Scrum 15 Days Sat 4/1/17 Thu 4/20/17

This document outlines a project schedule from April to June 2017. It includes three methodologies - Scrum lasting 15 days from April 1-20, Extreme Programming lasting 14 days from April 1-19, and RAD lasting 24 days from April 1 to May 2. Each methodology involves various tasks such as requirement gathering, coding, testing, and deployment. Resources are assigned to complete each task.

Uploaded by

Thapaa Lila
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views2 pages

Scrum 15 Days Sat 4/1/17 Thu 4/20/17

This document outlines a project schedule from April to June 2017. It includes three methodologies - Scrum lasting 15 days from April 1-20, Extreme Programming lasting 14 days from April 1-19, and RAD lasting 24 days from April 1 to May 2. Each methodology involves various tasks such as requirement gathering, coding, testing, and deployment. Resources are assigned to complete each task.

Uploaded by

Thapaa Lila
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID Task Task Name Duration Start Finish Predecessors

Resource Names Mar '17 Apr '17 May '17 Jun '17
Mode 1926 2 9 162330 7 142128 4 111825
1 Scrum 15 days Sat 4/1/17 Thu 4/20/17
2 Create product Backlog 3 days Sat 4/1/17 Tue 4/4/17 Dibesh Shrestha Dibesh Shrestha
3 Plan sprint 4 days Wed 4/5/17 Sat 4/8/17 2 Dibesh Shrestha Dibesh Shrestha
4 Execute sprint process 3 days Mon 4/10/17 Wed 4/12/17 3 Dibesh Shrestha Dibesh Shrestha
5 Sprint review 4 days Thu 4/13/17 Tue 4/18/17 4 Dibesh Shrestha Dibesh Shrestha
6 sprint retrospectives 2 days Wed 4/19/17 Thu 4/20/17 5 Dibesh Shrestha Dibesh Shrestha
7
8 Extreme Programming 14 days Sat 4/1/17 Wed 4/19/17
9 Requirement gathering 3 days Sat 4/1/17 Tue 4/4/17 Arbindra Sutihar Arbindra Sutihar
10 Coding 3 days Wed 4/5/17 Fri 4/7/17 9 Arbindra Sutihar Arbindra Sutihar
11 Testing 3 days Sat 4/8/17 Tue 4/11/17 10 Arbindra Sutihar Arbindra Sutihar
12 Listening 3 days Wed 4/12/17 Fri 4/14/17 11 Arbindra Sutihar Arbindra Sutihar
13 Designing 4 days Fri 4/14/17 Wed 4/19/17 Arbindra Sutihar Arbindra Sutihar
14
15 RAD 24 days Sat 4/1/17 Tue 5/2/17
16 Scope 4 days Sat 4/1/17 Wed 4/5/17 Anish Shrestha Anish Shrestha
17 Purpose 5 days Thu 4/6/17 Tue 4/11/17 Anish Shrestha Anish Shrestha
18 Structure 5 days Wed 4/12/17 Tue 4/18/17 Anish Shrestha Anish Shrestha
19
20 System Design 4 days Wed 4/19/17 Mon 4/24/17 Anish,Arbindra,Dibesh Anish,Arbindra,Dibes
21
22 Implementation and Deployment 9 days Tue 4/25/17 Fri 5/5/17 Anish,Arbindra,Dibesh
23 Construction 3 days Tue 4/25/17 Thu 4/27/17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Gantt chart.mpp
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish Predecessors
Resource Names Mar '17 Apr '17 May '17 Jun '17
Mode 1926 2 9 162330 7 142128 4 111825
24 Testing 3 days Fri 4/28/17 Tue 5/2/17 23
25 System Deployment 3 days Wed 5/3/17 Fri 5/5/17

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Gantt chart.mpp
Summary Manual Summary Rollup Progress
Date: Sun 5/7/17
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only