or process, means less uncertainty about outcomes and therefore
less risk. The degree to which this can happen in practice will continue to
be debated. To conclude this section of the discussion, a quote from
Raftery offers a balanced view:
In text question
The foregoing focussed on the risk and uncertainty that stems from
features of the project itself. The next section looks at the environment
within which the project exists and the influence this has on exposure to
risk and uncertainty. The concept of the project having an internal and
external environment is introduced.
Commercial opportunity/
social need
External Environment
controllable
Internal Environment
Project constitution/
organisation
uncontrollable
In text question
In text question
The project also affects its external environment in the way it changes the
environment and also affects people not directly involved in the project.
The very process of construction itself is a visible, often intrusive process.
Many individuals and groups can be affected in some way, positively or
negatively, by the project. For example, a new building may be perceived
to enhance an area. It may have aesthetic appeal, contribute to the
regeneration of an area, provide some service that is desirable to the
community or increase employment from the staffing and running of the
facility that will be required. In such circumstances it would be considered
an asset to an area and be positively received by the local community and
members of the public, who represent an aspects of the external
environment. Given this scenario, the stakeholders in the projects external
environment would not present a problem or risk to the project.
Conversely, projects may be received negatively by sections of the local
community. Projects which are perceived to be detrimental to an area for
any number of reasons- because they degrade the landscape, cause people
to worry about the effect on the value of their own property, object to the
activities that will be carried out in the building, or object to the nature of
the clients business. Perhaps the noise and disruption from the
construction process itself creates objections. There have been several
high profile examples of projects severely disrupted by individuals and
protest groups for environmental or political reasons. In such
circumstances the external environment and its stakeholders pose a
substantial threat to the project. Stakeholders have to be taken account of
as part of the RM process. Stakeholder mapping is a related aspect of
project management which is dealt with elsewhere in the programme.
In text question
Can you list some projects which have been threatened by external
environment stakeholders?
risks. Risks from the external project environment would fall into this
category. Although uncontrollable, such risks can be foreseen and
accommodated for.
In text question
Political change
Government legislation
In text question
Which of these risks are internal and which external to the project
environment?
The risk event is the actual manifestation of a risk on some part of the
project or the project as a whole i.e. how it occurs. For example, if an
unproven supplier is a potential source of risk, the associated event might
be late or wrong delivery of materials to the site. If severe frosts are a
weather risk, the associated event might be delay to concreting operations.
If volatile economic conditions are an example source of risk, the
associated event might be serious increase in the cost of skilled finishing
joiners later in the project. Generic risk checklists contain potential
sources of risk exposure on a project, but the associated risk event is
particular to the project and surrounding circumstances.
The effect of a risk refers to what impact or consequences it will have for a
party or parties to the project. The impact can be measured in time,
monetary or quality terms - though ultimately the impact of risk events
occurring will be monetary for somebody. Therefore, whilst it is true to
say there are many sources of risk on a project, the effects are few.
6.1 Introduction
This unit considers project risk from the perspective of the client. There
are 3 main aspects of risk that should be assessed from the outset, and a
systematic approach to doing this is described. These risk aspects centre
around strategic concerns about how the project relates to the clients
operations, as well as the risks inherent in the project deliverable itself
which are commercial, technical and managerial in nature.
buildings are investment goods- that is to say they are only a means to an
end- used as part of the production process but not contributing directly to
the generation of profit for an organisation. Even public sector investment
in building projects must have a sound business case. For commercial
clients the purpose may include furthering the production of goods and
services, through the provision of factories, offices or some industrial
process. Investing in new/adapted buildings or facilities to house some
process or activities will add value to the organisation.
In text question
1. How the T, C and Q objectives are established at the outset and the
degree of confidence in them
2. What the impact to the client organisation is in failing to meet
these objectives
3. The riskiness of the project itself- the risk profile of the building.
The table below shows how risky a project is according to how these
objectives are established. As the means of establishing T. C and Q
objectives become increasingly unsound and unclear, the risk rating for
the project increases. Notice how, for all criteria, it is the level of
information available which determines the level of risk involved. Projects
which have inbuilt contingencies (a form of RM) are the least risky, and
those with a higher risk rating indicate more unknown unknowns
Objective
Risk Time Cost Quality
Rating known knowns
1 Benchmarks were used to Benchmarks were used to Quality requirements have
establish schedule and establish budget and adequate been agreed and
adequate contingencies exist contingencies exist documented - Good PM & cost control
- More info across criteria
- Explicit contingencies
- Less uncertainty
2 Benchmarks were used to Benchmarks were used to Quality requirements have
establish schedule establish budget been agreed and are being
documented
known unknowns
3 The basis for the schedule is The basis for the budget is Quality requirements have
clear, but indications are that clear, but indications are that been agreed but not yet
overruns are possible overruns are possible documented
4 The basis for the schedule is The basis for the current Some initial discussions
unclear or the budget is likely budget is unclear or the budget with the client on quality
to be inadequate is likely to be inadequate requirements
- Absence of good PM
- Less information
- Increasing uncertainty
5 There is no clear schedule or There is no clear budget or the Quality requirements are
the schedule is clearly budget is clearly insufficient not known
insufficient unknown unknowns
In text question
Again, it can be seen from the table that the risk rating of the project for
this aspect increases as the consequences of failure to meet the objectives
become more critical. These range from nuisance value at the lowest level
(risk rating of 1), through to complete failure of the business at the highest
level (risk rating of 5).
