Critical Path Method PDF
Critical Path Method PDF
Method
www.projectbaseline.in 1
History
www.projectbaseline.in 2
Application
www.projectbaseline.in 4
Basic Technique
www.projectbaseline.in 5
Basic Technique
In project management, a critical path is the
sequence of project network activities which add up to
the longest overall duration.
This determines the shortest time possible to
complete the project.
Any delay of an activity on the critical path directly
impacts the planned project completion date (i.e.
there is no float on the critical path).
A project can have several, parallel, near critical
paths.
An additional parallel path through the network with
the total durations shorter than the critical path is
called a sub-critical or non-critical path.
www.projectbaseline.in 6
PERT Chart
A B
5 12
LS LF LS LF
www.projectbaseline.in 7
Activity Relationships
Finish-to-Start (FS):
A relationship between activities in which the start of a successor
activity depends on the finish of its predecessor activity.
B
Start-to-Start (SS)
A relationship between activities in which the start of a successor
activity depends on the start of its predecessor.
www.projectbaseline.in 8
Activity Relationships
Finish-to-Finish (FF):
A relationship between activities in which the finish of a
successor activity depends on the finish of its predecessor.
A
B
Start-to-Finish (SF):
A relationship between activities in which a successor activity
cannot complete until its predecessor starts.
A
Lags (or Leads):
An offset or delay from an activity to its successor. A Lag can be
positive or negative
www.projectbaseline.in 9
Activity Box
ES EF
A
5
LS LF
ES = Early Start
EF = Early Finish
LS = Late Start
LF = Late Finish
A = Activity Name
5 = Duration Of Activity
www.projectbaseline.in 10
Activity Network Diagram
ES EF ES EF
B C
10 8
LS LF LS LF
ES EF ES EF
A E
5 7
LS LF LS LF
ES EF
D
12
LS LF
Activity Name
A. Ordering of Pump
Assumptions
B. Pump Manufacturing
7 day work week
C. Pump Transportation
FS Relationships
D. Pump Foundation
No Lag or Leads
E. Pump Erection
www.projectbaseline.in 11
Forward Pass
In Forward Pass Early Dates are calculated
Forward Pass
B C
10 8
LS LF LS LF
ES=1 EF=5 ES=24 EF=30
A E
5 7
LS LF LS LF
ES=6 EF=17
D
12
LS LF
www.projectbaseline.in 12
Backward Pass
In Backward Pass Late Dates are calculated
B C
10 8
LS=6 LF=15 LS=16 LF=23
A E
5 7
LS=1 LF=5 LS=24 LF=30
ES=6 EF=17
D
12
LS=12 LF=23 Assuming LF = 30
Backward Pass
www.projectbaseline.in 13
Total Float
Total Float = The amount of time the activity can be delayed before delaying
the Project Finish Date
B C
10 8
LS=6 LF=15 LS=16 LF=23
www.projectbaseline.in 14
Critical Path Scenario-I
Scenario I Late Finish of the project = 30
Activities with Total Float =< 0 are on the Critical Path
B C
10 8
LS=6 LF=15 LS=16 LF=23
www.projectbaseline.in 15
Critical Path Scenario-II
Scenario II Late Finish of the Project is greater than 30 i.e. 40
Activities with Total Float =< 0 are on the Critical Path
B C
10 8
LS=16 LF=25 LS=26 LF=33
B C
10 8
LS=0 LF=9 LS=8 LF=17
www.projectbaseline.in 17
Total Float
www.projectbaseline.in 18