400 KV Tender Docs PDF
400 KV Tender Docs PDF
FICHTNER
5413A08/FICHT-7273319-v4
Table of Contents
C - DRAWINGS
5413A08/FICHT-7273319-v4
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
Section VI
Employers Requirements
5413A08/FICHT-7273316-v1 1
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
C - ANNEXES
5413A08/FICHT-7273316-v1 2
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
Each individual Bid for each Lot, shall be submitted in same order as indicated herein
below and should comprise of the following:
Volume 1:
1. Letter of Bid in the format attached in Section A4, duly completed in the
manner and detail indicated therein and signed by the Bidder.
The time schedule must be accompanied by a detailed step by step work program
including milestones, describing how the contractor intends to perform the works. The
Bidder shall clearly show all major and important activities, number of staff involved,
expected progress.
11. Tentative testing program: Tests in the factory and on site, which are planned to be
performed.
In the factory:
5413A08/FICHT-7273316-v1 1
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
On site:
during plant installation and execution of civil engineering works
during test run
during technical inspection and trial operation
during commissioning
during operational acceptance
12. Price schedules (in the format attached) duly completed by the Bidder in the
manner and detail indicated therein and following the requirements of ITB
clause 12, 14.1 and 17.
For ease of evaluation and reporting purposes price sheets shall also be
submitted as editable EXCEL2003 or 2007 files. However, the ORIGINAL
hardcopy will always take precedence over the electronic version in case of
discrepancies.
Volume 2
13. Documentary evidence established in accordance with ITB 16.1 that the Plant and
Installation Services offered by the Bidder conform to the Bidding Document.
The documentary evidence of the conformity of the facilities to the bidding
documents may be in the form of literature, drawings and data, and shall furnish a
detailed description of the essential technical and performance characteristics of the
facilities.
16. Technical Schedules (fully completed schedules with all required data properly filled
in)
If bidders offer data of goods/services from a subcontractor/supplier, authorization
forms for these goods/services have to be submitted in an annex.
5413A08/FICHT-7273316-v1 2
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
Volume 3
The following forms shall be included in the bid in the format attached in Section IV:
Historical Contract non Performance (Form CON-2)
Financial Situation (Form FIN-3.1, FIN-3.2 & FIN-3.3)
The Bidder shall be fully responsible to get approval by the Employer for
any subcontractor to be involved in the Contract realization and that any
plant, equipment or services to be provided by the contractor comply with
the Bid documents, prior to conclusion of the Contract.
Note: Bidders can combine three volumes into one with the same sequential
order as in Volume 1, 2&3 described above.
5413A08/FICHT-7273316-v1 3
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
B0
Employers Requirements
General Technical Requirements
5413A08/FICHT-7269866-v5
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Table of Contents
5413A08/FICHT-7269866-v5 I
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
B0.5.1 General 57
B0.5.2 Specification stage 57
B0.5.3 Stages after contract award 58
B0.5.4 Design and manufacturing stage 66
B0.5.5 Erection stage 66
B0.5.6 Registration of drawings and lists 68
5413A08/FICHT-7269866-v5 II
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Any changes on the design of any part of the Plant, which may become
necessary after signing of the Contract, have to be submitted by the Contrac-
tor in writing to the Employer for approval, being sufficiently substantiated
and justified.
The Plant shall be brand new and designed, manufactured and arranged so
that it will have a functional design and a pleasant appearance.
Length Meter m
Mass Kilogram kg
Time Second s
Temperature Degree Celsius C
Temperature Difference Kelvin K
Electric Current Ampere A
Luminous Intensity Candela cd
Area Square meter m2
Volume Cubic meter m3
Liter l
5413A08/FICHT-7269866-v5 1
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Force Newton N
Pressure (absolute) Bar bar
Kilopascal kPa
Pressure below 1 bar Millibar mbar
Stress Newton per square millimeter N/mm2
Velocity Meter per second m/s
Rotational speed Revolutions per minute rpm
Flow Cubic meter per day m3/d
Cubic meter per hour m3/h
Kilogram per hour kg/h
Liter per second l/s
metric ton per hour t/h
For gaseous substance: standard Nm3/h
cubic meter per hour (referred to
0C and 1013 mbar)
Density Kilogram per cubic meter kg/m3
Kilogram per standard cubic Kg/Nm3
meter
Torque, moment of force Newton meter Nm
Moment of inertia (mr2) Kilogram square meter kgm2
Work, energy or heat Joule J
Heat capacity, entropy Joule per Kelvin J/K
Calorific value Joule per cubic meter J/m3
Joule per gram J/g
Power, radiant flux Watt W
Heat release rate Watt per square meter W/m2
Thermal conductivity Watt per meter Kelvin W/mK
Dynamic viscosity Newton second per square meter Ns/m2
Kinematic viscosity Meter squared per second m2/s
Surface tension Newton per meter N/m
Concentration Parts per million ppm
Electrical conductivity Microsiemens per meter at 25C S/m
Frequency Hertz Hz
Electric charge Coulomb C
Electric potential Volt V
Electric field strength Volt per meter V/m
Electric capacitance Farad F
Electric resistance Ohm
Conductance Siemens S
5413A08/FICHT-7269866-v5 2
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Materials
All materials shall be new and of the best quality suitable for working under
the conditions, variations in temperature and pressure encountered in service
without undue distortion or deterioration or the setting up of undue stresses
in any part, such as not to affect the efficiency and reliability of the plant.
Either all materials shall conform to the approved standards and the respec-
tive code number, or exact analysis data and full information concerning
properties, chemical and mechanical treatment shall be submitted.
Only materials which have been tried and tested in similar plants shall be
used. Steel castings shall not have any casting defects which could com-
promise the function of the component and affect the appearance. The
materials employed shall serve their purpose, according to the operation
conditions. The Contractor shall be responsible for selecting, working,
treating and quality assurance of the materials to suit the intended purpose.
It is not permissible to use gray cast iron for components containing pres-
sure, unless the Employer expressly agrees to this beforehand.
5413A08/FICHT-7269866-v5 3
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Contractor shall guarantee the values in the technical data schedule.
The Employer reserves the right to reject any equipment that does not
respect these values.
All materials and equipment supplied and all work carried out as well as
calculation sheets, drawings, quality and class of goods, methods of inspec-
tion, constructional peculiarities of equipment and parts and acceptance of
partial plants, as far as these are beyond the special requirements of partial
plants and as far as they are beyond the particular requirements of the
technical requirements shall comply in every respect with the technical
codes of the International Organization for Standardization (ISO). IEC
recommendations apply to the electrical equipment.
Goods and special guarantees beyond the scope of ISO and IEC, shall
conform at least to the following standards and codes in the following
priority:
The Bidder shall clearly state in his proposal concerning the standards and
codes, he intends to apply.
5413A08/FICHT-7269866-v5 4
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Contractor shall supply all labels, nameplates, instruction and warning
plates necessary for the identification and safe operation of the plant. Their
inscriptions shall be in the national language of the Employers country if
not otherwise mentioned.
All labels, nameplates, instruction and warning plates shall be securely fixed
to items of plant and equipment with stainless steel rivets, plated self
tapping screws or other approved means. The use of adhesives will not be
permitted.
Nameplates for plant and equipment identification and record purposes shall
be manufactured from stainless steel with a mat or satin finish, and engraved
with black lettering of a size which is legible from the working position.
Warning plates shall be manufactured from stainless steel engraved with
white lettering on a red background and sited in the position where they
afford maximum safety of personnel.
Before being packed for shipment to the site, all items of the equipment
shall be carefully numbered and marked so that they can be readily assem-
bled and erected in the correct relative positions at the site. Wherever
applicable, these numbers and markings shall be punched or painted so that
they shall be clearly visible.
5413A08/FICHT-7269866-v5 5
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Packing shall be done in convenient sections, so that the weight and size of
sections are suitable for transport to the site and for handling at the site
under the special conditions applicable there.
All individual pieces shall be marked with the plant identification number
and the correct designation shown on the Contractor's detailed drawings and
on other documents like packing lists, spare parts lists, operation and
maintenance instructions, etc.
Marking shall be done identically on labels and by stamping the marks into
the metal before painting, galvanizing, etc., and shall be clearly readable
after painting, galvanizing, etc.
All parts of the plant shall be packed at the place of manufacture. The
packing shall be suitable for shipment by sea and for all special require-
ments of the transportation to the site. Where necessary, double packing
shall be used in order to prevent damage and corrosion during transporta-
tion, unloading, reloading and during intermediate storage.
Small items shall be packed in boxes and large items shall be protected,
where necessary, by timber, straw and sacking.
All parts shall be suitably protected against corrosion, water, sand, heat, any
adverse atmospheric conditions, shocks, impact, vibrations, etc. for later
transport and storage.
Tube ends and other similar open ends shall be protected against external
damage and ingress of dirt and moisture during transit and while awaiting
erection at site. Flanged pipes shall have their open ends protected by
adhesive tape or jointing and then be covered with a wooden blind flange.
Screws and not nails shall fix the lids and internal cross battens of all
packing cases.
The contents of the cases shall be bolted securely to the case or fastened in
position with struts or cross battens, and not wedged in place with wooden
shocks, unless these are fastened firmly in place. All struts or cross battens
are preferably to be supported by cleats fixed to the case above and below to
form ledges on which the batten may rest. Cases shall be up-ended after
packing to prove that there is no movement of contents.
Where parts are required to be bolted to the sides of the case, large washers
shall be strengthened by means of a pad. Wood-shavings shall be avoided as
far as possible for packing purposes.
Tower members shall be packed for shipment in bundles of the same size
and weight containing pieces of the same or similar identifications mark and
length.
5413A08/FICHT-7269866-v5 6
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The individual members may be stacked to bundles and plastic spacers shall
be placed in between the individual members, reducing the formation of wet
storage stains. All bolts, nuts, washers, step bolts and minor fittings shall be
shipped in wooden cases of suitable size and weight, with pieces properly
separated according to size and type.
Spare parts shall be packed for long duration storage. Individual steel
members stacked in bundles as spare parts shall be spaced by plastic spac-
ers. Wooden drums will not be accepted for the spare conductors, ground
wires and OPGW.
All cases, packages, etc. shall be clearly marked on the outside to indicate
the total weight, the position of the center of gravity and the correct position
of the slings and shall bear an identification mark relating them to the
appropriate shipping documents.
All packing shall be included in the scope of delivery and the cost be
included in the prices. The packing materials remain the property of the
Employer.
5413A08/FICHT-7269866-v5 7
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Purchaser may require to inspect and approve the packing before the
items are dispatched but the Contractor is to be entirely responsible for
ensuring that the packing is suitable for transit and such inspection shall not
exonerate the Contractor form any loss or damage due to faulty packing.
Prior to shipment the Contractor shall furnish by air mail, telefax, telex or
otherwise, as agreed the shipping documents to the Employer. Details will
be fixed during the Kick-Off Meeting.
All cases and boxes shall be clearly and boldly marked and shall be sent to
the Employer as per address details instructed by the Employer. When the
actual transport has been completed, the Employer shall be notified accord-
ingly.
The attempt to repair shall not bind the Employer to accept the repaired part
when this is re-offered for inspection.
5413A08/FICHT-7269866-v5 8
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
All equipment performing similar functions shall be of the same type and
manufacture, to limit the stock of spare parts required and maintain uni-
formity of plant and equipment to be installed.
B0.1.7 Signs
Safety colors, safety symbols and safety signs must comply in construction,
geometrical form, color and meaning with the ISO 7010 and ISO 3864
Signs for plant identification during the erection period shall be to Employ-
er's approval.
5413A08/FICHT-7269866-v5 9
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Warning signs
Warning signs should refer to the existence or possible existence of danger,
e.g., general danger, high voltage and climbing prohibited.
In the event of the surfaces not being cleaned to the Employers satisfaction,
such parts of the cleaning procedures or agreed alternatives as are deemed
necessary to overcome the deficiencies shall be carried out at the Contrac-
tors sole expense.
Machined surfaces shall be protected during the cleaning operations. For re-
cleaning small areas, hand cleaning by wire brushing may be permitted.
Wire brushes used on austenitic materials shall have austenitic steel bristles.
Austenitic stainless steels, copper and aluminum alloys, cast iron, bimetallic
and metallic/plastic items, and components fabricated by spot welding or
riveting shall not be chemically cleaned. All weld areas shall be suitably
stress-relieved before chemical cleaning.
Besides this, the Contractor shall take over all responsibility for the treat-
ment and disposal of wastes according to the local law and to the satisfac-
tion of the Employer.
The Contractor shall take all necessary precautions to ensure that the
internal surfaces of all plant are kept clean and free from injurious matter
during erection.
5413A08/FICHT-7269866-v5 10
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
B0.2.1 General
Under steel structures are to be understood all overhead line towers with
their body and leg extensions, additional crossarms if required, the founda-
tion stubs, and stub setting templates.
Under assembly material are to be understood all bolts, screws, rivets, nuts,
washers, locking devices which are necessary for the assembly of the steel
structures and their accessories as well as, for the assembling and mounting
of the line equipment like insulator sets, conductor and earthwire / OPGW
accessories.
The material to be used for the structures is high tensile and mild steel
sections and plates, according to internationally recognized standards (ISO
630, DIN 17100 or equivalent).
All structural steel shall be protected against corrosion by hot dip galvaniz-
ing.
5413A08/FICHT-7269866-v5 11
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
All bolts and screwed rods shall be galvanized including the threaded
portions. All nuts shall be galvanized with the exception of the threads,
which shall be oiled.
Where for any type of tower high tensile steel bolts are employed then bolts
of this type shall be used for all connections for every type of tower on that
line in order to avoid the use of mild steel bolts in error where high tensile
type should be employed. High tensile steel bolts shall bear a mark on the
head to allow identification of grades.
The nuts of all bolts attaching insulator set droppers, U bolts and earth
conductor clamps to the towers shall be locked in an approved manner.
All washers shall be included under this contract, including locking devices
and anti-vibration arrangements, which shall be subject to the approval of
the Employer / Employers Representative. Taper washers shall be fitted
where necessary.
Nuts when finger tight or snug tight (about one-fourth turn from tight) on
the bolt may be rejected if they are, in the opinion of the Employer / Em-
ployers Representative, considered to have an excessively loose or tight fit.
Bolts with threads re-died after galvanizing will be rejected. Nuts and bolts
of the same type shall be interchangeable and supplied from the same
manufacturer.
5413A08/FICHT-7269866-v5 12
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Steady-state loads
Steady state loads or dead loads are those loads imposed on a structure
for a long or continuous time period.
Transient loads
Transient loads or live loads are those loads imposed on a structure for a
short time duration or temporary time period.
Construction loads
Construction loads or erection loads are those loads imposed on a struc-
ture during erection or maintenance period.
The following design loads shall be considered for the foundation structure:
Dead load
Dead load is defined as the weight of all permanent foundation construc-
tion and super structure as well as overburden soils vertical above of the
foundation base.
Soil load
Horizontal soil load consists of lateral active and passive earth pressure
which by pile foundation for example may be considered for lateral bed-
ding.
Hydrostatic load
Hydrostatic load is the force acting on structures due to water pressure.
The design of foundations shall include the buoyancy load due ground
water which is equal to the weight of the volume of displaced water.
5413A08/FICHT-7269866-v5 13
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Highest water level under max. uplift load and lowest water level for
compression load are to be considered as dead load.
Wind load
The wind load shall be considered as live load superimposed to the dead
load with regard to conductor tension, member shape and structure height
of tower.
Earthquake load
The earthquake load shall be considered as live load superimposed to the
dead load and some wind load with regard to super structure elasticity
and possible soil liquefaction.
Erection load
Erection/maintenance load is defined as live load superimposed to the
dead load of structure but not permanently attached to it, i.e. loads im-
posed by lifting/temporary anchoring of pre-assembled structure parts,
erection equipment places/anchored temporary on structure parts; per-
sonnel standing on structure members.
Thermal load
Thermal loads shall be defined as forces caused by changes in material
temperature due to the expansion or contraction of the entire structure or
individual structural/plant components, e.g. increase of conductor tension
or differential line tension.
Impact load
Any live load that can produce dynamic action (such as a moving load or
a short circuit impulse) shall be described by static models in which the
dynamic effects are included, e.g. increase by an impact factor.
Exceptional load
Exceptional load is defined as live load superimposed to the dead load of
structure but nor permanently acting, i.e. loads imposed during stringing
operation or by broken wire condition or tower failure.
B0.3.3 General requirements for the design and execution of all civil
works
1.) The design of all structures under this contract shall be such that
differential and total settlements or other movements shall not ex-
ceed acceptable limits and full provision shall be made for all expan-
sion and other joints. The design shall be to the approval of the
Employer/Employer's Representative.
3.) Concerning the annex drawings which form part of these technical
requirements they are to be considered minimum requirements in
size and standard.
5413A08/FICHT-7269866-v5 14
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
4.) The clearance from the conductor to ground and tower structure shall
be such as to provide adequate space for the safe installation and
proper operation, maintenance and repair of all plant and equipment
of the transmission system.
5.) All materials used in the works shall be of the best quality of their
respective kinds as specified herein, obtained from sources and sup-
pliers approved by the Employer / Employers Representative.
7.) The work shall be carried out by competent personnel skilled in their
various trades.
8.) Before commencing the works the Contractor shall ascertain the
locations and nature of all existing overhead lines and underground
services within the right of way corridor and shall take every possi-
ble precaution against any damage occurring to them or interference
therewith, during the execution of the works.
10.) Access pists, bush clearing and site leveling is the responsibility of
the Contractor. Access roads which remain for maintenance shall be
in good condition when handing over to the Employer.
11.) Before staring of design works, the Contractor shall submit to the
Employer/Employers Representative for approval the proposed pro-
ject design procedure containing the design data, standards and rules
and the design criteria intended to be used for the civil works.
B0.3.4.1 General
The extent of the investigations shall be such as to permit the satisfactory
determination of all necessary subsoil characteristics, to exclude any
unacceptable settlement and to determine reliable type, size and execution
of foundations. These investigations have to be completed before the works
start.
5413A08/FICHT-7269866-v5 15
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The soil report containing the description of the soil conditions and the
foundation engineering proposals is to be prepared by an expert and is to be
signed by him. The expert shall supervise the boring works as well as the
laboratory tests.
The report should include but not be limited to the following information:
Note: Estimation of the possible max. ground water level shall be made
when the subsoil investigation is undertaken not at the end of wet season.
Chemical analysis
The groundwater and subsoil shall be chemically analyzed and classified
with regard to its aggressive action against concrete.
Earthing system
The report shall contain sufficient information regarding the conductivity of
the soils necessary for the design of earthing systems.
Conclusions
The investigation shall give accurate data about the level of the bearing
layers and the depth of the groundwater table.
5413A08/FICHT-7269866-v5 16
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The work includes furnishing all labor, materials and equipment, and
performing all work required for the survey at site, in accordance with the
conditions at site and in accordance of the Particular Technical Require-
ments of the Contract Documents.
The Contractor shall carry out all the necessary surveying works in order to:
The existing benchmarks (if available), related to the national network, shall
be used as basis for the surveying works.
For the final report, the Contractor shall also provide all the survey data in a
digital format so as to permit reprocessing of any desired part or aspect of
the survey.
5413A08/FICHT-7269866-v5 17
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
After the completion of the work, the temporary service roads which will
not be required for maintenance later on, buildings and relevant facilities
built by the Contractor, shall be removed.
All of the Contractor's facilities shall be provided with the services neces-
sary for their operation, such as electrical energy, potable water supply,
sewers, drainage system, fire extinguishing system, etc. The Contractor shall
install an independent communication system to his, to the Employer's/
Employer's Representatives offices.
The temporary site office buildings for the Employer/ Employer's Repre-
sentative shall be structurally sound and compatible with the weather
conditions on the site including the following rooms:
The Contractor has to submit for approval to the Employer all drawings and
details for the buildings, services, equipment intended to be used before
starting with the execution works on the site.
If necessary, during the execution works, the Contractor can make modifica-
tions of site installation works, but without any claims for extension of the
contractual execution time and additional costs.
5413A08/FICHT-7269866-v5 18
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
B0.3.7 Earthworks
B0.3.7.1 General
This section applies to all earth and rockwork required for the construction
of buildings, structures, foundations and burying service lines in the ground.
The Contractor shall satisfy himself as to the ground conditions on the site
including the nature of the strata to be excavated, obstructions, possibilities
of flooding and shall allow for all provisions necessary to carry out the work
in the most suitable manner when submitting his Bid.
Select fill
Select fill shall have the following properties:
well graded, non-cohesive and nearly silt-free, salt free, soils free of or-
ganic matter.
The material shall be of such nature and character that it can be compact-
ed to the specified densities. It shall be free of plastic clays, of all materi-
als subject to decay, decomposition or dissolution or other materials
which will corrode piping or other metal.
The intention is to use select fill below structures on foundation backfill and
access pists used for maintenance if original soil is deemed to be not suita-
ble.
Ordinary fill
Ordinary fill shall have the following properties:
Natural inorganic soils: salt content not greater than 5%, organic matter
less than 3%.
5413A08/FICHT-7269866-v5 19
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The intention is to use ordinary fill for non-built areas and for backfill of
tower foundations
Special fill
Special fill material shall be gravel or crushed rock.
The intention is to use special fill e.g. as sub-base material where required.
The Contractor shall carry out earth- and rockwork for the following works
as defined hereafter:
Safety precaution
The Contractor shall be responsible for all necessary safety measures.
Over excavation
If somewhere, and for any reason, excavation are executed beyond the
established lines and without the Employer / Employers Representative 's
previous approval, the Contractor shall at his own expenses backfill with
approved material (including required compaction) or with lean concrete to
Employer / Employers Representative s approval, the volume correspond-
ing to over-excavation. He shall not receive payment for over-excavation
not ordered.
5413A08/FICHT-7269866-v5 20
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Preparation of foundations
All surfaces on which or against which concrete is to be poured shall be
carefully cleaned and roughened to the Employer / Employers Representa-
tive 's satisfaction.
The rock surface shall be free of oil, stagnant or running water, mud, loose
rock, residue and impurities or any other improper material. Immediately
before concrete placing, all rock surfaces shall be thoroughly cleaned.
All earth surfaces against which concrete is to be poured, shall be clean and
free of any detrimental impurities, organic matter or unsuitable material.
Immediately after excavation, all such surfaces shall be moistened and
treated as directed by the Employer / Employers Representative. Surface
protection by means of a lean concrete layer, 5 cm thickness or plastic
sheets might be required in circumstances where larger areas in the vicinity
of the excavation is sensitive to water infiltration causing destabilization of
the adjacent terrain.
B0.3.7.4 Backfilling
Foundations and structures shall be back-filled as shown on the drawings
with approved material compacted in layers by suitable equipment until
optimum stability has been obtained to the satisfaction of the Employer /
Employers Representative. Compacting shall be carried out with special
care by means of pneumatic or mechanical rollers or other compactors of a
type previously approved by the Employer / Employers Representative.
The fill material shall be compacted by vibratory roller (min. weight 20t).
The minimum required degree of compaction shall be as defined under item
"Tests and Properties" here in below.
The Contractor shall prepare sheets for statistical analysis of the field and
laboratory tests, and shall submit the sheets to the Employer / Employers
Representative for approval. Controlling will consist of field and laboratory
tests, such as compaction and density tests, grain-size distribution, and shear
tests.
If not otherwise specified under relevant items the following min. tests have
to be carried out.
one (1) test analyzing the ingredients of the water used for performance
of the work
three (3) tests for specific gravity of soil
one (1) test for bearing capacity of soil for static load
three (3) tests for grain size analysis of soils, if "Replacement of Materi-
al" is required
three (3) tests for density of soil in place of sand-cone method for each
second layer of "Backfilling and/or replacement of material and/or road-
work"
Tests shall be performed for each 500m3 of fill and / or every 5th tower site.
5413A08/FICHT-7269866-v5 22
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
B0.3.8.1 General
This clause describes all foundation works which are to be performed so as
to ensure the bearing of all loads without detriment for and damage to the
structures. The Contractor has to choose up-to-date methods and equipment
to ensure this in accordance with relevant internationally recognized stand-
ards.
5413A08/FICHT-7269866-v5 23
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
sedimentary igneous
excavation requires chiseling or drilling and blasting
Class 1 cemented metamorphic very strong, tough,
hand held specimen can be broken by geological hammer
Hard Rock sandstone granite sound, durable
can be scratched by knife or steel nail
siltstone andesite
claystone basalt
breccia gneiss excavation can be done by pick axes
Class 2 medium tough, weak,
etc. etc. sample edge crumbles by heavy hand pressure or breaks
Soft Rock fissured, friable
can be scratched by thumbnail
Soil
Cohesive Soil Granular Soil
Type
35% Fines 65% Coarse State of Consistency / Density Field Test / Hand Probe of Soil
Soil
Comp. 0.06 mm Comp. 200 mm
Class
can be excavated by hand using spade
wooden peg 5x5 cm hard to drive by sledge hammer
silt cobbles hard, compact, steel bar 2 cm cannot be penetrated manually
Class 3 clay gravel cannot be indented by thumbnail
very dense, medium dense,
Good Soil peat sand very stiff, semi solid
sandy silt gravelly sand
clayey silt silty gravel
gravelly clay clayey gravel
can be excavated by hand using shovel
sandy clay clayey sand
firm, stiff, wooden peg 5x5 cm easily to drive by sledge hammer
Class 4 (5) silty clay silty sand
loose, very loose, steel bar 2cm can be penetrated manually with effort
Poor Soil etc. etc.
medium firm, soft can be molded by hand, readily indented by thumb
Field identification of cohesive and granular soil components by settlement test in a scaled jar with water, ie. sand settles out in approx. 1 min., silt 5 min. and clay 10 min. Differentiation of relative
quantities of dry samples by volume % estimation diagrams as particles of 0.06 mm are just visible to the naked eye. Depending on the state of consistency, density and hardness the corresponding
soil (rock) class can be determined as outlined in above table. Soil classes and its allocated index / engineering properties are defined in the Particular Technical Requirements under the Chapter Soil
Classification.
5413A08/FICHT-7269866-v5 24
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
If there is any doubt about the actual in-situ soil properties or if discrepan-
cies appear with regard to the previous decisions or investigations as stated
by the Employer / Employers Representative, then additional verification
measures shall be undertaken to ascertain that the actual soil parameters are
in compliance with the foundation design assumption after consulting the
Employer / Employers Representative.
Pile driving
Pile driving operation must be supervised by an experienced civil engineer
of 10 years practice. If the agreed pile criterion cannot be fulfilled according
to the preliminary approved pile length, then the Contractor has to initiate,
e.g. by site note, the necessary pile extension and/or increase the pile
quantity per tower footing as to match the actual soil class.
Dewatering
During the foundation works the excavated areas, foundation levels and pits
shall be kept free of water down to at least 0.5 to 1 m below the foundation
level.
Waterproofing
The necessary measures shall be taken to protect the structure against water
action
Pitwall stability
The excavated pit sides, walls or slopes have to be stable and comply with
safety regulations.
5413A08/FICHT-7269866-v5 25
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
B0.3.9.1 General
In general the concrete works shall be based on EUROCODE 1, 2 and 4, the
provisions of the EN DIN standards or equivalent and the local rules,
standards and regulations.
All materials shall be stored and handled in a manner that will prevent
contamination and/or deterioration. Deteriorated and/or contaminated
material shall not be used for the concrete and shall be removed from the
site at the expense of the Contractor.
Cement
The cement used for concrete, reinforced concrete, mortar, grout and plaster
works shall be a moderate sulfate resisting Portland Cement in accordance
with DIN 1164 or EN 197 or equivalent.
Cement which has been manufactured for longer than 6 months on the
proposed date of delivery to the site shall be inspected, sampled and tested
for approval purposes before delivery to the site.
5413A08/FICHT-7269866-v5 26
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Water
Water for preparing concrete and mortar shall be clean, fresh and free from
organic and/or inorganic matter in solution or suspension in such amounts
that may impair the strength or durability of the concrete. Water may be
obtained from local sources, after comprehensive testing and analysis of
samples. No seawater or water from excavations shall be used. Water shall
be stored in clean containers.
Aggregates
Materials used as aggregate shall be obtained from a source known to
produce aggregate satisfactory for concrete and shall be chemically inert,
strong, hard, durable, of limited porosity and free from adhering coats, clay
lumps, organic impurities that may impair the strength or durability of the
concrete. Aggregate may comply with and be tested in accordance with the
requirements of standards.
Concrete additives
Concrete additives approved by the Employer / Employers Representative
shall be used to improve consistency, workability, quality and strength of the
concrete. Unless otherwise agreed, an additive may comply with an approved
standard.
Plasticisers and air entrainers are intended to reduce bleeding of free water
at the surface. It shall only be used after the written approval of the Employ-
er / Employers Representative and in accordance with the manufacturer's
instructions.
5413A08/FICHT-7269866-v5 27
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Concrete Classification
Classes of Concrete:
C8/10 Plain concrete used for lean concrete, blinding, screeds, backfill
etc.
C16/20 Reinforced concrete for foundations, retaining walls
C30/37 Reinforced concrete for piles
Trial mixes
Before concreting commences, the Contractor shall, at his own expense,
make trial mixes to determine the mix proportions required to produce the
strengths specified for each class of concrete and for each degree of worka-
bility required to allow placing, transporting and compacting of the concrete
with the equipment he proposes to use in any particular situation. Only
materials which the Contractor intends to use for concreting (including all
admixtures) shall be used in the trial mixes.
Test cubes from trial mixes shall be made and tested in accordance with
approved standards.
Consistency of concrete
The amount of water used in the concrete shall be adjusted as required but
not exceeding the specified w/c ratio to ensure such a consistency that it can
be readily transported placed and compacted without segregation of the
materials or bleeding of free water at the surface. Addition of water to
compensate for stiffening of the concrete before placing shall not be permit-
ted. Consistency of the concrete shall be checked by slump tests.
Mixing of concrete
A weight batching would be desirable but an accurate volume batching
(+/- 3%) of aggregates and cement might be acceptable rather for the lower
concrete classes of C16/20 and C8/10 maintaining the specified concrete
strength of the foundation structure. The actual mixing time shall be in the
range of 1 minute by an efficient mixer with rotating drum and fixed arms.
5413A08/FICHT-7269866-v5 28
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The water shall not be added until all the aggregate and cement are in the
drum. Mixing shall continue until the concrete is uniform in color and for
not less than 1 (one) minute after all the materials and water are in the drum.