2 Alternative arrangements Some scope for additional funds Tolerable effect on clients
available (project cost 25000 - 250000) business
(project period 6 12 months)
3 Delays undesirable but could be Request for additional funds clients business
managed would be difficult moderately affected
(project period 12 18 months) (project cost 25000 - 1M)
4 Severe disruption to clients No additional funds available and clients business severely
business scope reduced disrupted
(project period 18-24 months) (project cost 1M - 2M)
5 Clients business ceases altogether No additional funds available and clients business ceases
(project period >24 months) project will not proceed altogether
(project cost >2M)
In text question
What is the riskiest scenario for a client in not meeting the projects
objectives?
Complexity of Outcome based Coordination of Design and Supply and Supply only
deliverable contract (e.g. PFI) services (e.g FM) construct installation
Financing Private sector Capital works not Capital works in Capital works Recurrent funds
funding or joint yet approved or forward estimates already allocated in current year
venture requested
Adequacy of Very likely to be Likely to be Tight budget, Adequate with Adequate with
funds inadequate adequate achievable with some contingency generous
control contingency
Project location Remote, Remote, Regional but Regional Metropolitan
inaccessible accessible distant
Site availability Site not identified Several sites Site identified but New site Existing site
identified not yet purchased purchased
Project Need has not Justification is Needs justified Need justified Need fully
justification been justified questionable but may change based on justified through
through project historical recognized
information process
Project Unidentified Potential Required Few approvals No approval
approvals approvals approval delays approvals are required or most required or
required have been known and obtained already obtained
identified documentd
Consultant Selection without Design Full EOI and RFP Period panel Consultant
selection approved competition consultant selected using
processes approved process
Stakeholder High level of High profile Stakeholder Project may Project unlikely
interest political, client or project groups involved attract to attract
community or stakeholder or stakeholder or
media sensitivity media interest media interest
In text question
From your own experience, list projects that you know of which
would fit into either end of the risk profile spectrum
Project
related
12 project location
13 project surroundings
14 hazardous materials (Tactical level)
15 availability of contractors
16 uniqueness of product
17 clients experience
Project 18 client relationships
Management 19 consultant selection
related
At one extreme scenario of low risk we would have a technically simple project
of modest cost, where sound information underpins the estimates and forecasts,
and with an impact to the clients business which is minimal anyway should they
not be met. At the other extreme of high risk we would have a difficult and novel
project, where forecasts are based on poor/incomplete information, and it forms a
critical part of the clients business. Of course these scenarios are an
oversimplification and, realistically, any project will have a mixture of risk
ratings across all three of the aspects as described.
2. There are many sources of risk, but ultimately few impacts. What
are the impacts of risk on any project?
7.1 Introduction
Previous units discussed the nature of risk and uncertainty and the ways in
which it can affect the construction project. The strategic and tactical
viewpoint of risk, according to where in the PLC it is being assessed has
also been examined. Hopefully, the importance of ongoing RM to project
success is now firmly established in the readers mind. This (and the next)
unit now turns attention to more specific matters of applying risk
management itself. i.e. how it is actually carried out in practice. The RM
framework, which sets the agenda for the team based study, is explained.
A number of these studies, applied at targeted stages throughout the PLC,
would constitute a comprehensive approach to project RM. A study
structure for combining both VM and RM together is also presented. The
unit which follows explains some of the actual tools and techniques that
can be employed by a team within a study.
7.3 RM terminology
As for the definition of what RM actually is, the description of what
constitutes the RM process differs slightly from author to author. Again,
though, there are a number of key steps recognisable in all which are
discussed. It is mainly a difference in terminology and emphases which
separates the various explanation of RM, rather than any matters of real
substance. The following is an overview of the generic RM process which
would fit any application, adapted from the PMI PMBoK
study
Risk analysis - quantitative: simulation, scenario analysis
- qualitative: nominal group techniques
For each risk study the appropriate members of the team will come
together and work through steps 2] to 4] as described below, within a
facilitated and highly structured workshop type setting. It is likely that
either the project manager or someone else with specific RM
responsibility will facilitate the risk study sessions. An external consultant
is often engaged to facilitate the study and effectively manage the work of
the group.
In text question
The purpose of the risk identification stage is to capture all possible range
of risks that might affect the project at that stage of its development. The
emphasis is to maximise the quantity of possible risks rather than their
quality. i.e. no assessment is intended at this stage as this may stifle the
creativity process. By generating a large quantity of imaginative risk
scenarios, it is more likely that all possible scenarios will be covered.
At the conclusion of the risk identification stage the team will have a list
of risks that threaten the project (or opportunities to be exploited)
In text question
In text question
Elimination
This is obviously the most desirable outcome to completely eliminate the
risk. Possible areas may be to eliminate a safety risk by not undertaking a
certain type of welding inside a building, but perhaps prefabricating.
Transfer risk
Contractual transfer of a risk perhaps to another party or insurance
company is a method of dealing with risks that cannot be wholly or
partially eliminated. Of course, transferring a risk does not reduce the
effect it would have, or the likelihood of its occurrence- it only passes the
responsibility for it to another party.
In text question
Threats Opportunities
Eliminate Exploit
Transfer Share
Insurance often does not represent value for money for an organisation,
since the premium will be based on general claims experience of other
organisations that may not reflect the firms own experience. Also there is
a high mark-up to cover the overheads and profit of the insurance
company, and also the possibility of disputed claims and delayed
payments if the service offered is poor.
In text question
1. Information
Select topics for Function and risk
brainstorming from FAST diagram
2. Creativity
Identification
Brainstorm risks associated with function
solutions. Brainstorm global risks
3. Evaluation
Analysis
Evaluate risks, select those requiring consideration
4. Development
Analysis
Consider remaining risks, weight them
and develop a response Response
5. Presentation
Self-assessment question
What are the practical benefits and limitations of combining value and risk
management into a single service?
