Hydrotest Procedure For Piping
Hydrotest Procedure For Piping
INDEX
Section No.
1.0 Scope
2.0 References
3.0 Definitions
2
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
1. Scope
2. References
3
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
Page 4 of 18
4
GI-0002.102 Pressure Testing Safely
3. Definitions
4. General Requirements
4.1 General Instruction GI-0002.102 Pressure Testing Safely shall be followed during
pressure testing.
5
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
Page 6 of 18
6
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
Page 7 of 18
7
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
4.7 The requirements for leak tests and service test and service during initial start-up and
T & Is shall be as follows:
4.7.1 New system after strength and tightness test and prior to initial start-up.
4.7.1.1 For systems with maximum operating pressure greater than 6.894
Mpa (1000psi), a leak test with inert gas, followed by a service
test, shall be conducted at the maximum operating pressure of the
piping system. Oil flow lines, trunk lines, test lines and water
injection lines are excluded from the requirements.
4.7.1.2 For systems with maximum operating pressure less than 6.894
MPA (1000psi), a leak test with inert gas or steam shall be
conducted at the available inert gas or steam system pressure (not
exceeding the maximum operating pressure), or damage as
recommended by responsible Operation Engineering Unit,
followed by a service test at normal operating pressure of the
piping systems. When inert gas or steam is not available, the
service test will satisfy the leak requirement.
8
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
4.7.2.2 For all other systems and pressure, a leak test with inert gas or
steam shall conducted at the available inert gas or steam system
pressure (not exceeding the maximum operating pressure), or at
pressure as recommended by responsible Operation Engineering
Unit, followed by a service test at normal operating pressure of the
piping systems. When inert gas or steam is not available, the
service test will satisfy the leak test requirements.
4.7.2.3 Procedures for both leak test and service test shall address, to the
extent possible, the safety precautions provided in GI-0002.102
Pressure Testing Safely.
If the drop in ambient temperature may cause the test medium to freeze
during the test, appropriate precautionary measures must be taken to
protest the equipment or piping system.
5. Specific Testing Procedure / Requirements
This section specifies in details which piping or equipment that shall be pressure tested
and provides the specific applicable standard. It also defines any specific exemptions.
5.1 Plant Piping
Pressure testing of plant piping shall be in accordance with SAES-L-150
9
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
Potable water piping outside of the building shall be tested in accordance with
the requirements of SAES-S-40.
5.3 Utility Piping System
Utility piping systems, including irrigation piping and water distribution
mains, shall be tested in accordance with SAES-S-070.
5.4 Industrial Drainage and Sewers
Industrial drainage and sewers shall be tested in accordance with SAES-S-
020.
6. Preparation of Test Packages
6.1 Carefully study the P & ID drawings and identify isometric drawing shall be
reviewed jointly by PMT, MFH, CZFP & APOD to ensure that all the tie-ins and
hydrotests are well coordinated to minimize the shut-down of facilities prior to
finalizing the hydrotest diagrams and packages.
6.2 MFH will prepare the Pressure Test Packages and Saudi Aramco will issue the
approved Test Package after the review and approval by Saudi Aramco. MFH
with the coordination of Saudi Aramco and will prepare the pressure test diagram
for each test pack showing the location of the isolation points or valve location,
test manifold, check valves, pressure relief valves and pressure gauges. It should
also identify the pressure rating of PRVs and shall be 5% above the maximum
test pressure. The capacity of the pressure gauges should be at least 4-times the
required test pressure.
6.3 MFH shall identify the location of the test limits in agreement with Saudi Aramco
and SAPMT if piping system is completely installed at site. If spools are in flange
10
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
type system, these can pressure tested at the shop and will be witnessed by
Saudi Aramco and SAPMT.
6.4 MFH shall provide the required blind or slip blind rating list and do all the
required fabrication. MFH to ensure that the required slip blind rating list
is in compliance with the pressure rating design and as per Saudi Aramco
Engineering Standards.
6.5 Saudi Aramco to finally issue the approval of pressure Package after the
review of SAPMT.
7. Preparation for Hydrotestesting
7.1 If fabricated spools cannot be pressure tested at the shop, ensure that all of
the weld joints are uncoated including field weld joints. Coating of weld
joints on spools shall be done only after the completion of pressure test.
Fabricated spools can be painted leaving all weld joints uncoated.
7.2 Flushing of new piping spools or piping systems shall be done prior to any
pressure testing to internal parts of each spools are clean and free from any
foreign debris or materials.
7.3 Prepare the records for all fabrication, erection, inspection, NDE and
PWHT (when required) for each test packages. Check for the completion
of the above activities on the lines to be pressure tested.
7.4 Pre-punch list the lines prior to pressure testing for items that can be
installed after the completion of the pressure test, and after test
completion, identify any missing items and activities and punch list it
again prior to MCC (Mechanical Completion Certificate.).