Partly set or excessively wet concrete shall not be used. No concrete shall be
mixed by hand.
Freshly filled test moulds shall remain on site for 1 to 2 days protected from
sun radiation and rain. For the remaining 26 to 27 days till crushing, they
shall be stored fully submerged in water or in a room having a constant rel.
humidity of > 95%.
If the results are less than those specified above respective in the standards,
the Employer / Employers Representative must suspend the concerned
concrete works respective backfill operation and order further in-situ tests,
for example core drilling. Any concrete found not to comply with the
General Technical Requirements/Particular Technical Requirements shall be
broken out and replaced or adequately reinforced to the satisfaction of the
Employer / Employers Representative.
5413A08/FICHT-7269866-v5 29
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Contractor shall pay all costs incurred in making, curing, delivering and
testing of concrete cubes/cylinders and core drilling.
Placing of concrete
Concrete shall be placed in the forms as close as possible to its final position
in a single operation to the full thickness of slabs and shafts/chimneys and
shall be placed in horizontal layers, not exceeding 2.5 m height in a single
pour of vertical shafts and chimneys with formworks and not exceeding 5 m
when concreted direct to soil.
The Contractor shall organize the pouring of concrete in such a manner that
once concreting of a section has started the operation shall be continuous
and each operation shall be completed prior to a stoppage.
5413A08/FICHT-7269866-v5 30
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Concrete shall not be dropped into place from a height exceeding 2 meters.
Trunking and chutes to Employer / Employers Representatives approval
shall be used for any concrete to be deposited from a height exceeding 2 m.
The Contractor shall ensure that the vibrators are used in such a manner that
the reinforcement is not displaced, the formwork not damaged and no
segregation caused, but complete compaction of the concrete is achieved.
Finish of concrete
The concrete face shall have the finishes indicated on the drawings or as
shown in the present General Technical Requirements/Particular Technical
Requirements. The foundation top shall be monolithically casted that the
finished surface of the concrete will be sound, solid and free from honey-
combing, protuberances, air holes or exposed aggregate. No plastering,
cement wash, mortar or paint shall be applied to cover defective concrete
surfaces.
5413A08/FICHT-7269866-v5 31
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Particular care should be taken in the placing of the new concrete close to
the joint. This concrete should be particularly well compacted and if possi-
ble a vibrator should be used.
A record shall be kept on site of the time and date of placing the concrete in
each section of the work.
Joints shall be straight and vertical, except where other specified, and
concrete surfaces on both sides of the joint shall be flush. Where necessary,
water stops of a type approved by the Employer / Employers Representa-
tive shall be embedded in the concrete. The water-stop should be made of
high-quality material which must obtain its resilience through the service
live of the structure for the double function of movement and sealing. To
ensure a good tightness with or without movement of the joints the water-
stop should be provided with anchor parts. The complete works of fixed and
welded connections must be carried out strictly in accordance with the
manufacturer's instructions.
The temperature of the mixed concrete shall not exceed 30 C. The Contrac-
tor shall take special measures in the mixing, placing and curing of concrete.
These measures shall include the shading of aggregates, spraying of aggre-
gates with water, cooling of the mix constituents (introduction of ice to the
mixing water) and reduction of transportation time to the minimum. During
placing suitable measures shall be provided to prevent premature setting of
concrete placed in contact with hot surfaces. All concreting areas, formwork
and reinforcement shall be shielded from the direct rays of the sun and
sprayed with water when necessary.
5413A08/FICHT-7269866-v5 32
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Immediately after the compaction of the concrete has been finished, the
Contractor shall ensure adequate protection from the weather. The concrete
surface shall be covered with a layer of sacking, canvas, straw mats or
similar absorbent material, special protection sprays kept constantly moist
for at least 7 days.
No load of any kind shall be allowed on concrete which has not properly set
and the Contractor shall prevent any load to be imposed on the concrete
structures until it has been declared by the Employer / Employers Repre-
sentative to be ready to carry loads.
Making good areas > 1m of extend and / or affected depth > 10% of the
concerned structure thickness shall not more be patched by cement mortar
and are subject to special repair procedure (epoxy based mortar) or structure
reinforcement or partial reconstruction procedure. Cracks wider then 0.3
mm and/or deeper then 10 mm as well as air holes, surface offset or ex-
posed/segregated gravel pockets deeper than 1 cm will also be subject to
repair procedures.
5413A08/FICHT-7269866-v5 33
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Reinforcement supports
Reinforcement supports shall include all spacers, chairs, ties, slab bolster,
clips, chair bars, and other devices for properly assembling, placing, spac-
ing; supporting, and fastening the reinforcing bars.
Spacers may be cast from concrete, but shall be of the same quality as that
in which they will be embedded.
Certificates
Each consignment of steel reinforcement shall be accompanied by a test
certificate from the manufacturer showing that the steel has been tested and
analyzed and the date of such tests and analyses and that such tests and
analyses comply in all respects with the standards.
Test
Reinforcing steel shall be tested as per EN 10080 in presence of the Em-
ployer/ Employers Representative. The costs for these tests are deemed to
be included in the contract price.
Rejection
The Employer / Employers Representative will reject any reinforcement
steel as the result of any failed test therefore not withstanding the manufac-
turer's certificates.
Reinforcing bars having excessive corrosion, mill-scale deposits and out of
diameter tolerance are also subject to rejection of the batch. Flash rust
however might be acceptable to a degree were no impairment of the bond-
ing property between steel surface and cement line may occur.
C: clear cover means the specified distance between the outer most steel
bar part (not center of stirup diameter) and the formwork or ground at
90 to the plane.
5413A08/FICHT-7269866-v5 34
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The top or final surface of all concrete works shall be finished monolithical-
ly and sloped by screeding, or floating, or troweling or grinding, or tooling
as approved by the Employer / Employers Representative.
Dry cement or cement and sand shall not be used to dry excess water on the
concrete surface.
Floating: shall follow screeding, but shall not be started until some stiffen-
ing of the concrete has taken place.
Grinding and tooling: Where specified, the methods to produce the desired
surface shall be approved by the Employer / Employers Representative.
The grinding and/or tooling shall not start until the concrete has hardened
sufficiently to prevent dislodgment of the aggregate.
Chiseling: Wherever possible all chiseling works shall be carried out with
mechanical devices.
5413A08/FICHT-7269866-v5 35
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
B0.3.9.15 Formwork
Design and construction
For stability and type of formwork and support framing used, DIN 4420 or
equivalent are to be observed.
The fair faced concrete facades have to be to the satisfaction of the Employ-
er / Employers Representative. The concrete surface for facades has to be
absolutely stainless and all efforts have to be taken to achieve this.
5413A08/FICHT-7269866-v5 36
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Striking of formwork
Formwork shall not be removed until the concrete has sufficient strength to
carry its own weight plus any constructional or designed loads likely to be
applied with a normal factor of safety. It shall be removed in such a manner
that no shock or injury shall result to the concrete.
Before removal of the formwork the concrete shall be examined and remov-
al shall proceed only on the instructions and under the supervision of a
competent person.
Material
The material to be used for erosion protection comprises the following:
clay bricks
solid or hollow concrete blocks
natural stones of granite, basalt or lime stone
any other type of blocks and stone artificially produced
binding agents
metal accessories
stone gabions
reinforced concrete walls
Execution
Masonry work, arranging and bedding stones, etc. shall be executed in
mortar to form a homogeneous mass and to bond them in such a manner that
point or other loads and stresses are dispersed and distributed through the
mass without the structure tending to disintegrate.
Block work partitions less than 200 mm in thickness shall be solid block
and strengthen around all openings by reinforced concrete frame of
200 mm width (as a minimum) and in the same thickness of the wall
5413A08/FICHT-7269866-v5 37
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Brickwork and/or block/stone work which has not been thoroughly wetted
can be detected by a thin crack between the brick/block/board and the
mortar joint. Such work shall be pulled down and rebuilt. All masonry work
shall be suspended during extreme weather unless adequately protected.
Block work under the ground slab, retaining walls and around foundations
shall be min. 200 mm thick.
Auxiliary work
Unless specified otherwise, all and any kind of work, materials, services,
safety measures, etc. as well as all tests and samples required for the com-
pletion of the work shall be included in the offer. Among others they also
have to include the following services:
a) two compressive test of soil block for load bearing walls per 200 m2
of bearing block walls
b) three compressive tests of each type of material as mentioned above
c) three compressive tests of each kind of mortar to be used
Quality assurance
Blocks and stones shall be hard, of selected quality, reasonable in size and
shape. The strength of the blocks and stones shall be according to the static
requirements, but not less than:
Mortar
Mortar for blockwork shall be cement mortar in the proportions 1:3 to 1:4
(Portland cement to sand). All mortar shall be mixed in a power-driven
mixer and in addition, all materials shall be screened before mixing to
remove lumps. Mortar whether with or without plasticiser shall be mixed
only in sufficient quantity for the work immediately in hand and no partly
set mortar shall be used.
Reinforcement
Horizontal reinforcement to brick or blockwork is called for. It shall be in
high tensile galvanized steel mesh 6 cm wide for 10 cm walls and 12 cm
wide for 20 cm walls. The reinforcement shall be laid in as long lengths as
practicable without laps. But where joints are necessary, the lengths shall be
lapped not less than 30 cm, except at corners or junctions where the lap shall
be equal to the width of the reinforcement and the reinforcement in one wall
bent over that in the other. Application: every second layer.
B0.4.1 General
B0.4.1.1 Introduction
This section contains general requirements for inspections and tests of
material, parts, equipment and workmanship of the plant during manufac-
ture, assembling and erection and upon completion to demonstrate compli-
ance with General Technical Requirements/Particular Technical
Requirements, codes and standards to ensure overall reliability of plant
operation and performance.
5413A08/FICHT-7269866-v5 39
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Quality assurance
The Contractor shall provide and operate a quality assurance system both in
his facilities and the facilities of his sub-Contractors and at site capable of
producing objective evidence that the material and equipment meet the
quality requirements of the technical requirements. The system shall be in
accordance with ISO 9001.
The Contractor shall include an outline inspection plan in his Bid. Before
delivery a detailed inspection plan shall be submitted to the Employ-
er/Employers Representative for approval. It shall describe the facilities
and site inspection for each major component and for the finally assembled
equipment and shall include the following:
a schedule or flow chart indicating each inspection and the stages in the
manufacturing and erection process where the Contractor proposes
inspection shall be carried out
a short written description of the method for each inspection
standards of acceptance, with references to International Standards or
Codes where applicable. Where the Contractor's acceptance standards are
proposed, copies of such standards shall be provided.
5413A08/FICHT-7269866-v5 40
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Contractor has primary responsibility for ensuring the quality of items
of equipment supplied under the Contract and remains accountable when
manufacture or erection is subcontracted. It is therefore a requirement of the
technical requirements that works are only subcontracted to companies with
effective Quality Assurance (QA) organization and that the Contractor
monitors the quality control by the attendance at tests of experienced
inspectors employed by the Contractor.
Adequate notice shall be given when the equipment is ready for inspection
or test and every facility shall be provided by the Contractor and his sub-
contractors to enable the Employer/Employers Representative to carry out
the necessary inspection of the plant.
A detailed record of the results of all tests and inspection shall be main-
tained by the Contractor and copies provided to the Employer/Employers
Representative within a reasonable time after the tests.
The Contractor shall submit test programs for factory and site testing that is
subject to approval by the Employer/Employers Representative. Test
methods shall be based on IEC recommendations and standards. The Bidder
shall state the applied standards and test methods. A tentative test program
and a test procedure shall be supplied before each individual test. The test
procedure shall specify in detail the tests to be performed, based on the
specified requirements. Detailed documentation (e.g. circuit diagrams, flow
charts) of the tested system/equipment shall also be available to the Em-
ployer / Employers Representative at the same time. Formats of the test
report which are intended to be used shall be submitted for approval togeth-
er with test program.
5413A08/FICHT-7269866-v5 41
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Within thirty (30) calendar days of completion of each and every test copies
of all test records, test certificates and performance curves shall be supplied
for all tests carried out in accordance with the provision of the contract,
whether or not the Employer / Employers Representative has witnessed
them. Information given on such test certificates and curves shall be suffi-
cient to identify the equipment and software to which the certificates refer
and shall also bear the Contractors reference and heading.
The test reports shall indicate the tests performed, contract references, the
results obtained, instruments used, names of test personnel, and provide for
witnesses' signatures. They shall also be numbered and dated.
The type and extent of inspection shall generally be in accordance with that
specified in the standard used for design and construction of the item of
equipment supplemented or amended by the requirements of this section of
the technical requirements.
Additional design tests are also to be carried out as described in the other
parts of this technical requirements.
5413A08/FICHT-7269866-v5 42
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
In all instances, the finally accepted applicable code or standard shall be the
version last published prior to the date of submission of the Bid selected as
the basis for this Contract.
The Contractor on request shall supply the Employer with a copy of draw-
ings and procedures at the time of the test.
All instruments and apparatus required for the inspection or used for the
performance of tests shall be calibrated to an agreed standard at a laboratory
of national standing. The cost of making such calibrations shall be borne by
the Contractor in all cases.
5413A08/FICHT-7269866-v5 43
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
All parts shall be properly match marked, identified and doweled to ensure
and, where practicable, to facilitate correct and quick field assembly.
If the corrections cannot be carried out in accordance with the terms men-
tioned above, the components concerned would be rejected. The decision on
possible subsequent corrections is reserved exclusively to the Employer /
Employers Representative. Faulted equipment parts shall not be delivered.
5413A08/FICHT-7269866-v5 44
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
All welders employed on items of plant for this Contract shall be qualified.
All welds shall be visually examined and shall be of smooth contour, free
from cracks, undercuts and other significant defects. Welds shall be non-
destructively tested in accordance with the construction standard applicable
to the item of plant. Where appropriate, the magnetic particle testing or the
ultrasonic examination is to be applied.
B0.4.2.1 General
As far as practicable, quality of materials, workmanship and performance of
all items of the equipment furnished under the present contract shall be
inspected at the places of manufacture by the Contractor's QA inspectors.
All facilities shall be provided by the Contractor to enable the Employer and
to carry out the necessary inspection of the equipment components and the
costs of all tests during manufacture and preparation of test records are to be
borne by the Contractor.
5413A08/FICHT-7269866-v5 45
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Contractor shall submit for approval procedures describing the pro-
posed test methods to be used. Type and layout of test facility, location of
instrumentation, formula for calculation of results and correction to site
conditions, etc. shall be included where appropriate.
The passing of the inspection or test will not, however, prejudice the right of
the Employer / Employers Representative to reject the equipment compo-
nents if they do not comply with the technical requirements when erected, or
give complete satisfaction in service. Where the Contractor desires to use
stock material, not manufactured specially for the work, satisfactory evi-
dence that such material conforms to the requirements of the Contract shall
be submitted. In this case tests on these materials may be waived, but
certificates are to be submitted.
1. for wires
diameter
conductivity
tensile breaking strength
wrapping
tensile stress at 1% elongation for steel wires
galvanizing for steel wires
5413A08/FICHT-7269866-v5 46
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
3. for grease
grease weight per metro
dropping point
b) Tests of dampers
Vibration dampers for conductors and earth wires shall be subjected to tests
according to IEC 61897.
The damper shall be vertically mounted on a shaker table and driven with a
constant table velocity of both 0.10 m/s and 0.05 m/s. The frequency range
shall be calculated with the formula:
V
f = 0.2
D
for a wind velocity range of 0.5 - 7 m/s. The sweep rate shall be 0.2 dec-
ades/minute.
The reaction force and the phase angle between the reaction force and the
velocity shall be measured and power and impedance shall be plotted
against the frequency over the given frequency range.
One half width value of the resonant peaks of the power curves provide
good information about damping capabilities of a damper. This value shall
be calculated for each resonant peak of the power curves. The values shall
not be smaller than 0.3.
Fatigue test
This test is intended to demonstrate that the dampers have an acceptable
fatigue limit.
5413A08/FICHT-7269866-v5 47
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
After the fatigue test a new dynamic characteristic test shall be performed.
There shall be no significant difference in the dynamic characteristics before
and after the fatigue test.
The damper clamp shall be installed on the conductor using the following
torque:
45 Nm for M10;
60 Nm for M12 or bigger threads.
Then a force shall be applied to the clamp along the axis of the conductor.
The minimum force required to cause the clamp to slip on the conductor
shall be recorded.
Torque test
This test is intended to demonstrate that the dampers fulfill the requirements
as per manufacturer's proposal and Employer / Employers Representative s
approval.
In addition to the type tests shown above, corona and radio interference tests
have to be carried out.
verification of dimensions;
check of dynamic characteristic (see type tests);
check of clamp slip (see type tests);
galvanizing.
The sample tests shall be carried out to the Employer / Employers Repre-
sentative 's requirements on an agreed basis.
5413A08/FICHT-7269866-v5 48
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
For the sampling rules and acceptance criteria the IEC Publication 60591 is
also to be considered.
For the insulator units only the tests under a1 and c1 have to be applied.
In addition to the type test shown above, the overall dimensions of the
insulator sets as designed and approved by the Employer / Employers
Representative shall be verified.
For the insulator sets only the tests under a2, b2 and e2 are to be applied.
a3 - visual examination
b3 - mechanical routine test
c3 - electrical routine test
d3 - thermal shock routine test (glass only)
The tests referring to the insulator sets have to be carried out on completely
equipped sets, with all clamp and fitting parts, installed in their characteris-
tic working position and having attached also an agreed length of conductor.
The tests shall be carried out only in approved testing laboratories, accord-
ing to IEC recommendations and other regulations.
5413A08/FICHT-7269866-v5 49
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
From time to time the Employer / Employers Representative may ask for
further tests as required to ensure that the quality of the product is being
maintained throughout the Contract.
Design tests
The tests shall be executed in accordance with IEC Publication 60652
"Loading tests on overhead towers".
The height of the towers to be tested shall be the tower with body extension
and with leg extension as approved by the Employer / Employers Repre-
sentative.
The tests shall be carried out for all specified loading assumptions (load
cases) which are decisive for rating of tower members.
Each tower shall then be subject to such test loads in such order as the
Employer and/or Employers Representative may specify to prove compli-
ance with the factors of safety. Loads for 100% load step shall be main-
tained for five minutes, during which time there shall be no slacking off or
adjustments of loads.
5413A08/FICHT-7269866-v5 50
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Should it become necessary to adjust the loading, the 5 minute period shall
start after the loading is stabilized and constant. All test loads shall be
removed completely before the loads for the next test are applied, unless
previously agreed to by the Employer. All test loads shall be applied directly
to the regular attachment details provided for these loads. The applied loads
shall be measured right in front of the tower loading points and the reading
of all measured loads shall be enabled at one central place.
Any conspicuous yielding or any failure under any of the test loading or the
use of an incorrect grade of steel shall be considered a defect. If a failure
occurs, the Contractor shall correct the defect and repeat the loading test at
his own expense, including any additional costs by the Employer and/or
Employer's Representative for witnessing of the repeated test.
Test samples shall be cut from members which fail in the destruction tests
and from those members judged to be critical from the design calculations,
and standard tensile tests shall be performed at the Contractor's expense.
Results of the tests on these samples shall be used to correct the assembled
tower test results for comparison with the design.
Any tower or part thereof which has been overloaded during destruction
tests shall not be used subsequently in the construction of the lines.
Where tower tests to nominal design loads are satisfactorily completed, the
corresponding towers shall be carefully inspected after dismantling to
ensure that no parts have been damaged and shall be marked for use in the
permanent works at positions to be indicated by the Employer / Employers
Representative. A complete set of new bolts and nuts shall be supplied in
such cases and their cost shall be deemed to be covered by the Contract
Price.
The Contractor shall furnish all test structures, complete testing facilities, as
may be required and shall perform all work herein specified, or implied. All
items not specifically mentioned shall be deemed incidental to testing.
Routine tests
Samples of the material for the towers - standard or procedure - shall be
tested in accordance with the relevant standards, recommendations and
codes of practice.
5413A08/FICHT-7269866-v5 51
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
B0.4.3.1 General
The Contractor's scope of delivery includes all site test and inspection
expenses, e.g. all labor, materials, water, electricity, consumables, chemicals
and stores as well as the instruments and apparatus as may be required to
perform such tests efficiently. The Contractor is responsible for and shall
include in his delivery all safety measures such as barriers, warning signs
etc. required for inspection and testing while erection is in progress and all
interruption of work in this connection will be at his expense.
All instruments and apparatus used for site inspection and testing shall be
calibrated to an agreed standard at a laboratory of an international standing
to be nominated by the Contractor. The cost of making such calibrations
shall be borne by the Contractor in all cases.
Before energizing certain checks need to be carried out. For start-up the
Contractor will propose a program to be approved by the Employer /
Employers Representative. The program should give a step by step guide
for the start-up taking into account, but not limited to, the checking of each
disconnector, circuit breaker, circuit identification, current, voltage and
power indication, phase rotation and correct phasing (this start-up shall also
include all the substation auxiliary supplies and air ventilation).
5413A08/FICHT-7269866-v5 52
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Contractor shall cooperate with the Employer and with the other
Contractors to permit all necessary tests to be performed.
The Contractor shall provide all necessary instruments to perform the tests
on plant within his scope of work. The test instruments shall be new, of a
current model and type, and with the precision required to conduct the
specified tests. The Contractor shall follow operating procedures agreed by
the Employer.
Copies of all log sheets and test readings shall be given to the Employer as
the tests proceed.
After the conclusion of the tests, the Contractor shall compile a comprehen-
sive test report to the approval of the Employer. This report shall include
copies of all log and calculation sheets and all necessary tables and curves to
record the results of the tests.
5413A08/FICHT-7269866-v5 53
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The measurements have to be clearly recorded. The schedules used for the
recordings shall contain in addition to the measured ohmic values, details of
the surface soil and under ground data at the time of tests as well as the soil
resistivity values.
The Contractor shall provide suitable equipment (such as the Chance Digital
Micro Ohmmeter) in order to perform the above tests, and shall submit
details of the proposed instruments to the Employer / Employers Repre-
sentative for approval. Suitable clamps shall also be supplied for connecting
the current leads of the measuring instrument to the test sample to provide
adequate surface contact at the interfaces. Test probes as used for potential
contacts are unsuitable for current connections. Stringing of conductor and
earth wire shall not commence until the instruments are on site and ready for
use.
The center mark on the steel inner sleeve of joint shall be checked by the
Employer / Employers Representative before completing the outer sleeve
jointing. Details of the method shall be approved by the Employer / Em-
ployers Representative.
The contact behavior of the conductor and earth wire joints and terminals
shall be tested according to DIN VDE 0212 Part 52 A1 (type tests) or
equivalent standard.
5413A08/FICHT-7269866-v5 54
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Contractor shall be responsible for the correct test procedures and
testing shall be done in the presence of the Employer / Employers Repre-
sentative.
The tests shall include but not be limited to the following:
5413A08/FICHT-7269866-v5 55
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Documentation has not been met, the Contractor shall locate and correct all
equipment faults, which have caused this shortfall in specified availability.
d) White rust
If evidence of white rust is apparent upon receipt at site of bundled steel
sections, the Employer / Employers Representative shall order the Contrac-
tor to make such tests as he deems necessary to determine the extent of
damage, if any, and the remedial measures necessary.
The erection check documentation shall include check sheets for all trans-
mission and shieldwire components for each line section.
The results of the final erection checks shall be recorded in the check sheets
including the deficiencies to be rectified and shall be signed by the parties
attending the checks. The deficiencies shall be rectified before energizing
and in coordination with the requirements of the Employer.
f) Tests on completion
At least 90 days prior the completion of the first line section the Contractor
shall submit a schedule of energizing. The schedule of energizing shall
contain a sequence of how the Contractor intends to energize the different
parts of the different line sections.
insulation measurement
line impedance
5413A08/FICHT-7269866-v5 56
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The line shall be energized at full working voltage before handing over and
the arrangement for this, and such other tests as the Employer or the Em-
ployers Representative shall desire to make on the complete line, shall be
assisted by the Contractor who shall provide such labor, transport and other
assistance as is required without extra charge.
B0.5.1 General
All information, documentation, calculations, drawings, schedules etc. have
to be submitted within such periods or at such dates which are required to
guarantee a smooth handling of the project without any delays. The Con-
tractor is responsible for submitting all documentation in accordance with a
program to be prepared by him allowing all participants sufficient time to
check, assess, comment and approve the documents. The quality of the
submitted documents must be in accordance with acceptable international
practice to allow a speedy checking procedure. Documents not fulfilling
these requirements will be returned to the Contractor without comments for
improvement and resubmission.
Any omission in both, drawings and the Specification, shall not relieve the
Contractor of his responsibility to include such detail or work in his supply.
The final sizes of equipment shown on the specification drawings have not
been fixed by the Employer's representative since these are dependent on
the size and shape of the tenderer's proposed equipment and materials
forming the works and the space required for installation, maintenance, lay-
down, storage, access etc. They are however to be considered as minimum
requirements. Any deviation has to be stated in the schedules "Departures
From or Qualifications To the Specification".
The specification drawings portray the basic layout of the Scope of Works
and the Tenderer shall incorporate these requirements in his tender draw-
ings.
5413A08/FICHT-7269866-v5 57
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Tenderer has to ensure that the information provided within the Specifi-
cation is sufficient to state his final Contract Price. No additional claims will
be allowed for supplies and services for the interconnecting or other works
to be performed by him.
The Tenderer has the liberty to comment on any document and drawing
issued with the Specification within the time specified in Section A0
'Instructions to Tenderer'. After the Tender has been submitted, the Tenderer
is deemed to have checked all these documents and drawings and they are
without any restriction accepted by him. No claim resulting out of omissions
or discrepancies in this respect will be accepted by the Employer's repre-
sentative/Employer.
B0.5.3.1 Correspondence
All correspondence shall be addressed to the Employer and copied to the
Employer's representative in accordance with the table shown below.
The Contractor shall distribute for approval two sets to the Employer and
two sets to the Employer's representative simultaneously within the dates
named in specifications such drawings, samples, patterns and models as
may be called for therein or as the Employer's representative may reasona-
bly require. Approval will be accorded by the Employer's representative
four (4) weeks after receipt of the two documents.
5413A08/FICHT-7269866-v5 58
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
One (1) copy of the drawings and other papers submitted will be returned to
the Contractor with one of the following examination endorsements applied
by the Employer's representative:
-- NOT APPROVED --
This drawing has been spot-checked for main dimensions and compliance
with the overall layout, and is being returned for the necessary modifica-
tions. The revised documents shall be resubmitted to the Client for approval.
Related activities on field works and/or manufacturing cannot commence.
-- APPROVED ON CONDITION --
This drawing has been spot-checked and limited approved with regard to the
main dimensions and compliance with the overall arrangement. Provided
that the necessary corrections will be considered and incorporated in the
final design and project implementation, related activities on field works
and/or manufacturing can commence. The revised documents shall be
resubmitted for approval. The approval does not release the Contractor from
his full contractual obligation on design liability and facility performance of
the installed transmission system.
-- APPROVED --
This drawing has been spot-checked and approved with regard to the main
dimensions and compliance with the overall arrangement. The related
activities on field works and/or manufacturing can commence. The ap-
proved documents shall be resubmitted stamped by the Contractor For
Construction. The approval does not release the Contractor from his full
contractual obligation on design liability and facility performance of the
installed transmission system.
If the Contractor receives drawings and papers endorsed with the stamp
N O T A P P R O V E D he shall without delay make all the necessary
alterations and corrections and resubmit copies of these as shown below to
the Employer's representative for approval.
If the Contractor receives drawings and papers with the stamp APPROVED
he shall without delay send copies as per table shown below stamped "FOR
CONSTRUCTION".
5413A08/FICHT-7269866-v5 59
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The drawing approval is not the official building permit for the planned
transmission lines and the concerned main crossing (roads, railways, aerials,
etc.)
The Contractor shall ensure that drawings, calculations, designs etc. for
approval are forwarded to the Employer's representative in sufficient time to
allow enough time for examination of the drawings in the Employer's
representative's office. In general this time period is 4 weeks from the date
the documents were received by the Employers representative office.
The Contractor shall also ensure that drawings are submitted early enough
prior to the date required for approval to permit amendments to be made and
the drawings re-submitted for approval without delaying the program
deliveries or the guaranteed completion dates of the Works.
If the Contractor has not received any notice within 5 weeks from the date
of submission (reception date by the Employers Representative), then the
documents and/or drawings shall be deemed of being approved.
If during the contract period, the Contractor is required to increase the size
of any buildings, foundations etc. from that shown on his tender drawings to
accommodate the finally approved arrangement of the works provided under
the Contract (with due allowance for access, lay down, maintenance etc.),
then such increases shall be deemed to be included in the Scope of the
Contract.
All drawings shall be black lines on a white background with all revisions
clearly marked.
5413A08/FICHT-7269866-v5 60
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
All drawings shall bear the approved contract references and title block as
agreed with the Employer's representative.
All drawings and other papers which have to be submitted to the Employer's
representative in accordance to these clauses, shall be composed in English.
The design, dimensioning and the technical data in the drawings and other
papers shall be based on the metric system only.
5413A08/FICHT-7269866-v5 61
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
For enlargements: 2 : 1 / 5 : 1 / 10 : 1
The quality of original drawings, master prints, blue-prints and of all other
copies, irrespective of the method by which they have been produced, must
be such that no damage whatsoever, such as partial or complete illegibility,
can occur as a result of the tropical climate or other extreme climatic
conditions. For drawings a paper grade weighing more than 80 grams per
square meter shall be used throughout. The out-printing quality of topo-
graphical maps shall reach at least 300 dpi (dot per inch) and for satellite
photos at least 600 dpi.
The Employer reserves the right to ask for all drawings directly.
The Employer's representative and the Employer shall have the right at all
reasonable times to inspect at the factory of the Contractor all drawings of
any portion of the Works. The Contractor shall submit design calculations
and shop drawings.
The Contractor shall, within the times named in the Specification, provide
drawings showing the manner in which the Plant is to be assembled with all
information relating, unless otherwise agreed, only to the Works, required
for preparing suitable foundations, for providing suitable access for the
Plant and any necessary equipment to the point on Site where the Plant is to
be erected and for making all necessary connections to the Plant (whether
such connections are to be made by the Contractor under the Contract or
not).