8.1 Introduction.
This unit introduces some of the more common tools and techniques
applied within a RM workshop study. These help the team lend structure
to the study for effectively identifying and assessing risks that affect the
project. Tools and techniques that are appropriate for a workshop study
will be easy to understand and straightforward to apply.
Historical data
Probably the best means of assessing what the risky aspects of a project
are is to draw from direct experience of similar past projects, since most
projects contain a number of reasonably standard and recognisable risk
situations. Useful historical data for risk identification in the construction
project may come from a number of sources. An obvious example of
historical data is that of the Meteorological Office for weather forecasting,
where prediction of future events is based on many years of recorded past
events of rainfall, temperature, wind speed and direction etc. Although
this is from outside the construction industry it obviously has its uses in
construction management and planning, such is the influence the weather
has on many operations.
effect that inflation has on the labour and materials markets. Based on this
data, predictions for the future are made.
In-text question
Checklists
Generic checklists are a useful source of information when compiling a
list of possible risks associated with a project. A checklist is simply a
comprehensive list of risks that could affect any project. Although
necessarily general in nature checklists can be used as prompts in
determining what the potential risks are for the project under study.
Published risk checklists in texts and journal papers can be consulted as
part of the risk identification process. Separate ones exist for client,
contractor and consultant perspectives. Whilst checklists are undoubtedly
a convenient and relatively simple approach to risk identification it is
important not to be over reliant on them. There is a danger that they can
act as a straitjacket and actually inhibit detailed thought on specific project
risks that may not be recorded on a generic checklist.
Brainstorming
This is one of the most powerful, and most widely used, techniques for
risk identification. Brainstorming is a creativity technique extensively
used in value management and much can be found written about it in
value management literature. Essentially a brainstorming session is a
short-term intensive group exercise, where a team of individuals will
generate as many ideas as possible for risk events that may adversely
affect the project. In a sense, this may be termed negative brainstorming
as the team of individuals is trying to determine all the things that may go
wrong with the project i.e. the downside risks, as compared with more
It can be seen from the second column of the tables below that an
informal, qualitative grading can be quantified and expressed in more
formal, numerical terms. This provides a format suitable for any
subsequent quantitative risk analysis.
PROB.
RISK MATRIX
LOW MEDIUM
PRIORITY PRIORITY M
IMPACT L
L M H IMPACT
Arrow of Attention
VHI VHI
HI HI
Probability
Probability
MED MED
LO LO
VLO VLO
After a risk list is compiled using brainstorming and any other appropriate
techniques each identified risk area is gone through and a quick
assessment made of its impact and probability of occurrence. This is a
group activity and the assessments should be based on consensus.
Depending on which box on the grid each risk is placed in, based on
probability and impact, it can be prioritised as having low, medium or
high priority for further investigation and consideration. The advantage of
the risk grid approach is that it is quick and easy to apply, and can be
readily understood by everyone involved in the risk workshop. Its
limitations are that it is a rough technique, and further analysis will almost
certainly be required for those risks having a higher priority. However it is
always useful as a first pass through the list to streamline it and quickly
focus on the most important areas. Hillson (IJPM 20, 2002) developed a
risk grid which separately identifies upside risk from downside risk, and
termed the high priority area as the arrow of attention.
Speculative Risk Risks which may result in loss or gain and will be
apportioned amongst parties to a project.
Strategic phase Initial stages of a project concerned with defining its
scope and developing the brief.
9.1 Introduction
This unit is a synopsis of the review of value engineering practice in the
USA in Value Management in Design and Construction (1993). A follow
up visit in 1997 confirmed that the practices reported here remain largely
unaltered. In the USA a significant proportion of value engineering is
undertaken for public sector organisations. Value engineering consultants
obtain this work through competitive fee bidding against a specification
drawn up by the public sector authority. This results in a prescribed and
relatively standardised value engineering service.
Described here in some detail are the Charette or 10% stage study, the
40-hour value engineering study at 35% stage, the audit and the
contractors change proposal.
There is a theory which states that the brief given by the client to the design
team is an amalgam of the wish lists of all of the parties who contribute to
the brief. This is particularly so for buildings that are to house organisations
comprised of diverse departments such as hospitals, universities, prisons,
The charette is organised along the traditional job plan lines with the first
stage being to gather as much information as is available regarding the
function of the spaces defined in the brief. The function of all of the spaces
are defined along with performance criteria e.g. this space must be held at a
constant 20C 5 where the activity within the space generates heat.
The ideas generated are recorded and analysed and the final decisions are
incorporated into the brief.
Secondly, the exercise was considered by some clients to be the best way of
briefing the whole team. One industrial client with a large and expanding
building stock stated that even if the exercise did not realise any great
rationalisation the very fact that all members of the team, the architect,
structural engineer, mechanical and electrical engineers, etc, were present
meant that all understood fully his requirements.
Third, the exercise occurs early in the process, stated by many to be the most
cost consequent stage. Fourthly, the exercise can be carried out in a short
period of time, only the most complex projects will involve more than two
days work.
and the design team themselves would not normally organise such a
meeting. The fact that it was a value engineering exercise under the
chairmanship of an outsider made it happen.
The client should inform the members of the design team at the time of their
fee bid that the project will be the subject of a value management exercise.
This is important both from a human relations aspect and also from the point
of view of establishing how the design team are to cover the cost of any
redesign work arising out of the exercise. Some clients require the members
to cover this cost within their fee bid. Others state at the time of the fee bid
that the design team members will be reimbursed for any necessary redesign
work on an hourly basis.
The client appoints the value engineer, the value manager and in discussion
with the design team establishes the date for the study. Normally the value
engineer will submit a fee bid that covers the cost of the complete value
management exercise described under.
