Long Intl Acceleration Claims On Eng and Constr Projects
Long Intl Acceleration Claims On Eng and Constr Projects
L ONG INTERNATIONAL
Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com
Acceleration Claims on
Engineering and Construction Projects
Richard J. Long, P.E.
Table of Contents
1. INTRODUCTION............................................................................................................................................... 1
2. TYPES OF ACCELERATION .......................................................................................................................... 2
3. KEY ELEMENTS OF ACCELERATION REQUIRED BY THE COURTS ............................................... 6
4. ACCELERATION CLAIMS OUTSIDE OF THE UNITED STATES ........................................................ 10
5. NOTICE REQUIREMENTS ........................................................................................................................... 13
6. THE RELEVANCE OF THE DATE WHEN THE TIME EXTENSION IS GIVEN................................. 15
7. CONTRACT PROVISIONS ASSOCIATED WITH ACCELERATION.................................................... 18
8. THE EFFECT OF A NO DAMAGE FOR DELAY CLAUSE ON ACCELERATION ............................... 23
9. IDENTIFYING ACCELERATION USING THE PROJECT SCHEDULES............................................. 25
10. DOCUMENTING ACCELERATION EVIDENCE ...................................................................................... 34
11. ACCELERATION DAMAGES ....................................................................................................................... 35
List of Figures
Figure 1: Proof of Acceleration ................................................................................................................................. 29
Figure 2: Schedule Analysis Showing No Acceleration Occurred ............................................................................ 30
Time is money especially on engineering and construction projects. Because delays in the
completion of the project usually result in increased owner, engineer, and contractor costs, the
overall time of performance is vital to the financial success of the project. The importance of
time is evidenced by the significant role played by CPM schedules, completion dates, and
milestones in the bidding and awarding of engineering and construction contracts. The desire to
minimize costs and the time of performance often causes the occurrence of acceleration.
Types of Acceleration;
Key Elements of Acceleration Required by the Courts;
Acceleration Claims Outside of the United States;
Notice Requirements;
The Relevance of the Date When the Time Extension Is Given;
Contract Provisions Associated with Acceleration;
The Effect of a No Damage For Delay Clause on Acceleration;
Identifying Acceleration Using the Project Schedules;
Documenting Acceleration Evidence; and
Acceleration Damages.
1
For a more detailed legal analysis of acceleration claims and relevant case law, see Wickwire, Jon M., Driscoll,
Thomas D., Hurlbut, Steven B., and Hillman Scott B., Construction Scheduling: Preparation, Liability, and
Claims, Second Edition, 7.10 Acceleration, Aspen Publishers, 2003; Cushman, Robert F., Carter, John D.,
Gorman, Paul J., and Coppi, Douglas, F., Proving and Pricing Construction Claims, Third Edition, 4
Acceleration Claims, Aspen Publishers, 2011.
There are three types of acceleration: directed acceleration, constructive acceleration, and
voluntary acceleration.
Directed acceleration occurs when the owner or construction manager issues a specific order to
its construction contractor under the contract provisions to 1) complete the project earlier than
the originally scheduled completion date, 2) re-sequence the work and/or utilize overtime,
additional shifts, and/or extra engineering or construction labor, supervision, or equipment to
complete the base contract work plus additional or changed work within the original contract
time,2 or 3) re-sequence the work and/or utilize overtime, additional shifts, and/or extra
engineering or construction labor, supervision, or equipment to make-up for contractor-caused
delays that threaten the on-time completion of the project. These measures can result in costs
being incurred that would not otherwise have been required.
Section 52.243-4 of the U.S. Federal Acquisition Regulations specifically permits the contracting
officer to issue a change order directing acceleration in the performance of the work, and
expressly requires a contractor to show that it notified the contracting officer that it regarded any
other written or oral communication causing acceleration as a change order. The regulation
provides, in relevant part, as follows:
(a) The Contracting Officer may, at any time, without notice to the sureties, if any,
by written order designated or indicated to be a change order, make changes in
the work within the general scope of the contract, including changes - (1) In the
specifications (including drawings and designs); (2) In the method or manner of
performance of the work; (3) In the Government-furnished property or services;
or (4) Directing acceleration in the performance of the work.
(b) Any other written or oral order (which, as used in this paragraph (b), includes
direction, instruction, interpretation, or determination) from the Contracting
Officer that causes a change shall be treated as a change order under this clause;
provided that the Contractor gives the Contracting Officer written notice stating
(1) the date, circumstances, and source of the order and (2) that the Contractor
regards the order as a change order.
The AIA Document A201, Article 8.3 (2007) contains a similar provision, as do many
private contracts.
2
See, e.g., Ace Constructors, Inc. v. United States, 70 Fed. Cl. 253, 281 (Fed.Cl. 2006); Mactec v. Bechtel
Jacobs, 346 Fed.Appx. 59 (6th Cir. 2009) No. 08-5764.
Many cases involving claims for constructive acceleration have been litigated in the federal
agency appeals boards and the United States Court of Federal Claims, and have involved
construction or procurement contracts with the federal government. Constructive acceleration
also been alleged in cases involving claims against private contractors, as well as state and local
government entities.3
Voluntary acceleration occurs when a contractor unilaterally decides to accelerate its own work.
In contrast to directed acceleration or constructive acceleration, in a voluntary acceleration, a
contractor is not entitled to damages as a result. A contractor may voluntarily accelerate its work
out of necessity, i.e., to make up lost time for the contractors own delays or to complete its
own work.
To determine whether a constructive acceleration condition exists, one must look at the facts of
each particular case. Generally, a request, as opposed to a directive, to accelerate is sufficient to
constitute a constructive acceleration order. Most changes clauses are worded to give the owner
or construction manager the power to accelerate the work, particularly if the contractor is falling
behind due to its own performance problems. If an owner or construction manager instructs the
3
See, e.g., Murdock & Sons Constr., Inc., 461 F.3d at 838; McDevitt & Street Co. v. Marriott Corp., 713 F.
Supp. 906, 915 (E.D. Va. 1989); Envirotech, 715 F. Supp. at 191; Sherman R. Smoot Co., 736 N.E.2d at 72;
Fru-Con Corp. v. State of Illinois, 50 Ill. Ct. CI. 50, 51 (Ill. Ct. CI. 1996); Dept. of Transp. v. Anio Constr. Co.,
666 A.2d 753, 756 (Pa. Commw. Ct. 1995).
Acceleration claims must establish a factual base that the owner or construction manager
directed acceleration or constructively required acceleration. A mere request by the owner or
construction manager for additional information on a requested time extension or for an updated
CPM schedule is not an order to accelerate. Contractors claims for acceleration have been
denied because the owner did not direct it to adhere to the original construction schedule.5 Key
words that are associated with acceleration include overtime, extra shift, longer work day/week,
schedule change, early completion, denial of time extension, insufficient time extension,
excusable delay, work efficiency, slow down order, and speed up.
