Motion For Summary Judgment
Motion For Summary Judgment
THURSTON COUNTY, WA
SUPERIOR COURT
July 24, 2017
Linda Myhre Enlow
1 EXPEDITE (if filing within 5 court days of hearing) Thurston County Clerk
No hearing is set.
Hearing is set:
2 Date: September 1, 2017
Time: 9:00 a.m.
3 Judge/Calendar: Carol Murphy - Civil
14
SEATTLE TUNNEL PARTNERS, a
15 Washington joint venture,
16 Third-Party Plaintiff,
17 v.
21 Third-Party Defendants.
22
23
24
25
26
12
HITACHI ZOSEN U.S.A. LTD.,
13
Plaintiff,
14
v.
15
WASHINGTON STATE DEPARTMENT OF
16 TRANSPORTATION and SHANNON &
WILSON, INC.,
17
Defendants.
18
SEATTLE TUNNEL PARTNERS, a joint
19 venture,
20 Plaintiff,
21
v.
22
SHANNON & WILSON, INC., a Washington
23 corporation; and WSP USA, INC., formerly
known as PARSONS BRINCKERHOFF,
24 INC., a New York corporation,
25
Defendants.
26
23 1
See STPs Answer, Counterclaim and Third Party Complaints filed 7/6/16 (Answer),
24 118. STP calls TW-2 the Abandoned Steel Well Casing see Id., 49. A casing is a vertical
pipe in the ground. See the Declaration of Karl F. Oles (Oles Decl.) filed herewith, 2.
25 2
WSDOT also denies that TW-2 caused any significant damage to the TBM, but that
26 issue is not raised in this motion.
10 Contract Section 5.7.2, referenced in this definition, provides that if the GBR and EBR are silent
11 about some condition, then STP may rely on the GEDR:
12
In the event the [GBR] or [EBR], as applicable, is silent with respect to a
13 particular geotechnical or environmental condition, Design-Builder may rely upon
the [GEDR] . . . as describing such condition.
14
15 STP admits that the GBR and EBR are silent with regard to TW-2.4
16 STP admits the [GBR] and [EBR] are silent with respect to the Abandoned
Steel Well Casing.
17
18 Therefore, the question whether TW-2 was a Type 1 DSC can be stated simply as follows: were
19 the actual conditions at TW-2 substantially or materially different from the conditions identified
20 in the GEDR?
21
22
23
24 3
Unless otherwise noted, the statements in this paragraph are supported by the
25 Declaration of Brian Nielsen (Nielsen Decl.) filed herewith, 3.
4
26 Oles Decl., 3, attaching STP response to request for admission.
8 installation of wells and other instruments for the study of groundwater along the planned
9 alignment of the new highway tunnel. GEDR Figure 1 (Vicinity and Key Map) is a general
10 map of the project area that provides a key to a more detailed series of maps identified in the
11 GEDR as Figure 2 (Site and Exploration Plan). Figure 2 (sheet 3 of 12) shows TW-2 within
12 the Proposed Bored Tunnel Alignment. Sheet 3 of Figure 2 is reproduced on the next page
14
16
17
18
19
20
21
22
23
24
25 5
The statements in this Subsection B are supported by the Declaration of Paul Van Horne
26 (Van Horne Decl.), filed herewith, especially 4-9.
6
7
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
14 This tells us that TW-2 was installed before the 2009-2010 timeframe and that TW-2 was a
15 pumping well as opposed to an observation well. This information is confirmed in
16 Subsection 2.5.8.1:
17
Three wells, designated PW-252, PW-254, and PW-255, were installed and
18 developed for use in the pumping tests. . . .
In addition to the newly installed pumping wells, a test well (TW-2) installed in
19 2002 . . . was incorporated into the pumping test program.
20 In a pumping test, water is pumped out of one or more wells (pumping wells) and
21 groundwater levels are measured in surrounding wells (observation wells). The behavior of the
22 observation wells provides information about subsurface conditions. For example, if during a
23 pumping test the water level goes down in an observation well, it can be concluded that the
24 pumping well and observation well are connected by a soil layer that allows water movement.