The value engineer will appoint a value management team, normally six to
eight professionals in a mix that reflects the characteristics of the project
under review. So for example, a project with a large amount of mechanical
and electrical servicing may attract a team including four members with
these professional backgrounds. These team members will be drawn from
professional practice and may or may not have any previous value
management experience. The team members are paid by the value engineer.
The study is normally held near the site of the proposed project, either in a
hotel or in a room provided by the client within the clients office.
The date of the study is a key date for the design team and the value
management team. The design team must be complete to sketch design stage
one week before the date of the study. This includes the architectural design
and also the structural, mechanical and electrical engineering designs. The
completed drawings are sent to the value engineer for distribution to the
team during the week preceding the study.
During the week of the study the team will follow strictly the stages of the
job plan. It is the logical step by step approach to the generation of
alternative technical solutions that makes value management unique.
Following the introduction the client and the design architect present the
project, answer questions and the client reaffirms which areas of the project
are within the scope of the exercise. This latter point is important since, for
example, if the client has already reached an agreement with a trade union
that a specific number of men will be employed within a plant, then any
ingenuity on the part of the value management team to reduce manning
levels will be in vain.
The team now concentrates its efforts on identifying the functions of the
various parts of the building. In the study emphasis is given to those
functions which are not important, or are secondary, but attract a high
cost. Attention will also be paid to those functions that are primary and
important but attract a low cost.
In one study for the modernisation of a boiler house on a large military site
in North America, with an estimated project cost of $71,500,948, the team
identified 17 functions of which 7 were selected for study.
acceptability of the ideas in principle. This can reduce abortive work if, for
instance, the design team had already thought of the idea and rejected it or if
the architect would not agree to such an idea under any circumstances.
In the afternoon those worked solutions accepted by the team are presented
to the design architect and the client.
The formal study is now at an end. The members of the study return to their
practice leaving the value engineer to take away the weeks work and write
the report.
In-text question
It also ensures the fixing of a date for the completion of a sketch design.
Although not a function of the study it has been stated that the setting of a
date for the study, forces the design team to complete to a more advanced
stage than would otherwise be achieved particularly by the engineering
designers.
In the majority of cases the costs of the study are a small proportion of the
savings achieved. Value managers state that on any project at least 10% of
the estimated contract value is within the area of unnecessary cost. They also
state that the value manager will achieve a 10:1 return on the investment
made by the client and therefore in the majority of cases the study fee,
usually quoted as a lump sum, would work out to be not less than 10% of the
savings realised.
The problems associated with the study relate to conflict, time and
resourcing. These centre on:
The fact that the client may consider that the design team should arrive
at the optimal solution without the need for a further exercise at
additional expense. This criticism may be countered in two ways, firstly
that it is the function of the design team to arrive at a workable solution
given the information in the client's requirements. Secondly, that a value
management study is an analysis of the ideas which have been
generated. A value management study cannot be carried out until there is
an idea to analyse and it is therefore truly a second phase of the design
exercise. Currently, designers are not expected to carry out nor paid for
such an exercise.
may stifle frank comments on the design. This potential area of conflict
can be alleviated through the education of the designers in value
management techniques, informing the members of the design team at
the time of their appointment that the exercise is to take place and
payment of an additional fee for implementing design changes.
The time of the value management study. It is beyond dispute that the
value management study will effectively take three to four weeks from
the design programme. That is one week prior to the study for the
distribution of drawings and information, the study week and the period
of time following the study for the submission of the report, discussion
and design changes. In some projects this period of time, during which
the design will be at a standstill, will be unacceptable. However, in the
majority of cases it is capable of being accommodated particularly in
view of the fact that the study itself is a watershed between sketch design
and working drawings and provides an immovable date for the
completion of the sketch design.
The study therefore is not without its problems, but has consistently proved
to be a very effective means for the application of value management.
Following the review the value manager will submit a report detailing the
primary objective and the most cost-effective method for its realisation.
requirements to the extent that the company now adopts a policy of holding
a charette before a proposal is submitted to the parent company.
The benefit of the clause is that it allows the contractor to be pro-active and
use construction/engineering knowledge to improve a facility at on-site
stage.
The disadvantage of the clause is that the contract may be delayed while the
design team investigate the viability of the change. For this reason changes
tend to be relatively superficial.
These were reduced to three for presentation to the client. For the selected
plan a number of structural solutions were generated and analysed on a
matrix along with solutions for the electrical and mechanical installations.
Once the building form was established construction work began. Meetings
continued with the construction manager in attendance through to the end of
the project. The final cost of the project was $9 million less than the budget.
In 1997 it was confirmed that the prime method used by the public sector
was the 40-hour value engineering study with an independent team. Heavy
public sector patronage of value engineering studies in construction
suggests a close linkage with public accountability. In respect of the 40-
hour value engineering study the authors (refs 1987, 1991 & 1993) and
Palmer (1992) noted that much of what was purported to be value
engineering was equivalent to the traditional specification reduction and
component substitution cost reduction exercises undertaken by quantity
surveyors in the course of their normal cost planning function. The major
difference was in the use of a team approach to problem identification and
problem solving.
There are no known examples of the value engineering audit being applied
in a UK context. Similarly, it is also concluded that while agreements to
share value engineering change proposals at the post contract stage have
been made in the UK, the application appears to be informal or based
upon an exchange of letters, rather than being incorporated into a standard
form of contract.
In-text question
9.9 Conclusion
This unit has described in outline the method of value engineering used in
the construction industry in the USA. Its use is typified by public sector
patronage where it can only be assumed that the use of the technique is for
public accountability purposes. In the UK, the professional quantity
surveyor is the member of the team who is liable for the correct budgetary
control of the project from post sketch design to its completion. This has
an impact on the type of study used in the UK. The UK construction
industry has learnt much from the Charette form of value engineering and
continues to develop this approach.