A related condition called deceleration can also be experienced on the project. Deceleration
occurs if the construction contractor is directed in writing or constructively to slow its job
progress. Many of the same considerations that apply to acceleration are also applicable to
deceleration. If overall project delay results from deceleration, the contractors extended
overhead costs may be recoverable.
Acceleration claims almost always occur on projects that have already experienced excusable
delays. Thus, an acceleration claim is typically included with a delay claim. If excusable delays
occur that would warrant an extension of time, or an extension of time and compensation, an
owner or construction manager may choose to direct completion of the work on an accelerated
basis rather than extend the contract date. By directing the contractor to accelerate, the owner or
4
See, e.g., Mobile Chem. Co. v. Blount Bros. Corp., 809 F2d 1175 (5th Cir. 1987).
5
See, e.g., Fuerland-Werkstatten Gmbh., ASBCA 32,970, 87-3 BCA 20,012.
Absent a direct or written order, it often becomes difficult to ascertain if a contractor has been
constructively accelerated. Such uncertainty often results in a dispute. Courts traditionally
examine five key elements to determine if a contractors work has been accelerated:
If these elements are proven, the contractor may be entitled to recover the costs that it incurred in
accelerating its performance if it can demonstrate its costs.6
Time extensions should be granted only for excusable delays that can be shown to have impacted
the current critical path of the schedule. Excusable delays can be delays that are caused by the
owner, such as changes to the scope of work, delays for which the owner assumes responsibility,
such as differing site conditions, or force majeure delays defined by the contract, which can
include unusually severe weather, strikes, or government actions. Therefore, owners or
construction managers should contractually require the contractor to update the CPM schedule
on a regular basis. Furthermore, to prove delays, the contractor should have updated the CPM
schedules on a regular basis, even if no contractual obligation to do so exists.
Recovery of acceleration costs attributable to making up lost time resulting from excusable
delays requires proof that the delay was unforeseeable and, in some material way, beyond the
6
M.S.I. Corp., GSBCA 2429, 68-2 BCA 7377. Also see Norair Engg Corp. v. United States, 666 F.2d 546
(Ct. C1. 1981), where the court held that for an acceleration claim to be successful the contractor must establish
three elements: (i) that an excusable delay had occurred; (ii) the contractor was ordered to accelerate; and (iii)
the contractor had actually accelerated and incurred costs.
Labor disputes;7
Changes in scope;8
Requirements to supply an alternative supply of material;9
Acts of God and unusually severe and unforeseeable weather conditions;10
Differing site conditions;11
Design changes;
Owners failure to coordinate multiple prime contractors;12
Owners failure to provide adequate access to the site;13
Owners failure to provide the right of way;14
Suspension of the contractors performance;15
Interference by the owner in the contractors performance;16
Third party delays under the owners control, such as the architect or the
engineer;17 and
Other causes beyond the contractors control.
7
See, e.g., Contracting and Material Co. v. City of Chicago, 20 Ill. App. 3d 684, 692, 314 N.E.2d 598, 604
(1974), revd on other grounds, 64 Ill. 2d 21, 349 N.E.2d 389 (1976).
8
See, e.g., Wallace Process Piping Co. v. Martin Marietta Corp., 251 F. Supp. 411, 418 (E.D. Va. 1965); J&K
Plumbing & Heating Co. v. State, 235 A.D.2d 751 (N.Y. App. Div. 1997).
9
See, e.g., Elte, Inc. v. S.S. Mullen, Inc., 469 F.2d 1127 (9th Cir. 1972).
10
Iconco, 224 Ct. Cl. 692. 27 Cont. Cas. Fed. (CCH) 80,392 (1980). Also see Edge Construction Company, Inc.
v. United States (Fed.Cl. October 29, 2010), No. 06-635C; Fraser Constr. v. United States, 384 F.3d 1354,
1360-61 (Fed. Cir. 2005); Constructors-Pamco, ENGBCANo. 3468, 76-2 BCA 11,940 (1976).
11
See, e.g., Transpower Constructors v. Grand River Dam Auth., 905 F2d 1413, 1418 (10th Cir. 1990).
12
See, e.g., Eric A. Carlstrom Constr. Co. v. Independent Sch. Dist. No. 77, 256 N.W.2d 479 (Minn. 1977).
13
See, e.g., Elte, Inc. v. S.S. Mullen, Inc., 469 F.2d 1127 (9th Cir. 1972).
14
See, e.g., Anderson Development Corp. v. Coastal State Crude Gathering Co., 543 S.W.2d 402.
15
See, e.g., T.C. Bateson Constr. Co. v. United States, 319 F2d 135 (Ct. Cl. 1963); Wallace Process Piping Co. v.
Martin Marietta Corp., 251 F. Supp. 411, 418 (E.D. Va. 1965).
16
See, e.g., Housing Auth. V. E.W. Johnson Constr. Co., 264 Ark. 5243, 573 S.W.2d 316 (1978).
17
See, e.g., Norair Engg Corp. v. United States, 666 F.2d 546 (Ct. C1. 1981).
If the contractor wants to hold the owner or construction manager liable for the cost of the
acceleration, the contractor should never accelerate without first requesting a time extension.
If the contractor accelerates without first requesting a time extension, the owner or construction
manager may reply to the contractors request for payment of acceleration costs by saying that
the contractor did not have to accelerate because the owner would have granted a time extension
if the contractor had only asked. The owner or construction manager may refuse to pay the
acceleration costs on the basis that the acceleration was unnecessary.
After requesting a time extension but before accelerating, a contractor should notify the owner or
construction manager that it will accelerate its work to attempt to overcome the owners or
construction managers delays. This notice is extra insurance to prevent the owner or
construction manager from later arguing that the acceleration was not necessary because it would
have granted a time extension or that the owner thought the contractor was accelerating to
compensate for its own delays.
The owner or construction manager can respond to the request for time extension either by
denying it or by ignoring it. If the owner or construction manager denies the time extension
request, the contractor can accelerate to attempt to meet the un-extended completion date and
claim acceleration costs against the owner or construction manager.
If the owner or construction manager ignores the time extension request, the owners or
construction managers silence is the equivalent of a denial because an owner or construction
manager that does not extend the completion date is telling the contractor that the project must be
completed by the un-extended date.
18
See, e.g., McDevitt & Street Co. v. Marriott Corp., 713 F. Supp. 906, 915 (E.D. Va. 1989); Hemphill
Contracting Co., 94-1 BCA (CCH) 26,491 (ENGBCA 1993).
19
See, e.g., James Walford Constr. Co., GSBCA 6498, 83-1 BCA (CCH) 16,277, 25 Govt Cont. Rep (CCH)
196 (1983).
20
See, e.g., Burns v. Hanover Ins. Co., 454 A.2d 325 (D.C. 1982).
21
See, e.g., Malor Constr. Corp., IBCA No. 1688-83, 84-1 BCA (CCH) 17,023 (1984).
