2013 TENCON ModelingAndValidation
2013 TENCON ModelingAndValidation
AbstractAs new technologies such as Photovoltaics physical constraints and real-time system state have
(PVs), Embedded Generators (EGs) and Electric Vehicles become crucial to designing a stable, efficient network
(EVs) penetrate Low Voltage (LV) distribution networks, facilitating smart grid development.
the need to understand the constraints and real time system
state of LV networks becomes essential for smart grid de- The two key components required to better understand
velopment. This paper demonstrates that, given household LV networks are accurate network models and smart
Smart Meter demand data combined with 66kV/22kV zone meter consumption data to provide real inputs into the
substation SCADA voltage data, it is possible to model LV model. This work aims to do this by modeling a three-
networks on a per-phase basis to a high degree of accuracy phase, four-wire unbalanced model [4] of an urban net-
in near real time. Our model is based on a real suburb in
urban northern Melbourne consisting of 113 customers, work in northern Melbourne consisting of 113 customers
and is populated with real conductor properties, route (Fig. 1). By linking each customers National Meter-
lengths and customer phase allocations to create a true ing Identifier (NMI) to the smart meter consumption
unbalanced three-phase, four-wire model. Time stepped database, real load data per customer is integrated into
load flow simulations of the model are compared with data the LV model. Combining an accurate LV model with
loggers installed on the LV network for validation, and on
average simulated results differ from real measurements real world and near real-time smart meter and SCADA
by less than 0.5% for phase voltages and less than 10% data, a solid foundation for EV and EG optimisation and
for phase currents. Such accuracy allows for evaluation of planning applications can be developed to better plan and
PV, EV and EG impact mitigation strategies and planning manage LV networks.
in reference to the Electricity Distribution Code with a
strong degree of confidence. This LV model is unique as it II. LV M ODEL C ONFIGURATION
has been validated and is the only bottom-up load model
that utilizes near real time Smart Meter and SCADA inputs A. LV Model Layout
to analyse impacts on distribution assets on a per phase, The LV model was created using the load flow pack-
unbalanced basis.
age DigSilent PowerFactory.1 Conductor properties were
I. I NTRODUCTION entered into the model using conductor specification data
sheets for the conductors used in the LV Network. In a
Electricity distribution companies own and operate similar manner, the distribution transformer was modeled
the infrastructure required to connect customers to the according to the specification datasheet. Conductor route
network. Distribution networks utilise different voltage lengths for the LV backbone (conductors between dis-
levels: High Voltage (HV 66kV), Medium Voltage (MV tribution poles) and the service cables to each customer
11kV to 22kV) and Low Voltage (LV 400V or 230V). were determined via physical onsite inspection and using
The majority of residential and small business customers GIS software cross-referenced with satellite photos of
are connected to the LV network with single phase the LV Network. The model also imports the 22kV
or three phase connections. Traditionally distribution conductor and zone substation data from available HV
companies had no requirement to model the LV network models. The infinite bus is defined at the 66kV bus into
in great detail and only considered the overall aggregate the zone substation.
load of each LV distribution transformer. Until recently, Each house (indicated by triangles in Fig. 2) is con-
this level of granularity was sufficient for distribution nected to a distribution pole via service cables. The
network planning and analysis. However as disruptive colour of each service cable indicates the phase that
technologies such as PVs, EGs and EVs are connected
to LV networks [1][2][3], the need to understand the 1 DIgSILENT PowerFactory http://www.digsilent.com.au/
This allows the model to access actual and near real
time demand data at a granular level. Each smart meter
provides voltage, current and consumption data at 30-
minute intervals. The zone substation component of the
model is fed with a SCADA voltage data stream from
the 66kV/22kV transformers (Fig. 3).
C. LV Data Loggers
Two GridSense PowerMonic PM45 loggers (Fig. 4)
were installed at two locations on the LV network as
shown by red circles in Fig. 1. The loggers measure key
Fig. 1. Model Topology (113 customers) - Red circles indicate
locations of LV Data Loggers used as reference for validation. parameters such as Voltage and Current at one-minute
intervals for all three phases and neutral. This data serves
as a reference point for the real state of the LV backbone.
the customer is connected to. Phase allocation for each
customer in the model reflects the actual connection to
the LV network in order to establish a true unbalanced
model.
III. VALIDATION
The LV model is said to be valid if the model outputs
match the current and voltage measurements of each
phase recorded via the loggers for each 30-minute time
Fig. 2. Phase allocation Red refers to Red Phase, Blue refers to Blue
Phase and Green refers to White Phase
interval over a period of one day. This is achieved by
importing the demand data from all 113 homes in the
LV network into the model at time 00:00:00. Load flow
B. Smart Meter / SCADA Data Integration analysis is conducted to determine the LV system state.
Each house in the LV model is integrated with a The voltage and current model outputs are recorded at
data stream from the individual customers smart meter. the two positions where the loggers are installed (Logger
2
Fig. 5. Voltage Validation at Distribution Transformer - Blue line
represents the voltage measured at the distribution transformer via the
LV Data Loggers. The red line is the LV model estimation of the
voltage at the same point.
3
Fig. 7. Voltage Validation at LV Network Midpoint - Blue line
represents the voltage measured at the distribution transformer via the
LV Data Loggers. The red line is the LV model estimation of the
voltage at the same point. Green dotted line represents the voltage at
the transformer for comparison purposes
4
Fig. 11. Transformer utilisation with limits