25 Subsection 2.5.8.2.1 provides further details about TW-2s role in the pumping tests:
26
5 tests that involved four pumping wells, three of which were installed in 2009-10 (PW-252, PW-
6 254, and PW-255). The fourth had been installed in 2002 (TW-2). Water was pumped out of the
7 pumping wells and various monitoring points (observation wells and VWPs) were studied to
8 see how their water levels changed. With respect to these tests, TW-2 is clearly and repeatedly
10 The GEDR appendices provide additional information about TW-2. Figure C.4-1, part of
11 GEDR Sub-Appendix C.4, again identifies TW-2 as a pumping well (a half-circle) surrounded
12 by monitoring points (circles with dots). That figure is reproduced on the next page:
13
14
15
17
18
19
20
21
22
23
24
25 6
This point is emphasized because, as explained below, STPs counterclaim depends on
26 the (incorrect) assertion that TW-2 was indicated to be an observation well.
6
7
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
6
7
10
11
12
13
14
15
16 Summarizing the above, the GEDR provides the following information about TW-2:
17 TW-2 was a pumping well installed in 2002.
18 TW-2 was used as a pumping well in March 2010.
19 TW-2 was located in the path of STPs tunnel boring machine.
20 TW-2 had an eight-inch diameter casing.
21 All of this information is accurate. The actual condition of TW-2 in the field did not
22 differ (materially or otherwise) from what the GEDR says about it.
23 C. STP Knew That TW-2 Was Within the Tunnel Alignment, Then Forgot About It.
24 As STP got ready to begin mining, its employee Justin McCain tested groundwater levels
25
26
6
7
10
11
12
13
14
15
16
17
18
19
20
21 Several days after mining through TW-2, STP found that its TBM was not advancing as
22 expected. STP investigated, eventually concluded that the TBM had sustained damage, and shut
23 it down for repairs.11
24 10
The statements in this paragraph are supported by the Oles Decl., 13-14, which
25 reports deposition testimony from Mr. Dixon and Mr. McCain.
11
26 See STPs Answer, 82-89.
16 What STP now alleges as clear is an interpretation invented in the summer of 2014
17 purely for claim purposes. No one at STP -- not Mr. Dixon, not Mr. McCain, and not Mr.
18 Stirbys -- ever actually believed that TW-2 had a two-inch PVC casing. Excerpts from the
19 Dixon, McCain, and Stirbys depositions follow:
20 Mr. Dixon:
21
Q: And before June 2014 you had not looked into the GEDR and drawn the
22 conclusion that it described TW-2 as having a two-inch PVC casing?
A: No.
23
Q: And do you know, before June of 2014 do you know of anybody else at STP
24 or its partners who had looked into the GEDR and concluded that it said TW-2
has a two-inch PVC casing?
25
12
26 The statements in this section are supported by the Oles Declaration, 15-20.
6 Q: Okay. You didnt think it, one way of the other, whether it had a PVC casing
before it was struck, did you?
7 A: No.
8 Mr. Stirbys:
9 Q: [Y]ou never heard from anyone that it [TW-2] had a steel well casing prior to
that date, December 4, 2013?
10 A: Not that Im aware of.
11 Q: Did you have a view personally that it was -- that it was made of PVC TW-2
before December 4, 2013, or did you not have a view?
12
A: I did not have a view.
13
6 Contract Section 5.7.3.4 provides that failure to give timely notice shall result in a waiver of
7 STPs claim for Differing Site Conditions.16
8 2. STPs Duty to Comply With Applicable Laws.
9 STPs Contract, Section 2.2(f), requires STP to comply with all requirements of all
10 Laws.17 Laws are defined broadly to include applicable Washington laws and regulations.
11 RCW 18.104.030 and WAC 173-160-381 require that wells (including wells like TW-2)
12 be decommissioned only in specific permitted ways.18 Not surprisingly, running into a well
13 with a tunnel boring machine is not a permitted method of decommissioning. Mr. McCain
14 admitted in a 2015 email that STP was in violation of the law relating to decommissioning
15 wells; Mr. Stirbys similarly admitted that STP was guilty for not decommissioning.19
16 3. STPs Duty to Protect Existing Wells.