Regarding the fifth key element above, the key word is attempted. The law has evolved so that
the costs to be reimbursed are not related to the achievement of the original or, indeed, to any
earlier-than-entitled completion date. The contractor only has to demonstrate that it attempted to
accelerate and incurred increased costs as a result of its reasonable attempt.24 Thus, if a
contractor fails to meet the original contract completion date but completes construction before a
valid, adjusted contract completion date, it may still have a valid claim for constructive
acceleration.25
The text, Government Contract Changes, by Ralph C. Nash, Jr., explains this concept:
At the outset, it should be stated that the central purpose of the equitable
adjustment for acceleration is no different than for any other changeto place
the contractor in the same position he would have been in, had it not been for the
acceleration order. There is no need to actually make up the time as long as the
contractor uses reasonable judgment in incurring the costs. Hence, the inquiry is
aimed at what costs were incurred rather than what was the result of the effort.26
22
See, e.g., William Lagnion, ENGBCA 3778, 78-2 BCA 13,260.
23
See, e.g., Superior Asphalt and Concrete Co., AGBCA No. 75-142, 77-2 BCA 12,851.
24
See, e.g., Natkin & Co. v. George A. Fuller Co., 347 F. Supp. 17 (W.D.Mo. 1972), reconsidered, 626 F. 2d 324
(8th CIR. 1980).
25
See, e.g., Mobile Chem. Co. v. Blount Bros. Corp., 809 F2d 1175 (5th Cir. 1987).
26
Nash, Ralph C. Jr., Government Contract Changes, 18-15, Federal Publications Inc., 1989.
As to jurisdictions other than the United States, it would appear that although acceleration claims
exist, they are rarely referred to as such. Rather, they are based on arguments related to breach
of contract and damages are requested because of that breach, or increased costs are pursued
simply as a variation.
The Society of Construction Law (SCL) takes an idealistic approach to actions that may require
acceleration not provided for in the contract:
Acceleration
Where the contract provides for acceleration, payment for the
acceleration should be based on the terms of the contract. Where the contract
does not provide for acceleration but the Contractor and the Employer agree
that accelerative measures should be undertaken, the basis of payment
should be agreed before the acceleration is commenced. It is not
recommended that a claim for so-called constructive acceleration be
made. Instead, prior to any acceleration measures, steps should be taken by
either party to have the dispute or difference about entitlement to EOT resolved
in accordance with the dispute resolution procedures applicable to the contract
(see Guidance Section 1.18).28
27
Duncan Wallace, Ian, QC, (ed.) Hudsons Building and Engineering Contracts (11th edn, 1995, Sweet &
Maxwell, p. 909 as referenced by Pickavance, Keith, Delay and Disruption in Construction Contracts, Third
Edition, T&F Informa (UK) Ltd., 2005, p. 390.
28
Delay and Disruption Protocol, Society of Construction Law, Oxford, October 2002, p. 9.
If there is not an acceleration provision in the contract, a collateral agreement may be made to
accomplish the required acceleration.30
Regarding directed acceleration, English courts have found that the contractor who fails to
accelerate upon proper instruction may be liable for actual loss as a result of the delay to the
completion date over and above the contractually stipulated liquidated damages.31
The SCL defines constructive acceleration as, Acceleration following failure by the Employer to
recognize that the Contractor has encountered Employer Delay for which it is entitled to an
extension of time and which failure required the Contractor to accelerate its progress in order to
complete the works by the prevailing contract completion date. This situation may be brought
about by the Employers denial of a valid request for an EOT or by the Employers late granting
of an EOT.32 However, the SCL states that constructive acceleration is, not (currently [as of
October 2002]) a recognised concept under English law.33
In one case in Canada regarding acceleration damages, the owner would pay nothing for
acceleration and also refused to grant extensions of time where these were entitled. Among other
things, the trial judge stated:
The trial court found in favor of the contractor and made an award on a quantum meruit basis.
The case was appealed and although the court of appeals overturned the quantum meruit basis
of the award, it approved the holding that the contractor was entitled to acceleration
damages stating:
29
Id., p. 31.
30
See, e.g., John Barker Construction Ltd. v. London Portman Hotel Ltd. (1996) 83 BLR 31.
31
See Masons v. W D King, [2003] EWHC 3124 (TCC) at 62-68.
32
Id., p. 53.
33
Id.
34
Morrison-Knudsen Company v. B.C. Hydro & Power Authority, 1978, 85 D.L.R., 3rd 186 (BCCA).
It may be that the award will be remarkably similar to the result of the quantum
meruit and that some rather arbitrary figures will have to be used, but difficulty of
assessment does not justify abandoning the attempt and making an award on
another basis.35
Thus, the court of appeals found that acceleration damages were to be paid and were to be treated
as any other damages.36
Similar to rulings by US courts, a UK case illustrates the contractors entitlement to recover its
acceleration costs if it is denied a time extension request.37 Micafil refused to grant a time
extension to the contractor, Motherwell, who had incurred excusable delays. The contractor then
accelerated by employing extra labor and working night shifts and claimed its acceleration costs.
The court held that Micafil had refused to grant a time extension that Motherwell was entitled to
receive and thus Motherwell had accelerated. Motherwell proved that the works would have
finished late but for the acceleration measures it employed. The court was satisfied that
Motherwell notified Micafil of the actual and projected extra acceleration costs either prior to or
at the time of taking the necessary measures. Thus, the court held that Motherwell was entitled
to its acceleration costs.
English courts have found that in the absence of express words to overcome the effects of an
owner-caused or excusable delay, there is no obligation on the part of the contractor to do so.38
35
Id.
36
Also see W Stevenson (Western) Ltd. v. Metro Canada Ltd., (1987) 27 Const LR 113 (BCS Ct.).
37
See Motherwell Bridge Construction Limited v. Micafil Vakuumtechnik (2002) 81 Con LR 44; (220) CILL 1913
at 581-582.
38
See Ascon Contracting Ltd. v. Alfred McAlpine Construction Isle of Man Ltd. (1999) 66 Con LR 119.
The contractor must give timely notice of any excusable delay as specified within the terms of
the contract.39 The requirement that a contractor gives notice to the owner and requests an
extension of time is excused only if:
40
1. The acceleration was directed.
2. The owner has indicated that no time extensions will be permitted.
3. The owner has waived the need for notice.
The waiver may be sufficient if the owner or construction manager has (1) informed the
contractor that no time extensions will be considered until after the contract completion date, (2)
informed the contractor that the construction must be completed by the contract completion date,
or (3) indicated that no delays in scheduling will be tolerated.41 However, in the absence of such
conditions, a failure to comply with a contractual provision requiring notice may preclude the
contractor from recovering on its acceleration claim.42
The owner or construction manager cannot be held to have constructively accelerated the work if
the opportunity to grant a time extension was not given. In addition, the notice permits the
owner or construction manager to take alternative action in order to avoid or reduce associated
acceleration costs. If the owner or construction manager is unresponsive to a request for a time
extension, the contractor should notify the owner or construction manager in writing that failure
to respond within a specified time period will be construed as a directive to accelerate.
