# Description of Works Unit Qty Exp - Days Ex - Lab.Cost

The document provides a summary of works to be completed for the balance of the Thinadhoo Sports Arena project. It includes a breakdown of tasks by floor (ground, first, terrace) with descriptions of works, quantities, expected duration, and estimated labor costs. The total estimated labor cost for all remaining works is MVR 448,242.23. Electrical, tiling and painting work rates may be finalized. Completion is expected by November 30, 2016. Reinforcement works and contingencies are excluded from the floor totals provided.

Uploaded by

Ibrahim Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views

# Description of Works Unit Qty Exp - Days Ex - Lab.Cost

The document provides a summary of works to be completed for the balance of the Thinadhoo Sports Arena project. It includes a breakdown of tasks by floor (ground, first, terrace) with descriptions of works, quantities, expected duration, and estimated labor costs. The total estimated labor cost for all remaining works is MVR 448,242.23. Electrical, tiling and painting work rates may be finalized. Completion is expected by November 30, 2016. Reinforcement works and contingencies are excluded from the floor totals provided.

Uploaded by

Ibrahim Ali
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Balance Works to be completed in Thinadhoo Sports Arena Project

Ground Floor

# Description of Works Unit Qty Exp.Days Ex.Lab.Cost


1 100mm thick concrete floor screed M2 1000 21 56,400.00
2 Plumbing Works LS 1 5 10,000.00
3 Partition Works M2 441.07 10 23,738.39
4 Doors & Windows (Interior) Nos 14 3 4,900.00
5 Electrical Wiring & Fixtures Nos 130 10 21,450.00
6 Distribution Board Nos 6 2 9,000.00
7 Tiling M2 416.25 10 27,056.25
8 Ceiling Works M2 772.234 10 83,123.21
9 Putty & Paint Works M2 761.342 5 24,362.96

First Floor

# Description of Works Unit Qty Exp.Days Ex.Lab.Cost


1 Cement Floor Screed M2 62.78 2 3,600.00
2 Plumbing Works LS 1 5 15,000.00
3 Partition Works M2 0 0 -
4 Doors & Windows (Interior) Nos 24 3 8,400.00
5 Electrical Wiring & Fixtures Nos 114 10 18,810.00
6 Distribution Board Nos 2 2 3,000.00
7 Tiling M2 251.621 10 16,355.37
8 Ceiling Works M2 758.180 10 81,610.50
9 Putty & Paint Works M2 726.930 5 23,261.76

Terrace Floor

# Description of Works Unit Qty Exp.Days Ex.Lab.Cost


1 Cement Floor Screed M2 163.469 3 5,400.00
2 Plumbing Works LS 0 0 -
3 Partition Works M2 0 0 -
4 Doors & Windows (Interior) Nos 1 1 350.00
5 Electrical Wiring & Fixtures Nos 2 1 330.00
6 Distribution Board Nos 0 0 -
7 Tiling M2 163.469 3 10,625.49
8 Ceiling Works M2 10.515 1 1,131.83
9 Putty & Paint Works M2 10.515 1 336.48

Summery of Estimated Cost for the Balance Works - Labour Only

Ground Floor 260,030.81


First Floor 170,037.62
Terrace Floor 18,173.80
448,242.23

Tiling, Electrical, Painting works rate to be finalized. Rates quoted as per standard rates
Expected Date of Completion - 30th November 2016
Total / Floor Remarks
Reinf. Works 15% Comp.

260,030.81

Total / Floor Remarks


Reinf. Works 15% Comp.

Half of Ceiling Works Compl.


170,037.62

Total / Floor

18,173.80