5413A08/FICHT-7269866-v5 62
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The Contractor shall submit detailed progress reports. The reports shall
show clearly and accurately the position of all activities associated with
design, material procurement, manufacture, QA activities, works tests,
shipping, mobilization, site erection, testing and commissioning with regard
to the agreed contract program.
The position on material procurement shall give the date and details of
orders placed and indicate the delivery quoted by the manufacturer. If any
delivery has an adverse effect on the contract program the contractor shall
state the remedial action taken to ensure that delays do not occur.
5413A08/FICHT-7269866-v5 63
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The site erection portion of the progress report shall be segregated into the
main and ancillary items of civil, mechanical and electrical work and each
item of work shall be monitored giving the percentage completion and the
projected completion date of the Work in accordance with the agreed
contract program.
Any delay which will affect the completion, testing and commissioning
dates of any item of Plant shall be detailed by the Contractor who shall state
the action he is taking to effect completion to the contract program.
The Contractor shall report in respect of the various groups of the Works the
erection equipment in use or held in readiness, a return of labor and supervi-
sory staff, and details of any matters arising which may generally affect the
progress of site Work.
The progress reports shall be set out in a format to the approval of the
Employer's representative.
The progress report shall be forwarded within the first week of the follow-
ing month so that on receipt the information contained therein is not out of
date.
5413A08/FICHT-7269866-v5 64
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
project definition
Contractor's Scope of Works (contract value)
original and final overall Contract Value with major reasons for deviation
original and final schedule with major reasons for deviations
Contractor's organization charts
commissioning report
performance test calculations and results
test certificates
inspection certificates
acceptance certificates
all final engineering calculations bound in separate volumes.
5413A08/FICHT-7269866-v5 65
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The instructions shall mention the inspection and maintenance intervals laid
down separately for each individual equipment or part, the exact description
of the operations to be carried out as well as the necessary spare parts and
materials.
The Contractor shall mention how and where additional spare parts can be
ordered specifying for each part the ordering number.
5413A08/FICHT-7269866-v5 66
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
The instruction shall contain indications how to use the earthing devices and
other service and protective equipment the safety measures required, clearly
presented and commented in detail.
5413A08/FICHT-7269866-v5 67
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Revision and Distribution: Here the last revision date, the revision index and
the recipient of the drawings are to be entered. The recipients noted in the
lists shall not include any internal work departments of the Contractor, with
the exception of their local representatives or site managements in Mozam-
bique. The recipients are already entered in the sample.
5413A08/FICHT-7269866-v5 68
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
O = print
C = reproducible copy
Example:
General:
Detailed time schedule for the design, manufacture, deliv- 3 updated every
ery, erection and commissioning period with important month
intermediate dates
Payment schedule - 3
5413A08/FICHT-7269866-v5 69
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B0)
Correspondence 2 1 1 1 5
Drawings
for approval (and 2 - 2 - 4
resubmission)
for construction 3* 2 1 2 8
as built 8** - 1* - 9
Insurance Certifi- 2 - 1 1 4
cates
Progress report (incl. 5 1 2 1 9
photos)
Damage reports 5 1 1 1 8
O + M manuals
draft 1 1 1 1 4
final 6 - 1 1 8
List of spare parts 2 - 1 1 4
Close out report 2 1 1 1 5
Test Certificates 2 1 1 1 5
5413A08/FICHT-7269866-v5 70
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1
Employers Requirements
Particular Technical Requirements
for 400kV Overhead Line
5413A08/FICHT-7269867-v13
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Table of Contents
5413A08/FICHT-7269867-v13 I
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
5413A08/FICHT-7269867-v13 II
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
5413A08/FICHT-7269867-v13 III
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
5413A08/FICHT-7269867-v13 IV
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
5413A08/FICHT-7269867-v13 V
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.1 General
Background
The proposed new HV transmission line project is part of TANESCOs
short-term strategy for National Grid transmission line reinforcement. This
new 670 km long power line from Iringa to Shinyanga will link existing and
future generating sources in the south and southwest of Tanzania to the load
centers in the Mwanza and Arusha regions in the North.
The power now being generated at Lower Kihansi, Kidatu and Mtera, and in
future at Kiwira, Mpanga, Ruhuji, Mchuchuma and Rumakali, shall be
transmitted to the load centers in the north and northwest of Tanzania by
reinforcing the existing transmission grid.
The planned energy expansion project shall boost the countrys central
south-north power transmission capacity from Iringa to Shinyanga for
improving electricity supply to the economically fast-growing north-western
part of the country. Forming a part of TANESCOs national grid, the new
high-voltage transmission line will also be a link of the future interconnect-
ed East-African High-Voltage Power Grid.
It has to be pointed out that this proposed project is one of the high priority
items in TANESCOs Capital Investment Plan (CIP). The project shall be
implemented forming three lots and working in parallel.
5413A08/FICHT-7269867-v13 1
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
ISWER system
The new 400kV transmission line shall be equipped with an ISWER system
in Lot 3. The issue deals with the power supply to the villages located along
the line route up to 126km distance from the high voltage transformer
substation. It is planned to use the rated voltage of 36kV for sub-
transmission and distribution to the following fourteen villages with low
load density:
DISTRICT VILLAGE
1. Kizonzo
Iramba
2. Mseko
3. Mgongoro
4. Makomero
5. Mbutu
Igunga 6. Bukama
7. Imalanguzi
8. Mwanakoma
9. Igurubi
10. Kalitu
11. Kiloleli
Kishapu 12. Mwajiginya
13. Mwaweja
14. Ngunga
The 36kV system is operated with the neutral solidly grounded transformer.
The configuration is solely radial. The system consists of the insulation of
the two shield wires of the 400kV transmission line (one normal earthwire
and one OPGW), energizing the two shield wires in the nearest high voltage
transformer substation as two phases of the 36kV system and establishing
the third phase via a series resister reactor (R-L-block) and earth-return.
At each point-off point, the current flows from the line through the primary
coil of a step-down transformer to earth through an earth rod. From the earth
stake, the current goes its way back to the main step-down transformer at
the head feed of the line. The secondary winding of the local transformer
will supply the customer with three phase (P-N-P, 2 x 240 V) power, with
the N-Volt conductor connected to a safety earth point.
36kV post insulators for leading one conductor to the other tower
side of the T-off direction
two 36kV tension strings to be fixed at the crossarm peak for the T-
off down-lead of the two phases
or alternatively cable up-lead to the earthwire crossarm level and
installation of cable end connector and surge arrester with jumper
link to the earthwire on an auxiliary platform
but the equipment is not in the scope of this Contract (except insulator
strings). The exact locations of these points are not known at the moment.
However, all construction detail preparations shall be done to install the T-
off or termination equipment at any tower.
B1.2.1 Geography
The line route and associated substations are located in the central highlands
of Tanzania between 35 and 36 east and extending in the latitudes from 4
to 8 south of equator as shown in the General Map of Project Area.
The planned line of approximately 670 km will interconnect four substa-
tions at the cities of Shinyanga, Singida, Dodoma and Iringa. Accordingly,
three line sections (lots) are resulting as shown below:
5413A08/FICHT-7269867-v13 3
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Each lot is independent of one another, i.e, have different consultants and
Contractors. Lot 2 from Migoli to Fufu, runs on both sides of the two
regions of Iringa and Dodoma.
The upgrading works of the road are already in progress for a duration of 36
months (3yrs) as from 16th March 2011. During that period of road con-
struction, the EPC Contractor will be encountering diversions as well as
restrictions to places whereby bridges and culverts are at construction stage,
such that much corporation is required so that disruption of either side of the
works is avoided or minimized during implementation of the construction of
the transmission line of which will be using the road or its diversions as per
time to time directives.
B1.2.2 Topography
Commencing from the south, the line passes from the Iringa Highlands to
the north over the Kidunda Ranges at 1,650 m a.s.l. From the rocky, steep
slopes, the highlands drop sharply within ~ 50 km nearly 1,000 m over a
dissected scarp towards the Mtera Reservoir. The line bypasses the power
plant Mtera in rolling hills over the Fufu Escarpments to Dodoma. Continu-
ing to north-west along the Great North Road, the terrain is in general rather
flat to gentle sloped. After Singida the line traverses moderately rising
countryside with another sharp drop into the partly swampy Wembere
Plains. Towards Shinyanga the terrain rises steadily from lightly hilly to
undulating landscape.
5413A08/FICHT-7269867-v13 4
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.2.3 Hydrology
The predominantly tropical climate in these latitudes is characterized by
frequent and intensive thunder showers during rainy season. The mountain
ranges around Iringa and Dodoma are like cloud-bursting obstacles in the
weather atmosphere. The annual rainfall of around 1m in the highlands to
less than half a meter in the plains is concentrated on the wet months only
from November to May, peaking in March and April.
This pattern of rainfall in combination with sandy ground let rivers and
marshy terrain dry up after rainy season. Only two rivers in the project area,
the Great Ruaha and its largest tributary, the Little Ruaha, which feed the
Mtera Reservoir, are perennial. The phenomenon of seasonal river and
seasonal swamp allow great mobility across the countryside during dry
season from June to October.
B1.2.4 Geology
Some parts of the line route are located in areas of outcropping meta-
igneous weather-rock basement. Differential continental plate drifts during
the late tectonic phase of the Precambrium period pushed the rock partially
to the surface. The fractured earth-crust underwent a medium-grade meta-
morphic transformation forming a rock basement in various hardness
predominantly of granite accompanied by gneiss and sequences of interca-
lated metacalcerous crystalline rocks, quartzite and schist. Two major
parallel faults of a highly sheared and down-thrown area between Fufu and
Isimani are forming the plains of the Great Ruaha River.
Composition of soil
predominantly metamorphosed outcrop rock of weathering granites
and gneiss on hills and alluvium in plains and residual soils in
depressions
B1.2.5 Geomorphology
The low-grade metamorphosed outcropping sedimentary rock and granites
are gradually weathering to partly gravelly sand with fines. The weathering
product of predominantly coarse crystalline sand forms the slopes of the
hilly terrain, whereas the large plains are of alluvial deposits and residual
soils of clayey fine sand with some silt. Although the soil is in general of
firm to dense compactness having good bearing properties, the low percent-
age of cohesive fine components makes the soil in exposed areas prone to
erosion.
Particular effort shall be made during the field investigation in locating and
recording these areas for tower spotting and erosion protection measures.
5413A08/FICHT-7269867-v13 5
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
In some isolated parts and marshy terrain localized lateritic and black cotton
soil have developed and is extending up to several meters depth.
Property of soil
predominantly red to yellow-brown and brown sandy earth of firm to
dense compactness of fairly good bearing capacity
B1.2.6 Vegetation
The vegetation is depending on climate pattern, rainfall quantity, irrigation
systems and soil fertility. The vicinity of the all-year well-watered banks
from the Little and Great Ruaha is an important maize-growing area with
some paddy fields and fruit plantations whereas the dryer zones cattle, crops
and bushes are prevailing.
B1.2.7 Wind
Winds in the plains around Singida and Shinyanga are light to moderate
throughout the year. Wind speeds are somewhat higher towards the end of
dry season. Thunderstorms during the wet season can generate strong
surface winds of mainly short duration.
B1.2.8 Earthquake
The East-African continental riff, an active fault line caused by differential
plate movements is associated with earthquakes in the range of a local
magnitude ML 6 to 7. This earthquake belt is located approx. 500 km to the
west of the planned transmission line in the neighboring country Rwanda.
B1.2.9 Summary
The climatic conditions for the new 400kV line are summarized as follow-
ing:
5413A08/FICHT-7269867-v13 6
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The Contractor shall assume at least the following works, duties and ser-
vices as the contract scope:
Lot 1, overhead line from Iringa S/S to Dodoma S/S, line length 225km
including temporary outgoing for 220kV operation at Iringa S/S
Lot 2, overhead line from Dodoma S/S to Singida S/S, line length 217km
including temporary incoming/ outgoing for 220kV operation at Dodoma
S/S
Lot 3, overhead line from Singida S/S to Shinyanga S/S, line length
228km including temporary incoming/ outgoing for the 220kV operation
at Singida S/S and temporary incoming for Shinyanga S/S
Temporary incoming and outgoing for the 220kV operation mean
surrounding of the future 400kV substation extension area with the help
5413A08/FICHT-7269867-v13 7
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
of a 400kV overhead line (see plans in the Annex). The new 400kV line
shall end at the dead end towers in front of the future 400kV T/L bays of
the S/S. The temporary line shall run from this dead end tower to the
220kV T/L bays of the S/S.
400 kV overhead line, double circuit, twin bundle ASCR Bluejay con-
ductor, insulator strings, steel latticed towers, reinforced concrete foun-
dations
two earthwires, one as normal ACSR conductor plus one as OPGW
in specified sections of Lot 3 ISWER system (one ACSR conductor plus
one OPPC both insulated for 36kV) instead of normal earthwire/ OPGW
all preparations for T-offs of the ISWER system
termination of ISWER system after 126km distance from the substation
and separation of the optical fibres for the OPPC/ OPGW
special 400kV towers with horizontal phase conductor configuration for
bird protection in Lot 3
The scope of line contract ends at the substation gantries, i.e. slack span
of conductors, insulator strings and their attachment at the gantry and
jumpers for the link to the substation conductors shall be included under
this scope.
The ISWER system ends at the gantry top including jumper link to the
substation and separation of the optical fibre part of the OPCC. The opti-
cal fibre termination box shall be installed at the gantry base.
The OPGW system ends at the gantry top including jumper link to the
substation. The OPGW termination box shall be installed at the gantry
base.
engineering services for the planned transmission system to the necessary
extent of a turn-key project
detail design of the transmission line components to the necessary extent
for manufacturing and construction
mobilization, store yards, access roads, bush clearing
survey of ground features, plotting of situation plan and longitudinal
profiles with tower spotting
soil investigation, penetration sounding, test pits, sampling and evalua-
tion of the engineering properties
procurement, manufacturing, testing, supply, insurance, shipping,
customs clearance, unloading, transport, storage of line material and
components
testing of tower and foundation
testing of conductors and insulator strings including their components
installation and erection of foundations, earthing system, erosion protec-
tion, towers, insulators, conductors, ground wire, OPGW
aircraft warning near airports by red/white structure painting and installa-
tion of orange cable spheres
installation of step bolts, anti-climbing device, tower number and danger
plates, landmarks for right of way
tidy-up maintenance roads
commissioning with final check and live test of transmission system
as-built documentation and operation & maintenance manual
supply of spare parts and maintenance tools
5413A08/FICHT-7269867-v13 8
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Line route maps, typical foundation types, tower outline drawings, insulator
and conductor configuration as well as earthing principles are annexed to
this specification.
The Bidder shall offer quantities according to the price schedules. These
quantities were estimated for bidding purpose, based on the preliminary line
design. They are not valid for the Contractors material ordering. A verifica-
tion and possible adjustment of the quantities will be done during the
engineering stage and detail design and shall be subject to approval of the
Employer / Employers Representative. The Contractor has to establish the
necessary quantities based on his final, approved design.
B1.4.1.1 General
The new European Standard EN 50341 Overhead electrical lines exceeding
AC 45kV, is in force since 2001 and was introduced officially in all
5413A08/FICHT-7269867-v13 9
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Based on the preliminary line route and the General and Particular Tech-
nical Requirements, the Contractor shall perform his own investigation,
calculations and studies to check and optimize the line design. The Contrac-
tor shall be responsible for the complete and comprehensive design adapted
to the actual project conditions.
General
EN 50341-1 (2010): Overhead electrical lines exceeding AC 45kV,
Part 1 - General requirements - Common specifications
IEC 60038 (1983): IEC standard voltages
IEC 60060 (1989): High voltage test techniques
IEC 60270 (2000): High voltage test techniques Partial discharge
measurements
Conductors
EN 50182: Conductors for overhead lines - round wire concentric
lay stranded conductors
ASTM B 232/ B 232M: Specification for concentric-lay-stranded
aluminum conductors, coated-steel reinforced (ACSR)
EN 60889: Hard-drawn aluminum wires for overhead line conduc-
tors
EN 50189: Conductors for overhead lines - Zinc-coated steel wires
5413A08/FICHT-7269867-v13 10
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
OPGW
IEC 60793: Optical fibers - Part 1: Measurement methods and test
procedures
IEC 60794-1-1: Optical Fiber Cables - Generic Specification -
General (Materials, Construction, Measuring Methods)
IEC 60794-1-2: Optical Fiber Cables - Generic Specification -
Basic Optical Cable Test Procedures
ITU-T G.652: Transmission media characteristics Optical fiber
cables - Characteristics of a single-mode optical fiber cable
ITU-T G.655: Transmission media characteristics Optical fiber
cables - Characteristics of a non-zero dispersion shifted single mode
optical fiber cable
5413A08/FICHT-7269867-v13 11
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Fittings
IEC 61284 (1997): Overhead Lines - Requirements and tests for
fittings
IEC 61854: Overhead Lines - Requirements and Tests for Spacers
IEC 61897: Overhead Lines - Requirements and Tests Stockbrigde
Type Aeolian Vibration Dampers
Towers
EN 1993-1-1: Design of steel structures - Part 1-1: General rules
and rules for buildings
EN 1993-1-8: Design of steel structures - Part 1-8: Design of
joints
EN 10025 (2004): Hot rolled products of structural steels
EN 10029: Hot rolled steel plates 3mm thick and above
EN 10056: Structural steel equal and unequal leg angles - Part 1:
Dimensions, Part 2: Tolerances
ISO 898 (1999): Mechanical properties of fasteners
ISO 1461 (1999): Hot dip galvanized coatings on fabricated iron
and steel articles
IEC 60652 (2002): Loading tests on overhead line structures
Paper 3B from IEE Effects of Interacting Construction Deviations
on 500 kV Power Line Structures by F. Villa, Kuala Lumpur, Ma-
laysia 1993
Foundations
EN 1997-1-1: Geotechnical design - Part 1: General rules
EN 197-1 (2000): Cement Composition, specification and con-
formity criteria
BS EN 12620: Specification for aggregates from natural sources of
concrete
EN 206-1 (2000): Concrete Specification, performance, produc-
tion and conformity
EN 10080: Steel for the reinforcement of concrete - Weldable rein-
forcing steel - General
EN 1992-1: Design of concrete structures - Part 1-1: General rules
and rules for buildings
EN 12350-1: Testing fresh concrete
EN 12390-3: Testing hardened concrete
IEC 61773: Overhead lines Testing of foundations for structures.
5413A08/FICHT-7269867-v13 12
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The following table shows the minimum design requirements from the
point of view of the electrical system.
In addition to the climatic and electrical design data, the following data shall
be taken into consideration for the design.
5413A08/FICHT-7269867-v13 13
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Final detail drawings of the final line route shall be submitted to the Em-
ployer for approval. The drawings form the basis for obtaining the building
permit by the Employer. The Contract Price shall include provision for
additional detail drawings as may be required by the Building Authority.
5413A08/FICHT-7269867-v13 14
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
During the survey, the Contractor shall also check the presence of existing
water or gas pipe lines, electrical signal lines within the vicinity of the line
or telecommunication antennas and to ensure that there will be no hazard-
ous, induced voltages or any other interference. In the event of complica-
tions within the proposed line route corridor of right of way the Contractor
shall prepare a technical solution and submit it for approval by the Employ-
er. Such services are deemed to be included in the Contract Price. Profiles
shall be produced as a result of a precision ground or aerial survey
The thedolites used and measuring techniques applied shall be state of the
art, employing digital recording technique. The vertical tolerance of levels
forming the profile and actual ground level shall not exceed 20 cm. The
horizontal distances shall have an accuracy of 1 in 2000 and angle meas-
urements of 1 minute accurate.
Those separate drawings are the planning base for tower legs extension and
check on foundations imbalanced inverted soil cone under uplift load.
Within the right of way corridor of 90 m width all features such as hedges,
fences, graves, ditches, roads, railways, rivers, buildings, canals, telecom-
munication and all power lines shall be shown.
Road numbers or name of roads shall be stated or, if unclassified, the
destination. Railways are to be given the destination, number of tracks,
whether or not electrified and the level at the top of rail stated. The voltage
level for power lines shall be indicated.
5413A08/FICHT-7269867-v13 15
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
All buildings or high obstructions within 45 m to each side of the center line
shall be shown dotted at their measured height with the distance left or right
of line indicated.
Along the bottom of the profile sheet a route map shall be drawn, to the
same scale as the horizontal scale of the profile showing all relevant details,
within a distance of 45 m to each side of the route center line.
The sag template used shall be suitable for the respective climatic zone and
for the ruling span of the section where the plotting is performed.
For suspension towers the minimum ratio of the weight span to wind span
shall be such as to guarantee that the maximum insulator set deflection
angles of I-type suspension sets is not exceeded and that both sub-strings
of V-type suspension sets remain tensioned.
The tower spotting shall take into consideration the specified minimum
ground clearances as well as the minimum distances of the conductors to
obstacles to be crossed such as power transmission lines, main roads,
houses, etc. as specified in the Technical Schedules. The profile plans shall
display the bottom conductor catenary, at 85oC, together with the ground or
special clearance curves, as well as the minimum temperature catenary. The
Contractor has to provide a clearance calculation for all crossings of all
classifications of roads, railways, rivers and all power and telecommunica-
tion lines in order to proof that the required clearance is met under the worst
conditions. Railways and main roads shall be crossed at an angle of 90
30 at maximum unless otherwise approved.
5413A08/FICHT-7269867-v13 16
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Special attention shall be observed near populated areas or close to the roads
where the OHL is to be parallel with existing OHTLs. The towers shall be
placed as aligned as possible to the existing ones and their positions shall be
subject to the Employers / Employers Representatives approval.
In this respect, the location of the existing OHTL towers shall be clearly
marked on the drawings.
The profile shall be plotted with the direction of the line route left to right
on the profile sheet. In general, individual profile sheets shall commence
and finish at tension supports but where this is not practicable and continua-
tion sheets are found to be necessary the ground line is to be drawn so that
there is an overlap of at least 300 mm between adjacent sheets. Each section
shall normally be started on a new sheet. The date of survey of each section
shall be added.
The negotiations with the landowners and authorities about the tower
locations, the right of way, the access to the line for the construction works
and the compensation for land acquisition, for crops, temporarily damages
etc. shall be in the responsibility of the Employer.
5413A08/FICHT-7269867-v13 17
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.3.1 General
The Contractor is urged to observance of the requirements of the national
environment protection legislation. The Contractor shall take all precautions
to avoid damage to public, land, property, crops, etc. and shall ensure that
the work is adequately supervised so that damage is avoided. The Contrac-
tor shall adhere to the recommendation of the Environmental and Social
Impact Assessment (ESIA) and Environmental and Social Mitigation Plan
(ESMP), a copy of which can be obtained from the Employer.
Where the Contractor considers that damage cannot be avoided, if the work
is to proceed normally, he shall notify the Employer/ Employers Repre-
sentative accordingly. If the Employer/ Employers Representative confirms
that such unavoidable damage will occur, the Employer will be responsible
for compensation in respect of the damage and the Contractor shall proceed
with the works within the limits indicated by the Employer.
All surplus material shall be removed after erection and the site shall be left
in a clean and tidy condition. The following rules and procedures shall be
adhered to by the Contractor with regard to protection of the environment:
The Contractor pledged himself to treat the waste in accordance with the
law of the United Republic of Tanzania
The Contractor pledged himself the treatment of all hazardous waste,
generated by his activities on site in accordance with the current law of
environmental regulations of the local Authorities.
The Contractor pledged himself to deposit all dismantled equipment
containing hazardous substances to the Employers places, which are
leak proof.
In case, that hazardous substances leak into the surface water or ground
water because of the Contractors activities, he is responsible and under-
takes improvement action. He will ensure on his own costs liquidation of
the incurred damages.
5413A08/FICHT-7269867-v13 18
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Due to loose sands and silts in some parts of the line surface protection and
erosion mitigation measures (drainage, small platforms, stone pitching,
gabions, vertiver grass for hedges, etc.) may become necessary as specified
below.
Ruts and scars shall be obliterated, damage to ditches, terraces, roads and
other features of the land shall be corrected, and the land shall be restored to
its original condition.
The Contractor shall be responsible to the occupants of the land which are
crossed by the transmission line for any damage to personal property
resulting from his fault or negligence, including damage caused by straying
livestock, and he shall make prompt settlement of damages to personal
property resulting from his negligence. The Contractor shall be responsible
for notifying the Employer in writing of all instances of damage to crops
plantation, livestock, etc.
The Contractor shall use all means necessary to control dust on roads,
construction areas and borrow pits. Surfaces shall be regularly watered to
prevent dust becoming a nuisance for the public and interfering with the
proper execution of the works.
The Contractor shall not bring any dog on or near the site or suffer or permit
any of his employees, representatives or agents or any Subcontractor to
bring any dog on or near the site and shall cause the immediate removal of
any dog which may be on or near the Site in breach of this provision.
5413A08/FICHT-7269867-v13 19
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The Contractor shall be liable for any injury to or loss of livestock due in the
opinion of the Employer/ Employers Representative to failure to comply
with the above requirements.
Means shall be provided on all lattice steel towers and tower extensions
were required to avoid the risk of livestock being caught between tower
members and being injured.
The monthly progress reports shall also focus on impacts during the con-
struction on site. Problems like
5413A08/FICHT-7269867-v13 20
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.4 Towers
The electrical and mechanical design and details shall conform to the
requirements of EN 50341-1.
In case of existing tower designs are proposed, it has to be proven that the
structures fulfill the minimum electrical and mechanical requirements as per
Technical Schedules, or that suitable design adjustments are offered. Such
design proving and shop detailing will be the responsibility of the Contrac-
tor but suitable design calculation shall be included in the offer to allow
technical evaluation of the bid.
B1.4.4.2 Materials
All materials shall be brand-new and of the best quality for use in the
conditions and the variations in temperature and pressure that will be
encountered in service without undue distortion or deterioration or the
setting up of undue strains in any part that might affect the efficiency and
reliability of the plant. Any steel member with traces of hole filling shall not
be used. Special attention shall be paid to eliminating the possibility of
5413A08/FICHT-7269867-v13 21
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Materials used for the design and construction of the steelwork shall comply
with the codes and standards listed below.
Unless the materials meet these codes and standards, they shall be subject to
the Employer/ Employers Representative approval.
c) Locking devices
All tower bolt connections shall be provided with one flat washer
and one spring washer.
d) Tower signs
Signs, consisting of aerial patrol signs, phasing signs, circuit name
signs, danger signs and number signs shall be made of mild steel
covered with enamel on both sides, or of aluminum. The thickness
shall not be less than 2 mm. Writings on signs shall be in the lan-
guage of the Country
B1.4.4.3 Design
5413A08/FICHT-7269867-v13 22
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Ed Rd
Ed ( F FK) Rd = RK / M
The directly calculated physical loads are increased by partial safety factors
whereas the resistances are divided by material factors in order to consider
uncertainties (see also Paragraph 4.4.3.6 below).
Type of Towers
The functional tower types of the tower families are selected based on the
line angles of the line route. For fabrication, tower testing and erection but
also for facilitate line maintenance and spare parts keeping, the following
tower types are specified:
NS, normal suspension tower, capable to be utilized for very small line
angles of up to 2
HS, heavy suspension tower, capable to be utilized for increased wind
spans, long spans, increased weight spans, small line angles up to 2 or
for a combination of such conditions. An unfavorable weight to wind
span ratio is assumed.
LA, light angle tower for line angles of up to 30
HA/ DE, heavy angle tower for line angles of 30 to 70 and dead-end
tower for 0 to 45 angle in line direction and 0 to 90 angle of the slack
span to the gantry.
TP, transposition tower at straight line 2.
For the DE tower the indicated angles refer to one side of the tower while
for angle towers the angles given are actual line angles (i.e. line deviation
angle at both sides).
The HA/DE tower will have to be designed for its utilization as angle tower
as well as dead-end tower. Therefore it will have to be provided with two
separate sets of crossarms. In addition, for the particular requirements of the
dead-end tower having a line angle of 90 degrees to the substation gantry,
detailed clearance and structural checks with consideration of necessary
jumper suspension sets and additional crossarms have to be performed.
5413A08/FICHT-7269867-v13 23
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The TP tower will have to be designed with auxiliary crossarms for transpo-
sition of the phases. For complete transposition cycle, three TP towers shall
be installed in each of the 3 line sections over the 670 km long 400 kV line.
Jumper and in-loop insulators shall be of composite type material to avoid
excessive sagging of insulator string.
the symbol for the tower functional type NS, HS, LA, HA/DE , TP which
stand for light normal suspension, heavy suspension, light angle, heavy
angle, dead-end and transposition respectively
an index h added to the symbols for the tower family with horizontal
phase conductor configuration in Lot 3
the respective tower height variant, i.e. the body extension used, if any.
For example LA+3 is the light angle tower having 3 m body extension. Leg
extensions are not included in the tower denomination.
Tower Outlines
The outlines of the suspension and angle towers shall comply with the
general requirements as specified and shown in the Annex and shall be such
as to provide the required minimum clearances between conductors, from
live parts and tower steelwork, and to ground as specified hereafter.
The basic tower height (standard tower height with body extension 0) shall
be determined taking into account the maximum conductor sag for the
nominal span (see the table below), the suspension insulator string length
and the minimum ground clearance.
In order to adapt the tower height to the terrain, to allow the crossing of
obstacles and to use the towers as economical as possible towers shall be
provided with body extensions and reductions.
The towers shall be provided with the following tower body extensions/
reductions:
Tower type Body extensions
NS, NSh -4, 0, +4, +8, +12
HS, HSh -4, 0, +4, +8, +12, +16
LA, LAh -4, 0, +4, +8, +12
HA/DE, HAh 0, +4, +8
TP 0, +4, +8
The hilly terrain over a part of the line requires leg extensions for the 400
kV towers. The leg extensions set to be designed for each tower type shall
5413A08/FICHT-7269867-v13 24
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
be suitable for all body extensions of the respective tower type and shall be
interchangeable. All structures have to allow a combination of different leg
extensions as follows:
Structure type Leg extensions
All tower types with any possible body -3, -2, -1, 0, +1, +2, +3
extensions / reduction
1) wind span values for the line angle of 0; for line angles >0 the wind
span has to be decreased accordingly
2) these are minimum values for the mid-span criterion; actual maximum
spans may be higher in case mid-span phase-to-phase spacing will be
determined by phase-to-tower steelwork clearances.