10.1 Introduction
This unit begins by introducing techniques that may be used in the
briefing process to describe the customer or clients requirements. The
concept of Function Analysis (FA) is introduced and its essential
principles are described. These principles are developed with the Function
Logic diagram and examples are presented to illustrate its application in
practice. The unit develops by considering technical orientated FA and its
application at the level of a buildings elements. The relationship with
traditional elemental cost planning as practised by the quantity surveyor is
then discussed.
9. A team can decide on the criteria for value, worth and quality by
consensus. In this respect a team acts as an individual.
In-text question
Verb/noun definition
Most texts recommend that the function of an item or a system be
expressed as a concise phrase, ideally one comprising just an active
verb followed by a noun.
verb/noun functions can be generated for the object under study. Further
consideration should see the team distinguish between needs and wants
functions. Client needs are those functions the project must possess to
serve its basic intentions. Client wants are those embellishments to the
project which are nice to have, but not critical to the survival or basic
integrity of the project. From the finalised and agreed list of functions, a
function logic - also known as FAST (Function Analysis System
Technique) - diagram can then be constructed.
Example 1
Consider the construction of function logic diagrams for the following
simple project. The project came into being when a local authority
decided to extend an existing country park to incorporate land on the far
side of a river. The project involved the investment of resources to
transport pedestrians, including disabled and children in prams/buggies,
safely across the river.
Generation of functions
The functions were generated by the team in a random fashion on post-it
notes and placed on a large sheet of paper.
Maintain
Facility Position
Meet People
Minimise Demand
Wear
Reduce
Establish
Downtime
Non slip Rules (of
(due to
Surface passage)
flooding)
Minimise
Labour
Support Protect Cater for
Peopler People children
Control
People
Direct
Routes Prevent Focal
Falling (into point
Span
river) River
Sorting of functions
Following the generation of functions, undertaken as a brainstorming
process, the team are invited to order the functions by putting the highest
order need at the top left hand corner of the paper and the lowest order
want at the bottom right. This is illustrated in Figure 8.2 below.
Facilitate Span
Passage River
Prevent
Support Protect Focal
Falling (into
Peopler People point
river)
Establish
Meet Control Position
Rules (of
Demand People People
passage)
Reduce
Downtime Direct Maintain
(due to Routes Facility
flooding)
Minimise
Labour
Diagramming
A diagram is constructed from the ordered post-it notes. The type of
diagram will depend upon the focus of the study being undertaken. To
gain a technical appreciation of the problem a function diagram with a
technical bias will be constructed. If the focus of the study is of a strategic
nature, such as a strategic briefing, a client orientated function diagram
will be constructed. The figures below illustrate the two types of
diagramming technique for the problems outlined above.
Minimise
Wear
Design Objectives Cater for Meet
Desired Objectives children Demand
Reduce
Downtime Cater for Maintain
(due to disabled Facility
flooding)
Educate Minimise
people Labour
Non slip
es
Surface e
tiv
tiv
ec
ec
bj
bj
O
O
ry
e
da
im
on
Pr
c
Se
Facilitate
Establish
Passage Support Position Protect Control
Rules (of
across Peopler People People People
passage)
River
Span Prevent
River Direct
Falling (into
Routes
river)
Pa
rra
lel
lO
bj
ec
tiv
e
It should be noted from the above diagram that the prime objective is a
technical objective and the brainstorming of ideas following the
construction of the diagram will therefore lead to the exploration of
technical solutions. The brainstormed solutions, for example, a suspension
bridge, a simply supported span bridge, stepping stones, etc, will be
audited back against the diagram to determine the extent to which the
ideas meet the functions.
The diagram is structured such that the prime objective of the project is
situated on the left-hand side of the scope line. The prime objective "
support people" is situated immediately to the right of the project
objective. Parallel objectives are below the prime objective in this case
"span river". Secondary objectives appear to the right of the prime
objective and design objectives are situated immediately above. Desired
objectives are located on the top right of the diagram above the secondary
objectives.
HOW WHY
Support
People
Span
Prevent NEEDS
Falling (into
River
river)
Protect
People
Establish
Rules (of
passage)
Control
People
Position
People
Direct
Routes
Cater for
children
Create a focal Meet
point for the Demand
park which
educates and
Cater for
facilitates the
disabled
crossing of the
river
Reduce
Downtime
(due to
flooding)
Minimise
Wear
WANTS
Maintain
Facility
Minimise
Labour
This section will outline the principles of cost planning using cost data
organised in the form of elemental cost analyses. This will be followed by
a debate on element function and put forward the idea that elements may
be defined by a list of characteristic functions which are not project
specific. A method of element function analysis is described.
A frame of reference.
A means of checking.
A method for remedial action.
The frame of reference comprises an elemental cost plan for the project
under review. For example, assume that a quantity surveyor is required to
compile a cost plan for an office building of 2000 square metres floor
area. The surveyor will select from the database of cost analyses an
analysis that bears the closest resemblance to the project. For example, the
surveyor may find a cost analyses for a 2500 square metre office building
with similar characteristics to the proposed project.
Inflation in prices between the date of tender of the analysis and the
date of tender of the proposed project.
Difference in prices between the location of the project represented by
the analysis and the proposed project.
Any major differences between the likely specification of the proposed
project and the analysis, for example, the type and extent of air-
conditioning, inclusion of car parking and access roads, etc.
Differences in the market prices due to demand for construction work.
Differences in risk costs brought about by choice of a particular
procurement method.
