Problem Solving Standard Costing and Variance Analysis
Problem Solving Standard Costing and Variance Analysis
***Questions 1 4 are based on the following information. Marshall Enterprises uses a standard cost
system in its small appliance division. The standard cost of manufacturing one unit of Kimball is as
follows:
Materials 60 lbs. at P1.50 per pound P90
Labor 3 hours at P12 per hour P36
Factory Overhead 3 hours at P8 per hour P24
The budgeted variable factory overhead rate is P3 per labor hour and the budgeted fixed factory overhead is
P27,000 per month. During May, Marshall produced 1,650 units of Marshall compared with a normal
capacity of 1,800 units. The actual cost per unit was as follows:
7. The total amount of factory overhead applied to production for November is:
a. P315,200
b. P315,000
c. P300,000
d. P324,000
200A 200B
Net Sales P192,500 P210,210
Cost of Goods Sold 115,500 165,400
Gross Profit P 77,000 P 44,810
11. The change in cost of goods sold due to change in quantity sold was:
a. P46,651
b. P3,700
c. P46,200
d. P42,500
13. Labba Corporation has a standard absorption and flexible budgeting system and uses a two-way
analysis of overhead variances. Selected data for February 2002 production activity is as follows:
Budgeted fixed factory overhead costs P 64,000
Actual factory overhead incurred P230,000
Variable factory overhead rate per direct labor hour P 5.00
Standard direct labor hours 32,000
Actual direct labor hours 33,000
14. A company has a production capacity of 10,000. The master budget for the current year included
scheduled production of 8,100 units and scheduled sales of 7,500 units. Actual production was 8,000
units and actual sales were 7,200 units. Each unit costs P15 and sells for P20. The unfavorable sales
revenue variance that should be reported for the marketing department is
a. P16,000.
b. P18,000.
c. P 4,500.
d. P 6,000.
The following information relates to a given department of Haven Company for the fourth quarter of 200A:
Actual total overhead (fixed and variable) P178,500
Budget Formula P110,000 + P0.50 per hour
Total overhead application rate P1.50
Spending variance P8,000 unfavorable
Volume variance P5,000 favorable
15. What were the actual hours worked in this department during the quarter?
a. 110,000
b. 137,000
c. 121,000
d. 153,000
16. Cox Company's direct material costs for the month of January were as follows:
For January there was a favorable direct material quantity variance of:
a. P3,360.
b. P3,375.
c. P3,400.
d. P3,800.
17. The Porter Company has a standard cost system. In July the company purchased and used 22,500
pounds of direct material at an actual cost of P53,000; the materials quantity variance was P1,875
Unfavorable; and the standard quantity of materials allowed for July production was 21,750 pounds.
The materials price variance for July was:
a. P2,725 F.
b. P2,725 U.
c. P3,250 F.
d. P3,250 U.
What was the actual purchase price per unit, rounded to the nearest centavo?
a. P3.06.
b. P3.11.
c. P3.45.
d. P3.75.
19. The Fletcher Company uses standard costing. The following data are available for October:
Actual quantity of direct materials used ... 23,500 pounds
Standard price of direct materials ......... P2 per pound
Material quantity variance ................. P1,000 favorable
20. Lab Corp. uses a standard cost system. Direct labor information for Product CER for the month of
October follows:
Standard direct labor rate ................. P6.00 per hour
Actual direct labor rate paid .............. P6.10 per hour
Standard hours allowed for actual production 1,500 hours
Labor efficiency variance--unfavorable ..... P600
21. For the month of April, Thorp Co.'s records disclosed the following data relating to direct labor:
Actual cost ............... P10,000
Rate variance ............. P 1,000 favorable
Efficiency variance ....... P 1,500 unfavorable
For the month of April, actual direct labor hours amounted to 2,000. In April, Thorp's standard direct labor
rate per hour was:
a. P5.50.
b. P5.00.
c. P4.75.
d. P4.50.
Questions 22-24. The Clark Company makes a single product and uses standard costing. Some data
concerning this product for the month of May follow:
22. The actual direct labor rate for May in pesos per hour was:
a. P12.50.
b. P12.00.
c. P11.75.
d. P11.50.
23. The total standard cost for direct labor for May was
a. P168,000.
b. P180,000.
c. P120,000.
d. P161,000.
24. The standard hours allowed to make one unit of finished product are:
a. 1.0.
b. 1.2.
c. 1.5.
d. 2.0.
25. Web Company uses a standard cost system in which manufacturing overhead is applied to units of
product on the basis of machine hours. During February, the company used a denominator activity of
80,000 machine hours in computing its predetermined overhead rate. However, only 75,000 standard
machine hours were allowed for the month's actual production. If the fixed overhead volume
variance for February was P6,400 unfavorable, then the total budgeted fixed overhead cost for the
month was:
a. P96,000.
b. P102,400.
c. P100,000.
d. P98,600.
26. Solo Corporation recently purchased 25,000 gallons of direct material at P5.60 per gallon. Usage by
the end of the period amounted to 23,000 gallons. If the standard cost is P6.00 per gallon and the
company believes in computing variances at the earliest point possible, the direct-material price
variance would be calculated as:
a. P800F.
b. P9,200F.
c. P9,200U.
d. P10,000F.
e.
Use the following to answer questions 27-28:
31. Simms Corporation had a favorable direct-labor efficiency variance of P6,000 for the period just
ended. The actual wage rate was P0.50 more than the standard rate of P12.00. If the company's
standard hours allowed for actual production totaled 9,500, how many hours did the firm actually
work?
a. 9,000.
b. 9,020.
c. 9,980.
d. 10,000.
32. Arling Company, which applies overhead to production on the basis of machine hours, reported The
following data for the period just ended:
If it takes four hours to manufacture a completed unit, the company's standard fixed overhead rate per
machine hour would be:
a. P12.00.
b. P14.40.
c. P14.60.
d. P15.00.
33. Herman Company, which applies overhead to production on the basis of machine hours, reported the
following data for the period just ended:
Actual units produced: 13,000
Actual fixed overhead incurred: P742,000
Standard fixed overhead rate: P15 per hour
Budgeted fixed overhead: P720,000
Planned level of machine-hour activity: 48,000
If it takes four hours to manufacture a completed unit, the company's fixed-overhead volume variance
would be:
a. P0.
b. P22,000 favorable.
c. P60,000 favorable.
d. P22,000 unfavorable.
34. Luke, Inc., has a standard variable overhead rate of P5 per machine hour, with each completed unit
expected to take three machine hours to produce. A review of the company's accounting records
found the following:
Actual production: 19,500 units
Variable-overhead efficiency variance: P9,000U
Variable-overhead spending variance: P21,000F
35. Bushnell, Inc., has a standard variable overhead rate of P4 per machine hour, with each completed
unit expected to take three machine hours to produce. A review of the company's accounting records
found the following:
Actual variable overhead: P210,000
Variable-overhead efficiency variance: P18,000U
Variable-overhead spending variance: P30,000F
How many units did Bushnell actually produce during the period?
a. 13,500.
b. 16,500.
c. 18,500.
d. 21,500.