3) considering the slack span between terminal tower and S/S gantry
5413A08/FICHT-7269867-v13 25
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
In detail:
The swing out angle determination for suspension insulator strings as per
EN 50341-1, Chapter 5.4.2.2.3, uses a three years wind (wind pressure 58%
of maximum pressure - QWc, QWi) for clearance calculations. The swing out
angle of the insulator string shall be calculated with
Q 0.5 QWi
arctan Wc
r QGc 0.5 QGi
where:
5413A08/FICHT-7269867-v13 26
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The insulator set swing angle may be also determined according to EPRI
Publication Transmission Line Reference Book 345 kV and above, second
edition 1987 and recommended by CIGRE SC22, WG 06 Appendix 11.1
Computation of swing angle distribution, Diagram A11.1.3.
The maximum sag for shall be used for the defined phase span (maximum
span). Li is the insulator string length of the I string. The factors k are
defined in EN 50341-3-4
for horizontal clearance 0.62
for vertical clearance 0.75 .
The sag of the earthwires or ISWER under every day temperature (25C)
shall be 5 % less than the sag of conductor for the nominal span.
The maximum and minimum conductor sags shall be calculated under still
air condition, for the conductor maximum and minimum temperatures, as
indicated in Technical Schedules.
5413A08/FICHT-7269867-v13 27
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The Contractor shall indicate in his bid the total creep which he will consid-
er after ten years operation and shall base his bid on the assumption that this
creep will be compensated by increasing the initial conductor tension
accordingly.
Wind Loads
The wind loads on the line equipment and tower shall be calculated based
on the reference wind speed factored for the respective height above ground
in accordance to EN 50341-1, chapter 4.2.2.1.6:
5413A08/FICHT-7269867-v13 28
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The tensions in the ISWER shall be such that the sag at everyday stress is
5 % less than that of the conductors calculated for the basic span.
The conductor / ISWER tension shall not exceed 18% of the ultimate
conductor tension for every day conditions.
5413A08/FICHT-7269867-v13 29
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Load Cases
The loading cases to be considered for the design of the line supports and of
their foundations are normal working cases and exceptional cases, as
follows:
5413A08/FICHT-7269867-v13 30
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Deadweights Deadweights
Wind on tower, accesso- Reduction of conductor or
Dead End ries and conductors earthwire/ ISWER tension
Conductor tensions under under wind condition by
Special Branch - wind load condition acting 100 % acting at any one
Off on one side attachment point
5413A08/FICHT-7269867-v13 31
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
For compression loading cases, the partial safety factor for the tower dead
weight is to be considered G = 1,1. In case of uplift loads for crossarms and
foundations, this factor shall be taken as G = 0,9.
Strength Factors
Based on the recommended failure sequence of structure components, the
following structure partial factors (M) for material strength are to be
applied:
The input data shall indicate all loads and their manners of application
including the determination of wind load on tower. Wind load on towers
shall be applied at each panel point along the height of the towers.
5413A08/FICHT-7269867-v13 32
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Name and version of the computer software and standards applied for the
structural analysis
Detail calculation of loads
Loading tree schemes
Outline drawing of tower model for the structural analysis, showing the
individual modeling elements (e.g. beams, trusses, stabilizers) including
joints (nodes)
Label and joint degree of freedom
Tower outline drawings of all 4 faces showing the joint labels (Auto-
CAD.dwg)
Three-dimensional coordinates of all tower joints in electronic format.
Total stresses in each member for each load case and the critical case
The effective slenderness ratio, calculated capacity and ratio of maxi-
mum total stress to calculated capacity for each member and connection
Size and type of steel for each member and number of bolts required for
its connection
The calculated weight of the complete galvanized tower
The compression and uplift reactions and corresponding horizontal
shears at each leg of all towers for all loading cases, for foundation calcu-
lation
Identifying the corresponding maximum load value decisive for design-
ing the foundation and outlining what partial load factor is included or
excluded
and on a drawing the scaled outline of the tower with all redundant, bracing
members and their sizes completely dimensioned in compliance with all
clearance requirements (clearance diagram).
The ultimate stresses for the different stress categories shall be taken from
EN 50341-1, Annex J (Lattice Steel Supports):
Bolted Connections:
Bolts in bearing Fu d t
5413A08/FICHT-7269867-v13 33
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
In computing the net section for tension members, the diameter of the bolt
hole shall be taken as 2.0mm greater than the nominal diameter of the bolt.
The determination of the net section area shall be as specified in the EN
50341-1, Annex J (Lattice Steel Supports).
Remark: The minimum connected leg of the angle section shall be such
that the bolt head or nut does not bear on the fillet.
Tower structures
The tower structure shall be modeled as a fully triangulated system. The
same goes for the secondary bracing.
Stubs suitable for the foundation types and for legs of the tower types are
part of the scope and templates for the alignment of the stubs shall be
provided.
5413A08/FICHT-7269867-v13 34
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
For the HA/DE towers having line deviation angles of 60 and more,
rectangular crossarms may be used so that live metal clearances are main-
tained with or without the use of jumper suspension insulator strings.
Connections
The tower structures shall be of the bolted type. Due to the danger of
embrittlement, welding shall be avoided as far as possible and have to be
approved by the Employer/ Employers Representative. Bolted connections
shall consist of metric threaded bolts together with a flat washer, a spring
washer and the nut. Rivets shall not be used.
The bolt length and washer thickness shall accommodate, that no threads
shall be located within the shear plane of the members/ plates being con-
nected maintaining the following bolt end projection after tightening the
nut: minimum projection of 2 treads and maximal 10 mm from the end of
nut.
The Contractor shall supply the net quantities plus 5 % of all permanent
tower bolts, nuts and other similar items and materials required for installa-
tion of the works at the site. Quantities of such bolts, nuts, etc., which are
surplus after the installation of the equipment has been completed shall
become spare parts and shall be wrapped, marked and handed over to the
Employer.
5413A08/FICHT-7269867-v13 35
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
For structural connections, one bolt size is preferred. The minimum diame-
ter and number of bolts at each connection for stressed members shall be as
follows:
Diameter: 16 mm
Number of bolts: 1
All nuts, washers and bolts shall be hot dip galvanized. Threads before
galvanizing shall be coarse threads. There shall be no excess of galvanizing
at the root of the thread and nuts shall turn easily on the complete bolts
without excessive looseness.
Bolts and nuts shall be hexagonal and dimensioned adequate to develop full
strength. The bearing faces shall be perpendicular to the axis of threads, free
of burns and projections and shall have chamfered corners.
B1.4.4.3.8 Detailing
General
Tower dimensions, framing, member sizes and length, number, size and
length of bolts, thickness of each filler, detailed dimensions of gusset plates
and other necessary details to fabricate each piece shall be shown on the
approved detailed drawings. No change shall be made without the written
approval of the Employer/ Employers Representative.
All bracing members shall be in one piece where practicable. All double
diagonal bracing members shall be connected at their point of intersection
by at least one bolt.
The angle included between any two connecting stressed members shall not
be less than 15.
5413A08/FICHT-7269867-v13 36
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The angle included between diagonal members and main members for the
HA/DE and TP towers shall not be less than 25.
Stubs shall be provided with suitable holes for connection to the standard
grounding system.
The lowest bolt hole in the stub for connection of the main bracing member
shall be 50mm above the foundation concrete level.
Drawings
All members and plates shall be designed on drawings, the Contractor shall
endeavor to use as few designations as possible, and each member of
identical size and detail shall have the same designation, regardless of its
position in the structure.
A bill of materials shall be submitted containing the size, length and galva-
nized weight of each member and the total weights of body, body extension
and foundation stub conforming to the detailed drawings approved. It shall
also include the number of bolts, nuts, washers and attachment devices per
structure.
Joints
All joints shall be such that eccentricities are kept as small as practicable.
Profile thickness variation resulting in gapes 2 mm between members at
connecting points or composed members or bolted diagonal intersecting
points shall be filled by galvanized or stainless steel made packing or shims
of appropriate thickness. For all bolts in tapered flanges beveled washers
shall be furnished.
Gusset plates, where used, shall be designed by the Contractor and shall be
in accordance with the relevant standards.
Bolt spacing and edge distance from the centre of bolt hole, in mm, for
double circuit towers shall be as follows:
5413A08/FICHT-7269867-v13 37
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Tolerances within the bolt group 1 mm for the end and edge distances as
well as distances between holes.
Step bolts
Each tower shall be provided with step bolts of an approved type on two
diagonally opposite legs spaced alternately on the angle flanges at not more
than 380 mm between centers, starting immediately above the anti-climbing
device and continuing to each earthwire. The minimum diameter of the step
bolts shall be 16 mm. Step bolts shall not be used as connection bolts.
Holes for removable step bolts below the anti-climbing guards shall be
provided at not more than 380 mm between centers on the legs to which the
permanent step bolts are fitted.
Attachment devices
Attachment devices shall be suitably furnished on all crossarms to suspend
and to terminate insulator strings or earthwire assemblies. Provisions shall
be made to fix the OPPC-joint units at the earthwire crossarms of towers
used in Lot 3. The attachment points shall be designed in accordance with
the requirements of this technical requirements and the calculation shall be
submitted together with the structural analysis of the tower.
Tower signs
5413A08/FICHT-7269867-v13 38
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The Contractor shall furnish all materials for tower signs including all bolts,
nuts, washers, brass eyelets fitted with the holes and supporting structures, if
required, for attaching signs to the structure as per the structure list.
a) Airborne plates
On each tension and every tenth suspension tower an airborne observa-
tion number plate shall be provided. The tower number shall be cut
from the sheet metal in black coating, with a letter height of min.
450 mm. The plate background shall be yellow. The plates shall be in-
stalled, either on the top crossarm or on the earthwire peak, in a position
that is easily recognizable from the air.
c) Phase plates
Phase plates shall show the letters R, Y and B, in black color, on
red, yellow and blue background, respectively. One set of three phase
plates shall be installed above the anti-climbing guards at every tower.
d) Danger plates
Danger plates shall feature black symbols on a white background. They
shall comprise a skull with crossed bones, as well as lightning arrows.
The text DANGER shall be boldly written in both English and local
languages. The voltage shall be shown, as well. Danger plates shall be
attached above the anti-climbing guards at every tower.
e) Number plate
The tower number plate (1 No.) shall show the tower number in black
letters, on a white background. The figures height shall be 150 mm. The
number plate shall be attached above the anti-climbing guards at every
tower.
Anti-climbing devices
Each tower shall be fitted with an approved anti-climbing device with gates
which shall provide climbing facilities for use by authorized personnel. The
height of the anti-climbing device above heighest ground level of tower
5413A08/FICHT-7269867-v13 39
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Bird guards
Tower members positioned above or near insulator strings shall be fitted
with galvanized steel needle strips, effectively preventing birds from sitting
in these locations. The strips shall extend horizontally enough beyond the
protected location and shall be applied to all surfaces a bird can sit on. The
bird guard measures have particularly to be applied on the insulator strings
of the ISWER. Where needles are projecting from cross arm contour
towards live parts, the tower clearance diagram shall consider the height of
the needles.
B1.4.4.4 Fabrication
B1.4.4.4.1 Workmanship
Fabrication of materials shall be in accordance with the state of art and as
specified. Fabrication shall not commence until approval of drawings and
completion of successful tower tests, unless otherwise directed by the
Employer/ Employers Representative.
All identical pieces bearing the same erection number must be exactly
interchangeable with each other and interchangeable in their relative
position in all structures of which they form a part.
The Contractor shall be responsible for the correct fitting of all parts. He
shall replace, free of charge, any defective material discovered during
5413A08/FICHT-7269867-v13 40
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
erection, and pay all costs of field corrections for such replacement.
All parts of the structure shall be neatly finished and free from kinks, twists
or bends. The fabrication shall be in strict accordance with the shop draw-
ings prepared by the Contractor and approved by the Employer/ Employ-
ers Representative.
The use of a burning torch is permissible for cutting members provided all
irregular edges are trimmed smoothly before galvanizing. Stresses shall not
be transmitted into the metal through a burned surface. The material
adjacent to a burned surface for a distance equal to the thickness of the
material shall not be considered a part of the net section for tension
members. The use of a burning torch for cutting bolt holes will not be
allowed.
All members shall be cut to jig and all holes shall be punched or drilled to
jig.
Holes are to be punched with racks and jigs employed to ensure accuracy
throughout. The punches and dies for this work must be maintained suffi-
ciently sharp so as to produce clean round holes normal to the plane of
material. Holes shall be free of burrs, folds and depressed, upset, or ragged
edges.
Bolt holes shall be drilled full size and at right angles to the surface of the
steel, accurately spaced and true to line, pitch gauge and edge distance. Any
member having holes or cut more than 1 mm from correct position will be
subject to rejection. No welding, filling or plugging will be permitted unless
otherwise approved by the Employer/ Employers Representative.
5413A08/FICHT-7269867-v13 41
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The diameter of bolt holes shall be 13.5, 17.5, 21.5 and 26 mm for 12, 16,
20 and 24 mm bolt diameter respectively, or for larger sizes not greater than
2.0mm greater than the bolt diameter.
All parts shall be carefully cut and holes accurately located so that when the
members are in position the holes will be truly opposite each other before
being bolted up. Drifting of holes will not be allowed.
Bolts shall pass freely through matching holes in a direction at 90 to the
member being connected.
B1.4.4.4.4 Bending
All bending of high-strength structural steel must be done hot. Bends of a
difficult nature on structural steel shall be done hot, but otherwise cold
bending can be employed.
Hot bends shall be left for slow cooling in air. Where bends are near splices,
the upset metal shall be forged smoothly for full bearing on the contact
surface.
All bends shall be finished, free from waves, folds, or localized reduction in
sectional area shall not exceed 3 % of the nominal area. Member length
variation shall not exceed the tolerances shown below to its projected
straight length.
A member bent in error with respect to the location of a bend line shall be
rejected.
B1.4.4.4.5 Welding
All welding shall be performed in accordance with the Standard EN 1993-1-
1 or equivalent. A shielded arc-welding process shall be used. All welds
shall be made in such a manner that residual shrinkage stresses will be
reduced to a minimum. If not previously qualified, the welding process and
the welders employed in performing the work covered by the Contract
5413A08/FICHT-7269867-v13 42
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.4.4.7 Marking
All individual pieces shall be marked with the correct designations shown
on the detailed drawings approved and shall indicate the type of towers also.
Markings shall be done by stamping the marks into the metal before galva-
nizing and details shall be clearly legible after galvanizing. The figures and
letters shall be minimum 12mm in height.
Galvanizing
a) Cleaning
After fabrication has been completed and accepted, all materials shall be
clear of rust, loose scale, dirt, oil, grease and other foreign substances that
may affect the uniformity of the coating.
5413A08/FICHT-7269867-v13 43
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
b) Galvanizing
All defects of the steel surface including cracks, surface laminations, laps
and folds shall be removed. All drilling, cutting, welding, forming and final
fabrication of unit members and assemblies shall be completed before the
structures are galvanized.
The preparation for galvanizing and the galvanizing itself shall not adverse-
ly affect the mechanical properties of the coated materials.
It is essential that the shape of steel members and assemblies which are to
be hot-dip galvanized shall conform to the requirements of the process.
On removal from the galvanizing bath, the resultant coating shall be smooth,
continuous, free from gross surface imperfections such as bare spots, lumps,
blisters and inclusions of flux, ash or dross. Excessively thick or brittle
coatings due to high levels of silicon or phosphorus in the steel, which may
result in an increased risk of coating damage and/or other features that make
the final product non-fit-for-purpose shall be cause for rejection.
Bolts, nuts and washers including the threaded portions shall be hot-dip
galvanized and subsequently centrifuged. The threads shall be cleaned of all
surpluses on packing, clear of the ground and stored away from all materials
that might stain or corrode the galvanizing. Dies shall not be used for
cleaning threads other than on nuts. Nuts shall be galvanized and tapped 0.4
mm oversize and threads shall be oiled after galvanization to permit the nuts
to be finger-turned on the bolt for the full depth of the nut.
5413A08/FICHT-7269867-v13 44
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Protected slings shall be used for off-loading and erection. Galvanized work
to be stored at the works or on site shall be stacked so as to provide ade-
quate ventilation to all surfaces to avoid wet storage staining (white rust).
Spacers between individual members or plates being stacked shall be used.
Small areas of the galvanized coating damaged in any way shall be restored
by:
Cleaning the area of any weld slag and thorough wire brushing to give a
metallic clean surface.
The application of two coats of zinc powder-rich paint, or the application
of a low melting point zinc alloy repair rod or powder to the damaged
area, which is heated to 300C.
c) Minor repair
Under this Contract minor repairs are defined as permitted repairs undertak-
en at site or outside the contractual manufacturing plant at galvanized
(finished) steel parts. All finished steel parts which exceeds the criteria
shown below shall be replaced by new, correct components as per approved
drawings free of charge.
5413A08/FICHT-7269867-v13 45
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The test loads shall be the design loads multiplied by the corresponding
partial safety factors and by the material factor for steel member sections.
a) Tower
The tower shall be fabricated according to the detailed drawings ap-
proved in a manner as close to final production procedures as practica-
ble. The tower shall be complete in every detail. Markings for test
tower members shall be prefixed with the letter "T".
b) Erection
The tower shall be erected on a rigid foundation using the specified
tower bolts and nuts tightened to the specified torque.
5413A08/FICHT-7269867-v13 46
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
c) Rigging
The Contractor shall submit for approval diagrams showing the pro-
posed methods of applying loads and deflection measuring.
d) Loading
Test loads shall be the design working loads multiplied by correspond-
ing partial safety factors for loads and materials. All test loads corre-
sponding to conductor and earthwire loading shall be applied directly to
the regular attachment details provided for those loads. Test wind loads
equivalent to wind loads on the tower shall be applied where convenient
and in such a manner that the locations and the summations of applied
load and overturning moment are as close as possible to the actual con-
ditions, as designed.
The first load case in a Heavy Angle tower testing program should be
the one that produces the largest leg force. If subsequent load cases also
give sufficiently high leg force, tower bolts at major joints must be
loosened and re-tightened prior to the test to minimize residual loads.
e) Loading program
The Contractor shall program the tests for the decisive load cases in or-
der to most favorably demonstrate that the towers will carry all design
loads and conditions specified in the loading diagrams.
f) Deflection measurements
Deflections shall be recorded at the beginning and end of each loading
period to provide longitudinal and transverse deflections at the tower
top, at the elevation of the crossarms and at least at one intermediate
point of tower body.
g) Load tests
The initially applied loads and the increment of loading shall be 25% of
the working loads given in the loading diagrams. However, the incre-
ments of load shall be in accordance with IEC 60652. Each load incre-
ment shall be maintained for not less than two minutes except that
under full design load, the period of five minutes shall be maintained
and during this time there shall be no slacking off or adjustment of the
loads. Should it become necessary to adjust the loading, the two or five
minutes period shall start after the loading is stabilized and constant.
All test loads shall be removed completely before the loads for testing
under different loading conditions are applied. The ultimate normal
conditions or the most critical load case shall be the last test to be car-
ried out in the presence of the Employer/ Employers Representative.
5413A08/FICHT-7269867-v13 47
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Load Cell Calibration shall be carried out before and after each test or
series of tests in the presence of the Employer/ Employers Representa-
tive.
h) Destruction test
After the successful completion of the ultimate load tests, the tower
shall be further tested to destruction by increasing the loads for a given
loading case, as specified/approved by the Employer/ Employers Rep-
resentative. The load increments shall not exceed 5 % of the ultimate
design load. Each load increment shall be held at least five minutes
while deflections are being recorded. The maximum test load may be
limited to 1.3 times the ultimate design load or the test stations load
capacity.
The expenses associated with re-design and re-test due to a defect in the
Contractor's work shall be borne by the Contractor.
j) Material tests
Steel materials used for test towers shall be subject to tension or bend
test in accordance with the relevant material standard. Tests shall be
performed by the Contractor at no additional cost to the Employer. The
test specimens shall be selected as follows:
i) Four sets selected from the destruction members of each test tower.
ii) Four sets selected from the undisturbed members of each test
tower.
iii) Two sets of bolts and nuts selected from the adjoining destruction
members of each test tower.
iv) Two sets of bolts and nuts selected at random from each test tower.
k) Reports
The Contractor shall furnish certified copies of full reports of all tower
and material tests, the calibration of the dynamometers or gauges, in-
cluding clear photographs of the test set-ups and nature of all failures,
diagrams showing deflection of towers at each interval of loading, de-
tailed diagrams showing the manner in which all the loads were applied
and deflection records.
B1.4.4.6 Packing
The whole of the goods shall be packed where necessary in non-returnable
cases or on non-returnable drums or otherwise prepared for overseas
shipment in a manner suitable to withstand rough handling without sustain-
5413A08/FICHT-7269867-v13 48
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
ing damage. All packing materials shall remain the property of the Employ-
er.
Bolts and nuts shall be crated for shipment. Crating together of components
of dissimilar metals is unacceptable.
If light parts are fastened to the sides of a case, hoop iron straps secured by
screws shall be used for the purpose. Nails driven in and bent over shall not
be permitted.
Where bolts are used, large washers shall be fitted under the head and nut to
distribute the pressure and the timber shall be strengthened by means of a
pad.
5413A08/FICHT-7269867-v13 49
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Waterproof paper and felt linings shall overlap at seams at least 13mm and
the seams secured together in an approved manner, but the enclosure shall
be provided with screened openings to obtain ventilation.
All cases, packages, etc., shall be clearly marked on the outside to indicate
the total weight, to show where the weight is bearing and the correct posi-
tion of the slings and shall bear an identification mark relating them to the
appropriate shipping documents.
B1.4.4.7.1 General
The Contractor shall supply a detailed Quality Assurance Procedure includ-
ing an Inspection and Test Plan (ITP) which shall be submitted to the
Employer for approval. The Contractor shall be responsible for performing
all tests and inspections required during the production of the towers.
5413A08/FICHT-7269867-v13 50
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
required quality and to complete the works nor prejudice or affect the rights
of the Employer/ Employers Representative set forth under this contract.
The Contractor shall identify all materials, including bolts and nuts used in
the project on the appropriate mill test reports and/or material certificates,
and shall furnish the mill test reports and/or certificates to the Employer/
Employers Representative for approval.
The Contractor shall make dimensional checks of all materials for conformi-
ty to the relevant material standard. The Contractor shall make a visual
inspection of all materials before and after galvanizing. Size of test "lot" and
number of tests shall be in accordance with appropriate standards.
5413A08/FICHT-7269867-v13 51
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
number of bolts need be used to hold members in their true position one to
another.
B1.4.5 Foundations
B1.4.5.1 General
The Contractor has to choose up-to-date methods and equipment to ensure
that the design and erection of foundations will be in accordance with
relevant internationally recognized standards.
The works shall be designed and executed with due regard to the need for
inspection, cleaning and repair works, and service for prolonged periods of
operation requiring minimum of inspection, adjustment and repair works.
All materials shall be new and of the best quality, suitable for working
under the climatic conditions without undue distortion or deterioration or
the occurrence of undue stresses in any part, such as to affect stability safety
as well as the efficiency and reliability of the works.
5413A08/FICHT-7269867-v13 52
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
competent workmanship
full serviceability in unrestricted continuous operation
observance of the technical requirements.
B1.4.5.2.1 General
The Contractor shall be responsible at his own cost for ascertaining that the
foundations to be employed are suitable for the sub-soils encountered at
each tower and support site at an early stage of the Contract.
Detailed soil investigations shall be carried out by the Contractor along the
line route as a prerequisite for planning of the foundations. The extent of the
investigations shall be such as to permit the satisfactory determination of all
necessary sub-soil characteristics, to exclude any unacceptable settlement
and to determine reliable type, size and execution of foundations. For
classifying the soil, the Contractor shall carry out investigations by test pits
or auger borings and penetration tests at all line angle point locations and
additionally, at sufficient locations between the angle points depending on
the terrain and geology, but not more than 4 km apart. These investigations
have to be completed before the design works start. The soil investigation
report shall also contain details about the soils earthing resistivity.
After the tower locations have been pegged out, each tower location shall be
investigated by penetration test except where soundings have been under-
taken during the initial investigations by the Contractor. Reference is also
made to the General Technical Requirements.
B1.4.5.2.2 Standards
The tests are to be carried out in conformity with international standards
EN, DIN, BS, IEEE or equivalent by a well experienced and reputable
Institute to be named by the Contractor and approved by the Employer/
Employers Representative. Other standards are subject to the approval prior
to the performance of the laboratory tests.
The following standards are important and acceptable but the list is consid-
ered to be incomplete:
5413A08/FICHT-7269867-v13 53
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.5.2.3 Investigations
The geotechnical investigation shall be based on in-situ testing for the
determination of the soil strength and visual tactile examination of disturbed
samples for the determination of soil classification.
5413A08/FICHT-7269867-v13 54
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The index parameters for soil classification and its correlation to the speci-
fied engineering properties shall be based on the in-situ test results. The SPT
provide soil samples for classification beside of the penetration resistance
for correlation with the soil properties. These correlations are generally
more reliable for compact granular soil than for soft cohesive soils. The
DPL provides dynamic penetration resistance only which are generally more
reliable for semi-solid to loose fine soils than for hard or very soft soils. The
CPT provides static penetration resistance and local friction only which are
generally more reliable for medium stiff to very soft cohesive soils than for
compact granular soils. Accordingly requires the DPL and CPT test com-
plementary auger borings or test pits for obtaining subsoil samples and its
classification.
For all soil investigation locations, the contractor shall give clear infor-
mation, in addition to boring results for the following local conditions:
surface condition and inclination of the ground in the area of the future
foundations
inclination of cracks and fissures in the rock and their stratification and
judgment about the global stability
relevant inclination of the ground surface in the vicinity of the future
tower foundations if sliding or rock fall hazard is expected
possible flooding or scour (wash out) action possible around foundations
during periods of heavy water flow
data about the maximum groundwater level for all tower sites. Conse-
quently, the investigations shall preferably be undertaken towards the end
of rainy season. Otherwise inquiries and assumptions on the max. subsoil
water level shall be made.
At all soil investigation locations the in-situ testing shall be advanced to the
following limits:
5413A08/FICHT-7269867-v13 55
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Every test pit or auger boring or SPT sampling at -1m, -3m, -5m (for test
pits -4m) depth to take each one disturbed soil sample.
The Contractor shall order Laboratory Tests to determine the necessary soil
mechanic parameters for the foundation design of towers. The index proper-
ties to be determined and observations to be provided are:
The Contractor shall name a professional soil mechanics expert and founda-
tion engineering expert. The expert shall supervise the boring works.
B1.4.5.2.4 Procedures
a) Execution of Borings
For the drilling in non-cohesive soil, the Contractor shall supply a bore
equipment with a diameter of at least 150mm. The equipment shall allow
the additional execution of Standard Penetration Test (SPT) and disturbed
sampling for instance by using piston samplers. During boring, in case hard
rock is encountered, it shall be continued with rock drilling to establish
continuity of rock strata.
For drilling work in hard rocky soils a double tube core barrel of between
7,5 cm to 12,5 cm inside diameter shall be used exclusively, provided that
this kind of boring can be continued to the final bottom of the bore hole in
question. Depending on the rock quality a core sample recovery rate of
90 % should be achieved.
Beyond this, the Contractor may choose for his own convenience the type of
equipment and accessories to be used at each individual bore hole and
depth, provided that in the Employers/ Employers Representatives
opinion the equipment chosen is suitable for the drilling. The Contractor
may also choose the initial and intermediate diameters of each bore hole for
5413A08/FICHT-7269867-v13 56
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
his own convenience, provided that he will secure the before mentioned
minimum acceptable size of core.
Adequate casing has to be used to ensure the stability of the bore hole. The
Contractor will not be entitled to any compensation or additional payment
for casing.
b) Sampling
Undisturbed samples if required shall be of 100mm diameter and 450mm
length. Samples shall be collected in such a manner that the structure of the
soil and its moisture content are not changed.
Disturbed soil samples shall be collected in bore holes and test pits at
regular intervals. Jar samples weighing approximately 1kg shall be collected
in bore holes and test pits and SPT at 1m intervals starting from a depth of
1m below ground level and at every identifiable change of strata to supple-
ment the boring records.
c) Bore Logs
Detailed bore logs/field books must be kept for all borings. They shall
include all pertinent data and results and all observations, measurements or
tests as may be directed by the Employer/ Employers Representative.
B1.4.5.2.5 Report
Field reports have to be handed over to the Employer/ Employers Repre-
sentative at site including bore-logs protocols with all pertinent data, SPT,
DPL, CPT sounding diagrams, ground water locations, core drilling dia-
grams, test pit logs as well as readings within the agreed time after comple-
tion of the corresponding work.
5413A08/FICHT-7269867-v13 57
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.5.3.1 General
The foundations shall be designed by the Contractor on the basis of accept-
ed codes of practice, the relevant literature or methods which have been
used with satisfactory practical experience by the Contractor, and agreed by
the Employer/ Employers Representative. General the design approach
shall follow the recommendations of EN 1997-1-1 (Geotechnical Design,
Part1: General Rules), EN 1992-1-1 and EN 1992-3 (Design of Concrete
Structures, Part3: Concrete Foundations). But also other accepted standards
may be applied like EN 50341-3-4 (German National Normative Aspects),
clause 8 or BS 8004 and BS 8110.
An overview on foundation design practice and most common tower footing
types used in practice are presented in CIGRE Recommendation 206 of
August 2002.
5413A08/FICHT-7269867-v13 58
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Similarly, maximum foundation shear force from any load combination for
the uplift leg will be assumed to act simultaneously with the maximum
foundation uplift force. If a limit state method is used the obtained tower
reactions forces shall include the partial safety factors for the loads and the
resultant reactions shall be used for foundation design. The partial safety
factors for material and soil are given in the Technical Schedules.
Out of all the load cases the maximum tower footing reaction forces shall be
applied for designing the foundations taking into account possible liquefac-
tion effects of loose fine uniform graded sands in ground water. Transition
zones of variable ground water table shall be assumed of being completely
submerged.
The Contractor will be responsible for the suitability of the foundation types
applied for the existing underground conditions. Any information given in
these technical requirements in relation to the foundation design is for
bidding purpose only. For the final foundation design the Contractor has to
perform the required soil investigations and has to base his design calcula-
tions on the detailed information obtained. The Contractor is requested to
quote firm unit rates for the different types of foundations and towers as set
out in the Price Schedules. These unit rates will be considered as flat rates
covering all foundation costs for any type of soil encountered along the line
and no adjustment of the rates will be permitted.