17 The Technical Requirements in STPs Contract, Section TR 2.54.3.2, provide that one of
18 STPs responsibilities was to Protect from damage instruments installed by Design-Builder and
19
20
16
The statements in this paragraph are supported by the Nielsen Decl., 5.
21
17
The statements in this paragraph are supported by the Nielsen Decl., 6.
22
18
RCW 18.104.030 provides, in pertinent part, that ([i]t is unlawful: (1) [f]or any person
23 to . . . alter, or decommission a well without complying with the provisions of this chapter . . .
24 WAC 173-160-381 sets standards for decommissioning wells. For cased wells, the regulation
requires either (a) perforating and then pressure sealing the casing or (b) removing the casing and
25 filling the hole with concrete or grout.
19
26 Oles Decl., 24-25.
4 191 Wn. App. 142, 166, 364 P.3d 784 (2015) (King County v. VPFK). STP cannot satisfy
6 B. The GEDR Does Not Indicate That TW-2 Has a Two-Inch PVC Casing.
7 The counterclaim challenged in this motion is based on the allegation that the GEDR
8 identifies TW-2 as having a two-inch PVC casing. Determining what the GEDR indicates is a
9 question of contract interpretation. When the relevant provisions are clear, as they are here,
10 contract interpretation is a question of law that is appropriate for summary judgment. See
11 Go2Net, Inc. v. C I Host, Inc., 115 Wn. App. 73, 83, 60 P.3d 1245 (2003) (summary judgment is
12 proper if the written contract, viewed in light of the parties objective manifestations, has only
14 Section II.B above reviews parts of the GEDR that describe TW-2 as a pumping well
15 with an eight-inch casing. The Court may reasonably ask, Does any part of the GEDR say that
16 TW-2 has a two-inch PVC casing? The answer is no. The GEDR never says that TW-2 has a
18 STPs argument to the contrary fails, as can be seen by analyzing the statement of that
22 2. GEDR Section 2.5 says that certain observation wells are shown in Figure 2 (as
blue shaded symbols).
23
3. GEDR Section 2.5.1 says each observation well was constructed with a two-
24 inch diameter PVC casing.
25 4. TW-2 is shown in Figure 2 with a blue shaded symbol.
26
16 If TW-2 were one of the observation wells being discussed in this section, it would be
17 listed on GEDR Tables 1 and C-1.23 But TW-2 is not listed there. Every observation well listed
18 in Tables 1 and C-1 has an installation date in 2009 or 2010. TW-2, which we know from
19 repeated GEDR references is a pumping well installed in 2002, is not one of the things being
20 discussed in GEDR Section 2.5.
21 STPs point (3) is also correct but again irrelevant. GEDR Section 2.5.1 begins, Each
22 observation well was constructed using a 2-inch-diameter, polyvinyl chloride (PVC) well
23 casing. But Section 2.5.1 is talking about the observation wells described in Section 2.5 which,
24
22
25 Cited portions of the GEDR are in Exhibit C to the Nielsen Decl.
23
26 Table C-2 lists VPWs, so it is not relevant here.
23
24
25
26
3 1. I am a legal practice assistant employed by the law firm of Stoel Rives LLP, a
citizen of the United States, over the age of 18 years, not a party to this matter, and competent to
4 testify herein.
5 2. On the date indicated below, I caused to be delivered one true and correct copy of
the foregoing document on counsel of record as follows:
6
Attorneys for Defendant and Third Party
7 Plaintiff Seattle Tunnel Partners hand delivery via legal messenger
overnight delivery
John Parnass, WSBA #18582
8
Zachary Tomlinson, WSBA #35940 mailing with postage prepaid
Sarah S. Washburn, WSBA #44418 e-service per agreement of the parties:
9 [email protected]
PACIFICA LAW GROUP, LLP
1191 Second Avenue, Suite 2000 [email protected]
10
Seattle, WA 98101 [email protected]
11 Phone: 206 245-1700
25
26