Project Planning

The document outlines a project plan with 13 tasks over several quarters in 2017 and early 2018. The project involves meeting with a supervisor, researching a title, creating objectives, literature reviews, simulations, experimental testing, thesis writing, and final presentation preparation. Key milestones include preparation of three progress reports across Q2, Q3, and Q4 of 2017.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views

Project Planning

The document outlines a project plan with 13 tasks over several quarters in 2017 and early 2018. The project involves meeting with a supervisor, researching a title, creating objectives, literature reviews, simulations, experimental testing, thesis writing, and final presentation preparation. Key milestones include preparation of three progress reports across Q2, Q3, and Q4 of 2017.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID Task Name Duration Start

Qtr 2, 2017 Finish Qtr 3, 2017 Qtr 4, 2017 Qtr 1, 2018


Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
0 PROJECT PLANNING186 days?Thu 01-06-17Thu 15-02-18
1 MEET PROJECT 4 days Thu Tue
SUPERVISIOR 01-06-17 06-06-17
2 FINDING PROJECT 5 days Tue Mon
RESEARCH TITLE 06-06-17 12-06-17
3 CREATE 3 MAIN 6 days Mon Mon
OBJECTIVE 12-06-17 19-06-17
4 RESERCH 15 days Mon Fri 30-06-17
UNDERSTANDING 12-06-17
5 PREPARATION PR1 12 days Fri 23-06-17 Mon 10-07-17 10-07
6 UNDERSTANDING 11 days Mon Sat 22-07-17
MORTE CARLO 10-07-17
7 SIMULATION
LITERATURE 3 days Sat 22-07-17 Tue
REVIEW AND 25-07-17
8 METHDOLODY PR2 7 days
PREPARATION Sat 22-07-17 Mon 31-07-17 31-07
9 PREPARATION 11 days Mon Mon 14-08
FOR ORAL 31-07-17 14-08-17
10 PRESENTATION
EXPERIMENTAL 11 days Mon Sun
TEST AND RESULT 09-10-17 22-10-17
11 COLLECTION PR3 9 days
PREPARATION Thu 19-10-17Tue 31-10-17 31-10
12 RESEARCH THESIS 40 days Thu Wed 03-01
WRITING 09-11-17 03-01-18
13 PREPARATION 32 days Wed Thu 15-02
FOR FINAL 03-01-18 15-02-18
PRESENTATION

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: PROJECT PLANNING.m
Milestone Inactive Summary Start-only Progress
Date: Sun 09-07-17
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 1