5413A08/FICHT-7269867-v13 59
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
5413A08/FICHT-7269867-v13 60
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
soils. The equipments characteristic data and its reliability of results are
outlined in the previous section of Soil Investigation.
Hard rock is defined to consist of hard material (mineral composition) of
high geological age, which is only slightly weathered. It can contain joints
and fissures but shall attain an uniaxial compressive strength > 5 MN/m as
well as an RQD > 0.6 at the same time (Rock Quality Designation > 60 %,
i.e. the total length of recovered core consisting of pieces of at least 10 cm
length shall be more than 60 % of the drill run length).
5413A08/FICHT-7269867-v13 61
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The pad, raft and slab thickness shall be d 0,1 times the foundation
base width (d 0,1B) but not smaller than the minimum thickness of
d 0,3 m by vertical edge and of d 0,4 m by undercut edge.
The spacing between piles within one group of foundation type E must
be sufficiently large, so that no damaging or displacing should occur.
Driven piles orientated in the same direction shall have a minimum axis
distance of e = 3 times max. a (where max. a = maximum side dimension
or diameter or pile). The clear distance should, however, be not less than
1.0 m, for driven piles. For bored piles the above is only valid inside the
bearing horizon.
The work includes all work for the execution of piles as well as the work
required for test piles, pile load tests and working piles (including logs
and reports). The pile bearing capacity and settlement behavior shall be
checked by quality control tests (preferably by pulling tests):
up to 10 piles 1 test
up to 30 piles 2 tests
more than 30 piles 1 more test for every further 30 piles
Chimney extension above ground to lift the steel structure (by 0,5 m
and 1,0 m) when the flood level exceeds 0,2 m above terrain around
the tower location
Connection (tie) beams below ground when the tower span exceeds
500m and/or the terrain slope of tower location exceeds 1:2
Minimum lateral soil zone shall extend two times the depth (2T)
horizontally from the outer most foundation edge to steep embank-
ments or cliffs. If the adjacent area to the footings is prone to erosion
or slope instability or have insufficient clearance, protective measures
shall be put in place such as installation of stone gabions or retaining
walls or shifting the tower location.
The cost for the specified secondary upper pad and edge undercut shall be
included in the unit price of the respective foundation class.
Grillage foundations shall explicitly not be applied in this project due to the
partly aggressive soil conditions and the large foundation uplift loads which
cannot be transferred safely and economically into the subsoil.
The type of foundations specified above and shown in the attached drawings
are for tender purpose and may be altered for construction by the Contractor
subject to correlation results obtained from ultimate load foundation tests. It
can be select also other type and alternative solutions for the foundations
which are considered more economical or more adequate for the effective
soil and topographical conditions of the OHL.
no extra cost for changes compared to the agreed contract unit price of
the respective soil class
identical or higher safety in all aspects for the proposed foundation
type(s)
5413A08/FICHT-7269867-v13 63
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
All relevant calculations and checks are to be established with the following
as minimum:
All foundations on slopes greater than 1:4 shall be checked for stability
against rotation where appropriate. Due consideration shall be given to the
increased uphill lateral loading of the soil and the decrease in downhill
resistance provided by the soil, when compared to foundations installed on
level ground. Due consideration shall also be taken of any decrease in the
uplift resistance of the foundation. Where appropriate decrease in soil
bearing resistance shall also be considered.
A selection of the foundation type shall be made for each tower to suit its
particular site conditions, and the final tower list prepared there-from. The
tower foundation list shall be submitted for approval to the Employer/
Employers Representative. The decision of the Employer/ Employers
Representative which type of foundation shall be employed at a given
location shall then be final without change of Contract Price.
5413A08/FICHT-7269867-v13 64
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Only one foundation type applying the maximum loads resulting from the
maximum body (+8/+12/+16 m), leg (+3 m) and cap (+1 m) extension shall
be designed for each soil class and tower type.
For the resistance to uplift loads, the concrete foundation shall be assumed
to mobilize the frustum of an inverted earth cone having an angle of not
more than 35 to the vertical from the foundation base. The net weight of
the soil shall be taken as specified or when confirmed from the soil investi-
gation report. Alternative methods of design can be adopted, subject to
approval of the Employer/ Employers Representative.
The utilization of standard concrete (mixed in-situ, quality not higher than
C20/25 according to EN 206-1) is preferable since higher concrete classes
often fail to reach the specified design strength under power line site
conditions.
In the calculations and drawings, the Contractor has to state clearly whether
the calculations for pad & chimney foundations are made for "undercut
conditions" and pouring the concrete directly against the soil surface or for
"no undercut conditions" and pouring the concrete inside formwork.
Design method
The design philosophy shall principally be based on the limit state concept
applied in conjunction with the partial factor method. The concept of
differentiated partial material factors of foundation structure and foundation
geotechnic shall be applied as recommended by EN 50341-1.
Strength factors
Based on the recommended failure sequence of structure components, the
following structure partial factors (M) for material strength are to be applied
for the foundation design:
5413A08/FICHT-7269867-v13 65
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Stubs
Stubs for tower body and leg extensions shall be of the same design as that
for a standard height tower. Only one design of stub shall be permitted for
each type of tower, and shall not be bent or cranked.
The thickness of the stub legs shall not be less than the corresponding tower
leg member.
In addition to stubs of normal length, short stubs may be used, provided that
provision is made for the attachment of bolted cleats.
Chimney
Reinforced concrete chimneys shall be designed to withstand the maximum
resultant horizontal residual shear component, with due allowance given
where appropriate to resultant lateral (passive) earth pressure of the backfill
(assumed to increase linearly with depth).
To eliminate the need of muff concrete, the lowest bracing leg connection
shall not be less than 400 mm above nominal ground level.
Foundations for lattice steel tower legs with high hillside shear force, due to
certain combinations of unequal leg extensions may however differ from
those designed for level ground by the addition of extra reinforcement in the
chimney, and/or tie beams connecting the individual legs.
5413A08/FICHT-7269867-v13 66
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Caps
All concrete foundations shall be sloped off around the steel leg section and
smoothly finished to ensure water drainage away from the tower steel. The
foundation cap shall be monolithically casted having optimal bond with the
chimney part of the foundation. No concreting shall be commenced in any
portion of the work until the designed portion has been approved by the
Employer/ Employers Representative.
Concrete Cover
All structural steelwork and reinforcing including links and stirrups below
ground level shall be completely encased in concrete to ensure a minimum
cover of 50 mm. Such cover shall exist from the point of entry into the
concrete base to either 300 mm above final ground level, or to the top of the
concrete leg extension.
5413A08/FICHT-7269867-v13 67
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The tests shall be carried out and the results shall be submitted in a format in
accordance to IEC 61773 and Cigre Brochure No. 81.
The particular rates entered in the Price Schedules shall include the excava-
tion, pouring concrete and backfill for the foundation, the test operation, the
supply and removal of the testing equipment and any ancillary works which
are necessary for the test to be carried out. The Contractor should also
include in his testing rates the cost of breaking out the concrete and cutting
off the stub to a depth of not less than 700 mm below ground level after the
test has been concluded.
5413A08/FICHT-7269867-v13 68
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.6.1.1 Design
The Contractor shall carry out all works in skilled manner in compliance
with modern methods of engineering. In addition, the Contractor shall
conform to all applicable regulations regarding the manufacture and deliv-
ery of the goods and shall follow all instructions issued by the Employer/
Employers Representative.
Basic Standards
for the complete conductors ASTM B232
for the component wires
aluminum wires EN 60889
steel wires EN 50189
grease EN 50326
for conductor creep IEC 61395
If the Contractor wishes to base his bid on standards or codes other than
those specified e.g. such authoritative standards appropriate to the country
of manufacture, he may do so provided that he submits with his bid com-
plete data about the standards or codes applied and confirms in his bid that
such standards or codes meet, as a minimum, the requirements of the
designated standards. The Contractor shall submit with and as a part of his
bid a tabulated list of the differences between the standards or codes applied
and those designated herein.
The conductors shall be suitable for service in the specific climate with the
main characteristics as specified in the Technical Schedules. The conductors
shall be of design and construction as to ensure long service with high
economy and low maintenance costs. They shall be suitable in every respect
for continuous operation at nominal parameters as well as in transient
operating conditions.
All materials used under this contract shall be of the best quality and
workmanship shall be of the highest class throughout with the designs and
dimensions of all parts such that the stresses to which the conductors are
5413A08/FICHT-7269867-v13 69
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
subjected shall not render them liable to distortion or damage under the
most severe conditions encountered during installation as well as in service.
Special attention shall be paid to the conductor stranding process to ensure
the necessary tightness between different layers in order to avoid slippage or
relative movement of strands or cage formation during stringing.
In the event of any machinery used for conductor manufacture being used
for materials, other than aluminum, galvanized or aluminum clad steel, the
manufacturers shall furnish the Employer with a certificate stating that the
machinery has been thoroughly cleaned before use on aluminum, aluminum
alloy, galvanized or aluminum clad steel wire and that the conductor is free
from contamination.
The main design data and performances of the conductors are to be entered
by the bidders in the Technical Schedules and become part of the Contract.
All these data shall be proven by means of calculations and tests as speci-
fied. If the guaranteed values are not achieved, the Employer/ Employers
Representative may reject the said part of the goods at the Contractor's
expense. The Contractor shall submit certificates of analysis giving the
percentage and nature of aluminum impurities. The copper content shall not
exceed 0.04 %. If the electrical resistance per kilometer of conductor on any
drum exceeds the guaranteed resistance, the Employer/ Employers Repre-
sentative may then reject any drum found faulty in this respect.
5413A08/FICHT-7269867-v13 70
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The conductor shall have, within the adopted limit state design method, the
following partial safety factors:
The Bidder shall supply for the conductor stringing data (initial and final)
calculated for different line spans in a chart or tabular form, sag and ten-
sions for the temperatures between 10 - 85 C.
5413A08/FICHT-7269867-v13 71
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.6.2.1 Design
The 400 kV OHTL line will be equipped with two (2) earthwires. Both
earthwires are to be implemented either as normal earthwires (one a classi-
cal ACSR conductor, the other one a similar OPGW) or as Insulated Shield
Wire Earth Return (ISWER - one a classical ACSR conductor, the other one
a OPtical Phase Conductor (OPPC)) in Lot 3.
Basic Standards
for the complete conductors EN 50182
for the component wires
aluminum wires EN 60889
steel wires EN 50189
grease EN 50326
for conductor creep IEC 61395
If the Contractor wishes to base his bid on standards or codes other than
those specified e.g. such authoritative standards appropriate to the country
of manufacture, he may do so provided that he submits with his bid com-
plete data about the standards or codes applied and confirms in his bid that
such standards or codes meet, as a minimum, the requirements of the
designated standards. The Contractor shall submit with and as a part of his
bid a tabulated list of the differences between the standards or codes applied
and those designated herein.
The conductors shall be suitable for service in the specific climate with the
main characteristics as specified in the Technical Schedules. The conductors
shall be of design and construction as to ensure long service with high
economy and low maintenance costs. They shall be suitable in every respect
for continuous operation at nominal parameters as well as in transient
operating conditions.
All materials used under this contract shall be of the best quality and
workmanship shall be of the highest class throughout with the designs and
dimensions of all parts such that the stresses to which the conductors are
subjected shall not render them liable to distortion or damage under the
most severe conditions encountered during installation as well as in service.
5413A08/FICHT-7269867-v13 72
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
In the event of any machinery used for conductor manufacture being used
for materials, other than aluminum, galvanized or aluminum clad steel, the
manufacturers shall furnish the Employer with a certificate stating that the
machinery has been thoroughly cleaned before use on aluminum, aluminum
alloy, galvanized or aluminum clad steel wire and that the conductor is free
from contamination.
The main design data and performances of the conductors are to be entered
by the bidders in the Technical Schedules and become part of the Contract..
All these data shall be proven by means of calculations and tests as speci-
fied. If the guaranteed values are not achieved, the Employer/ Employers
Representative may reject the said part of the goods at the Contractor's
expense. The Contractor shall submit certificates of analysis giving the
percentage and nature of aluminum impurities. The copper content shall not
exceed 0.04 %. If the electrical resistance per kilometer of conductor on any
drum exceeds the guaranteed resistance, the Employer/ Employers Repre-
sentative may then reject any drum found faulty in this respect.
The earthwire/ ISWER will also be installed to protect the line against
lightning strikes and shall withstand the specified fault current without
suffering damage. It shall have the characteristics shown in the Technical
Schedule.
5413A08/FICHT-7269867-v13 73
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Line sections equipped with warning spheres on the earthwire / ISWER, the
nominal tension in the earthwire / ISWER and conductor as well as the
actual spans might be reduced as to offset the additional load imposed by
the warning balls achieving similar differential load conditions at the angle
towers compared to sections without warning spheres.
The earthwire / ISWER shall have, within the adopted limit state design
method, the following partial safety factors:
For the nominal span under every day condition, the final earthwire /
ISWER (normal ACSR) sag shall not exceed 95 % of the phase conductors
sag.
The Contractor shall supply for the earthwire / ISWER (normal ACSR)
stringing data (initial and final) calculated for different line spans in a chart
or tabular form, sag and tensions for the temperatures between 10 to 85 C.
5413A08/FICHT-7269867-v13 74
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The Bidder shall fully detail the composition of the optical fiber unit including
heat shielding material and maximum temperature rating of the materials.
Moisture ingress is not permitted into the optical fiber unit and Bidders are to
provide details as to how this is achieved.
Regarding the optical fibers, the OPGW/ OPPC shall have 48 fibers (24
fibers as per ITU-T G.652 plus 24 fibers as per ITU-T G.655).
The radius of the tightest curve into which the stressed and unstressed cable
may be bent during installation without having any adverse effect upon the
specified properties shall be less than twenty times the outer diameter of the
cable.
5413A08/FICHT-7269867-v13 75
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The OPGW/ OPPC shall be suitable for service in the specific climate with
the main characteristics as specified in the Technical Schedules. The main
design data and performances of the conductors are to be entered by the
bidders in the Technical Schedules and become part of the Contract. All
these data shall be proven by means of calculations and tests as specified. If
the guaranteed values are not achieved, the Employer/ Employers Repre-
sentative may reject the said part of the goods at the Contractor's expense.
The short circuit parameters are similar to that defined for earthwires. These
shall not cause breakage or deformation of any component of the cable.
The attenuation coefficient shall not rise to more than 0,05 dB/km above
that of the unloaded cable at a normal ambient temperature. Any increase in
attenuation shall be temporary and shall return to its original level within 15
minutes.
5413A08/FICHT-7269867-v13 76
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Basic Standards
optical fibers IEC 60793
ITU-T Recommendation G. 652
If the Contractor wishes to base his bid on standards or codes other than
those specified e.g. such authoritative standards appropriate to the country
of manufacture, he may do so provided that he submits with his bid com-
plete data about the standards or codes applied and confirms in his bid that
such standards or codes meet, as a minimum, the requirements of the
designated standards. The Contractor shall submit with and as a part of his
bid a tabulated list of the differences between the standards or codes applied
and those designated herein.
Manufacture
All materials used under this contract shall be of the best quality and
workmanship shall be of the highest class throughout with the designs and
dimensions of all parts such that the stresses to which the conductors are
subjected shall not render them liable to distortion or damage under the
most severe conditions encountered during installation as well as in service.
Special attention shall be paid to the conductor stranding process to ensure
the necessary tightness between different layers in order to avoid slippage or
relative movement of strands or cage formation during stringing.
5413A08/FICHT-7269867-v13 77
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
In the event of any machinery used for conductor manufacture being used
for materials, other than aluminum, galvanized or aluminum clad steel, the
manufacturers shall furnish the Employer with a certificate stating that the
machinery has been thoroughly cleaned before use on aluminum, aluminum
alloy, galvanized or aluminum clad steel wire and that the conductor is free
from contamination.
The optical core design shall prevent longitudinal fiber transport in the loose
tubes.
The stainless steel tube shall consist of a welded or extruded metallic tube.
5413A08/FICHT-7269867-v13 78
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The tube shall not deform and shall continue to fulfill its function when
subjected to the following:
The electrical, thermal and mechanical loads stated in this generic
specification
The high-frequency (>1 Hz) and low-frequency (<1 Hz) vibrations
occurring in the high-voltage line
Use with the prescribed suspension and tensioning equipment and
vibration dampers
All regular and permissible conductor assembly processes
All the cabled fibers shall be of the same type and technology.
Back-scatter pattern:
The optical fibers in any length of cable shall not be spliced and shall be
homogeneous in quality. The back-scatter pattern shall therefore not dis-
play any reflections or irregularities of more than 0,10 dB, before or after
cable installation, whereby the maximum detected pulse length shall be
50 ns at the -10 dB pulse level and a resolution of 1 meter.
c) Cut-off wavelength
The cut-off wavelength (cc) of the processed optical fiber shall be less than
1260 nm (cabled fiber deployment).
d) Filling compound
The filling compound shall:
be a silicone-free, electrically non-conductive, homogeneous gel
prevent formation of gaseous hydrogen within the loose tube
not be harmful to any component of the cable
be dermatological safe
shall not inhibit movement of the fiber within the tubes
be free of air entrapments
remain pliable and maintain its water resistance over the operating
temperature range and over the OPGW/ OPPC service life.
5413A08/FICHT-7269867-v13 79
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
e) Strain margin
The optical core design shall be such that the specified load combinations
will never result in an excess of the strain margin. The strain margin shall be
greater than the sum of:
the cable elongation due to the load combination (the withstand short
circuit current, at 200 oC with the OPGW/ OPPC stressed at EDS), or the
cable elongation at 50 % RTS and 20 oC.
OPGW/ OPPC creep determined for duration of 10 years, in acc. to IEC
61395.
residual cable elongations determined while applying the EDS tensile
load.
for the stranded loose tube design, a reserve of at least 0,2 % shall be
applied.
Fiber Design
a) General
The optical fiber phase conductor (OPGW/ OPPC) and the optical fiber
underground cable (OPUG - see paragraph below) shall have 48 fibers (24
fibers as per ITU-T G.652 plus 24 fibers as per ITU-T G.655).The following
characteristics of each optical fiber are preferred for both OPGW/ OPPC
and OPUG:
5413A08/FICHT-7269867-v13 80
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The Tenderer shall state the refractive index of the optical fibres at 1310 nm
and 1550 nm.
b) Fibre Coating
The optical fibre are to be coated with a tight outer UV-hardened acrylate
protective coating; diameter 250m 15m. Alternatives may be proposed
to the Employer for approval.
The optical fibre coating material shall not generate H2 gas around the
optical fibres that will increase the optical loss as specified above over the
designed life span of the optical fibre. The Tenderer shall supply details of
the methods employed to minimise the generation of H2 gas.
5413A08/FICHT-7269867-v13 81
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Any extra hermetic coating applied to the optical fiber to impart mechanical
strength or provide protection against dirt shall only remain on the fiber if it
does not unnecessarily complicate splicing.
Test level: 0,7 GPa, maintained for at least 1 second (real time) with a
minimum elongation of 1.1 %.
Only the fibers which pass this strain level will be accepted. The Tenderer
shall supply details of the test method and references to any standards used,
including a copy of the applied standards.
f) Tractability of fibers
Subcontractors shall apply certified fibers. The identification of each optical
fiber shall be guaranteed from the moment it is drawn.
The OPGW/ ISWER (OPPC) shall have, within the adopted limit state
design method, the following partial safety factors:
5413A08/FICHT-7269867-v13 82
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
For the nominal span under every day condition the final OPGW/ ISWER
(OPPC) sag shall not exceed 95 % of the phase conductor sag.
The Contractor shall supply for the OPGW/ ISWER (OPPC) stringing data
(initial and final) calculated for different line spans in a chart or tabular
form, sag and tensions for the temperatures between 10 to 85C.
Before starting the delivery of the goods, the Contractor shall submit the
detailed OPGW/ ISWER (OPPC) length calculation for the line, according to
the actual sections, spans and dislevelments.
The Bidder is required to state the maximum tension to which the OPGW/
ISWER (OPPC) may be strung without affecting the optical properties of
the fibers and to retain efficient operation of the communication link.
At the tension towers not provided with joint boxes, the Contractor shall
provide suitable attachment fittings to by-pass the tower without any addition-
al joint. At all angle points the prescribed minimum bending radius shall be
observed. If necessary, special tandem or multiple stringing blocks have to
be used for stringing the OPGW at angle points.
The joint boxes shall be of the 'hood' type with encapsulated cable entry and
they shall be mounted within the framework of the transmission towers
above the anti-climbing device. The OPGW access to the casing should be
via entry ports in the base, properly sealed to prevent moisture ingress. Same
joint casing shall be suitable for jointing OPGW with OPUG by substitution of
appropriate glands in entry ports.
5413A08/FICHT-7269867-v13 83
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The Bidder shall present in his bid by means of detailed description and
drawings, the OPGW/ OPGW and OPGW/ OPUG jointing procedure and
devices and is responsible for the operational continuity of the optical fiber
system considering that the interface point between line and underground
cable is the joint casing at the gantry. The Contractor shall provide detailed
drawings showing the location of all joints. Each joint shall be uniquely
numbered. All documents supplied by the Contractor shall be submitted to
the Employer/ Employers Representative for approval before starting of the
manufacture in the workshop.
Weatherproof units shall be provided for the joint boxes (casings). The joint
boxes shall include all necessary hardware to terminate, protect and fix the
spliced fibers. Optical losses shall be no more than 0.08 dB at average per
splice and no single splice loss shall exceed 0.10 dB. Each splice shall have
a spare length of fiber of approximately 1m or more. A finished splice shall
be supported within the joint box by suitable clips or restraints. It shall be
possible to remove and replace the splice in the support device without risk
of damage to the splice or fiber.
The inlets of the joint boxes shall be sealed with thermofit plastics. These
inlets shall be possible to match necessary branches. The outer material of the
box shall be oil resistant and metallic, preferably aluminum. The enclosure is
to be re-enterable and re-sealable without detriment to the integrity of the
enclosure and optical fibers. Enclosure re-entering and sealing shall not
require power tools and use a minimum number of special tools.
The Bidder shall submit with his bid a calculation of the total attenuation
(overall losses) for the complete telecommunication link considering all
splices, fiber aging, etc. The total alternation shall be a guaranteed value.
The quality and performance of all joints shall be consistent with achieving
the mechanical requirements over its design life.
As part of the jointing procedure the Contractor shall monitor the optical
performance of each joint using an Optical Time Domain Reflectometer.
Upon completion of jointing and prior to sealing the joint casing an estimate
of joint loss and measurement of the total fiber attenuation shall be made. If
the total fiber loss is projected to exceed the designed installation loss then
the joint shall be broken and rejoined until the specified performance is
achieved.
If local injection and detection techniques are used to measure the attenua-
tion then any fiber bends necessary shall not affect the physical properties of
the fiber and shall not shorten its life span.
5413A08/FICHT-7269867-v13 84
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The fusion splice tray shall not have any sharp edges or protrusions which
may damage the optical fiber.
The Bidder shall present in his bid by means of detailed description and
drawings, the OPPC/ OPPC jointing procedure and devices and is responsi-
ble for the operational continuity of the optical fiber system. The Contractor
shall provide detailed drawings showing the location of all joints. Each joint
shall be uniquely numbered. All documents supplied by the Contractor shall
be submitted to the Employer/ Employers Representative for approval
before starting of the manufacture in the workshop.
The Bidder shall present in his bid by means of detailed description and
drawings, the OPPC/ OPGW and OPPC/ OPUG jointing procedure and
devices and is responsible for the operational continuity of the optical fiber
system considering that the interface point between line and underground
cable is the joint casing at the gantry. All documents supplied by the Con-
tractor shall be submitted to the Employer/ Employers Representative for
approval before starting of the manufacture in the workshop.
5413A08/FICHT-7269867-v13 85
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.6.4 OPUG
The OPUG will be used to connect the OPGW/ OPPC from the overhead
line termination gantry or special structure into the Substation buildings
The optical fibers shall not constrain firmly against other fibers, loose tubes,
strength members, moisture barrier compound, binding type or any other
cable components in order that the fiber strain is de-coupled from the strain in
other components is under tension.
The corresponding maximum cable elongation shall not exceed 0,2 % plus
the strain margin. If the cable is stressed with a load equal to Qp the cable
shall be fully elastic and protective layers shall not abrade.
Mechanical strength
The mechanical strength shall be derived entirely from its constituent load-
bearing layers. Any reinforcing elements in the optical cable core shall be
ignored. The breaking strength of the cable shall be greater than the permissi-
ble tensile resistance (QP).
Bending radius
The minimum bending radius of the cable, during installation as well as after
installation, without having any adverse effect upon the specified properties
shall be less than fifteen times the outer diameter of the cable within the
temperature range TL and TH. This bending shall not cause any significant
fiber strain and no attenuation increase greater than 0.02 dB of bent fiber.
5413A08/FICHT-7269867-v13 86
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The cable jacket shall be marked with the inscription OPTICAL FIBER
CABLE at a spacing not exceeding two meters as well as the distance
markings in meters in order to assist possible future fault location.
The markings are to be legible and indelible even after the installation process
and shall not reduce the effectiveness of the cable to protect itself against
outer damaging factors.
The cable will be installed in a plastic duct. The main purposes of using the
plastic tubes are:
easy installation of the OPUG cable straight in the digging or in the
existing sewage;
cable mechanical protection;
stand-by capacity for the second cable installation
5413A08/FICHT-7269867-v13 87
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Selection of ducts
The selection of a particular basic design (smooth, corrugated or ribbed)
depends on the need for a specific pulling strength, flexibility and the coef-
ficient of friction.
Pre-lubricated inner ducts shall be either permanently impregnated with
antifriction compounds or coated with liquid lubricant during manufacture.
When using supplementary lubricant with pre-lubricant, the Contractor
shall check the compatibility of the lubricant with pre-lubricant in order to
prevent an increase of the friction coefficient instead of a decrease.
The following duct types are to be distinguished:
Direct buried inner duct.
Buried, in conduit.
If any aerial sections are required, the inner duct shall be attached to a
steel carrier.
In building. The use of PE without fire retardant additives instead of
FRPE (fire retardant polyethylene) and PVC is required.
For the selection of inner ducts, the following applies except if the Con-
tractor submits a selection to the Employer for approval otherwise. The
selection guide is based upon the ratio of outer duct diameter and wall
thickness of the duct (SDR). When selecting a decreasing SDR number,
this indicates a more robust inner duct capable of withstanding more se-
vere mechanical stresses.
Requirements
The inner duct shall have a maximum permanent ovality of 6% (at 50C).
This is to be inspected on the last two layers on the drum.
The compression resistance shall be greater than 1350 N (at 50C). This
load shall not cause a permanent reduction of the outer diameter greater
than 4 %.
When subjected to an impact of 136 J at -20 C non-corrugated inner ducts
must remain free from cracks or tears. Corrugated inner ducts must remain
free from cracks and tears when subjected to impact loads of 68 J.
The conductivity of the duct must be greater than 10 M per meter duct.
Ducts shall be made of HDPE material.
Inner ducts shall be detectable at any buried depth up to 1 meter. The
horizontal location shall be measurable within 10 % of the inner duct
depth.
Applied lubricants shall comply with inner ducts pre-lubricated impregnat-
ed or antifriction compound coatings. This matter of compatibility counts
for all installation methods.
Any pulling pilot strings in the duct shall be non-conductive.
The color (black; orange or green) shall be resistant to staining in the
presence of sulphides. Identification marks to be printed on the ducts will
be indicated by the Employer after contract award. The markings must be
permanently extruded into the inner duct and easy to distinguish.
5413A08/FICHT-7269867-v13 88
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.6.5 Tests
B1.4.6.5.1 General
The Employer/ Employers Representative is entitled to attend tests and
inspections, and the Contractor shall bear all costs and expenses of tests and
attendance as per price schedules. The Contractor shall give the Employer/
Employers Representative notification in writing, not less than 45 days in
advance, of the date of material testing. Test program shall demonstrate
procedures of test in order to proof the specified technical requirements and
be subject to approval by the Employer prior testing starts. Additional tests
may be called by the Employer/ Employers Representative to ensure that
the required quality is met. The Contractor shall supply all necessary labor,
material, equipment and competent and authorized test personnel. Calibra-
tion of equipment is deemed to be included. Six (6) copies of test reports
and/ or certificates are to be provided showing all results and information
necessary. If the Employer/ Employers Representative waive to attend the
test, it will neither relieve the Contractor of his full liability to meet the
required quality and to complete the works nor prejudice or affect the rights
of the Employer/ Employers Representative set forth under this contract.
B1.4.6.5.2 Conductors
General
The Contractor shall supply a detailed Quality Assurance Procedure includ-
ing an Inspection and Test Plan (ITP) for all conductors (phase conductor,
earthwire, OPGW and both ISWER conductors) which shall be submitted to
the Employer for approval. The Contractor shall be responsible for perform-
ing all tests and inspections required during the production of the conduc-
tors.
All materials used in the manufacture of conductors shall be covered by test
certificates stating their mechanical and chemical properties to prove
compliance with this technical requirements and EN 50182 or IEC as
appropriate. The following certificates/ test records shall be submitted for
approval:
Conductors
The following tests shall be applied for all conductors (phase conductor,
earthwire, OPGW and both ISWER conductors as normal ACSR and
OPPC). Tests shall be undertaken in accordance with the requirements of
EN 50182 and referred standards:
Existing type test certificates may be submitted for the appropriate conduc-
tor type and are acceptable provided that they are not older than 8 years and
show
Reference lists are also accepted for the proof of stringing capability.
In case such type test certificates and reference lists cannot be provided, the
type tests have to be carried out in presence of the Employer/ Employers
Representative, and the costs are deemed to be included in the contract
price.
In the event of the sample from any length not passing the mechanical or
resistance tests, a second and third sample shall be undertaken from the
same length, and if one of these also fails under test, the length of conductor
(i.e. drum) from which it has been taken shall be rejected.
Details of the test results shall be made available to the Employer/ Employ-
ers Representative upon request for approval.
Grease
The manufacturer's type test certificates for proving compliance with the
technical requirements as per EN 50326 with regard to the following grease
properties shall be submitted to the Employer/ Employers Representative
for approval:
Type Test
Tests shall be performed in accordance with IEC 60794-4 and IEC 60794-
2. Existing type tests certificates may be accepted provided that tested
OPGW/ OPPC structure corresponds to the offered one and the certificates
are not older than 8 years.
