FMP Schedule

1) The document outlines a 10-week schedule for a student's film production project (FMP) on social realism. 2) Key dates include pitching the proposal by March 29th, completing pre-production by April 10th, filming between April 10th-May 8th, and releasing the first teaser on May 19th. 3) Editing takes place between April 24th-May 22nd, with the final run-through on May 24th and the project due for final hand-in on May 25th. The schedule is reviewed at the end of each week.

Uploaded by

api-331095474
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views

FMP Schedule

1) The document outlines a 10-week schedule for a student's film production project (FMP) on social realism. 2) Key dates include pitching the proposal by March 29th, completing pre-production by April 10th, filming between April 10th-May 8th, and releasing the first teaser on May 19th. 3) Editing takes place between April 24th-May 22nd, with the final run-through on May 24th and the project due for final hand-in on May 25th. The schedule is reviewed at the end of each week.

Uploaded by

api-331095474
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

FMP SCHEDULE

Studen
PRODUCTION TITLE FMP: Social Realism t George Rogers
Name:
Week Week
Day Activity Notes
No Beginning
Monday Given assignment Pitch and Proposal
Tuesday Ideas Pre-Production
Wednesd
Production
1 06tt March ay
Thursday
Ideas
Ideas Post-Production
Friday Releases
Weekend
Monday Ideas Schedule will be reviewed at the
Tuesday Ideas end of each week
Wednesd
2 13th March ay
Thursday
Ideas
Ideas
Friday Ideas
Weekend
Monday Ideas Schedule will be reviewed at the
Tuesday Ideas end of each week
Wednesd
3 20th March ay
Thursday
Ideas
Ideas
Friday
Weekend
Monday Ideas Schedule will be reviewed at the
Tuesday Ideas end of each week
Wednesd
4 27th
March
ay
Thursday
PITCH + proposal
Planning Pitch and proposal both due on 29th
Friday March
Weekend
3th April Monday Planning Schedule will be reviewed at the
5 Tuesday Planning end of each week
Wednesd Planning
ay Pre-production needs to be finished
Thursday Planning
Friday by 10th April
Weekend

Monday BEGIN FILMING - Filming Schedule will be reviewed at the


Tuesday Filming end of each week
Wednesd
EASTER Filming
10th April ay
1
Thursday Filming
Friday GOOD FRIDAY COLLEGE CLOSED
Weekend
Monday EASTER MONDAY Schedule will be reviewed at the
Tuesday Filming end of each week
EASTER Wednesd
17th April Filming
2 ay
Thursday Filming
Friday Filming
Weekend Filming
Monday Editing (reshoots if necessary) Schedule will be reviewed at the
Tuesday Editing (reshoots if necessary) end of each week
Wednesd
6 24th April
ay
Thursday
Editing (reshoots if necessary)
Editing (reshoots if necessary) Footage will be checked at the
Friday Editing (reshoots if necessary) beginning of this week to check if
Weekend reshoots are needed
Monday BANK HOLIDAY MONDAY COLLEGE CLOSED Schedule will be reviewed at the
Tuesday Editing (reshoots if necessary) end of each week
Wednesd
7 1st May
ay
Thursday
Editing (reshoots if necessary)
Editing (reshoots if necessary) All filming needs to be finished by
Friday FINAL RE-SHOOTS Monday 8th May
Weekend FINAL RE-SHOOTS
Monday Editing - opening sequence Schedule will be reviewed at the
Tuesday Editing - opening sequence end of each week
Wednesd Editing - opening sequence
8 8th May ay
Thursday Editing - opening sequence
Friday
Weekend
Monday Editing - first and second drafts Schedule will be reviewed at the
Tuesday Editing - second draft end of each week
Wednesd Editing - closing sequence
9 15th May ay
Thursday Editing - colour correction and effects Teaser 1 released on 19th May
Friday TEASER 1 RELEASED
Weekend
Monday Editing - final edit FMP will be finished and released
Tuesday Editing - final edit on 25th May
Wednesd Editing - final edits and additions
10 May
22nd
ay FINAL RUN-THROUGH
24th May final run-through
Thursday FINAL HAND-IN
Friday
Weekend