Aeration Tank and Clarifier Design

The document provides design calculations for an aeration tank and secondary clarifier used in a sewage treatment plant, including oxygen requirements, air flow needs, sludge recycling rates, and sizing parameters for tanks, pumps, and other equipment based on design flow rate, BOD loading, and other operating conditions. Design criteria are referenced from standard texts like Metcalf & Eddy to support the calculations and ensure components meet typical design specifications. The system is designed to treat 175 cubic meters per day of sewage to meet discharge limits for BOD, TSS and other parameters over a retention time of 15 hours in the aeration tank and 4.29

Uploaded by

Rajesh Nare
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views

Aeration Tank and Clarifier Design

The document provides design calculations for an aeration tank and secondary clarifier used in a sewage treatment plant, including oxygen requirements, air flow needs, sludge recycling rates, and sizing parameters for tanks, pumps, and other equipment based on design flow rate, BOD loading, and other operating conditions. Design criteria are referenced from standard texts like Metcalf & Eddy to support the calculations and ensure components meet typical design specifications. The system is designed to treat 175 cubic meters per day of sewage to meet discharge limits for BOD, TSS and other parameters over a retention time of 15 hours in the aeration tank and 4.29

Uploaded by

Rajesh Nare
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

IV Aeration Tank (ETP-TK-213)

Flow 175
BOD 250
MLSS 4000
TSS 300
F/M ratio 0.1
Volume((Flow X BOD)/(MLSS X F/M)) 109.38
SWD 4.5
Area 24.31
Length 7.0
Width 3.5
Free Board 0.5
HRT 15

Oxygen Requirement calculation:


Flow:
Theoritical kg O2 required/kg of BOD:
Inlet BOD:
Hence BOD removed:
Total O2 required:
Oxygen required under Standard condition(SOR):
SOR =
Where T:
Csw:
C'sw:
C:
:
:
F:
Hence SOR:
Calculation of Air required at field condition

SWD of Aeration Tank: 4.5


HLL of Aeration Tank at avg flow: 4
Height of diffuser: 0.2
Effective Aeration Depth: 3.8
SOTE: 24.8
Fraction of O2 in Air: 23.18
Specific gravity of Air: 1.29
Hence Air required(SOR/((SOTE X 1761.8
Fraction
Hours of of Air)X( Specific gravity of
operation: 24
Air):
Air required: 73.41
No of Working Air blower: 1
Capacity of Air Blower: 73.41
Capacity of Air Blower provided: 75
No of Blower Provided: 2
Hence no of operating Blower: 1
No of standby provided: 1
Free Air Delivery 10
No of diffusers required 7.5
No of diffusers provided 8

Calculation of SRT based on excess sludge :


Excees sludge generated/kg of BOD: 0.3
Kg of Total Sludge/day with total TSS 96.25
load:
Hence excess sludge: 28.88
Sludge solid consistency at bottom of 1
clarifier:
Volume of Excess sludge(Qw): 2.89
Hence sludge concentration(XR): 10000
Volume Aeration tank: 109.38
MLSS concentration(X): 4000

V Secondary Clarifier Tank (ETP-TK-214)


Flow 175
Overflow Rate 14
Area 12.5
Diameter required 3.99
Diameter provided 4
SWD 2.5
Free Board 0.5
Total sludge=BOD Load + TSS Load 96.25
Solid Loading rate 7.7
Retention Time 4.29
Weir Loading 14
Feedwell Size 0.7

VIII Sludge Recirculation Pump (ETP-PA-207A/S)

Flow 175
Capacity (based on 100% recirculation required during startup) 7.3

Head 10
m3/day
mg/lt
mg/lt (Accoring to sewage manual it may vary from 30005000)
mg/lt
(Accoring to sewage manual it may vary from0.10.18.)
m3
m
m2
m
m
m
hrs(As per Sewage manual HRT 1224 hr, Hence OK)

175 m3/day
1.5
250 mg/l
250 mg/l
65.63 kg/day(AOR)

AOR/[(( C'swC)/Csw) X 1.024^(T20) X XF)


Field Temperature 25
Solubility of Oxygen at 20degC 9.17 mg/l
Solubility of O2 at field temperature: 9.08 mg/l
Design DO concentration 3 mg/l
Oxygen transfer correction factor 0.8 mg/l
Salinity surface tension correction factor 0.95
Diffuser fouling factor 0.9
130.65 kg/day 1 131.9491645017

m
m
m
m
%
%

Nm3/day
hr
Nm3/hr/basin

Nm3/hr
Nm3/hr
No.
No.
No.
N m3/hr
nos
nos

As per CPEEHO Sewage manual the range is 0.250.35


Kg/day
Kg/day

m3/day
mg/l
m3
mg/l

m3/day
m3/m2.day(Ranges 816, Refer page 687, Table 87, Matcalf Eddy)
m2
m
m
m
m
kg/day
kg/m2.day <120 Hence OK(Refer page 687, Table 87, Matcalf Eddy)
hrs
m3/m.day<185 Hence OK(Refer Sewage Manual)
m(15% to 20% of clarifier dia)

m3/day
m3/hr

m
Metcalf Eddy page 429

Refer Table D1 Appendix D


Metcalf
Refer Table D1 Appendix D
Eddy
0.4 topage:1745
Metcalf0.8 for diffused system and 0.6 to 1.2 for mechanical system
Eddy page:1745
0.7 to 0.98
0.65 to 0.9