Stress-strain
A sample of OPGW/ OPPC not less than 10m length, complete with the
proposed end fittings shall be subject to a stress-strain test. The test shall be
undertaken in accordance with IEC 61089, Annex B and the measuring
techniques in accordance with IEC 60794-1-1. There shall be no visual
change to the OPGW/ OPPC strands after the test and that the fiber strain
must be less than 0.05 % at 85% of the UTS of the cable.
Tensile Performance
The test shall be undertaken in accordance with the load conditions speci-
fied in IEC 61089, Annex B and the measuring techniques in accordance
with IEC 60794-1-2. There shall be no permanent change in the fiber
attenuation at the specified wavelength after the test, while the change in
attenuation during the test shall be less than 0.05db/km from zero load to
85 % of the UTS of the cable.
The crush test shall be undertaken by applying a 10kN load for 1min to the
OPGW/ OPPC via a 100 x 100 mm movable flat plate. There shall be no
measurable permanent change in the fiber attenuation at the specified
wavelength, while any temporary change in attenuation shall be less than
0.1db.
5413A08/FICHT-7269867-v13 91
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The impact test shall be undertaken by dropping a 4kg weight from a height
of 150mm onto the end of a 20 mm diameter steel mandrel placed on the
OPGW/ OPPC. After 20 repeated applications, there shall be no measurable
change in fiber attenuation at the specified wavelength, while any temporary
change in attenuation shall be less than 0.1db.
Temperature Cycling
The optical performance under temperature cycling shall be tested in
accordance with IEC 60794-1-2, with TA and TB as stated in the Technical
Schedules and the duration of 4 hours. The test should be undertaken twice.
Water Ingress
The optical sub-unit shall be tested for water ingress in accordance with IEC
60794-1-2.
Lightning Strike
The test shall consider both an initial stroke and a power follow through.
The test conditions shall be Class 0 according to IEC 60794-1-2. The test
shall be carried out on a sample of OPGW/ OPPC not less than 2m long.
The acceptance criteria shall be that OPGW/ OPPCs calculated residual
strength is not less than 90 % of the original stated ultimate tensile strength.
Any damaged strands shall be assumed to be broken.
Sample Tests
Tests for aluminum clad steel wires/aluminum alloy wires shall be carried
out in accordance with the requirements of IEC 61232/ IEC 60889.
Samples taken on random sampling basis from the OPGW/ OPPC drums
ready for shipment against each batch shall be tested for overall diameter,
the lay length and lay ratio of layers, lay directions and DC resistance in
accordance with IEC 61089 or EN 50182 at the factory by the manufacturer
which may be witnessed by the Employer/ Employers Representative.
5413A08/FICHT-7269867-v13 92
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Routine Tests
OPGW/ OPPC on all drums shall be tested for mechanical tests including
measurement of overall diameter of OPGW/ OPPC, measurements of
thickness of Al and ACS wires, diameter of tube, wrapping test of Al and
ACS wires, check of surface quality and OPGW/ OPPC weight, checking of
lay length and lay ratio of layers, checking of lay directions, breaking load
test of OPGW/ OPPC and DC resistance measurement in accordance with
IEC 61232/ IEC 60889/ IEC 61089 or EN 50182 at the factory by the
manufacturer as routine tests.
The Bidder shall nominate in the Technical Schedules the type tests he
proposes for these joints. Joint box and termination box type tests shall
include a water immersion test for proving the joint water tightness and
seals, with measuring of attenuation variation of the splice and loss
characteristic in an assembled joint at the start and end of a seven (7) days
immersion period. Type test certificates may be submitted to the Employer/
Employers Representative for approval.
The costs for these tests are deemed to be included in the Bid Price.
The quantities of the spare conductors are shown in the Price Schedules.
Corresponding prices shall be entered by the Bidder in this price list. If any
additional quantities should be ordered after the date of the Taking-over
Certificate, the prices may be subject to adjustment.
5413A08/FICHT-7269867-v13 93
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Tools
Any special tools and test equipment needed to maintain the fiber optic link
over its expected lifetime shall be included. The type and quantity of tools is
given in the price sheets.
The test equipment and other special tools proposed shall be of the same
type as used by the Contractor for erection and commissioning. The test
equipment and tools included in the Contract shall, however, not be made
available to the Contractor during erection and commissioning.
All test equipment and electrically operated tools shall be suitable for
operation from 50Hz, 230V AC mains supply. In addition, the Fusion
Splicer and Optical Time Domain Reflectometer (OTDR) shall be fitted
with batteries for operation in the field.
5413A08/FICHT-7269867-v13 94
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
All drums with conductors shall have a layer of waterproof wax paper or
plastic sheet which must be safe against chemical reactions laid around the
barrel under the conductors and another one laid over them and under the
lapping. Drums shall be securely fastened around the perimeter and shall be
suitable for rolling on the flanges without causing damage to the conductor.
The disposal of all empty drums shall be the responsibility of the Contrac-
tor.
Contractor shall submit a sketch or drawing showing the full details of drum
design and the details of the proposed method of impregnation and lagging the
inner drum surfaces with approved tarred paper or equivalent material. The
minimum length of the conductors on drums is subject to the Employers/
Employers Representatives approval.
B1.4.7.1 General
Complete insulator sets consisting of long-rod composite insulator units and
assembling fittings as well as fittings for phase conductor, earthwire,
OPGW and ISWER system are required as described below and in the
Technical Schedules.
The Contractor shall provide detailed assembly drawings for each type of
assembly required.
5413A08/FICHT-7269867-v13 95
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
All insulator sets shall be provided with the necessary guarding devices in
order to keep their radio and television noise as low as possible. A noise level
less than 46 dB above 1 microvolt shall be ensured under standard laboratory
conditions. This is to be proven by tests as per the mentioned standards.
All insulator sets shall be designed to withstand the single-phase fault currents.
This performance shall be proven by design tests in the workshop or laborato-
ries in accordance with the tests described below.
The upper and lower horns and guard rings shall be installed on the insulator
assemblies as recommended by the fittings manufacturer and confirmed by
electrical tests.
Locking devices for the insulator units themselves and for associated ball and
socket fittings shall be of stainless steel and shall comply with IEC 60372. The
design shall be such as to allow easy removal for replacing of insulator units or
fittings without the necessity to remove the insulator set from the crossarms.
Locking devices shall be incapable of rotating when in position.
For the dimensioning of the insulator sets from the mechanical point of
view, the loads and loading conditions shown below along with partial
safety factors for loads, as well as the material safety factor have to be
considered:
the weight of the conductors and of the insulator set
the wind loading on conductors
the maximum working tension of the conductors
partial load safety factors as specified above
partial material safety factor for intact insulator string M = 2.50
partial material safety factor for broken insulator string M = 1.25 .
The electromechanical failing load for the insulator units and the nominal
loading capacity for the insulator string fittings shall be referred to.
5413A08/FICHT-7269867-v13 96
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The electrical and mechanical performance requirements for insulator sets are
shown in the Technical Schedules.
The suspension towers will be equipped with suspension insulator sets. The
tension towers (angle-tension and dead-end towers) and gantries will be
equipped with tension insulator sets.
The 400kV insulator sets shall be designed for horizontal twin bundle of the
ACSR BLUEJAY type conductor, spaced at 450 mm.
The double suspension insulator set shall be used for crossings of buildings,
main roads, overhead transmission lines 110kV, railways and for HS tower
types in general. Double suspension insulator sets shall have the two strings
in a plane parallel to the line and be fixed in two points to the crossarm.
Double tension sets will be installed on all tension and terminal towers. The
insulator set attachments to the tower crossarms are of special importance.
Therefore two independent fixing points to the tower are specified for
double insulator sets. Attachments to the tower are to be of secure connec-
tion such as with swivels. Hooks are not acceptable.
Suitable adjustment, in case of tension sets, has to be done for the different
line angles in order to assure equal repartition of the loads to the two
insulator strings of the set.
Between the terminal towers and gantries (in the slack span), low duty
tension sets shall be installed in conductor direction and down droppers.
The 36kV insulator sets for the ISWER shall be designed for ACSR 184-
AL/30-ST1A respectively ACSR 184-AL/30-A20SA (OPPC).
The single I suspension insulator set shall be used as standard set on suspen-
sion towers and as jumper suspension set on the tension and terminal towers,
where clearance requirements so demand. Single tension sets are to be used at
5413A08/FICHT-7269867-v13 97
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
In case of ISWER T-off solutions, the swinging out of the conductor shall be
restricted. A V-suspension insulator string is to be used therefore instead of a
normal I-string at suspension towers and for fixing the jumper at anchor
towers if necessary (see Annex).
5413A08/FICHT-7269867-v13 98
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Design of components
The insulators shall be of sufficient length to provide the required electrical
performance in one single unit. In-line coupling of two or more units is not
acceptable.
The core shall be an epoxy resin rod with axial glass fiber reinforcement of
high strength (fiber reinforced plastic rod). The rod shall be resistant against
hydrolysis under service conditions. Therefore, E-CR-glass fibers embedded
in an epoxy matrix shall be used for the core. The FRP core shall be assem-
bled by means of modern Statistic Process Controlled (SPC) and Acoustic
Emission (AE) monitored crimping technology. Temperature certificate
issued by the manufacturer shall indicate an application range of the core
material and the core / end fitting assembly of -50+100C. All other core
material properties shall be in accordance with CIGRE Technical Brochure
No. 255.
The housing shall be designed in such a way that the end fittings are not
covered with housing material in order to avoid electrical punctures and
electrical overstress of the housing. The preferred design of the interconnec-
tion between rod and end fitting is of type a according to CIGRE Paris
Session 2000 Paper 33-204 figure 2. The housing shall be fully coaxial at
the shank in order to avoid punctures and flashunders.
5413A08/FICHT-7269867-v13 99
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The metal end fittings should be made of forged steel and hot dip galvanized
according to ISO 1461. The fittings shall be attached onto the rod by a
compression method process which does not damage the individual fibers of
the rod in any way.
Fittings configuration shall be defined by the actual need (e.g. ball and
socket or clevis and tongue connection) and shall comply to the standard
requirements.
The gap between fitting and core housing shall be sealed permanently
against the ingress of moisture. Sealing by compression only is not regarded
to be permanently waterproof. Covering the gap, even partly, with housing
material or sealing in form of over-molding the end fittings are unacceptable
due to electrical reasons. Sealing of the interface by application of a meta-
stable silicone elastomere with permanent elasticity is considered an ac-
ceptable solution. The material shall adhere to the surface of the metal cap,
as well as to the housing. The sealing shall be hidden in a special gap and
not be subjected to critical electrical field stresses.
Design of string
Suitable electrical field grading devices in accordance with CIGRE Tech-
nical Brochure TB 284 shall be applied in order to protect the composite
insulator against premature failure and electrical field stress induced ageing.
If the supplier is not responsible for the complete insulator string design,
then written recommendation for the grading / corona ring setup has to be
given to the main contractor. The effectiveness of the grading / corona
protection devices shall be proven by 3D electrical field calculations where
the complete insulator strings and the entire tower configuration shall be
simulated for 3 phase voltage stress. The results of these calculations shall
be part of the project documentation.
Manufacture
All parts of the insulator shall be free from any defects which may impair
the mechanical or electrical properties of the insulator.
5413A08/FICHT-7269867-v13 100
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.7.4.1 General
All clamps and fittings shall be suitable for the above specified phase conduc-
tor type ASCR BLUEJAY twin bundle. They shall comply with the
requirements of this Bidding Document and must be approved by the Employ-
er/ Employers Representative.
The Contractor shall ensure close and continuous liaison between the manu-
facturers of conductors, clamps, insulators and fittings so that the equipment
will be perfectly adapted.
5413A08/FICHT-7269867-v13 101
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
All clamps and fittings except for spacer dampers and vibration dampers shall
be supplied by the same manufacturer. Splitting up of the supply of clamps
and fittings will not be permitted.
For the dimensioning of the fittings from the mechanical point of view, the
loads and loading conditions shown below along with partial safety factors
have to be considered:
the weight of the conductors and of the insulator set
the wind loading on conductors
the maximum working tension of the conductors
partial load safety factors as specified above
partial material safety factor for fittings M = 2.50
partial material safety factor for fittings in case one
part of insulator string is broken M = 1.25 .
In order to maintain low corona and low radio interference, the design of all
clamps and fittings shall avoid sharp corners or projections, which would
produce high electrical stress.
The design of adjacent metal parts and mating surfaces shall be such as to
prevent corrosion of the contact surfaces and to maintain good electrical
contact under service conditions.
Particular care shall be taken during manufacture of clamps and fittings and
during subsequent handling to ensure smooth surfaces free from burrs and
sharp edges.
All line fittings concerned shall be dimensioned and designed to withstand the
single-phase fault current shown in the Technical Schedules. Each insulator
set shall withstand such a short-circuit without the temperature exceeding
200C in the fittings and without welding between the component parts. The
Employer/ Employers Representative may require tests to be carried out to
demonstrate the short circuit characteristics of each type of insulator set. The
cost of such tests shall be borne by the Contractor.
All ferrous parts of the assemblies component elements and of the accessories
for conductors shall be hot dip galvanized according to ISO 1461. The split
pins of all clamps and fittings shall be of stainless steel.
5413A08/FICHT-7269867-v13 102
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The mouth of the supporting groove shall be slightly flared in plan. The
grooves in the clamping piece shall be bell-mouthed at each end and all
conductor grooves and bell-mouths shall be smooth and free from waves,
ridges or other irregularities.
The bolts used in the suspension clamps shall be hexagonal hot-dip galvanized
or stainless steel bolts. The washers underneath the bolt head shall be made
from stainless steel only.
The clamp bolts and the clamping force shall be chosen to satisfy also the
electrical requirements. The phase conductor clamps must be capable of
withstanding the three-phase and the single-phase fault currents shown in the
Technical Schedules without any damage.
Attention must be paid to the elimination of fair weather corona emission from
all parts of conductor suspension clamps under the specific site conditions.
5413A08/FICHT-7269867-v13 103
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Conductor tension clamps and joints shall be of the compression type, suitable
to withstand a working temperature of 85C. The conductor tension clamps
shall be supplied with a jumper terminal which may be bolted at 0 or 30. The
coupling element of the tension clamps to the string shall be clevis-type, hot
dip galvanized.
The electrical conductivity and current carrying capacity of the tension clamps,
joints and jumper terminals shall be not less than those of the equivalent length
of conductor.
The tension clamps and joints of the phase conductors must be capable to
withstand also the three phase short-circuit current shown in the Technical
Schedules without damage.
Attention must be paid to avoid fair weather corona emission from the conduc-
tor tension clamps and joints.
Joints and tension clamps shall be supplied with filler compounds, to protect
the assembly clamp-conductor against corrosion.
The design of the joints and tension clamps shall be such that only one pair
of dies is necessary for the compression of the conductor.
Mid-span joints shall not be less than 30m from the nearest conductor
clamp.
Joint sleeves and repair sleeves for the conductors shall be of compression
type. The joint sleeves shall consist of steel compression sleeve for the steel
core of conductor, and aluminum compression sleeve for the complete of
conductor. The aluminum compression sleeves shall be of aluminum alloy
conforming to the specification in IEC 60889 standard or equivalent, and
5413A08/FICHT-7269867-v13 104
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
After compressed, the electrical resistance of the joint sleeve must be less
than that of the jointed conductor with the same length as the sleeve, and the
ultimate tensile strength of the joint sleeve must not less than 95 % of the
ultimate tensile strength of the conductor.
The direction of the armor rod lay shall be equal to the direction of the
outermost wire lay of the conductor.
The suspension clamps offered for the phase conductors shall accommodate
the increased diameter resulting from armor rods.
The ends of the armor rod wires shall be well rounded, without sharp edges,
to avoid an increase in corona level.
As arcing device, the guard rings shall be designed to protect insulators and
conductors when flashover occurs. The arcing fittings shall be made of hot
dip galvanized steel and must have the capability to withstand a three-phase
short circuit current as per Technical Schedules. The arcing fittings must be
designed so that in case of flashover the arc will be led to the end burning
spot.
They may reach a final temperature not exceeding 600C during the short-
circuit. The function of arcing protection must not be greatly altered by the
power arc.
As corona shield devices, the guard rings shall be designed to ensure under
fair weather and under the specific site conditions a corona-free insulator set
line end as well as the specified insulator set radio noise performance.
5413A08/FICHT-7269867-v13 105
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.7.5.1 General
All clamps and fittings shall comply with the requirements of this Bidding
Document and must be approved by the Employer/ Employers Representa-
tive. They shall be suitable for the insulated ACSR earthwire/ OPPC types
specified. The Contractor shall ensure close and continuous liaison between
the manufacturers of earthwire/ OPPC, clamps and fittings so that the
equipment will be perfectly adapted.
All clamps and fittings except for vibration dampers shall be supplied by the
same manufacturer. Splitting up of the supply of clamps and fittings will not
be permitted.
Besides, the Contractor shall assure perfect fitting of the earthwire/ OPPC
set attachment armatures (connecting hardware) to the tower steel construc-
tion. The design of adjacent metal parts and mating surfaces shall be such as
to prevent corrosion of the contact surfaces and to maintain good electrical
contact under service conditions. The attachment sets shall withstand
lightning strokes and fault currents as specified in the Technical Schedules
without suffering damage, and this performance must be checked in accord-
ance with the requirements. The Employer/ Employers Representative may
require tests to be carried out to demonstrate the short circuit characteristics
of each type of connection-to-tower set. The cost of such tests shall be borne
by the Contractor.
5413A08/FICHT-7269867-v13 106
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
All ferrous parts of the assemblies component elements and of the accesso-
ries for conductors and earthwire/ OPPC shall be hot dip galvanized accord-
ing to ISO 1461.
The split pins of all clamps and fittings shall be of stainless steel.
The suspension towers will be equipped with suspension sets and the
tension towers with tension sets. All sets shall be designed for the specified
earthwire/ OPPC selected type and for the mechanical loads and loading
conditions shown below as well as the safety factors given in the Technical
Schedules:
Particular care shall be taken during manufacture of clamps and fittings and
during subsequent handling to ensure smooth surfaces free from burrs and
sharp edges.
The material of the clamps should satisfy the norms EN 1559 for aluminum
alloy castings and EN 1562 for malleable cast iron.
The rotational axis of the clamp shall be in the longitudinal axis of the
earthwire/ OPPC to avoid unacceptable distortion of the earthwire/ OPPC due
to unbalanced longitudinal loads. The Contractor shall ensure by appropriate
design a suitable performance of the clamp-conductor assembly by wind
induced vibration.
Connecting hardware is required for a suitable connection to the tower and the
Contractor is responsible to supply the complete set of the suspension assem-
bly.
5413A08/FICHT-7269867-v13 107
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The material of the clamps should satisfy the norms EN 1559 for aluminum
alloy castings and EN 1562 for malleable cast iron.
The protection part is defined to protect the earthwire/ OPPC against radial
forces produced by the high longitudinal tensions during operation. The
protection part must be laid in the opposite direction of the outer layer of the
earthwire/ OPPC and the dead-end part must be laid in opposite direction to
the protection part. The grip strength shall be at least 95 % of the ultimate
tensile strength of the earthwire/ OPPC.
The tension attachment devices must correspond to the earthwire/ OPPC type
and dimensions. The protection part must be longer than the tension (dead-
end) part and the length must be sufficient to install vibration dampers. The
number and diameter of the spiral rods of the two parts are generally different
but must be coordinated to meet the operational requirements.
5413A08/FICHT-7269867-v13 108
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
They may reach a final temperature not exceeding 600C during the short-
circuit. The function of arcing protection must not be greatly altered by the
power arc.
B1.4.7.6.1 General
All clamps and fittings shall comply with the requirements of this Biding
Document and must be approved by the Employer/ Employers Representa-
tive. They shall be suitable for the earthwire/ OPGW types specified. The
Contractor shall ensure close and continuous liaison between the manufac-
turers of earthwire/ OPGW, clamps and fittings so that the equipment will
be perfectly adapted.
All clamps and fittings except for vibration dampers shall be supplied by the
same manufacturer. Splitting up of the supply of clamps and fittings will not
be permitted.
Besides, the Contractor shall assure perfect fitting of the earthwire/ OPGW
set attachment armatures (connecting hardware) to the tower steel construc-
tion. The design of adjacent metal parts and mating surfaces shall be such as
to prevent corrosion of the contact surfaces and to maintain good electrical
contact under service conditions.
5413A08/FICHT-7269867-v13 109
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
All ferrous parts of the assemblies component elements and of the accesso-
ries for conductors and earthwire/ OPGW shall be hot dip galvanized
according to ISO 1461.
The split pins of all clamps and fittings shall be of stainless steel.
The suspension towers will be equipped with suspension sets and the
tension towers with tension sets. All sets shall be designed for the specified
earthwire/ OPGW selected type and for the mechanical loads and loading
conditions shown below as well as the safety factors given in the Technical
Schedules:
Particular care shall be taken during manufacture of clamps and fittings and
during subsequent handling to ensure smooth surfaces free from burrs and
sharp edges.
The material of the clamps should satisfy the norms EN 1559 for aluminum
alloy castings and EN 1562 for malleable cast iron.
The rotational axis of the clamp shall be in the longitudinal axis of the
earthwire/ OPGW to avoid unacceptable distortion of the earthwire/ OPGW
due to unbalanced longitudinal loads. The Contractor shall ensure by appropri-
ate design a suitable performance of the clamp-conductor assembly by wind
induced vibration.
5413A08/FICHT-7269867-v13 110
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The material of the clamps should satisfy the norms EN 1559 for aluminum
alloy castings and EN 1562 for malleable cast iron.
The protection part is defined to protect the earthwire/ OPGW against radial
forces produced by the high longitudinal tensions during operation. The
protection part must be laid in the opposite direction of the outer layer of the
earthwire/ OPGW and the dead-end part must be laid in opposite direction to
the protection part. The grip strength shall be at least 95 % of the ultimate
tensile strength of the earthwire/ OPGW.
B1.4.7.7 Tests
B1.4.7.7.1 General
The Employer/ Employers Representative is entitled to attend tests and
inspections, and the Contractor shall bear all costs and expenses of tests and
attendance as per price schedules. The Contractor shall give the Employer/
Employers Representative notification in writing, not less than 45 days in
advance, of the date of material testing. Test program shall demonstrate
procedures of test in order to proof the specified technical requirements and
be subject to approval by the Employer prior testing starts. Additional tests
may be called by the Employer/ Employers Representative to ensure that
the required quality is met. The Contractor shall supply all necessary labor,
5413A08/FICHT-7269867-v13 111
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Type, sample and routine tests shall be performed. The costs for these tests
are deemed to be included in the Bid Price.
Regarding composite insulators, the following sample tests shall be carried out
in addition to IEC 61109 in order to guarantee first class quality and long
service, and the costs are deemed to be included in the Bid Price:
5413A08/FICHT-7269867-v13 112
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
5413A08/FICHT-7269867-v13 113
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The Joints for OPGW/ OPPC (joint enclosure and splices) are subject to the
requirements of IEC 61073, IEC 61300 and shall be tested as specified in the
documents.
The mechanical tests specified in IEC 61073-1, par. 4.5, shall be performed.
The tensile test shall be agreed with the OPGW/ OPPC manufacturer and
the optical attenuation shall be measured. The clamp bolts have to be
tightened according to the recommended moments and the OPGW/ OPPC
shall be checked afterwards visually.
The costs for these tests are deemed to be included in the Bid Price.
corona test;
radio interference test;
thermal stability test (OPGW/ OPPC).
The tests referring to the insulator sets have to be carried out on completely
equipped sets, with all clamp and fitting parts, installed in their characteris-
tic working position and having attached also an agreed length of conductor
bundle. The costs for these tests are deemed to be included in the Bid Price.
Corona Tests
The corona tests shall be carried out as design tests in the manufacturer's
works or in specialized laboratories.
The line components to be corona tested are all insulator set types as well as
the conductor accessories like joints and repair sleeves.
5413A08/FICHT-7269867-v13 114
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Each type of insulator set has to be completely equipped with all clamp and
fitting parts and installed in its characteristic working position, having
attached also agreed length of conductor bundle.
The suspension sets will be provided with armor rods and, if applicable,
with counterweights also.
The conductor accessories can be installed as separate test object or inserted
in the insulator set test arrangement.
For the corona tests, the optical detection method with pre-stressing accord-
ing to IEC 60270 (1981) shall be applied.
The test object has to be energized for 5min at minimum 267kV (r.m.s)
phase-to-ground. Then the voltage shall be continuously decreased in order
to establish the voltage value of which visible discharges disappear (corona
extinction voltage = Ve). After this, the voltage shall be continuously
increased in order to establish the voltage value at which visible discharges
appear (corona inception voltage = Vs). Five (5) successive tests have to be
performed according to this procedure. The average value of the resulting
corona extinction voltages Ve shall be considered as test result.
Pictures shall be taken during the test at several voltage levels in order to
demonstrate optically the corona performance of the test object.
Same line components like for corona tests (see above) shall be tested for
radio interference or radio noise.
Same requirements and recommendations regarding the completeness and
arrangements of the test objects like for corona tests (see above) are applied
also for RI tests.
5413A08/FICHT-7269867-v13 115
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The RI tests will be based on the IEC 60437. The test voltage will be
267 kV. The radio noise limits (across 300 ohm at 1 MHz) is 46 dB above
1 microvolt.
The arrangement of the considered objects for tests, the measuring circuit as
well as the simulated atmospheric conditions shall be subject to agreement
between Employer/ Employers Representative and Contractor.
Each attachment set type shall be completely installed in its typical working
position together with a sufficient OPGW/ OPPC wire length in order to
allow for a simultaneous test (OPGW/ OPPC and attachment set).
Each set type will be submitted to a cycle of three (3) tests with different
test parameters as shown below:
Photographs shall also be taken from the tested object before and after test.
The Contractor shall have available on site for the Employers/ Employers
Representatives use an instrument suitable for the accurate checking of
galvanizing thickness. The measuring instrument shall be available from the
5413A08/FICHT-7269867-v13 116
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
time of arrival of the first consignment of material until the issue of the
operational acceptance certificate. The cost of the gauge and other operating
expenses are deemed to be included in the Contract price.
B1.4.7.8 Packing
The insulators shall be packed and carried out in suitable boxes. Each
package of insulators shall be marked with the type designation used by the
manufacturer. A handling guide shall be attached to each crate. The guide
shall reflect the best practice documented in CIGRE Technical Brochure
No. 184.
B1.4.8 Dampers
B1.4.8.1.1 Requirements
Phase conductors arranged in twin bundle shall be fitted with spacer damp-
ers in order to maintain a distance of 450 mm between the sub-conductors
under all working conditions and to protect the conductors under aeolian
vibrations.
5413A08/FICHT-7269867-v13 117
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
data for the calculations shall be performed under the responsibility of the
Contractor and shall be subject for approval of the Employer/ Employers
Representative.
For bolted clamps, all bolts of the spacer dampers shall be captive. The
shape of the clamp shall provide a large radius around the conductor in
order to guarantee a corona-free level similar to that of the conductor
bundle.
The clamp shells and the spacer himself shall be made of corrosion-resistant
high-strength aluminum alloy. For bolted clamps, the bolts and nuts used in
the spacer clamps shall be galvanized or of stainless steel. The washers
underneath the bolt head shall be made from stainless steel only. The
clamping bolts shall be of steel having a minimum tensile strength of 800
N/mm2. The tightening torque shall be defined for conditions of friction for
bolt head, thread and washer and shall consider a setting of the connection.
Nuts shall only need slackening, not removal, in order to fit the spacer to the
conductors. The nuts or bolts shall be locked in an approved manner against
vibration loosening.
The spacer dampers shall be capable of the movements shown below without
damaging the conductors:
5413A08/FICHT-7269867-v13 118
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
by them for overhead transmission lines with horizontal twin bundle con-
ductors and can also show that the equipment supplied has provided several
years of trouble free service.
The Contractor shall provide evidence by end users certificates and show
details which include a full and complete specification of the materials,
manufacture and guaranteed performance of the spacer dampers.
the corona extinguishing voltage shall be not less than 267kV r.m.s.
phase-to-earth
radio interference (RI): 46 dB above 1 microvolt at 420 x 1.1/ 3 = 267
kV r.m.s. voltage value phase-to-earth
static compression and tensile performance: 5kN for 1min and the
separation of the clamps before and after the test shall not differ by more
than 5 %
impulse compression performance by short-circuit: 40kA peak with one
clamp offset longitudinally by 35 mm (spacing 450 mm), conductors at
everyday tension
compression and tensile fatigue performance: 10 million cycles at 1Hz each
clamp loaded to 500N (fatigue test sub-span oscillation)
vertical fatigue performance: 100 million cycles at 20Hz with a relative
displacement of the clamp of 15 mm
torsion fatigue performance: 100 million cycles at 20Hz with a relative
displacement of the clamp up to 2
for bolted clamps, a clamp slip: max. 1mm by a load of 6kN applied for
10min.
Alternatively and verified by a Damping Study, rigid spacers together
with stockbridge dampers for each sub-conductor may be offered.
B1.4.8.1.2 Tests
The Employer/ Employers Representative is entitled to attend tests and
inspections, and the Contractor shall bear all costs and expenses of tests and
attendance as per price schedules. The Contractor shall give the Employer/
Employers Representative notification in writing, not less than 45 days in
advance, of the date of material testing. Test program shall demonstrate
procedures of test in order to proof the specified technical requirements and
be subject to approval by the Employer prior testing starts. Additional tests
may be called by the Employer/ Employers Representative to ensure that
5413A08/FICHT-7269867-v13 119
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
the required quality is met. The Contractor shall supply all necessary labor,
material, equipment and competent and authorized test personnel. Calibra-
tion of equipment is deemed to be included. Six (6) copies of test reports
and/ or certificates are to be provided showing all results and information
necessary. If the Employer/ Employers Representative waive to attend the
test, it will neither relieve the Contractor of his full liability to meet the
required quality and to complete the works nor prejudice or affect the rights
of the Employer/ Employers Representative set forth under this contract.
Spacer dampers shall be type and sample tested in accordance with IEC
61854 (Requirements and Tests for Spacers). All tests shall not cause
damage to the conductors to which the test spacers were applied.
For short-circuit tests, the peak and r.m.s. values as well as the method is
described above.