Failure to provide proper notice may invalidate an otherwise meritorious acceleration claim.43
Even if the contractor is entitled to a time extension due to an excusable delay, the contractors
failure to notify the owner may invalidate a constructive acceleration claim, and the contractors
actions to accelerate may be deemed voluntary.44
For example, in finding that the contractors notice of its intention to file a claim for its
acceleration efforts was not timely for all of its acceleration efforts during the contractual period,
the court stated:
39
See, e.g., Wallace Process Piping Co. v. Martin Marietta Corp., 251 F. Supp. 411, 418 (E.D. Va. 1965);
Johnson Controls, Inc. v. National Valve & Mfg. Co., 569 F. Supp. 758, 760, 761 (E.D. Okla. 1983) ; Hemphill
Contracting Co., 94-1 BCA (CCH) 26,491 (ENGBCA 1993).
40
See, e.g., Norair Engg Corp. v. United States, 666 F.2d 546, 548 n.5 (Ct. C1. 1981).
41
See, e.g., Corbetta Constr. Co., PSBCA, 77-2 BCA (CCH) 12,669 (1977).
42
See, e.g., Rogers Excavating, AGBCA No. 79-180-4, 83-2 BCA (CCH) 16,701 (1983); Johnson Controls, Inc.
v. National Valve & Mfg. Co., 569 F. Supp. 758, 760, 761 (E.D. Okla. 1983).
43
See, e.g., Fru-Con Construction Corporation v. United States, 43 Fed. Cl. 306 (1999).
44
See, e.g., Johnson Controls, Inc. v. National Valve & Mfg. Co., 569 F. Supp. 758, 760, 761 (E.D. Okla. 1983) .
Nevertheless, AMECs notice is timely for its claim for acceleration efforts after
April 2004 because the notice was given prior to acceleration efforts made after
that time. Therefore, AMECs notice was timely under Code 33.1-386 for
acceleration efforts after April 2004 because it was given at the beginning of the
work upon which AMECs claim was based.45
Such decisions by the courts are based on the owners right to investigate the relevant
information and mitigate the potential cost impact before additional costs are incurred.
Defenses most commonly employed by contractors to circumvent failure to provide notice are:
46
1. The owners position or options were not prejudiced by lack of notice.
2. The specifications were defective resulting in a constructive change not
subject to the notice requirements set forth in the changes clause.47
3. The owner knew or reasonably should have known that a claim would be
forthcoming.48
4. The owner had constructive notice even though a formal notice letter was not
written and provided to the owner.
In both the first and second of these potential defenses, the matter of the owner being prejudiced
by lack of notice bears consideration. Constructive changes, even if caused by defective
specifications, will often be subject to the prejudice argument prohibiting contractor recovery for
costs that may have been avoided or mitigated had the contractor given timely notice.
45
Commonwealth v. AMEC Civil, LLC, 280 Va. 396 (2010) 699 S.E.2d 499.
46
See, e.g., C. H. Leavell & Co., ASBCA No. 16099, 73-1 BCA (CCH) 9,781 (1973).
47
See, e.g., John F. Cleary Construction Co., GSBCA No. 3158, 71-2 BCA (CCH) 9,127 (1971); Kelly Electric,
Inc., DOTCAB No. 71-34, 71-2 BCA (CCH) 9,097 (1971); Chaney & James Construction Co. v. United
States, 421 F.2d 728 (Ct. C1. 1970).
48
See, e.g., Vanderlinde Electric v. City of Rochester, 54 A.D.2d 155, 388 N.Y.S.2d, 388 (1976).
An issue that frequently becomes contentious in constructive acceleration claims is the date by
which entitled time extensions have to be given. Time extensions most often relate to damages
for delay, either in the form of liquidated damages that could be assessed by the owner if the
contractor does not perform by the contractual completion date or extended home office and field
general conditions costs that would be incurred by the contractor. Therefore, the date at which
the time extension is given will be relevant when a constructive acceleration situation exists.
Time extension must be granted in a timely manner such that they can be incorporated into the
progress schedule and the timing of the remaining work can be coordinated with the contractors
site supervision. If a time extension is not granted for excusable delay in a timely manner, the
CPM schedule cannot be revised to reflect the excusable delay. Thus, the progress schedule may
show that the contractor is behind schedule when, in fact, the contractor may be on or ahead of
schedule if the excusable delay was properly reflected in the schedule. Also, if an owner or
construction manager fails to grant an extension of time and continues to insist on completion
per the original completion date, a late time extension will be of no benefit to the contractor who
has already incurred costs accelerating in an attempt to meet the original completion date.
This situation, at least for the United States, is well described in government contracting,
as follows:
This rule clearly places the contractor in a difficult position, however, if it cannot
find out whether the Contracting Officer intends to grant the time extensions it
has requested, it has no basis for making a rational decision on whether to
accelerate or to run the risk of a default termination or the assessment of
liquidated damages. Once the contractor has accelerated, of course, time is of
little useand more recent decisions have recognized this fact.49
The owner or construction manager is obligated to respond in a timely manner to the contractors
request for a time extension. If the owner or construction manager takes unreasonable time to
grant a time extension or fails to respond and the contractor accelerates in an attempt to meet the
schedule, believing the time extension request will not be granted, the contractor may be
permitted recovery for the acceleration. For example, in Fortec Constructors v. United States,50
the Corps denied the contractors request for a time extension in a timely manner because the
Corps refused to grant modifications in a timely manner and, thus, relied on schedules that did
49
Nash, Ralph C. Jr., Government Contract Changes, 15-29, Federal Publications Inc., 1989.
50
Fortec Constructors v. United States, 8 Ct Cl. 737 (1972). Also see, e.g., Brock & Blevens Co. v. United States,
343 F.2d 951 (170 Ct. Cl. 1965), 7G.C. 192. M.S.I. Corp., GSBCA 2429, 68-2 BCA 7377; Continental
Consol. Corp., ENGBCA Nos. 2743, 2776, 67-2 BCA 6624.
Owners often fail to grant time extensions in a timely manner because of the following:
The contractor has not submitted a properly prepared time impact analysis to
demonstrate its entitlement to a time extension or quantified the entitled
time properly;
The contractor has made too many time extension requests that appear to be
unreasonable. While this may be true, the current request may, in fact, be
valid and should be addressed in a timely manner;
The owner lacks the expertise to properly evaluate a time extension request.
An experienced schedule delay expert should be brought in to evaluate the
contractors requests;
The owner believes that the contractors schedule updates are not accurate;
thus, any modeled impacts to its schedule to determine time extension
entitlement will also be inaccurate. The owner should require that the
contractors baseline schedule and schedule updates be corrected immediately
such that a proper time impact analysis can be performed;
An unrealistic belief that the threat of liquidated damages will cause the
contractor to accelerate and negate any entitlement it may have to a time
These positions may ultimately cause the contractor to prepare and submit a complex delay,
disruption, and acceleration claim near the end of the project, which could result in expensive
arbitration or litigation if not equitably resolved.
