TABLE OF CONTENTS
1. Scope
2. Reference Documents/Drawings
3. Access /Egress
4. Health and Safety Hazards
4.1 Safety Rules During Testing
4.2 Safety Lighting
4.3 Task Lighting
4.4 Emergency Arrangements
4.5 Risk and Controls
5. Abbreviations & Definitions
6. Roles/ Responsibilities / Competence
7. Testing & Commissioning Procedures
7.1 Pre-Commissioning
7.2 Start up procedure
7.3 System Programming
7.4 Final Testing
8. Training
9. Working Hrs.
10. Manpower Requirement & Supervision
11. Test Instruments Requirements
12. Personnel Equipment
13. Distribution
14. Attachments
1. Scope:
The method statement aims to provide necessary information for Testing and Commissioning
of SIEMENS Lighting Control System installed in Ducab Extension.
The system consists of Lighting Control Panels Power Supply, Relay Module, Timer and Push
button in different areas to provide effective energy management as per the requirement.
2. Reference Documents/Drawings:
Lighting Control system Drawings
Schematic Diagram
Commissioning Checklist
3. Access /Egress:
The Commissioning of the System will commence only when Main Contractor clearance is given for
access to conduct Testing and Commissioning.
4. Health and Safety Hazards:
Health and Safety procedures by Main Contractor and MACAIR/BMTS will be implemented for this job.
A routine safety check will be done by the Safety Officer In-charge as per MACAIR Safety Procedure.
4.1 Safety Rules during Testing & Commissioning:
In order to ensure safe conditions during testing the following rules have to be followed:
Persons engaged with this commissioning are experienced and have received proper and adequate
training related to procedures and test equipment utilized for the particular testing activity.
Test instruments and test leads should be maintained in a safe condition and the test methods not to
create danger either for the operator or for other persons.
PM - will have the overall responsibility of the Project for execution, quality and safety; maintain the
planning and progress and coordination with Main Contractor.
PE - will be responsible for day to day activities in the Site for System Testing and Commissioning,
report preparation and demonstration of System Commissioning.
SCE - will be directly responsible for the System installation.
SO - will be responsible for Health and Safety aspects in the Site in line with Main Contractor Safety
requirements.
QA/QC - will oversee the quality requirements and quality control measures for the Project.
8. 8. 8. Training:
Commissioning Engineers who will conduct the Commissioning shall have the experience in
Lighting Control System Commissioning.
Tool Box talks will provide general training and awareness for each activity and also undergo
further training by the Quality Assurance Department
9.Working Hours :
Site Normal Working Hours.
Rev.: 0.0
Date of Issue:
Page No.: Page 6 of 7
13. Distribution
Main Contractor
Consultant
MEP Senior Mechanical Engineer
Health and Safety Officer
14. Attachments
14.1 Commissioning Check List
14.2 Risk Assessment.