Observed Consolidation in A Ring With Vertical and Radial Drainage
Observed Consolidation in A Ring With Vertical and Radial Drainage
3
Certificate Project work qualifies for submission
4
Approval of the Supervisor Approved/Rejected/Needs Revision
5
Signature of the Supervisor/s
1. ABSTRACT
Underwater concrete construction is a critical component of foundations and which subsequently becomes an integral
the any project. Therefore, its significance in the project far part of the substructure. A cofferdam is an enclosure within
beyond the concreting operations themselves, in essence, a water environment constructed to allow water to be
underwater concrete can be constructed with the same displaced by air for the purpose of creating a dry work
degree of reliability as above-water construction. But if it is environment. Commonly used for oil rig construction and
not carried out properly, with the proper concrete mixture repair, bridge and dam work, the cofferdam is usually a
and placement procedure, underwater concrete construction welded steel structure that is temporary, typically
can result in a major cost and schedule overrun. This is the dismantled after work is completed. Its components consist
area where sound design and competent construction of sheet piles and cross braces.
planning can achieve a meaningful reduction in risk and
cost. 3. CAISSONS
6. CONCLUSION
7. REFERENCES