Rate Analysis
Rate Analysis
LABOUR
Wireman day 0.20 500.00 100.00
Mason, Grade 2 day 0.10 400.00 40.00
Painter day 0.02 400.00 8.00
helper day 0.30 250.00 74.10
TOTAL 838.85
Add 15% for Overheads & Profit 125.85
TOTAL 964.70
Rate per Point 964.70
Item 11.1
LABOUR
Wireman day 0.10 500.00 50.00
Mason, Grade 2 day 0.10 400.00 40.00
Painter day 0.01 400.00 4.00
helper day 0.01 250.00 2.5
TOTAL 246.50
Add 15% for Overheads & Profit 36.95
TOTAL 283.45
Rate unit 283.45