After these and a large number of other adjustments are made the surveyor
will have an elemental costs plan which displays a high degree of cost
certainty. This is the point when the cost plan becomes the frame of
reference. The cost plan figure is given to the client for the building and
therefore, generally, may not be exceeded. It should be noted that the cost
plan compiled in this way could precede sketch design but rarely does.
With the sketch design the surveyor will measure the elements and revise
the costs plan figures based upon priced measurement. In the event, and it
should be emphasised that generally only in the event of an increase in
costs the surveyor will ask for a design team meeting to address the
overspend. This highlights the use of the frame of reference, and the
method of checking.
The method of elemental costs planning and cost control described above
is appropriate to design where a high level of certainty has been
established, i.e., at the completion of the final sketch design. The
advantage of a value management exercise prior to the final sketch design
is that it ensures that sketch design fulfils the performance specification of
the brief and in accordance with the clients value system.
The important point to note here is that while value management will
address the functions of all elements, cost planning only triggers action in
the event of an overspend.
For example, an internal wall will have one or more of the following
functions irrespective of the project context.
Support load.
Divide space.
Separate environments.
Dampen noise.
Transmit light.
Secure space.
Support fittings.
Facilitate finishing.
Restrict fire-spread.
Demonstrate hierarchy.
Minimise distraction.
Debate
10.7 Conclusion
The understanding of the functionality of projects, whether at concept,
physical spaces, construction elements or components level, in a value
management context, is critical to the strategic and tactical stages of a
projects evolution. The unit has considered FA and function logic (or
FAST) diagrams at the strategic and tactical project levels. At this point in
time relatively little academic work has been undertaken in the
development of procedures, tools and processes to properly understand
The frame, floors and substructure exist to support and transfer load.
Lifts and escalators exist to minimise walking.
Heating and air conditioning exist to maintain comfort.
The external walls, roof, windows and external doors protect the space
and express aesthetic.
Only the internal walls, internal doors, floor wall and ceiling finishes, and
fittings and furnishings overtly serve the client function. In traditional
cost planning it is likely that these elements will be targeted for cost
reduction. In other words the very elements that the client requires service
from in order to achieve the strategic objective are often those that, from a
value perspective, are mismanaged.
At which stage of the project life cycle might a customer oriented FAST
diagram be prepared in a VM workshop?
11.1 Introduction
This unit investigates identifiable briefing structures and the commonly
identified problems in briefing. The questions at the end of this unit are
intended to promote further reading and analysis.
The text is taken from Kelly J, MacPherson S and Male S, The Briefing
Process; A Review and Critique RICS, 1992, ISBN 0 85406 541 5.
11.2 Glossary
Project brief The full statement of the clients functional and
operational requirements for the completed
project.
finance, however private sector clients did not report the same concern
over funding, and there appears to be an assumption that money could be
found if it were needed. For developers, on the other hand, the decision to
build is opportunistic and based on the availability of desirable sites.
Highly sophisticated clients often retain their own design consultants who
participate in the briefing process and so provide some design advice at
the early stages. They may also take the advice of letting agents about the
design of commercial buildings so that their 'purpose built' properties are
not designed so specifically to their particular requirements as to
compromise their asset value and be difficult to dispose of should this be
necessary at some future time. Such clients will often have developed
model briefs for certain generic types of building such as an office, a
school or a leisure centre. A rather dated example of this is the system
described by IBM (AJ, 1987a). The brief for a project is developed by an
in-house project manager who consults with a facilities manager and
representatives of the user groups, with advice on the design and cost
implications of decisions coming from in-house design consultants. The
extremely rigid brief is then passed to the design team who will work on
the project. The project design team must then liaise exclusively with the
project manager. They never meet the users of the building, and if they
wish to deviate from the brief they must present an extremely good case
for doing so.
Buildability.
Incomplete briefs.
For unsophisticated clients, the initial approach to the industry can present a
problem. Most initially contact an architect and subsequently rely on his
advice for the selection of other design team members and contractors. It
has been observed, however, that this approach results in the client being
steered down the traditional procurement route without the option of
considering alternative methods (Newman et al, 1981).
For owner occupiers, the usual way of doing this in all but the smallest of
organisations is to appoint representatives for each of the user groups (e.g.
departments affected by the building project) and form a committee to draft
the brief. There is little information available on how clients select these
representatives, but there is some evidence to suggest that many client
organisations, in underestimating the importance of the briefing process,
appoint representatives of relatively low status (O'Reilly, 1986).
Consequently, their ability to access information quickly and to make
decisions is limited, and this can slow down the briefing process. It can also
be frustrating for the design team, because they are effectively denied access
to the business case team. These representatives do however have the power
to influence the briefing process by their interpretation of information
between the client interest groups and the design team, and between the
design team and the other more powerful members of the business case
team. If this interpretation is not faithful, the brief can become distorted in
relation to the real client needs and decisions.
time. Moreover, the interests of the members of the client body can be quite
diverse.
Another difficulty facing the brief writer is the competition for resources
within the client organisation. When asked to state their requirements, it has
been found that user groups tend to maximise their 'wish list' in anticipation
of being bargained down from this (Kelly and Male, 1988). The problem
confronting the brief writer is then to understand the priorities of the user
groups such that high priority needs are not sacrificed for lower priority
wants.
A third difficulty facing brief writers is the changes that can occur in the
client organisation and the environment during the briefing and design
process. A brief can only reflect the needs (and anticipated future needs) of
the client at a particular point in time, however these needs can change
during the course of the project. These changes can be sudden and
Dealing with the above problems is an exceptionally difficult task for the
brief writer, and it is all the more difficult for him if he is unfamiliar with the
client organisation. This is one of the reasons behind IBMs briefing. They
maintain that it would be impossible for a consultant architect to reach an
understanding of IBMs corporate culture in the short time available at the
briefing stage.
