Chapter 3 Formwork
Chapter 3 Formwork
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
3 FORMWORK
3.0 Introduction
Formwork is a temporary mould into which wet concrete and reinforcement is placed to form
a particular desired shape with a predetermined strength. The main function of formwork is
to place wet concrete until it retain its shape, size and position in order to form any concrete
member. There are various of modern technology used in the formwork system such as
slipform and precasting.
There are different ways to classify the formwork systems:
1. Traditional vs system:
Old stick-by-stick vs innovative approaches
2. Reusable vs lost forms:
lost formwork forms part of permanent structure and by definition can only be used once,
e.g., precast panels, steel tubes and Bondeck, etc.
3. Static vs movable (climbing) forms:
Movable or climbing forms relocate themselves to the next location using an integral
power source, e.g. slip form, jump form.
No loss of constituents
Uncontaminated of the concrete Possible
to be dismantled
Requirements for
Formwork
Withstand safely Controlled
all the loads size & surface
Economic Reusable
- 31 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
In determination the good formwork system, various question can be consider by the engineer
such as:
1. How formwork can be erected and de-shuttered fast.
2. How good concrete quality and surface finish can be achieved.
3. What is the optimum stock of formwork required for the size of work force, the specified
time schedule and flow of material.
4. What is the overall cost savings that can be achieved using the right type of formwork.
5. How SAFETY can be improved for the site personnel.
To achieve the requirement, three main items must be applied in the preliminary level. The
constructor must use the appropriate design, equipment and material the do the checking for
dimensions and stability. Before the formwork are ready to use, its must be clean from debris and
dirty the surface will be applied with release agent.
Cost is one the most important component in the construction works. In order to
minimize the cost, the economic essentials should be identified. In formwork, the constructor
should ensure the formworks are:
1. Low cost
2. Strength material and support members.
3. Finish method, materials and linings to produce the desired result direct from the
formwork.
4. Assembly use mechanical handling plant or patent systems.
5. Material careful in selecting material.
6. Design repetitive and adaptable.
7. Joints - tight enough to prevent grout leakage.
- 32 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
Each type of formwork has their own properties and disadvantages compare to advantages.
No Advantages Disadvantages
1 Relatively cheap Limited durability
2 Relatively light in weight for The pattern of grain tends to
handling leave an imprint
3 Easy to fix inserts on the side Its moisture content cause
of a form face for casting the significant dimensional changes
concrete
4 Easy to cut or to shape
- 33 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
No Advantages Disadvantages
1 Durable Relatively high cost
2 Not easily modified Heavy material
3 Can be used as sheet/frame Need more time
4 Dimensionally stable Liable to rust
5 Difficult to make it proof
against leakage
No Advantages Disadvantages
1 Durable More expensive
2 Usually used as special Reaction between concrete &
extrusions as beams aluminium results in corrosion
No Advantages Disadvantages
1 Used for surfaces which Require a considerable thickness
are not flat (circular etc) Of material to achieve adequate
resistance to deflection
2 More expensive
Ties will be required across the top of the form as a top restraint and these can be utilized
to form the kicker or used to position holding-down bolts.
- 34 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
General practice however to cast the columns up to the underside of the lowest beam
soffit and to complete the top of the column at the same time as a beam using make-up pieces to
complete the column and receive the beam intersections. Column forms are held together by:
a) Cleats
b) Timber yokes
c) Column clamps (steel)
d)
The spacing of the yokes and clamps should vary with the anticipated pressures and the greatest
pressure occurring at the base of the column box. The Actual Pressure will vary according to:
a) Rate of placing
b) Type of mix being used generally the richer the mix the greater the pressure.
c) Method of placing if vibrators are used pressures can increase up to 50% over
hand placing and compacting.
- 35 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
d) Air temperature the lower the temperature the slower is the hydration process
and consequently higher pressures are encountered.
Generally, the beam form is also used to support the slab formwork and the two structural
members are then cast together. The construction of the beam formwork can be done by using
single or double prop. Before the construction of the beam formwork, the prop are positioned
and level enough. The soffit are placed, leveled and position checked. After that the side forms
- 36 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
placed and their positioned checked before fix. Final check will be conduct before casting. The
materials of formwork will be according to its requirement.
- 37 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
- 38 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
- 39 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
- 40 - Construction Engineering
DEPARTMENT OF BUILDING AND CONSTRUCTION ENGINEERING
FKAAS
UNIVERSITI TUN HUSSEIN ONN MALAYSIA
- 41 - Construction Engineering