Two basic types of acceleration provisions may be included in the contract. The first gives the
owner the right to accelerate the contractor when the contractors performance has been delayed.
The second gives the owner the right to accelerate the contractor even if the contractor is
performing on schedule. The effect of these provisions is to transfer the risk of breaching the
construction contract from the owner to the contractor. When the owner directs the contractor to
accelerate pursuant to the provision, the contractor must comply or the contractor, not the owner,
will be liable for breach of contract damages. Thus, the acceleration provisions remove any
doubt as to whether the owner has the right to accelerate the contractor. However, to be
enforceable, both provisions must be reasonable.
The following are two examples of two enforceable acceleration provisions. The first provision
entitles the owner to accelerate a contractor who has been delayed; the second entitles the owner
to accelerate a contractor who is still on schedule.
Provision 1:
In the event of a nonexcusable delay in the performance or progress of the Work,
Owner may direct that the Work be accelerated by means of overtime, additional
crews or additional shifts, or resequencing of the Work. All such acceleration
shall be at no cost to Owner. In the event of an excusable delay in the
performance or progress of the Work, Owner may similarly direct acceleration,
and Contractor agrees to perform same on the basis of reimbursement of direct
cost (i.e., premium portion of overtime pay, additional crew, shift, or equipment
costs, and such other items of cost requested in advance by Contractor and
approved by Owner, which approval will not be unreasonably withheld) plus a fee
of percent (%) of such cost, but Contractor expressly waives any other
compensation therefore unless otherwise agreed to in writing in advance of
performing the accelerated work. In the event of any acceleration requested
pursuant to this paragraph, Contractor shall provide promptly a plan including
its recommendations for the most effective and economical acceleration.
Should Owner have reason to believe that the Contractor will not achieve
Mechanical Completion by the Scheduled Mechanical Completion Date, Owner
shall have the right (but not the obligation) to so notify Contractor, whereupon
Contractor shall, at no cost to Owner, work such additional overtime, engage
additional personnel and/or take other measures as necessary to achieve
Mechanical Completion by the Scheduled Mechanical Completion Date.
This requirement alone would seem harsh if the owner or an excusable event were the cause of
delay. Accordingly, the contract also provides the contractor relief, as follows:
(2) The Contractor, within 5 days from the beginning of any such
delay notifies the Owner in writing of the causes of delay.
Therefore, if an excusable delay occurs and the contractor provides timely notice, the owner can
either: 1) provide a time extension, for which the contract states that the contractor waives
damages, costs, or expenses of any nature; or 2) not provide a time extension, which will then
cause either directed or constructive acceleration. If the contractor has provided timely notice of
delay, the delay affected the as-built critical path of the project, and acceleration is required, the
owner may be exposed to acceleration costs. However, the contractor will have to also
demonstrate that such acceleration was not also the result of delays for which it is responsible.
An allocation of acceleration costs between the owner and the contractor would be appropriate if
acceleration is caused by contractor-caused and excusable delays.
The FIDIC 1987 Conditions of Contract for Works of Civil Engineering Construction, as
adjusted in 1988 and 1992, have several related provisions, as follows:
Revised Programme
14.2 If at any time it should appear to the Engineer that the actual progress of
the Works does not conform to the programme to which consent has been given
under Sub-Clause 14.1, the Contractor shall produce, at the request of the
engineer, a revised programme showing the modifications to such programme
necessary to ensure completion of the Works within the Time for Completion.
The FIDIC clause does not, however, address who pays for such changes in the programme
(schedule). The FIDIC contract also clearly addresses responsibility for costs of regaining
delayed progress in the schedule:
Rate of Progress
46.1 If for any reason, which does not entitle the contractor to an extension of
time, the rate of progress of the Works or any Section is at any time, in the
opinion of the Engineer, too slow to comply with the Time for Completion, the
Engineer shall so notify the Contractor who shall thereupon take such steps as
are necessary, subject to the consent of the Engineer, to expedite progress so as to
comply with the Time for Completion. The Contractor shall not be entitled to any
additional payment for taking such steps. If, as a result of any notice given by the
Engineer under this clause, the Contractor considers that it is necessary to do any
work at night or on locally registered days of rest, he shall be entitled to seek the
consent of the Engineer to do so. Provided that if any steps, taken by the
Similarly, the 1999 FIDIC Yellow Book Contract for Plant and Design Build Contracts states the
following:
Unless the Engineer notifies otherwise, the Contractor shall adopt these revised
methods, which may require increases in the working hours and/or in the numbers
of Contractors Personnel and/or Goods, at the risk and cost of the Contractor. If
these revised methods cause the Employer to incur additional costs, the Contractor
shall subject to Sub-Clause 2.5 [Employers Claims] pay these costs to the
Employer, in addition to delay damages (if any) under Sub-Clause 8.7 below.
Including acceleration provisions in the contract benefits both the owner and the contractor.
With such provisions, the owner knows that it has the legal right to order acceleration, and the
contractor knows the costs to which it will be entitled should it be accelerated.
Contractors should read and understand contract documents and avoid entering contracts that
attempt to shift all risk to the contractor. Contractors should know what risk they will incur due
to uncontrollable delays. They should carefully examine the completion date and time extension
Contracts may be written with clauses that contain very broad language with regard to No
Damages for any delay, regardless of cause. However, if such clauses are contradictory with
other contract provisions, they may be overruled by the courts.
No Damage for Delay clauses specifically referencing particular types of delays are often used
by owners or construction managers to preclude time-related damages. These clauses are
generally valid. However, if the delay breached the contract, was of a kind not contemplated by
the parties, was caused by the owners or construction managers active interference, or was the
result of an owners or construction managers bad faith, the No Damage for Delay clause may
be barred. Such clauses typically refer to time-related damages, but if a valid time extension is
denied, and the contractor is required to complete its work by the original contract completion
date, its acceleration costs to attempt to meet the original completion date may be recoverable.
In a Chicago case,51 for example, the City relied on the No Damage for Delay clause contained
within the contract and refused to grant a time extension to a construction contractor who had
incurred excusable delays. The Court found that, because the contractor was entitled to a time
extension for suspension and strike delays, the action of the City in denying the time extension
and holding the contractor to the original contract completion date constituted acceleration.
In allowing the contractor to recover its acceleration costs, the appellate court made
following observation:
Plaintiff contends that since it was entitled to more performance time, defendants
action denying the extensions and holding plaintiff to the original contract
completion date was tantamount to acceleration.
We agree.