11
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
7.5 Identify the required sizes of blinds or slip blinds and their ratings that
shall be installed on the reference test limits for pressure test. PMT is
requested that the installed slip blinds are verified and signed by APIU
prior to pressuring of the piping circuits.
7.6 Prepare a list of piping pipe supports prior to and after pressure test. All
spring supports shall be locked prior to pressure test and unlocked on
completion of pressure test.
7.7 Isolate equipment to piping such as pumps, pressure relieving devices,
control valves, pressure indicating gauges, etc., which should not be
subjected to pressure test. Isolation by installing a dummy spools,
temporary slip blinds or blinds are acceptable to Saudi Aramco, SAPMT.
7.8 MFH QC shall raise an RFI for the joint inspection and walk through of
the lines with Saudi Aramco, Saudi Aramco SAPMT prior to the approval
for pressure testing.
7.9 Ensure that the pressure gauges and pressure relief valves have been
calibrated and the calibration certificates are available for verification by
Saudi Aramco and Saudi Aramco Project Inspector. Pressure guage
instruments should have a valid calibration certificate and a sticker is
placed to the gauge. Pressure gauges shall be calibrated every one (1)-
month while pressure relief valve shall be tested, dated and tagged within
one week (7-days) prior to the hydrotest for new construction projects, and
within one (1)-month for the maintenance.
7.10 The pressure test manifold in the actual system pressure test shall be
separately pressure tested to at least 1.2 times the system test pressure.
12
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
13
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
14
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
9.11 Firewater systems shall be tested for 4 hours in accordance with SAES-B-017.
9.12 Pressure sewers shall be tested under the same conditions as for pressure piping.
9.13 Buried lines should be tested before backfilling. In case where a trench has been
backfilled prior to a pressure test, a 24-hours pressure/temperature recorded test is
required per SAES-L-150.
9.14 Welded connections that are impractical to pressure test may be 100% inspected
by NDE in lieu of a pressure test (SAES-A-004, para. 3.67.2). the Appendix of
SAES-A-004 shall be submitted to the applicable approval authority at least 24
hours prior to actual test.
9.15 Safety requirements described in SAES-A-004 shall be reviewed and closely
followed when pressure testing.
9.16 MFH to provide the pressure test diagrams and procedures, for new projects to the
inspector conducting the test. Refer to SAES-A-004, para. 5.6.1 for details of
these documents.
9.17 Piping detail drawings for end connections, branches, crossings, etc. including
pipe support and anchor details shall be available for review and approval.
9.18 Highlighting any special features or precautions, tie-in temperature range, any
other test required, lay-up and commissioning as applicable.
9.19 Perform pressure test as detailed below:
15
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
-Pressure test lines shall be carried out using potable water with the addition of
rust inhibitor (when required). Maximum chloride content shall not exceed
30ppm.
-Test shall be carried out at ambient temperature (10oC and 35oC).
-Pressure gauges calibration and reading scale shall have a range to be between
and of the scale
-Employ the pressure test manifold in the actual system pressure test that had
been separately tested at 1.2 times the system test pressure but not less than the
discharge pressure of the pump used for the pressure testing.
-Expansion joints and spring hangers or spring supports shall be provided with
temporary restraint where needed to prevent excessive travel or deformation
under the test load.
-Filling and pressurizing shall be done on the upstream side of check valves in the
system or the flapper of the check valves shall be removed and replace back after
completion of the test. All test vents shall be open during filling.
-The test fluid shall be injected at the lowest point in the system to minimize
entrapped air.
16
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
-All test vents shall be opened before draining to facilitate draining and to prevent
formation of a vacuum. No test fluid shall remain in low spots.
17
Tel : 837-3777 FAX : 837-3888
M.F. AL-HAJRI CONTRACTING EST.
P.O. BOX 4626 Al-Khobar 31952
QUALITY PROCEDURE NO. : QP-MFH-L-02 Rev. 00
11.3 Perform dye penetrant test on the ground surface location of leak and identify any
form of surface defect or discontinuity.
11.4 Weld the prepared surface in accordance with the approved WPS. Perform 100%
NDE on this joint, MT/PT for socket weld joints and RT for butt weld joints.
11.5 The repaired joint shall be subjected to the same type of testing as specified for
the lines.
12. Safety Precautions
12.1 Work permit must be requested by MFH on pressure testing of piping systems or
plant piping, which will be under review, verification and approval, by Saudi
Aramco.
12.2 Barricade the area for pressure testing.
12.3 Place a signboard indicating the system.
12.4 Restrict entry for unauthorized personnel.
12.5 Check for the use of proper test pumps, manifolds, relief valves and pressure
gauges.
12.6 Check the lines to ensure that they are properly supported prior to the pressure
test.
13. Records and Documents
Below are the permanent quality records to be filled up after completion of the
pressure test;
Cleaning / Flushing Record
Pressure Test Records
Pressure Test Certificates