Finally, there is the position of the architect who is designing a building for a
developer and is unable to consult the ultimate users regarding their needs.
Indeed the users will normally be a number of different groups who will
change during the life of the building. Here, assumptions must be made
about the user requirements, and the building designed to be flexible enough
to satisfy most of the requirements for most of the time.
Until recently, the needs of the users have been largely ignored in
development. It has been suggested that where demand has outstripped
supply, as in the London office market during certain periods in its
history, users placing exceptionally high priority on location have been
forced to accept what buildings were available. In the absence of any
consumer pressure therefore, bad design has gone unchecked during these
periods. When there is a relaxation in demand, however, design becomes
more important and users can be seen to exercise their judgement by
renting those buildings which they consider better designed (McIntosh,
1984).
Agents are now arguing that this brings the longer term requirements of
the funders and the users closer together. They believe that although the
users are not part of the business case team, commercial pressures will
force the funders to take user requirements more seriously in future,
placing pressure in turn on the developers to build better buildings (Ellis,
1984). Of course, funders have always had criteria for office building
design, but as Duffy (1986a) points out, the basis for these criteria laid
down by the anonymous, far seeing gnomes within the funding
institutions was never clear, and has since proved disastrously wrong as
witnessed by the growing number of obsolete office buildings constructed
in the boom of the 1960s. Consumer research is therefore on the increase
among funders and developers, as they make an effort to understand the
requirements of their customers more clearly (Evans, 1989).
11.4.6 Buildability
The issue of buildability in relation to early design decisions is also much
written about. Ever since the Tavistock report of 1966 there have been calls
for contractors to be involved at the earliest opportunity to provide advice on
the practical construction implications of design decisions. The traditional
separation of the design and construction processes has been described as a
division of responsibility not meant for this world(Quantity Surveyor,
1982). The design and build procurement method is supposed to allow
greater integration in this respect, although to what extent design practice is
truly influenced by procurement method is not clear. However, the design
and build procurement method (although the fastest growing method) only
accounts for about 10%-15% by value of all work in the UK (Franks,
1990b), furthermore there is no universal agreement that it is an appropriate
procurement route in all cases, and so the debate over how to introduce
buildability advice into early design continues. Gray (1985) suggests that
the only way to accomplish this is to involve a contractor at the early stages
or to employ a buildability consultant. However, there are actually very
few people within a contractors organisation who have the skills to analyse
design decisions and give advice of this kind. The same skill shortage
applies to buildability consultants, and as a result, states Gray, there are very
few good ones.
In the second stage (project brief), the general statement above is developed
further, usually in a series of committee meetings of some kind and a more
detailed document produced in the form of room data sheets with a budget
cost for the project and a target completion date.
Questions
Question 1 Outline the differences in the processes used by large and
small clients in briefing.
References
AJ (1986a) Development economics series No 2: Sites Architects' Journal,
23 April 1986, pp 49 - 50
Cave, C. Not least the users Architects' Journal, 19 & 26 August 1987, pp
80 - 81
Newman, R., Jenks, M., Dawson, S. and Bacon, V. Brief Formulation and
the Design of Buildings Oxford Polytechnic, 1981
12.1 Introduction
This unit is intended to provide the framework for the undernoted topics,
but reference to further reading and consideration of the questions is
required for a fuller understanding of the units subject matter. It should
be noted that, prior to 1997, Public Private Partnership (PPP) was
formerly known as Private Finance Initiative (PFI) under the Conservative
government administration and is often still referred to as PFI. This
includes official policy and good practice documentation produced by the
Treasury. Therefore the terms PFI and PPP may be thought of as
being synonymous. PPP projects provide a particularly good means of
introducing project risk issues at the strategic stage and, although PPP is
particular to the UK, its generic form of BOOT (Build Own Operate
Transfer) procurement exists throughout the world.
12.2 Glossary
PFI Private Finance Initiative. The procurement policy introduced in
1992.
Public Sector The government department client body procuring a PPP project.
Concession The long term contract between public & private sector for
providing services.
Concessionaire The private sector operator responsible for providing the services as
contracted.
Purchaser The public sector client who wishes to purchase specific services
from the operator.
Operator As Concessionaire.
Output Specification A statement of the services to be provided that define the PPP
project.
Reference Project A costed notional project used by the public sector as a benchmark
in assessing PPP bids.
Treasury Taskforce The Treasury body formed to co-ordinate and develop central PPP
policy.
Base Estimate Estimated cost of the project excluding any allowance for risk.
Investment Appraisal Financial model of a PPP projects cost and revenue stream over its
life to assess viability of project.
Payment Mechanism Contractual basis linking payment with the service delivered.
Note: Technically the term Public Private Partnership (PPP) replaced PFI
in 1997. However, PFI has become so established that it remains the most
commonly used term to date. Indeed, emerging Treasury publications
refer to PFI rather than PPP. In practice the terms are interchangeable.
A key principle of PPP is that of risk transfer. The transfer of risk over the
lifetime of projects from the public sector client body to private sector
provider is one of the main motivations for the clients decision to procure
through the PPP. It has also proved to be one of the most controversial
feature of PPP to date. Risk transfer necessarily involves identifying key
risks at the earliest phases of the project, and allocating them to public or
private sector.
The PPP has had a major impact on the UK construction industry since its
launch in 1992 through the wide ranging changes it makes to a large
sector of the industry and the value of work it will affect. The scale of PPP
means that the construction professions, consultancy and contracting
organisations and government departments are all having to develop
awareness of and expertise in dealing with PPP procurement. In the future
most government funded projects are likely to be procured through the
PPP as the industry and the government gets to grips with the policy.