Except as provided in this Article 4.7, the Owner shall not be obligated or liable
to the Contractor for, and the Contractor hereby expressly waives, any claims
against the Owner on account of any damages, costs or expenses of any nature
which the Contractor may incur as a result of any delay which may occur,
regardless of its cause. It is understood and agreed that the Contractors sole
and exclusive remedy in the event of an excusable delay for which Contractor is
51
Contracting and Material Co. v. City of Chicago, 20 Ill. App. 3d 684, 692, 314 N.E.2d 598, 604 (1974), revd
on other grounds, 64 Ill. 2d 21, 349 N.E.2d 389 (1976). Also see Siefford v. Housing Authority, 192 Neb. 643,
223 N.W.2d 816 (1974).
In addition, if there are known potential causes of delay that may affect the contractors work,
such as the completion of a design package by a licensor or the purchase order of a long-lead
item that is being performed by the owner, these delays should be identified by the owner prior
to contract award to put the contractor on alert.
Owners should expect that contractors will attempt to take exception to No Damage for Delay
clauses. Otherwise, the contractor is taking considerable risk for increased costs that are not
within its control. The owner also needs to be aware that not all jurisdictions will enforce such a
clause, and it may not provide the intended shield. If exceptions to this clause are taken by a
bidding contractor, the owner should request some bid price concession from the contractor who
would otherwise put extra contingency in its bid to cover this risk.
The first step in proving an acceleration claim typically involves establishing that the
contractors as-planned schedule is proper and reasonable. Then, the contractor must maintain
accurate and reliable schedule updates showing as-built progress on a periodic basis, usually
monthly unless a shorter periodic schedule is contractually required. The importance of
reliability cannot be overemphasized. Because an as-built schedule reflects all changes,
modifications, and delays that occurred during the construction process, the contractor should not
wait until construction is complete to prepare an as-built CPM schedule. To ensure the accuracy
and reliability of the as-built schedule, the contractor should continually update its as-planned
schedule as changes, modifications, and delays occur. If the contractor does not maintain an
updated CPM schedule and the owner does, the court will most likely use the owners schedule
in determining whether the contractor was accelerated.
Proof of an acceleration claim is similar to a delay claim where only compensable delays are
added to the statused schedule, except that the properly adjusted schedule (baseline/as-planned
schedule for delays during the early period of the project, or schedule updates for delays that
occur later in the project) includes both owner-caused and excusable but noncompensable delays
with a focus upon the specific period of time during the project when the acceleration was
initiated.52 If changes or impacts have occurred, the contractor should adjust that schedule,
typically by use of a Time Impact Analysis or Update Impact Analysis without constraints on the
completion date, to reflect owner-caused and excusable delays up to the time of the acceleration
order or when constructive acceleration is acknowledged. When all of the impacts for a
particular time period have been developed and inserted into the schedule, the schedule is
recalculated. This schedule can then be compared to the as-built schedule to determine if, in the
absence of a time extension, acceleration was accomplished, i.e., the as-built completion date is
earlier than the impacted completion date.
AACE International, in its Forensic Schedule Analysis Recommended Practice 29R-03, provides
that many different schedule analysis methods can be used to demonstrate acceleration. The
following commentary is provided regarding observational/static analyses, MIP 3.1 through 3.4:
Observational / static analysis methods can note differences in logic but cannot
directly quantify net critical path impact. However, there may be evidence of
reduced individual activity duration, which when coupled with detailed records of
increased man-hours, would serve as adequate proof of acceleration. Note that
52
See, e.g., Continental Consolidated Corp. v. United States, 17 CCF 81,137 (1972), Ct. C1. 737 (1972);
Kenneth Reed Construction Corp., ENGBCA 2748, et al., 72-1 BCA (CCH) 9,407 (1972).
However, AACE International also states that observational/static analysis methods are, not
suited for clearly demonstrating acceleration.
AACE International discusses the use of the as-planned impact analysis (single base, additive
model) method (MIP 3.6) for identifying acceleration:
The comparison between the completion date of the longest path of the additive
model and the actual completion date will provide a gross approximation of
acceleration or delay mitigation. This is based on the theory that if non-
contractor delays inserted into the baseline yield a completion date that is later
than that actually achieved, it must have resulted from shortening of actual
performance duration and/or the use of more aggressive logic. Note that the
gross comparison does not provide the detail necessary in order to address the
issue of who gets the credit for the acceleration.55
53
Forensic Schedule Analysis, AACE International, April 25, 2011, p. 43.
54
Id. p. 61.
55
Id., p. 74.
In using the multiple base, additive model (MIP 3.7), such as is done in the Update Impact
Analysis method, AACE International states that, If the longest path is the same but the overall
completion date of the progressed version is earlier, there was acceleration or some other delay
mitigation on the delays on the longest path.57 In addition:
In MIP 3.7, after inserting delays into the update closest in time preceding the
delay, the identity and the movement of the critical path is monitored. Then, when
the update is progressed with actual progress data and the same logic path
reexamined, if the logic path is shorter than that which was calculated prior to
adding actual progress, there was acceleration or schedule recovery during the
period for which actual progress was entered.58
As with the single base, additive model, this method can be used to identify and quantify
acceleration, although actual performance that is better than predicted by use of this method
does not, in and of itself, necessarily demonstrate active implementation of acceleratory
measures.59
The as-built but for-analysis can also be used to demonstrate acceleration. In using the single
base form of this subtractive model (MIP 3.8), AACE International states:
The difference between the as-built completion date and the collapsed as-built
completion date resulting from the extraction of all owner-caused delays is the
total ECD. If the owner has paid the contractor specifically to accelerate, then
any negative delay durations (delay mitigation) resulting from the owner-paid
acceleration should be credited to the owner against the total ECD to avoid
double payment to the contractor for acceleration. Where the quantification of
the duration of the specific paid mitigation is not reasonably feasible, the credit
adjustment may be accomplished by crediting the monetary value of the
acceleration payment against the monetary value of the ECD.
56
Id., p. 75.
57
Id., p. 78.
58
Id., p. 80.
59
Id., p. 81.
The difference between the as-built completion date and the collapsed as-built
completion date resulting from the extraction of all contractor-caused delays is
the total NND. If the contractor accelerated or implemented other mitigating
measures and the owner did not reimburse the contractor for the cost of
mitigation, the net critical mitigation duration should be subtracted from the
total NND.60
However, subtractive modeling methods may not be the best tool for identifying and
quantifying specific instances of acceleration and delay mitigation:
The subtractive modeling methods are not the best tools for identifying and
quantifying specific instances of acceleration and delay mitigation, since the
methods start with the as-built schedule that already incorporates all acceleration
measures to the extent that they were actually implemented. When the delays are
subtracted the resulting schedule still retains all acceleration measures that were
built into the as-built. Therefore, the resulting comparison is that of one
accelerated schedule to another, albeit one without delays.61
And:
The SCL supports the use of the Time Impact Analysis for the analysis of acceleration claims:
Time impact analysis is based on the effect of Delay Events on the Contractors
intentions for the future conduct of the work in the light of progress actually
achieved at the time of the Delay Event and can also be used to assist in resolving
more complex delay scenarios involving concurrent delays, acceleration and
disruption.63
Figure 1 demonstrates an acceleration scenario using an additive model, such as a time impact
analysis or a single base or multiple base additive model to adjust the schedule by inserting the
excusable delays to create a Time Impacted Schedule. The quantification of acceleration is
60
Id., p. 85. Also see p. 93 regarding the comments as they apply to the multi-base subtractive model, MIP 3.9.
