1st Quarter Accomplishment Report (Jan.-March 2017)
1st Quarter Accomplishment Report (Jan.-March 2017)
DATE
Location No. of a. Started CONTRACT MODE OF
NAME OF PROJECT DISTRICT
Classroom COST IMPLEMENTATION
b. Completed
3 . Improvement of Mini Social Hall & Bugallon 2nd a. 12-12-16 P319,084.11 By Contract
Gueset E/S, Brgy. Gueset b. 01-11-17
4 . Const'n. of Additional 2 Span of Lingayen 2nd 192.76 sq.m. a. 12-16-16 P570,202.22 By Contract
Multi-Purpose Gym @ Libsong E/S b. 01-16-17
5 . Rehabilitation of Perimeter Fence Bugallon 2nd 192.76 sq.m. a. 12-12-16 P94,895.83 By Contract
@ Laguit E/S, Laguit Padilla b. 01-03-17
10 . Construction of Multi-Purpose Gym San Carlos 3rd 507 sq.m. a. 07-25-16 P2,469,391.62 By Contract
@ Central I E/S b. 01-13-17
12 . Construction of Covered Court Bautista 5th 507 sq.m. a. 12-16-16 P2,354,984.55 By Contract
(Gymnasium) @ Diaz E/S b. 01-18-16
85 c.d
85 c.d
85 c.d
85 c.d
85 c.d
85 c.d
85 c.d