B1.4.8.2.1 Requirements
Vibration dampers of Stockbridge type shall be installed at all earthwire
suspension and tension points and shall be mounted on armor rods. The
expression earthwire is to be understood as either non-insulated ACSR
conductor and OPGW or insulated ACSR conductor and OPPC (ISWER
system).
Minimum two dampers per span shall be provided; one damper per span is not
permitted. The exact number of dampers shall be determined by a Damping
Study which is deemed to be included in the scope of work. The Contractor
shall submit all data and calculations regarding the characteristics, number and
placement of the vibration dampers to be used for the various ranges of spans.
The calculations shall cover the range of 1 to 7 m/s wind velocity and typical
earthwire tensions (EDS) and the range of span lengths. All data for the
calculations shall be performed under the responsibility of the Contractor and
shall be subject for approval of the Employer/ Employers Representative.
5413A08/FICHT-7269867-v13 120
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The damper clamps shall be of forged aluminum alloy or cast and shall be
designed to ensure that dampers do not cause damage to the earthwire type
for which they are used.
As function of the necessary distance between the first vibration damper and
the mouth of the suspension clamp on earthwire, the damper clamp shall be
dimensioned taking into account the installation on the earthwire or on the
armor rods.
For bolted clamps, the clamping bolts shall be of steel having a minimum
tensile strength of 800 N/mm2 and shall be designed to facilitate an easy
damper mounting. The screws shall be locked in an approved manner. The
washers shall be made of stainless steel.
B1.4.8.2.2 Tests
The Employer/ Employers Representative is entitled to attend tests and
inspections, and the Contractor shall bear all costs and expenses of tests and
attendance as per price schedules. The Contractor shall give the Employer/
Employers Representative notification in writing, not less than 45 days in
advance, of the date of material testing. Test program shall demonstrate
procedures of test in order to proof the specified technical requirements and
be subject to approval by the Employer prior testing starts. Additional tests
may be called by the Employer/ Employers Representative to ensure that
the required quality is met. The Contractor shall supply all necessary labor,
material, equipment and competent and authorized test personnel. Calibra-
tion of equipment is deemed to be included. Six (6) copies of test reports
and/ or certificates are to be provided showing all results and information
necessary. If the Employer/ Employers Representative waive to attend the
test, it will neither relieve the Contractor of his full liability to meet the
required quality and to complete the works nor prejudice or affect the rights
of the Employer/ Employers Representative set forth under this contract.
5413A08/FICHT-7269867-v13 121
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The system shall comprise white spheres (RAL 9010), alternating with
red ones (RAL 3000)
The spheres on two earthwires for any span shall be so staggered that the
maximum distance between any two spheres is not greater than 30 m
The first and the last spheres in any span shall be approximately 15 m
from the towers defining the span
The fixing clamps of the spheres shall match the preformed armor rods to
be supplied for each sphere, to be mounted between sphere shell and
earthwire
The type and details of the spheres shall be closely coordinated with the
OPGW/ OPPC manufacturer in order to avoid any excessive stress on the
OPGW/ OPPC.
5413A08/FICHT-7269867-v13 122
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Cleaning
Prior to chemical treatment/ surface preparation, the galvanized surfaces
shall be carefully cleaned by brushing with fresh water to remove all foreign
substances such as salt, white rust and zinc corrosion products, dust sand
and dirt. Chemical treatment procedure of galvanized steel surfaces shall be
subject to the approval of the Employer/ Employers Representative.
Painting
For better adhesion and corrosion protection priming coats shall be applied
by brush or by airless spray only. The other coats of paint are to be applied
by brush roller or spray and in accordance with the paint manufacturers
recommendations:
All surfaces to be painted must be moisture-free and paintings shall not take
place when:
All finishes shall be clean and in good sound conditions. Each coat shall
completely and uniformly cover the coat underneath it. Depending on the
authorities requirements, epoxy based multi layer coatings may be applied.
5413A08/FICHT-7269867-v13 123
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Excessive coat thickness shall not exceed the maximum specified by the
paint manufacturer.
The aircraft obstruction lights shall have the following general features:
It shall be noted that the supply of equipment shall include the necessary
spare parts as per manufacturers recommendation, for a service period of
five years. Expenditure incurred is deemed to be included in the price
quoted in the price tabulation sheet.
5413A08/FICHT-7269867-v13 124
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.10 Earthing
B1.4.10.1 General
The line route is located for a part in hilly terrain with predominantly firm to
compact silty clay and sand and localized outcropping rock a condition
which is unfavorable for the tower earthing. Therefore the natural earthing
of the foundation steel in combination with artificial earthing system is
specified.
The earthing material shall be supplied in advance before other line material
will be shipped to enable foundation works to be carried out.
The design and tests shall generally follow EN 50341 and IEEE 80-1986.
The tower earthing system will be composed of:
Connection of the earthing devices to the tower steel shall be made approx.
10 cm above the foundation concrete cap and connected by bolts to two
diagonally opposite located tower legs.
The ground earthing wire shall be embedded in suitable plastic hoses from
the foundation cap top down to 1.0 m below ground level as shown in the
Annex.
5413A08/FICHT-7269867-v13 125
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The stringing of the OPGWs may commence after final approval of the
resistance value by the Employer/ Employers Representative.
Natural Earthing
To include the foundation steel into the tower earthing, inside the concrete
the vertical reinforcing bars will be connected electrically by a steel tape
loop which shall be also welded/screwed to the stub angle.
Artificial Earthing
The earthing system provided shall be adapted to the soil conditions existing
along the line route. If the measured resistance is higher than the specified
limit values at the line and approximately 2 km before the substations 10
Ohms, the Contractor shall propose measures for improvement. These
measures can be but are not limited to:
5413A08/FICHT-7269867-v13 126
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
If the measured resistance is higher than the limit values after installation of
artificial earthing extension, earthing pits of minimum 1.5 m depth shall be
provided and filled with Ground Enhancing Material. An earthing rod shall
be driven in the filled pit and connected to the extended artificial earthing
system by an additional grounding wire.
Grading Rings
At tower locations subject to special requirements of safety of public, a
closed earthing ring has to be buried around the tower leg, to a depth of
0.6 m at a distance of 1 m to the tower steelworks. The ring is to be con-
nected to counterpoise tower leg earthing.
B1.4.10.3 Material
Earthing conductor
The tower grounding wire or the grounding tape (earthing strap) shall be at
least
11.5mm diameter galvanized steel wire
40x6mm galvanized steel band.
The earthing conductor shall be connected to the tower steel structure (stub) by
using connectors and/ or bolts.
Connectors
The connection of the basic and additional earthing system to the tower stubs
inside the concrete or above the foundation shall be made by means of a flat
connector compressed on the steel wire and bolted to the stub. In case of using
an earthing tape, the tape may be connected directly to the stub by two bolts.
The bolts shall be of sufficient length to suit the steel connecting angle/ plate
thickness and provide for the nut and washer.
of ground wire. The effective length of the clamp shall be sufficient to grip the
connecting wires firmly under normal service conditions.
Grounding Rod
The ground rods shall be of galvanized steel type, delivered in modules and
provided with connectors. The minimum length may not be smaller than 2.0m
and the diameter not smaller than 15mm.
The earth electrode shall be connected to the tower steel by using ground
wires/ tapes and connectors.
B1.4.11.1 General
The following Bidding Document part contains the requirements and
conditions for the work on site like preparation of access roads, route
clearing, tower pegging, preparation of tower locations, foundation works
and erosion protection, tower erection, conductor and OPGW stringing and
sagging works as well as final commissioning. The requirements and
conditions for the work are described in the following chapters.
The Contractor has to develop a suitable planning and has to split the line
length suitably into several transmission line sections, which have to be
treated separately and simultaneously in order to meet the target completion
5413A08/FICHT-7269867-v13 128
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
date. The necessary number of teams for each sub-process shall be deter-
mined.
5413A08/FICHT-7269867-v13 129
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
All working methods employed and all plant and equipment supplied under
this Contract shall be approved by the Employer and applied by the Con-
tractor accordingly.
Living Accommodation
The Contractor shall make his own arrangements with regard to accommo-
dation for his expatriate and locally recruited staff during the construction
period. All dwellings and buildings existing or erected shall comply with
local regulations with regard to construction, water supply, sanitation and
other requirements.
Medical Services
The Contractor shall make his own arrangements where medical services
may be required for his repatriate and locally engaged staff.
Staff Transport
The Contractor shall provide at his own expense all necessary transport for
his personnel and materials.
Office Accommodation
The Contractor shall provide for his own such buildings as may be neces-
sary for office accommodation for site staff during the construction period.
The cost of these shall be deemed to be included in the Contract Price.
Storage Facilities
The Contractor shall make his own arrangements for storage area and shall
obtain the approval of the Employer for the places along the line route. The
5413A08/FICHT-7269867-v13 130
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The site storage area shall be prepared with an adequately compacted base
coarse for ordinary storage of conductor drums, tower steel, insulators and
fittings so that the material will not be damaged by in-transit re-loading
operations and effects of adverse weather during storage. Materials and
equipment packed in flammable crates or drums shall be stored in such a
manner as to avoid any damage arising from fire.
Lifting Facilities
The Contractor shall make his own arrangements to purchase or provide
lifting facilities required for materials and equipment handling and transport
on the site.
If the Employer detects defects in the works, the Contractor shall provide
enough staff for a sufficient period of time to remedy the defects.
If the Employer finds the Contractor will be unable to complete the works in
the agreed time schedule, then the Contractor shall work overtime but shall
not make any claims for any extra expenses thereby incurred.
Responsibility of Contractor
Until each section of the works has been taken over or deemed to have been
taken over under the Conditions of Contract, the Contractor shall be entirely
responsible for such section of the works under construction and during test.
During the period of maintenance the Contractor shall ensure that a compe-
tent representative is available at the Site for the purpose of carrying out any
work of maintenance for which the Contractor is responsible.
The Contractor shall be responsible for the behavior on site of all personnel
employed by him.
5413A08/FICHT-7269867-v13 131
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Removal of Obstacles
Where clearing is necessary, the following requirements shall be observed:
Re-Clearing
Before the issue of the Operational Acceptance Certificate or at the time
agreed by the Employer, the Contractor shall have re-cleared the vegetation
within the easement of the specified line corridor.
All new access roads required over reasonably good shall be located as far
as possible within the easement, and the number of new access routes
between existing roads and the easement shall be kept to a minimum. Finger
roads are preferable instead of a continuous access along the line. The
Employer will negotiate with the landowners about permission and compen-
5413A08/FICHT-7269867-v13 132
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Construction
The Contractor shall (after getting permission for the routes) do what is
necessary to make the access suitable for his use and shall take all reasona-
ble precautions to avoid damage, including, if required the erection of
temporary fences or gates where permanent fences, hedges or gates have
been removed. The Contractor shall not be entitled to any additional pay-
ment in the event of a particular access being difficult.
New earth access tracks shall be 4 m suitably compacted. The final surface
level shall be at least 0.5 m above the existing ground level and shall be
constructed in such a way as to be adequately drained to prevent washouts.
Occasional drain ducts laid into the road bed may become necessary to
control drainage run off. Junctions between new tracks and existing roads
shall not impede or damage neither the latter nor any associated drainage
channels, etc.
The bearing capacity of the terrain and its suitability for vehicles shall be
checked before transporting the materials to the designed location.
All necessary measures connected with the access, transport and mainte-
nance are in the responsibility of the Contractor.
Angle (terminal) and suspension towers shall be placed within the following
survey accuracy limits relative to their specified position on the profile plan:
5413A08/FICHT-7269867-v13 133
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
5413A08/FICHT-7269867-v13 134
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
B1.4.11.8.1 General
The execution of tower foundations shall be done in accordance with IEEE
Standard 977 1991 (R1997) as well as CIGRE Recommendation 308
(Foundation Installation) May 2006 and shall include the following main
activities:
Excavation works
execution of the necessary preliminary works before pouring concrete of
the foundations (anchors, groutings, coned shapes, soil exchange, com-
paction, reinforcement laying, placing of formwork, stub setting, etc.)
5413A08/FICHT-7269867-v13 135
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
concreting of foundation
backfill works
cleaning of site and transport of all superfluous materials
protection of the interface between steel tower leg and top section of
concrete function
B1.4.11.8.2 Earthworks
General
Detailed procedures are specified in the part of General Technical Require-
ments. Particular attention is drawn to the requirements of verifying and
assessing of the actual soil condition at each tower footing by an experi-
enced soil mechanic/civil expert.
Excavation
In soil class 1 to 4 the pad concrete is directly placed against the natural soil.
The excavation dimension shall be within 2 cm + 10 cm on the specified
nominal dimension observing the minimum reinforcement cover and
allowable concrete pad eccentricity not exceeding 15 % of the foundation
base width. If loose soil pockets or mismatched excavation position exceed
the tolerances, symmetrical enlargement and reinforcing bar extension shall
be made to achieve a throughout reinforced centric concrete footing struc-
ture.
5413A08/FICHT-7269867-v13 136
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Tests shall be performed for each 500m3 of fill but not less than once per
shift.
Blasting
The Contractor shall not obtain or make use of any explosives without the
express permission in writing by the local authorities.
The Contractor shall comply strictly with the regulation as required by the
authorities regarding purchase, storage, issuance and use of explosives and
transport of same to and from site, and shall be deemed to have included in
his bid all costs arising from the use, storage and transport of explosives as
well as from supervision of blasting by security forces.
All blasting shall be carried out by approved experts only and the Contractor
shall be fully liable for any claims arising from damage or alleged damage,
injury to the public etc. due to blasting.
Drilling and blasting plans shall be submitted well in advance for the
Employers/ Employers Representatives approval prior to commencement
of any blasting work.
5413A08/FICHT-7269867-v13 137
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
When blasting is carried out, trees, structures etc. in exposed position shall
be adequately protected from damage.
Drilling and blasting shall be arranged and, where necessary, the rock being
blasted shall be protected so as to prevent any scattering of the rock liable to
cause injury to the public or damage to dwellings, buildings and other
property and the works.
Blasting shall be carried out carefully to avoid the loosening of rock surfac-
es that are to remain intact, particularly in those cases where concrete is to
be placed directly against these rock surfaces.
Backfill
Unless otherwise directed, all filling shall be approved selected material and
shall be deposited and compacted using approved material in layers not
exceeding 150 mm thick for hand compaction and 250 mm for mechanical
compaction. In presence of ground water, dewatering of the foundation pit
shall be maintained during backfilling as to guarantee proper compaction of
the subsequent fill material layers.
shall be as detailed below and are applicable prior to erecting the tower
structure.
The stub setting and positioning will require the application of theodolites,
mm-graduated steel tapes, templates or lower tower base assembly, rigid
stub fixing frames and control measurements during the concreting opera-
tion. Final control measurement shall be recorded in the foundation installa-
tion sheet.
5413A08/FICHT-7269867-v13 138
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
General
Concrete material requirements and concrete testing procedure are specified
in the part of General Technical Requirements.
Placing of concrete
Concrete shall not be dropped into place from a height exceeding 2 m.
Trunks and chutes to Employers Representatives approval shall be used
for any concrete to be deposited from a height exceeding 2 m.
5413A08/FICHT-7269867-v13 139
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Concrete that is damaged from any cause such as fractured and honey-
combed shall be cut out to a depth at which sound concrete is exposed and
filled within dry pack, mortar or concrete matching the structure. All
concrete used for patching shall be bonded tightly to the surface of the
sound concrete and shall be sound and free from shrinkage cracks and rough
areas after curing and drying. All areas to be patched shall be coated with an
approved concrete bonding agent in accordance with the manufacturer's
printed instructions. Acceptance criteria of defective concrete are specified
in the General Technical Requirements.
Eccentricity of the final concrete structure relative to the stub axis shall not
exceed 10 % of cross sectional dimension of the encasing concrete (chimney
side or pile cap part).
Offsetting of formwork to meet minimum concrete cover at all times and
corresponding form enlargement up to +10 cm on the nominal dimension
may be permitted to achieve final centricity of concrete footing.
General
The Contractor shall erect the towers and tower accessories in accordance with
the approved detailed drawings.
No steel tower shall be installed until at least seven days after the last placing
of concrete in the foundation, and back-filling has been completed
Bolt tightening
In general, the towers shall be assembled and erected with bolts finger-tight
only. Finger-tight or snug-tight is about one-fourth turn from tight. Final
tightening of bolts shall only take place when all members are in place.
Bolts installed with spring washers shall be tightened to an approved torque
range and as indicated in the following table:
5413A08/FICHT-7269867-v13 140
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
5413A08/FICHT-7269867-v13 141
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Damaged members
Members that are bent, twisted or otherwise deformed in storage, transporta-
tion, handling or erecting operations shall be straightened or replaced by the
Contractor. Straightening shall be done only by the use of methods that will
not damage the zinc coating. Tolerances for lateral variations of straightened
members shall be as follows:
The Contractor shall have available on site for the Employers/ Employers
Representatives use an instrument suitable for the accurate checking of
galvanizing thickness on site. The measuring instrument shall apply an
electronic measuring method and be available from the time of arrival of the
first consignment of material until the issue of the operational acceptance
certificate. The cost of the gauge and other operating expenses are deemed
to be included in the Contract price.
Wet storage stain or bulky white deposits, flux stains or bar spots of an area >
2 cm and resisting by rubbing finger tips shall be removed by an approved
procedure till sound coating reveals and shall be subject to the application of a
repair coat as outlined below.
Damaged galvanizing
Tower members arriving on site with damaged galvanizing due to mishandling
or formation of white rust shall be repaired by an approved means and submit-
ted to the Employer/ Employers Representative for approval before erection
commences. Members rejected by the Employer/ Employers Representative
shall be reworked until the Employer/ Employers Representative is satisfied
that the repaired coating will provide protection to the member similar to an
undamaged galvanized coating.
Painting of towers
For sites liable to be flooded, the tower body (all types) shall be painted with
two coats of coal tar epoxy to a height of 1 m above ground level.
5413A08/FICHT-7269867-v13 142
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The first coat of coal tar epoxy shall be spray applied to the clean, dry steel to
give a dry film thickness of not less than 150 m. The coating shall be
checked for thickness using a magnetic coating thickness gauge and for
pinholes using a spark tester. Any deficiencies shall be repaired immediately.
A second coat of coal tar epoxy shall be applied after a minimum of four hours
after the application of the first coat but not later than five days after the
application of the first coat to give a total dry film thickness of not less than
300 m. Coal tar epoxy shall not be applied when relative humidity exceeds
85 %.
B1.4.11.10 Earthing
General
Earthing continuity from the earthwire/ OPGW to support fittings to the
earthing system is provided by surface contact of bolted members (except
ISWER system).
The use of the natural earthing consisting of the structural foundation steel is
essential. Welded connections shall be provided to include the vertical rein-
forcement bars of the chimney as well as the horizontal ones of the foundation
base (pad) into the earthing system. These weld connections shall be inspected
by the Employer/ Employers Representative before concreting.
The metallic fence gates within the right-of-way shall be electrically bound-
ed to the fences.
After installation of the earthing system, the earthing resistance test shall be
carried out.
5413A08/FICHT-7269867-v13 143
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The special instructions for stringing of the OPGW/ OPPC advised by the
OPGW/ OPPC manufacturer shall be followed. The Contractor shall engage
the manufacturer erection supervisor for the duration of the entire stringing
works.
The tension stringing method as well as the selection of equipment and tools
shall be done in accordance with IEEE Standard 524 2003. Special attention
is to be paid to the chapters regarding grounding of equipment and protection
of personnel.
The scaffolding which is used to cross specified low, medium and high voltage
power lines shall be of such dimensions to allow clearances that the power
lines being crossed may remain in operation during construction of the new
transmission line. Shut-downs on the lines to be crossed may be given for
construction of new line but shall not be given continuously for longer periods.
Such restrictions in building and use of the scaffolds shall not be grounds for
claiming additional costs. Design and construction of the live line scaffold
shall not be inferior to the minimum standards outlined in the following
clause.
The scaffold shall be designed to withstand the maximum design wind speed,
except that a reduced return period will be accepted. Consideration shall also
be given due to impact loading by dropping of the upper phase conductor. The
scaffold shall consist of square mesh nylon nets attached to steel wire ropes
running perpendicular to the lower line route, carried by metal scaffolding at
3m intervals. The nets shall be attached to the catenary wires by means that do
not require the presence of any persons on the net or the catenary wires whilst
the lower line is alive. The scaffold shall extend at least 5 m either side of the
outermost conductors of the upper line. a maximum of 2 m of this distance
may be provided by means of catchers. Catchers shall be provided at each end
of each scaffold support. The catchers may be vertical or inclined to a maxi-
mum angle of 45 from the vertical.
5413A08/FICHT-7269867-v13 144
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Where possible the resistance to earth of the scaffold shall be less than 10
ohms. Special consideration by the Employer and the lower line operator shall
be given in cases where this is not attainable with a reasonable number of
driven earth rods. Bonding the scaffold to the earthing systems of either the
life-line or the line under construction is not normally acceptable.
Drawings of the scaffold, complete with details of the clearance plates and
earthing arrangement, together with supporting, calculations shall be submitted
to the Employer/ Employers Representative for approval.
Repair of the damage shall be carried out in the manner indicated or approved
by the Employer/ Employers Representative at the expense of the Contractor.
When damage
to the conductor does not exceed two aluminum strands, either broken or
nicked deeper than one-third of their diameter
to the earthwire does not exceed two AL strands, nicked deeper than one-
third of their diameter
When more than two strands are broken, abraded or nicked deeper than one-
third of their diameter, or two AL strands, nicked deeper than one-third of their
diameter,
the damaged section of the conductor shall be cut out and jointed and
the OPGW/ OPPC shall be replaced.
When there is repeated damage on the same span or in consecutive spans, all
the conductors and earthwires affected in these spans shall be replaced.
5413A08/FICHT-7269867-v13 145
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Conductor and earthwire repair sleeves shall not be used without the permis-
sion of the Employer/ Employers Representative and will be granted only in
exceptional circumstances.
All compression joints shall be filled and finished with emery cloth to produce
a smooth surface, free of flash and sharp points, which might be a source of
corona or radio interference. The Contractor shall furnish all necessary tools,
including compression tools required.
The Contractor shall keep a record of each compression fitting showing its
location, date of assembly, and the name of the linesman responsible for the
assembly.
All conductor joints shall be located in the span at least 30m away from a
suspension clamp or tension clamp or compression dead-end. There shall be
not more than one such joint per conductor in any one span.
Sagging
The conductors and earthwires shall be sagged in accordance with ten-
sion/sag tables calculated by the Contractor and approved by the Employ-
er/Employers Representative.
5413A08/FICHT-7269867-v13 146
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
The system shall be such that other components of the line are not overload-
ed during stringing operations and conductors and earthwires are not unduly
exposed to Aeolian vibration damage in the period following the erection.
The creep calculation shall consider that the conductors hang in the string-
ing blocks 48h before being pulled to the specified sag.
z 1 0,5 S
S: horizontal span length, in (m)
z: vertical deviation in (cm) relative to the initial sag
5413A08/FICHT-7269867-v13 147
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Clearances between conductors and ground and between jumpers and all
structures are to be checked during erection and before handing over the
line.
Clipping in
All conductors and earthwires shall be accurately marked for clipping-in at
all towers on the same day following final sagging.
5413A08/FICHT-7269867-v13 148
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
center on the point of attachment. Under such circumstances the armor rods
may be reused if not damaged.
The Contractor will not be allowed any additional compensation for such
removal, re-installation, or replacement of armor rods where required.
The final suspension insulators shall hang plumb after clamped-in conductor
by a tolerance to the vertical of 2 % of the insulator set length.
The final mid-point position of sag adjuster links after clamped in conduc-
tors shall be within of l from the centre of adjustable range length (l).
The final jumper loop clearance radial from the most bottom projecting steel
part of crossarm shall be within 10 cm on the nominal dimension of the
vertical distance in the loop bend.
The execution of line hardware and insulator string set installation shall be
done in accordance with IEEE Standard 951 1996 (chapter 10 insulators
and hardware) as well as with IEEE Standard 524 2003 (chapter 10.8
damper and chapter 10.9 spacer and spacer damper).
5413A08/FICHT-7269867-v13 149
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
to ensure that the required quality is met. The Contractor shall supply all
necessary labor, material, equipment and competent and authorized test
personnel. Calibration of equipment is deemed to be included. Six (6) copies
of test reports and/ or certificates are to be provided showing all results and
information necessary within two weeks after test performance.
B1.4.11.13.2 Commissioning
The Contractor shall be responsible for satisfying the Employer/ Employers
Representative when the lines are ready to be commissioned and shall conduct
the commissioning/tests in the presence of and as instructed by the Employer/
Employers Representative. The Contractor shall provide labor, transport and
other assistance as required for Commissioning without extra charge.
If any failure is detected, the Contractor shall locate and determine the cause of
the failure and shall make any replacement or repair necessary or correct any
errors in the installation to the satisfaction of the Employer/ Employers
Representative and at no extra cost.
Prior to the energizing, the Contractor shall provide the Employer/ Employers
Representative with a written statement that all personnel and all temporary
erection earthing points are withdrawn and the line is ready for energizing.
Prior to the operational acceptance of the completed line, the following (as a
minimum) tests shall be carried out:
5413A08/FICHT-7269867-v13 150
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Telecommunication
The Contractor shall be responsible for the testing of the telecommunication
link between NDC telecommunication rooms of the substations. The corre-
sponding program shall be included in the test program.
5413A08/FICHT-7269867-v13 151
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
5413A08/FICHT-7269867-v13 152
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
1. General
Conductors
phase conductor type ACSR BLUEJAY
earthwire type ACSR 95/55
OPGW type similar to
AL/ACS 95/55
5413A08/FICHT-7269868-v8 153
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Design Temperatures
Line Data
Tower Types
o
Angle of deviation angle 0 2
5413A08/FICHT-7269868-v8 154
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
o
Angle of deviation angle 0 - 30
TP (transposition)
5413A08/FICHT-7269868-v8 155
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Structural steel sections, plates, etc for suspension towers factor 1.1
Structural steel sections, plates etc for angle towers factor 1.25
3. Clearances
Railways m 11.00
5413A08/FICHT-7269868-v8 156
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Highway m 22.5
Mid-span phase to phase clearance for horizontal phase c 0,62 f max li b 3.08
m
arrangement
Mid-span phase to phase clearance for quasi-vertical c 0,75 f max li 3.08
m
phase arrangement
Mid-span phase to OPGW clearance for quasi-vertical wire c 0.75 f max li b 2.5
m
phase arrangement
Minimum clearances between conductors/live fittings
and tower steel structure 400 kV:
Under still air for the lateral phases of double circuit line
m 3.30
towers
For suspension insulator set calculated swing under
moderate wind (58% of maximum wind pressure) m
jumper suspension sets and free jumpers under 15 swing 2.50
5413A08/FICHT-7269868-v8 157
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
All four footings per tower and soil class, horizontal terrain
level, factored loads from max. tower body and leg
extension, nominal volume excluding excess concrete, soil
parameters as shown below and dimensional conditions as
specified in the Technical Requirements, Foundation
Design.