61
Id., p. 85.
62
Id., p. 90 and p. 97.
63
Delay and Disruption Protocol, Society of Construction Law, Oxford, October 2002, p. 47.
If the as-built completion date is equal to or greater than the impacted completion date, no
compensable acceleration has occurred because of owner-caused or excusable/noncompensable
delays, as shown in Figure 2.
An as-planned impacted analysis using a single base additive model, such as described by
MIP 3.6 in AACE Internationals Forensic Schedule Analysis R29-03,64 may not be a valid
schedule delay analysis method for evaluating delays that occur throughout the project. For
example, if the original as-planned schedule contained invalid logic, the results of the as-planned
impacted analysis could be meaningless. Also, actual work sequences and progress may be
significantly different from the as-planned schedule. These changes in work sequence may be
the result of circumstances unrelated to the claimed owner-caused delays. Consequently, the
as-planned impacted analysis may fail to properly account for contractor-caused delays and
should not be used to determine the amount of delay for which the contractor may receive
extended overhead costs. Numerous decisions by the U.S. Court of Claims and Boards of
Contract Appeals have made it clear that attempts to prove delay through the usage of as-planned
impacted CPM analyses are not acceptable. Three decisions that confirm the deficient nature of
as-planned impacted schedule analysis are Gulf Contracting, Inc.,65 Titan Pacific Construction
vs. United States,66 and Ealahan Electric Company.67
Thus, windows approaches using an Update Impact Analysis68 or a Time Impact Analysis, where
the schedule is statused up through the day prior to each delay event before the delay impact is
added to the schedule, may be more appropriate analysis methodologies to determine the
contractors entitlement to a time extension because these methodologies evaluate delays to the
then current critical path of the project.
The impacted schedule will demonstrate the contractors entitlement to a time extension if the
impacts affected the critical path of the work. The objective of the adjusted CPM schedule in an
acceleration claim is to demonstrate that the contractor was making adequate progress toward job
completion when the acceleration order was given or when a request for a valid time extension
was denied and the contractor was entitled to finish at a later date than actual completion. Basic
to the proof of this aspect of the claim is that a contractor is only required to commit to the
project a reasonable amount of men and equipment and not an infinite or unreasonable amount of
men and equipment.
64
See MIP 3.6, April 25, 2011, pp. 70-75.
65
Gulf Contracting, Inc., ASBCA Nos. 30,195, 32,839, 33867 et al., 89-2 BCA (CCH) 22,812 (1989) on recon.
90-1 BCA (CCH) 22,393 (1990).
66
Titan Pacific Construction Corp., ASBCA Nos. 24,148, 24,616, 26,692, 87-1 BCA 19,626 (1987), affd
17 Cl. Ct. 630 (Cl. Ct. 1989).
67
Ealahan Electric Company, Inc., DOTBCA No. 1959, 90-3 BCA (CCH) 23,177 (1990).
68
See AACE Internationals Forensic Schedule Analysis R29-03, April 25, 2011, MIP 3.7, pp. 75-82.
The more difficult case to resolve is when the owner grants a time extension to the contractor,
but the contractor claims that the time extension was insufficient to cover the excusable delay.
This is known as disputed constructive acceleration, and the contractor must provide two levels
of proof: first, that it was entitled to a time extension, and second, that the extension granted by
the owner was less than the extension to which the contractor was entitled. For example, if a
contractor receives a 50-day time extension, and the contractor completes the project within that
50-day extension but feels that it was entitled to a 70-day time extension, then the contractor
may claim that it was constructively accelerated by 20 days. The contractor must be able to
prove its acceleration claim by showing not only that it was entitled to the 50-day time extension
that it received but also that it was entitled to the additional 20 days beyond the 50-day time
extension. The contractor, however, may have waived its claim to the additional 20-day
extension if it accepted the 50-day extension without reserving its rights for the additional time.69
The contractor should avoid producing schedule updates throughout the project which show an
on-time completion date even after delays have occurred. This tendency to hide delays in
construction progress makes the analysis of delays and resulting acceleration more difficult later.
Trying to prove that an event caused a critical delay early in the project when the contractors
schedule updates show no effect on completion is not an easy task. Showing updates to the
owner that reflect delayed project completion and discussing means of remedying them may lead
to a request for an agreement to compensate for acceleration.
Owners may argue that the contractor was also responsible for days during the analysis period.
However, the courts have held that the contractor is entitled to a time extension even when a
contractor delay is concurrent with an owner-caused or excusable delay.70 Thus, if the time
extension is denied or ignored, and acceleration is directed or constructively required, then the
owner may be responsible for the contractors acceleration damages. The owner may argue that
the acceleration costs should be allocated between the owner and the contractor because the
contractor also accelerated to mitigate delay caused by the contractor and to avoid liquidated
damages. The contractor could argue that it would not have accelerated as these costs were
69
Freeman Elec. Constr. Co. v. United States, 618 7.2d 124 (221 Ct. Cl. 1979), cert. denied, 449 U.S. 825 (1980).
70
See, e.g., Acme Process Equipment Co. v. United States, 171 Ct. C1. 324, 347 F.2d 309 (1965).
It is essential that owners, engineers, and contractors develop and implement a documentation
collection system. CPM schedules, budgets and estimates, change orders, design changes, daily
logs and diaries, daily reports, memos, meeting minutes, and correspondence all record the actual
events that resulted in acceleration of performance. Acceleration claims lacking documentation
necessary to show excusable critical path delays are often dismissed.71
1. Daily individual payroll records (by cost code and indicating schedule activity
or area worked on). This information should include regular hours, regular
labor cost, overtime hours, overtime labor cost, and benefits.
2. Daily, weekly, or monthly equipment charges (by cost code and schedule
activity). Information on idle time or working time for equipment is helpful
and supplements the documentation in the superintendents log.
3. Progress information (by units installed or percent completed, by cost code
and schedule activity). This data is extremely helpful when measuring the
effect on productivity caused by impacts to the project. It can be recorded at
any time on the project, but it gives more information when recorded on a
weekly basis.
4. Weekly or monthly subcontractor costs (broken down by cost codes or
activities worked on).
5. Any other costs affecting the project.
6. Estimates and budgets, especially when prepared in detail at the beginning of
the project. These provide a good basis for comparing the costs to perform as
well as anticipated productivity. As such, they should be maintained in the
project files.
71
See, e.g., Kenneth Reed Construction Corp., ENGBCA 2748, et al., 72-1 BCA (CCH) 9,407 (1972); Lane
Verdugo, ASBCA No. 16327, 73-2 BCA (CCH) 10,271 (1973).