Major infrastructure projects and projects requiring substantial capital
investment typically associated with the public sector including transport,
schools, health, water and sewerage treatment works are already being
delivered through PPP. In addition, major client organisations in the
private sector who invest heavily in the construction industry are
becoming interested in PPP style procurement for their own property and
facilities needs.
Identification, allocation and costing of project risk is carried out with the
development of a Reference Project by the client which will be used to
guide their negotiations with the private sector in ascertaining VFM. Stage
3 deals with this and risk management activity is defined below.
Costing of the reference project has to be in whole life terms and includes
capital investment, operation, maintenance and FM costs of the project
over its life i.e. all the costs that a bidders PPP solution would include.
These would constitute the base estimate. Significantly, the reference
project also has to include costing of the risks so that a true comparison
can be made with private sector bids which will include a pricing of the
risks that they absorb. This is comparable to the VFM guide which
requires explicit pricing of risks from the outset, and no sanctioning of
funds for general contingencies. All risks transferred under the PPP
option, but which would not be transferred under traditional procurement
have to be costed.
In-text question
There are a number of key risk areas to be considered from the earliest
stages:
The pure performance nature of the output specification puts all the
responsibility on bidders for developing solutions for meeting those
service specifications. This is part of the philosophy of PPP, that the
private sector should have the flexibility to innovate in designs and
proposals for the project, and not be constrained by prescriptive
specification. The thinking behind this is that the private sector driven by
commercial considerations can provide the service more efficiently than
the public sector, thus providing greater value for money than the
traditional approach. Risk inherent in bidding has been a major
contentious issue in the evolution of PPP as many industry reports and
journals will testify. Risk lies in investing time, money and effort
researching solutions and preparing bids and negotiating with the client
with no guarantee of success. The process is lengthier and investment is
greater than for traditional tendering, which essentially involves pricing a
ready defined solution by the client. As the private sector have a long term
interest (the duration of the concession) and responsibility for the project,
there is far greater uncertainty and therefore risk associated in trying to
account for future variables that must be assessed as part of the investment
appraisal. In general terms variables include design and construction risks,
cost of finance and operational and management costs.
There are cases where responsibility for, and therefore operation risk
associated with, certain core services will be retained by the public sector
for policy reasons. In prisons, prison officers will always be employed by
HM Prison Services, the public sector department. Likewise, core clinical
services in hospitals will be the responsibility of doctors and nurses
employed by NHS health trusts, not the private sector operator of the
hospital. As a PPP principle, though, as little operating risk as possible
should be retained by the public sector
The volume risk held by the private sector relates to availability of the
service i.e. ensuring that a minimum capacity of service can be delivered
throughout the concession. For example, this could be ensuring a certain
number of hospital beds, or prison cells are available at all times, or that a
sewerage treatment works guarantee that a certain volume of sewerage
can be processed at all times.
In-text question
1. If the asset has significant residual value at the end of the concession,
future bidders will want to take ownership of it and its value will be
reflected in a lower bid to for the next concession.
The need for specific legislation or planning permission for the asset
which would be a prerequisite to enable the PPP contract to take
effect. For example, if outline planning permission is required for
buildings or facilities then it is unlikely the private sector will take on
the risk for securing this. In the experience of PPP procurement of
prisons, the public sector obtains outline planning permission, leaving
the private sector to obtain detailed planning permission for their
design solutions.
there are still risks posed by the long term movement of prices. For
example, sector specific wage rises or an underestimation of the effects of
general inflation would not be correspondingly compensated for in the
payment mechanism.
Reading
PPP is a fast evolving area with new policy and procurement procedures
emerging regularly as the industry tries to improve its performance, and
address the many problems (not least risk transfer) that exist. As such,
there is no definitive text book on the matter. Instead journals and web
based sources are the best means of keeping up to date. The following are
good examples.
Note: These (and other) papers are available for download as PDF files
through the University library web site. See the electronic journals
section for details.
Questions
1. Consider the range of PPP type projects being procured. In view of
the risks discussed, what would you consider to be the least and most
risky type of projects on a whole life basis and why?
3. In your view, has the PPP been a success to date and will it succeed in
the future?
Some of the more important points and principles of PPP are discussed
below in relating to procurement of two prisons at Bridgend and
Fazakerley.
Prison A
800 category B places at Fazakerley on Merseyside. Securicor, Siefert and
W S Atkins consortium with construction partners Costain and Skanska.
Prison B
600 Category B places at Bridgend, awarded to Tarmac and Group 4
consortium.
Risk transfer
The public sector were satisfied that design, planning, construction and
operation risks were substantially transferred through the terms of the
contract, payment mechanisms agreed and the output specification
developed for the project. Some risks were retained as outlined below.
Features of deals
The concession periods are for 25 years, after which ownership of the
prisons is passed to the public sector. This is NOT the usual structure of
PPP deals, where there is no reversion of ownership to the public sector. It
was an unusual feature of these deals due to substantial difficulties in
obtaining outline planning permission for new prisons. The public sector
client (HM Prison Service) do not recommend this for future deals if
possible, as an asset designed today may not be suitable for service
provision in 25 years and may simply become a liability. The normal
route is for the service contract to be re-bid, with the facility offered to the
Contract termination
Should the operator become insolvent or be in serious breach of
obligations the Prison Service can terminate the contract. Alternatively,
the consortiums lenders can provide an alternative operator if there is
outstanding debt.
Construction cost and time overruns. No payment was made until the
projects were actually operating.
Speculative Risk Risks which may result in loss or gain and will be
apportioned amongst parties to a project.
Strategic phase Initial stages of a project concerned with defining its
scope and developing the brief.