Soil investigation
SPT or
Penetration equipment in accordance with the characteris-
DPL or
tic data as specified in the Technical Requirements, Soil type
CPT or
Investigations; If other types, specify characteristic data.
other
Foundation material
2
Concrete class (nominal cube strength 20 N/mm )
class C20/25
according to
standard EN 206-1
2
Reinforcing grade (ripped bars fy 420 N/mm ) grade BSt 420
according to standard EN 10080
Cement grade (standard Portland cement) grade CE 32.5
according to standard EN 197
Supporting documents
5413A08/FICHT-7269868-v8 158
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
3
Reinforced concrete density kN/m 24
3
Homogeneous rock density kN/m 25
3
Reinforced concrete volume incl. anchor mortar LA tower m
3
Reinforced concrete volume LA tower m
5413A08/FICHT-7269868-v8 159
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
3
Reinforced concrete density kN/m 24
3
Reinforced concrete volume LA tower m
3
Reinforced concrete density kN/m 24
3
Compacted backfill density kN/m 16
3
Concrete reinforcing content kg/m
3
Reinforced concrete volume NS tower m
3
Reinforced concrete volume LA tower m
5413A08/FICHT-7269868-v8 160
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
3
Reinforced concrete volume LA tower m
Shallow raft
Principal Foundation category type submerged or
piles
2
Ultimate bearing pressure kN/m 80
3
Reinforced concrete density kN/m 14
3
Reinforced concrete volume LA tower m
Manufacturer company -
5413A08/FICHT-7269868-v8 161
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Material used:
bolt diameter mm 16
5413A08/FICHT-7269868-v8 162
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Gusset plates mm 6
- 3m to 6m mm 2.5
- greater than 6m mm 3
Tower layout
5413A08/FICHT-7269868-v8 163
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Design spans:
Wind span m 440
Weight span max. m 700
Maximum span m 650
Minimum ratio weight to wind span for clearance
check ratio 0.80
Main dimensions:
Total height above ground for tower body/leg basic
0m m
Design spans:
Wind span m 800
Weight span max m 1100
Maximum span m 950
Minimum ratio weight to wind span for clearance check ratio 0.6
Main dimensions:
Total height above ground for tower body/leg basic m
0m
5413A08/FICHT-7269868-v8 164
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Main dimensions:
Total height above ground for tower body/leg basic m
0m
Spacing of crossarms top-middlebottom m
5413A08/FICHT-7269868-v8 165
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
o
Line angle, as Angle tower () 30 70
o
Line angle, as Terminal tower () 0-45 line direction
0-45 to S/S
gantry
Main dimensions:
Specific data
5413A08/FICHT-7269868-v8 166
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Main dimensions :
Specific data:
Design spans:
Wind span m 440
Weight span max. m 700
Maximum span m 650
Minimum ratio weight to wind span for clearance
check ratio 0.80
Main dimensions:
Total height above ground for tower body/leg basic
0m m
5413A08/FICHT-7269868-v8 167
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Design spans:
Wind span m 800
Weight span max m 1100
Maximum span m 950
Minimum ratio weight to wind span for clearance check ratio 0.6
Main dimensions:
Total height above ground for tower body/leg basic m
0m
Main dimensions:
Total height above ground for tower body/leg basic m
0m
Height of l crossarm above ground level for tower m
body/leg basis 0 m
Width between tower stubs at ground level for tower m
body/leg basic 0 m
5413A08/FICHT-7269868-v8 168
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Specific data:
o
Line angle, as Angle tower () 30 70
o
Line angle, as Terminal tower () 0-45 line direction
0-45 to S/S
gantry
Main dimensions:
5413A08/FICHT-7269868-v8 169
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
6.1 Phase Conductors
Manufacturer company -
2
Steel mm 39.3
2
Total mm 564.0
Aluminum No / mm 45 x 3.995
Steel No / mm 7 x 2.684
Ultimate breaking load, min. kN 133
Weight kg/km
2
Modulus of elasticity N/mm 72500
0
Thermal expansion coefficient 1/ C 0.0000208
5413A08/FICHT-7269868-v8 170
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Long term thermal current carrying capacity (for 40 C A
ambient temperature, 0.5 m/sec wind velocity, solar
2
radiation of 1250W/m for 85 C conductor end-
temperature)
Manufacturer company -
Aluminum No / mm 12 x 3.20
Steel No / mm 7 x 3.20
Design cross-sectional areas:
2
Aluminum mm 96.5
2
Steel mm 56.3
2
Total mm 152.8
2
max. working stress N/mm
2
EDS (25C, still air) N/mm
Weight kg / km
5413A08/FICHT-7269868-v8 171
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Standard delivery length per drum m
Manufacturer company -
Aluminum No / mm 26 x 3.00
Steel No / mm 7 x 2.33
Design cross-sectional areas:
2
Aluminum mm 183.8
2
Steel mm 29.8
2
Total mm 213.6
2
max. working stress N/mm
2
EDS (25C, still air) N/mm
Weight kg / km
5413A08/FICHT-7269868-v8 172
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Standard delivery length per drum m
Manufacturer company -
Aluminum No / mm
Steel No / mm
Design cross-sectional areas:
2
Aluminum mm
2
Steel mm
2
Total mm
Conductor diameter mm
5413A08/FICHT-7269868-v8 173
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Ultimate breaking load min. kN 44.5
2
max. working stress N/mm
2
EDS (25C, still air) N/mm
Weight kg / km
Aluminum No / mm
Steel No / mm
Design cross-sectional areas:
2
Aluminum mm
2
Steel mm
2
Total mm
Conductor diameter mm
2
max. working stress N/mm
2
EDS (25C, still air) N/mm
Weight kg / km
5413A08/FICHT-7269868-v8 174
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Modulus of elasticity N/mm
Electrical Characteristics
- T initial C 40
Lightning strike
- Current kA 100
- Duration s 0,5
- Charge transfer C 50
Temperature cycling
- TA C + 10
- TB C + 40
Fiber Characteristics:
5413A08/FICHT-7269868-v8 175
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Fiber Type ITU-T G.655
Fiber coating:
Material -
PMD ps/ km
5413A08/FICHT-7269868-v8 176
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Life span: (min) years 30
Core diameter m
Transmission wavelength nm
Fiber coating:
Material -
Nominal diameter m
- average dB/km
Attenuation at 1550 nm
-
- average dB/km
- 0 min
5413A08/FICHT-7269868-v8 177
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
- 0 max nm 1324
5413A08/FICHT-7269868-v8 178
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Corona test voltage kV 267
Specific data:
5413A08/FICHT-7269868-v8 179
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
arcing gap mm
Manufacturer company
Standards for:
- design standard
- eyes type
- swivels type
5413A08/FICHT-7269868-v8 180
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
- yokes type
Thickness of horn:
- of upper device mm
- of lower device mm
Diameter of horn
- of upper device mm
- of lower device mm
5413A08/FICHT-7269868-v8 181
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
End of lower device provided with ball - yes
Specific data:
Type type
2
Suitable for cross-sections: mm
Type type
2
Suitable for cross-sections: mm
Type type
5413A08/FICHT-7269868-v8 182
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
2
Suitable for cross-sections: mm
Type type
Material material
2
Suitable for cross-sections mm
Specific data:
I Suspension set mm
V Suspension set mm
Tension set mm
arcing gap mm
5413A08/FICHT-7269868-v8 183
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Insulator Type for Suspension and Tension Sets
Composite
IEC designation term
Manufacturer company
Standards for:
- design standard
- eyes type
- swivels type
5413A08/FICHT-7269868-v8 184
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
- split pins for bolts type
Arcing gap mm
Tension assembly
Manufacturer company
Type type
- Dead-end material
2
Suitable for cross-sections: mm
Suspension assembly
Manufacturer company
5413A08/FICHT-7269868-v8 185
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Type type
2
- Suitable for cross-sections: mm
Manufacturer company
Standard standard
Specific data:
5413A08/FICHT-7269868-v8 186
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Tension assembly
Manufacturer company
Type type
- Dead-end material
2
Suitable for cross-sections: mm
Suspension assembly
Manufacturer company
Type type
2
Suitable for cross-sections: mm
5413A08/FICHT-7269868-v8 187
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Type:
- complete with
Or
0
Temperature C
Humidity %
8. Dampers
5413A08/FICHT-7269868-v8 188
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Manufacturer company
Type type
Weight of damper kg
Material:
5413A08/FICHT-7269868-v8 189
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
- galvanized steel - yes/no
2
- tensile strength N/mm 80
- tightening torque Nm 44
0
Non metallic material temperature withstand C 10-60
Manufacturer company
Type type
- Elastomer material
Clamping bolts mm
Material:
5413A08/FICHT-7269868-v8 190
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
2
- tensile strength N/mm 80
- tightening torque Nm 44
0
Non metallic material temperature withstand C 10-85
Epoxy Polyam-
Type
ide-cured
- at 20 C h
- at 50 C h
5413A08/FICHT-7269868-v8 191
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Intermediate Coat
- at 20 C h
- at 50 C h
- red % 55
- white % 55
5413A08/FICHT-7269868-v8 192
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Color
- at 20 C h
- at 50 C h
- Diameter mm 600
international re
- Color (fadeless) color
and white
- Drainage yes
mild steel
- Fitting materials material
galvanized
- Spheres separation m 60
Manufacturer company
5413A08/FICHT-7269868-v8 193
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Experience years 10
Rated voltage V
Temperature range C 0 to 60
Humidity % 100
Rated Power W
Photovoltaic modules:
Type type
Rated voltage V
Length mm
Width mm
Depth mm
Weight Kg
Batteries:
sealed mainte-
Type type
nance free
Rated voltage V
Capacity Ah
5413A08/FICHT-7269868-v8 194
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Length mm
Width mm
Depth mm
Weight kg
Earthing conductor
round steel
galvanized
Material -
or galvanized
steel tape
Diameter round steel mm 11.5
2
cross section tape mm 40 x 6
Earth rods
round steel
Material -
galvanized
Length m 2.0
5413A08/FICHT-7269868-v8 195
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Diameter mm 15
Type of connection -
Connections:
Bolt/nut/lock washer -
5413A08/FICHT-7269868-v8 196
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Filing Cabinets 2
no.
Bookshelves 2
no.
Drawing Table 1
no.
Storage Locker 1
no.
Pin board 1
no.
Heavy duty colour printer 1
no.
Heavy duty colour photocopying machine (A4 & A3 size) 1
no.
Fire extinguisher 1
no.
Set window curtains for all windows 1
set
Cooker 1
no.
Latest version of software: Autodesk-AutoCAD 1
no.
Desktop computer, Intel Pentium4, 3.8Ghz, 1GB of DDR- 2
533 or above,300GB, 10k rpm or above internal DVD,
internal CD-WR, Professional 3D graphic windows xp
no.
Professional factory pre-loaded +recovery CD and manual,
20 TFT colour, flat screen
5413A08/FICHT-7269868-v8 197
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Air conditioner (capacity 18000 BTU) 2
no.
Refrigerator 1
no.
Filing Cabinets 2
no.
Bookshelves 2
no.
Storage Locker 1
no.
Pin board 1
no.
Fire extinguisher 1
no.
Set window curtains for all windows 1
set
Cooker 1
no.
12. Vehicles
A. Mandatory Specification
5413A08/FICHT-7269868-v8 198
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
A.3 Clutch
i. Single heavy duty dry friction disc
ii. Diaphragm spring pressure plate
iii. Hydraulic operation
A.4 Transmission
i. Automatic or
ii. Five (5) speed+reverse gear/ Manual transmission
A.5 Wheel, tires
i. Best quality 285/65 R16 (8 J alum) 8-12 ply
ii. One Spare tire suitably mounted and locked with key
iii. All tires fitted shall comply with internationally
recognized standards
A.6 Suspension
Front: High mount double wishbone using coil spring
Rear: Four link coil independent stabilizer front and rear
A.7 Brake system
i. Power assisted, independent dual hydraulic circuit
ii. Front and Rear ventilated brakes
A.8 Steering
Right Hand Drive,
Power assisted.
A.9 Electrical
i. 12 or 24 volt system
ii. Hazard warning lights, exterior lights and indicators and
twin fog lights that shall comply with Tanzania Road
regulations
iii. 6 CD Changer + Cassette + AM/FM with 6 speakers
iv. Air conditioner provided with own regulation by
passengers at the back
B. General Specification
5413A08/FICHT-7269868-v8 199
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
A. Mandatory Specification
1.0 Dimensions
1.1 G.V.W. (kg). 2500-2800
5413A08/FICHT-7269868-v8 200
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
3.1 Right-hand.
5413A08/FICHT-7269868-v8 201
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
11.4 Full vehicle tool kit including jack and wheel brace.
B. General Specification
12.0 Requirements
12.1 Long wheel base four door Double cabin, seating for
5 persons.
12.2 Color
Green.
12.3 Single or Double fuel tank with total capacity not less
than 80 litres
12.4 Fuel lids tank.
12.5 Driver/ Operator instruction manual.
12.6 Workshop instruction manuals.
13.0 Wheel, tyres
13.1 Best quality radial ply on/ off highway tyres.
5413A08/FICHT-7269868-v8 202
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
17.1 Manufacturer
17.2 Model
Address:
5413A08/FICHT-7269868-v8 203
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Plotter no. 1
5413A08/FICHT-7269868-v8 204
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Printer/Scanner/Photocopy machine
(Including supply of 30 rims of A4 and 10 rims of A3
printer/copier papers per month as well as services and
consumables such as cartridges for the entire contract
period).
1. HOOK LADDER
Material; Aluminum, Length; 8.0m, working load 600kg, no. 8
weight; 27kg,
2. WIRE ROPE
Material: steel wire with Diameter: 16mm diameter,
strength: 230kN, Length: 150m, Tapered end, Hooked no. 8
end, with reel
5413A08/FICHT-7269868-v8 205
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
4. CONDUCTOR TRIMMER WITH ONE POPULAR
BUSHING MORE BUSHING
Duty & Bushing: to trim 85 sizes of ACSR cable, one no. 4
standard bushing included,
Video storage
MPEG -4
Video streaming
MPEG-4,IP-link
5413A08/FICHT-7269868-v8 206
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Environmental
-15C to +50C
Physical characteristics
1.7kg w/battery
3. PORTABLE GENERATOR
Type: Brushless, self exciting, 2-pole, 1-phase,
Voltage output: 240,AC-50Hz, Power output:
10KW, Cooling system: Air, Cycles: 4, Fuel, no. 4
Gasoline, Starting system, Recoil starter(electric
starter optional)
5413A08/FICHT-7269868-v8 207
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
8. SAFETY BELT:
Material : nylon
Safety ropes length mm : 2000 no. 20
Safety rope diameter: 14mm
9. SAFETY HELMET
Yellow colour no. 40
1. FAULT LOCATOR
Wavelength
635 nm
Batteries
2 x alkaline AAA
Battery life
40 / 80 hours
CW / Pulsed
Operation mode
Pulsed at 2~3 Hz
5413A08/FICHT-7269868-v8 208
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Coupled power
9/125 m or
larger fiber core:
0.6 mW or -2.2
dBm2 type
Operating / storage
-10 to +45C / -
40 to +70C
2. SPLICER
5413A08/FICHT-7269868-v8 209
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
SM fibre.
Splicing modes Total number
available equals
100; for pre-set
modes and user
programmable
modes
Return loss 60dB or greater
Splice loss estimate Several types of
core defor-
mations as well
as core axis
offset are taken
into account
Attenuation splice function Intentional high
splice loss of
0.1dB to 15dB
(0.01dB step)
can be made for
an inline fixed
attenuator
Storage of splice result The last 2000
results to be
stored in the
internal memory.
Fibre display X/Y, or both X
and Y simulta-
neously
Magnification 300x for single X
or Y view, or
187x for X and Y
view.
Viewing method By two CMOS
cameras for fibre
viewing and
4.1inches TFT
colour LCD
monitor
Image change over The fibre image
is turned upside
down automati-
cally according
to the monitor
position.
Operating condition 0-5000m above
sea level, 0-95%
RH and -10 to
Mechanical proof test 50C respective-
2N (standard)
ly.
4.4 N (optional)
5413A08/FICHT-7269868-v8 210
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Carrying case 1
Cleaver 2
3. POWER METER
5413A08/FICHT-7269868-v8 211
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Case Polycarbonate, 1
metre drop
tested
Power 2 alkaline C
cells (7.6 A/Hr)
External DC
with 2.5mm
+ve pin or via
USB port.
Selectable
auto-off, low
battery indica-
tor, backlit
display
5413A08/FICHT-7269868-v8 212
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
General Specifications
Operating environment Temperature 0 to
45C (0 to 35C
when charging
the battery)
Humidity 85% RH or less
(no condensa-
tion)
Storage temperature -20 to 60C
Battery Operation time 6
hours
Recharge time 5
hours *2
Rated power voltage 100 to 240 VAC
Rated supply frequency 50 to 60 Hz
Power consumption Max 70 W
Laser safety standards Class 1 M (IEC
60825-1:1993 +
A2:2001)*3
21CFR1040.10*
4
Safety standard EN61010-1
Emission EN61326-1
Class A
EN55011 Class
A Group 1
Immunity EN61326-1
Table 2
Horizontal Axis Parameters
5413A08/FICHT-7269868-v8 213
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Measurement
distance 2
10-5
Sampling error:
1 sampling
resolution
Vertical Axis Parameters
Vertical axis scale 0.2 dB/div, 0.5
dB/div, 1 dB/div,
2 dB/div, 5
dB/div, 7.5
dB/div
Readout resolution 0.001 dB (Min.)
Loss measurement accuracy * 0.05 dB/dB
*When the
measuring loss
is 1 dB or less,
the accuracy is
within 0.05 dB.
OTDR Measurement Function
Distance measurement
Displays up to eight digits of the relative one-way
direction between two arbitrary points on the trace.
Loss measurement
Displays one-way loss in steps of 0.001 dB to a
maximum of 5 digits. Displays the one-way loss,
loss per unit length, and splice loss between any
arbitrary points on the trace.
Return loss measurement
Measures return loss and total return loss of a fi-
ber cable or between two arbitrary points on the
trace.
Scheduling function
Performs measurements and saves results onto a
USB storage in a user defined time frame and in-
terval
automatically.
Analysis functions
Multi trace analysis, 2 way trace analysis, differen-
tial trace analysis, section analysis
5413A08/FICHT-7269868-v8 214
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Internal Memory
Memory capacity 1000 waveforms or more
Can store measured waveforms and measurement
conditions
Display
5413A08/FICHT-7269868-v8 215
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
File Formats
Read: SOR,
TRD, TRB,
SET
(AQ7270/75)
Write: SOR
(Telcordia),
SET, CSV,
BMP, JPG,
PNG
Stabilized Light Source Function
Modulation frequency 2 Hz
5413A08/FICHT-7269868-v8 216
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part B1)
Technical Schedules
Bidder / Contractor
400 kV Overhead Transmission Line
Description
Power Monitor Function
Dummy Fiber
Optical fiber SM (ITU-T
G.652)
5413A08/FICHT-7269868-v8 217
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part C)
C
Employers Requirements
Drawings
5413A08/FICHT-7370493-v1 C1-1
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI (Part C)
List of Annexes
5413A08/FICHT-7370493-v1
1.1
1.2
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Iringa Dodoma Field Data Sheet
Field investigation
Data accuracy
1 nr. 2 100 m 100 m 0.15 km 10 houses 20% of density 1 cl. on soil state see report
Line Details
new S/S Iringa
Gantry 35 Grid Zone 36 M gentle slope, workshop -
801 040 9 138 120 buildings, tel. overhead med. dense, clayey,
0.11 line scrub, grass land
coarse sand, boulders
good access
A1 35 r 800 960 9 138 200 close to road
flat to steep slope, river med. dense, clayey,
b ~ 20m, Little Ruaha, grass land, small coarse sand,
0.72 district gravel road, trees boulders, partly
national asphalt road ground water access from field track,
80 r hilly terrain, seasonal upper part slope to
A2 800 960 9 138 920
(2 x 40) rivers, localized erosion construct, 2 angle
grass land, towers 40
prone zones dense, clayey, coarse
1.81 cultivation, scrub,
sand, boulders
some trees
-
A3 40 l 802 740 9 139 230
hilly terrain, hill foot, scattered access slope to
small seasonal brooklet cultivation, some dense, clayey sand,
0.45 construct
partly outcrop rock
bush with trees -
steep slope, seasonal access from field track,
A4 40 l 803 020 9 139 580 dense, coarse clayey
river grass land, scrub, 55m paral. exist.
1.6 sand, boulders and
some bush 220 kV
outcrop rock
5413A08/FICHT-7268302-v1 1
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Iringa Dodoma Field Data Sheet
75 l
109 809 600 9 177 500
(45 + 30) extensive
clayey coarse sand, near road, 55 m paral.
slightly hilly, ~ 5 brick cultivation,
3.7 dense, underlain by exis. 220 kV
houses, seasonal river scattered small
rock blocks
trees
5413A08/FICHT-7268302-v1 2
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Iringa Dodoma Field Data Sheet
5413A08/FICHT-7268302-v1 3
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Iringa Dodoma Field Data Sheet
transposition tower,
access from road, 55m
to 220 kV
5413A08/FICHT-7268302-v1 4
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Iringa Dodoma Field Data Sheet
5413A08/FICHT-7268302-v1 5
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Iringa Dodoma Field Data Sheet
5413A08/FICHT-7268302-v1 6
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Iringa Dodoma Field Data Sheet
5413A08/FICHT-7268302-v1 7
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Dodoma - Singida Field Data Sheet
1 nr. 2 100 m 100 m 0.15 km 10 houses 20% of density 1 cl. on soil state see report
Line Details
5413A08/FICHT-6290832-v 8
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Dodoma - Singida Field Data Sheet
5413A08/FICHT-6290832-v 9
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Dodoma - Singida Field Data Sheet
5413A08/FICHT-6290832-v 10
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Dodoma - Singida Field Data Sheet
5413A08/FICHT-6290832-v 11
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Dodoma - Singida Field Data Sheet
5413A08/FICHT-6290832-v 12
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Singida - Shinyanga Field Data Sheet
1 nr. 2 100 m 100 m 0.15 km 10 houses 20% of density 1 cl. on soil state see report
Line Details
Gantry Grid Zone M36 gentle slope, 220 kV dense, clayey sand new S/S Singida
10 cultivation, grass
Singida 695 000 9 465 000 0.1 line between tower 1 with some larger
land
and 2 boulders field track from S/S
1 (Term.) 90 l 60m to 220 kV
695 000 9 464 900 some cultivation, dense, clayey sand,
Arusha (2 x 45) flat, village road,
1.9 some trees, some occ. large boulders,
seasonal river field track, 55m to 220
grass land partly ground water
kV, 150m off tower 7
7th (14) 75 l
696 850 9 464 800 flat to gentle slope, towards S/S Singida
Arusha (2 x 40)
220 kV line between dense, clayey sand,
scattered
tower 6 and 7, main occ. boulders, partly
cultivation, some
9.5 gravel road, village outcrop rock, partly
trees, grass land,
road (bad. cond.), ~ 10 swampy, partly access from village
open bush
A1 40 l 700 200 9 473 700 mud houses, seasonal ground water road (bad condition)
river, swamp
5413A08/FICHT-6290832-v 13
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Singida - Shinyanga Field Data Sheet
5413A08/FICHT-6290832-v 14
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Singida - Shinyanga Field Data Sheet
5413A08/FICHT-6290832-v 15
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Singida - Shinyanga Field Data Sheet
5413A08/FICHT-6290832-v 16
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Singida - Shinyanga Field Data Sheet
5413A08/FICHT-6290832-v 17
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP), Bidding Documents Annex 1.2
Line Section: Singida - Shinyanga Field Data Sheet
5413A08/FICHT-6290832-v 18
Iringa
New Su
bstatio o ma Legend
nA lternati Dod
ve Existing Installations
a
om
Dod 220 kV transmission line
SB Substation Building
MV Medium Voltage Switchyard
LF
New Installations
TR
TR
LF
TR TF R 220 kV Reactor 2013
MV
LF
BC
LF
LF
SB
BC
TF
TR
Future -
TF
Future -
LF LF 220 kV Line Feeder 2013 (Space for 220 kV Spare Feeder 2021)
TR SV
CF
EHV transmission line 2013 - 2021
Kihansi
Existin 220 kV interim connection strip 2013 - 2021
g 220 kV
switchg
ear EHV transmission line 2021
ve
Mbeya
ANNEX 1.4.1
Satellite picture: 2007 Digital Globe New Iringa Shinyanga Transmission Line
2008 Europa Technologies FICHTNER
2007 Google
Iringa Substation - Incoming Transmission Line
Dodoma
Legend
Existing Installations
220 kV transmission line
tation
New Subs
SB Substation Building
MV Medium Voltage Switchyard
LF
TR 220 kV / MV Transformer
LF LF
LF LF 220 kV Line Feeder
LF
R RF TF 220 kV Transformer Feeder
LF
RF
ingida R
220 kV Reactor Feeder
Singida S
RF
LF
BC Space for 220 kV Spare Feeder
LF(TF)
TR
TF
LF
RF New Installations
TF TR
R 220 kV Reactor 2013
a
Singid
MV
SB
CCB CCB 220 kV Coupler Circut Breaker at Place of Spare Feeder 2013)
Substatio
TR EHV / 220 kV Transformer
TF EHV Transformer Feeder
n Location
n Location
Iringa
Alternative
ANNEX 1.4.2
Satellite picture: 2007 Digital Globe New Iringa Shinyanga Transmission Line
2008 Europa Technologies FICHTNER
2007 Google
Dodoma Substation - Incoming Transmission Line
Singida
Legend
Existing Installations
220 kV transmission line
SB Substation Building
MV Medium Voltage Switchyard
New Substation
SVC SVC Installation
TR 220 kV / MV Transformer
Future LF
Future LF
220 kV Line Feeder
BC
TF
TF
LF
LF
LF
LF
LF
TR
TR
SVC
SB
LF
TF
LF
TF
TF
RF
RF
TF
RF
LF
LF
LF
Dod
ng
om
oma
ma
- ANNEX 1.4.3
Satellite picture: 2007 Digital Globe New Iringa Shinyanga Transmission Line
2008 Europa Technologies FICHTNER
2007 Google
Singida Substation - Incoming Transmission Line
Shinyanga
M
w
Legend
an
Bu
za
Existing Installations
ly
an
hu
220 kV transmission line
lu
132 kV transmission line
SB Substation Building
MV Medium Voltage Switchyard
SVC SVC Installation
TR 220 kV / MV Transformer
agi 132
zw 132 kV Installations
Bu LF LF
kV
TR
SV
TF 220 kV Transformer Feeder
Exi witch
SB
C
TF Singid
a 220 kV Reactor Feeder
MV
RF
TR
g2
LF
Space for 220 kV Spare Feeder
20
TF
132
TR
kV
kV
RF
New Installations
r
RF Sing
ida R 220 kV Reactor 2013
TF
TR
LF LF 220 kV Line Feeder 2013 (Space for 220 kV Spare Feeder 2021)
LF EHV transmission line 2013 - 2021
LF 220 kV interim connection strip 2013 - 2021
ure
Fut
LF EHV transmission line 2021
ure
Fut
tion
sta TR EHV / 220 kV Transformer
Sub
New TF EHV Transformer Feeder
a
and
/ Ug LF EHV Line Feeder
nda
Rwa BC EHV Bus Coupler
Space for EHV Spare Feeder
ANNEX 1.4.4
Satellite picture: 2007 Digital Globe New Iringa Shinyanga Transmission Line
2008 Europa Technologies FICHTNER
2007 Google
Shinyanga Substation - Incoming Transmission Line
Pad & Chimney Foundation
Design Parameters
C 0.3 m
T 2.0 m
B/T 0.5 1.0
D 0.1 x B 0.3
U 0.5 x D 0.2
Frustum 0 - 25
a 450
450
450
300 mm
480 mm
Black
White
500 mm
Note:
Minimum of eight rods plus one
centre rod to prevent bird nesting,
made of non-conductive material.
Example of Bird/Perch
Rejector
7
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
5413A08/FICHT-7273316-v1 I
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
Date:
Loan/Credit No:
IFB No:
______________________________
To: _________________________________
However, you are required to complete the outstanding items listed in the attachment
hereto as soon as practicable.
This letter does not relieve you of your obligation to complete the execution of the
Facilities in accordance with the Contract nor of your obligations during the Defect
Liability Period.
Title
(Project Manager)
5413A08/FICHT-7273316-v1 1
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
Date:
Loan/Credit No:
IFB No:
_________________________________________
To: ________________________________________
This letter does not relieve you of your obligation to complete the execution of the
Facilities in accordance with the Contract nor of your obligations during the Defect
Liability Period.
Title
(Project Manager)
5413A08/FICHT-7273316-v1 2
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
Date:
Loan/Credit No:
IFB No:
CONTENTS
1. General
2. Change Order Log
3. References for Changes
ANNEXES
5413A08/FICHT-7273316-v1 3
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
This section provides samples of procedures and forms for implementing changes in
the Facilities during the performance of the Contract in accordance with GC Clause
39 (Change in the Facilities) of the General Conditions.
The Contractor shall keep an up-to-date Change Order Log to show the current status
of Requests for Change and Changes authorized or pending, as Annex 8. Entries of
the Changes in the Change Order Log shall be made to ensure that the log is up-to-
date. The Contractor shall attach a copy of the current Change Order Log in the
monthly progress report to be submitted to the Employer.
Note: (a) Requests for Change issued from the Employers Home Office and the
Site representatives of the Employer shall have the following respective
references:
(b) The above number nnn is the same for Request for Change, Estimate
for Change Proposal, Acceptance of Estimate, Change Proposal and
Change Order.
5413A08/FICHT-7273316-v1 4
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Employers Letterhead)
Attention: ______________________________________
With reference to the captioned Contract, you are requested to prepare and submit a
Change Proposal for the Change noted below in accordance with the following instructions
within _______________ days of the date of this letter ____________________.
(a) Please submit your estimate to us showing what effect the requested Change
will have on the Contract Price.
(b) Your estimate shall include your claim for the additional time, if any, for
completion of the requested Change.
5413A08/FICHT-7273316-v1 5
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(c) If you have any opinion negative to the adoption of the requested Change in
connection with the conformability to the other provisions of the Contract or the
safety of the Plant or Facilities, please inform us of your opinion in your
proposal of revised provisions.
(d) Any increase or decrease in the work of the Contractor relating to the services
of its personnel shall be calculated.
(e) You shall not proceed with the execution of the work for the requested Change
until we have accepted and confirmed the amount and nature in writing.
(Employers Name)
(Signature)
(Name of signatory)
(Title of signatory)
5413A08/FICHT-7273316-v1 6
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Contractors Letterhead)
Attention: _______________________________
With reference to your Request for Change Proposal, we are pleased to notify you of the
approximate cost of preparing the below-referenced Change Proposal in accordance with
GC Sub-Clause 39.2.1 of the General Conditions. We acknowledge that your agreement to
the cost of preparing the Change Proposal, in accordance with GC Sub-Clause 39.2.2, is
required before estimating the cost for change work.
(Contractors Name)
2
Costs shall be in the currencies of the Contract.
5413A08/FICHT-7273316-v1 7
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Signature)
(Name of signatory)
(Title of signatory)
5413A08/FICHT-7273316-v1 8
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Employers Letterhead)
Attention: ________________________________
We hereby accept your Estimate for Change Proposal and agree that you should proceed
with the preparation of the Change Proposal.
6. Other Terms and Conditions: In the event that we decide not to order the Change
accepted, you shall be entitled to compensation for the cost of preparation of Change
Proposal described in your Estimate for Change Proposal mentioned in para. 3 above
in accordance with GC Clause 39 of the General Conditions.
(Employers Name)
(Signature)
5413A08/FICHT-7273316-v1 9
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Contractors Letterhead)
Attention: _______________________________
(Amount)
(d) Subcontracts
3
Costs shall be in the currencies of the Contract.
5413A08/FICHT-7273316-v1 10
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
12. Validity of this Proposal: within [Number] days after receipt of this Proposal by the
Employer
(a) You are requested to notify us of your acceptance, comments or rejection of this
detailed Change Proposal within ______________ days from your receipt of this
Proposal.
(b) The amount of any increase and/or decrease shall be taken into account in the
adjustment of the Contract Price.
2
Specify where necessary.
5413A08/FICHT-7273316-v1 11
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Contractors Name)
(Signature)
(Name of signatory)
(Title of signatory)
5413A08/FICHT-7273316-v1 12
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Employers Letterhead)
Attention: _______________________________
We approve the Change Order for the work specified in the Change Proposal (No.
_______), and agree to adjust the Contract Price, Time for Completion and/or other
conditions of the Contract in accordance with GC Clause 39 of the General Conditions.
5. Authorized Price:
5413A08/FICHT-7273316-v1 13
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Employers Letterhead)
Attention: _______________________________
We instruct you to carry out the work in the Change Order detailed below in accordance
with GC Clause 39 of the General Conditions.
5413A08/FICHT-7273316-v1 14
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Employers Name)
(Signature)
(Name of signatory)
(Title of signatory)
5413A08/FICHT-7273316-v1 15
BACKBONE TRANSMISSION INVESTMENT PROJECT (BTIP) TANESCO
400kV Transmission Line Lot 1, 2 & 3 Bidding Documents
Section VI
(Contractors Letterhead)
Attention: _______________________________
We hereby propose that the below-mentioned work be treated as a Change in the Facilities.
8. Appendix:
(Contractors Name)
(Signature)
(Name of signatory)
(Title of signatory)
5413A08/FICHT-7273316-v1 16