72
See, e.g., Nat Harrison Assoc. v. Gulf States Utilities Co., 491 F.2d 578 (5th Cir. 1974).
The types of costs that are typically allowed for acceleration claims include the following:
1. Increased construction labor costs for overtime, additional shifts, six or seven
days per week, or combinations of these efforts.
2. Increased construction equipment maintenance costs associated with longer
work hours.
3. Increased construction equipment rental expenses associated with overtime work.
4. Cost of additional construction equipment or materials.
5. Expediting equipment and material deliveries.
6. Increased field supervision.
7. Increased job site expenses.
8. Increased home office overhead expenses directly related to the acceleration
effort.
9. Subcontractor costs. In order to finish on time, some work may be
subcontracted at a higher cost than that of the contractors own labor force.
The difference in the cost is damages.
10. Loss of inefficiency and productivity associated with overtime, increased crew
sizes, stacking of trades, and re-sequencing of work.
One way to prove these costs is to compare the actual cost of performance before accelerating to
the actual cost after accelerating. For example, if a contractor is required to accelerate on the
installation of 5,000 feet of straight run pipe after only 2,000 feet has been installed, it may be
possible to measure the cost of installing the 2,000 feet and compare it to the cost of installing
the remainder of the pipe to determine damages, i.e., a measured mile approach. However,
because it is likely that delays also occurred during the installation of the 2,000 feet, this
approach may be problematic. To the extent that the owner or construction manager is
responsible for the delay, it can also be responsible for the cost of the acceleration effort. If the
contractor is also responsible for certain of the delays, then an allocation of the acceleration costs
may be appropriate.
When faced with acceleration on a project, the contractor is obligated to mitigate the damages
whenever reasonable. This may involve using a larger labor force rather than incurring overtime,
using extra equipment rather than more labor, or reducing jobsite overhead when an accelerated
project is completed earlier. The contractor must use any available and reasonable means it has
to reduce the damages. As a practical matter, on an accelerated project the contractor may be
Cost savings that the contractor achieved in the normal performance of the contract, such as in
the buyout of subcontracts and material, do not need to be subtracted from the acceleration
damages. The contractor would have been entitled to benefit from these savings had no
acceleration occurred.
List of Cases
Cases
Ace Constructors, Inc. v. United States, 70 Fed. Cl. 253, 281 (Fed.Cl. 2006) .............................................................. 2
Acme Process Equipment Co. v. United States, 171 Ct. C1. 324, 347 F.2d 309 (1965) .............................................. 33
Anderson Development Corp. v. Coastal State Crude Gathering Co., 543 S.W.2d 402 ............................................... 7
Ascon Contracting Ltd. v. Alfred McAlpine Construction Isle of Man Ltd. (1999) 66 Con LR 119............................ 12
Brock & Blevens Co. v. United States, 343 F.2d 951 (170 Ct. Cl. 1965), 7G.C. 192 ............................................... 16
Burns v. Hanover Ins. Co., 454 A.2d 325 (D.C. 1982) .................................................................................................. 8
C. H. Leavell & Co., ASBCA No. 16099, 73-1 BCA (CCH) 9,781 (1973) .............................................................. 14
Chaney & James Construction Co. v. United States, 421 F.2d 728 (Ct. C1. 1970)..................................................... 14
Commonwealth v. AMEC Civil, LLC, 280 Va. 396 (2010) 699 S.E.2d 499 ................................................................ 14
Constructors-Pamco, ENGBCANo. 3468, 76-2 BCA 11,940 (1976) ......................................................................... 7
Continental Consol. Corp., ENGBCA Nos. 2743, 2776, 67-2 BCA 6624 ................................................................ 16
Continental Consolidated Corp., v. United States, 17 CCF 81,137 (1972), Ct. C1. 737 (1972) .............................. 26
Contracting and Material Co. v. City of Chicago, 20 Ill. App. 3d 684, 692, 314 N.E.2d 598, 604
(1974), revd on other grounds, 64 Ill. 2d 21, 349 N.E.2d 389 (1976) ................................................................ 7, 24
Corbetta Constr. Co., PSBCA, 77-2 BCA (CCH) 12,669 (1977) ............................................................................ 13
Dept. of Transp. v. Anio Constr. Co., 666 A.2d 753, 756 (Pa. Commw. Ct. 1995) ....................................................... 3
Ealahan Electric Company, Inc., DOTBCA No. 1959, 90-3 BCA (CCH) 23,177 (1990) ....................................... 32
Edge Construction Company, Inc. v. United States (Fed.Cl. October 29, 2010), No. 06-635C .................................... 7
Elte, Inc. v. S.S. Mullen, Inc., 469 F.2d 1127 (9th Cir. 1972) ......................................................................................... 7
Envirotech, 715 F. Supp. at 191 .................................................................................................................................... 3
Eric A. Carlstrom Constr. Co. v. Independent Sch. Dist. No. 77, 256 N.W.2d 479 (Minn. 1977) ................................ 7
Fraser Constr. v. United States, 384 F.3d 1354, 1360-61 (Fed. Cir. 2005)................................................................... 7
Freeman Elec. Constr. Co. v. United States, 618 7.2d 124 (221 Ct. Cl. 1979), cert. denied, 449 U.S.
825 (1980) ............................................................................................................................................................... 33
Fru-Con Construction Corporation v. United States, 43 Fed. Cl. 306 (1999) ............................................................ 13
Fru-Con Corp. v. State of Illinois, 50 Ill. Ct. CI. 50, 51 (Ill. Ct. CI. 1996) ................................................................... 3
Fuerland-Werkstatten Gmbh., ASBCA 32,970, 87-3 BCA 20,012. ........................................................................... 4
Gulf Contracting, Inc., ASBCA Nos. 30,195, 32,839, 33,867 et al., 89-2 BCA (CCH) 22,812 (1989)
on recon. 90-1 BCA (CCH) 22,393 (1990) ........................................................................................................... 32
Hemphill Contracting Co., 94-1 BCA (CCH) 26,491 (ENGBCA 1993).............................................................. 8, 13
Housing Auth. V. E.W. Johnson Constr. Co., 264 Ark. 5243, 573 S.W.2d 316 (1978) ................................................. 7
Iconco, 224 Ct. Cl. 692. 27 Cont. Cas. Fed. (CCH) 80,392 (1980) ............................................................................ 7
J&K Plumbing & Heating Co. v. State, 235 A.D.2d 751 (N.Y. App. Div. 1997) ......................................................... 7
James Walford Constr. Co., GSBCA 6498, 83-1 BCA (CCH) 16,277, 25 Govt Cont. Rep (CCH)
196 (1983) ................................................................................................................................................................. 8
John Barker Construction Ltd. v. London Portman Hotel Ltd. (1996) 83 BLR 31 ..................................................... 11
John F. Cleary Construction Co., GSBCA No. 3158, 71-2 BCA (CCH) 9,127 (1971) ........................................... 14