Project Managment Plan
Project Managment Plan
This name of this project is Using Simply Order Software and Customer Service
Training.
Project Description/Overview
The management at A-Z Specialties has set a goal to increase net profit from $3
million last year to $5 million this year. To achieve that goal, A-Z has identified
several issues that prevent their desired business growth. Specifically, they
recorded a 30% increase in customer complaints with Telephone Operators in the
call center. They also identified several Human Resource issues, including high
turnover of Telephone Operators and Customer Service Supervisors and a need for
improved training for Telephone Operators and Supervisors. A-Z has contracted
WoE to develop training for telephone operators that would reduce call duration,
improve customer service, increase employee satisfaction and as a result, increase
A-Zs profitability.
West of Eastern (WoE) conducted a performance analysis to determine the gaps in
the current state at A-Z in contrast to their desired state, and presented their
findings to Jane Mackenzie. WoE presented Jane their top three solutions to the
issues identified by the gap analysis. From the meeting, Jane determined that WoE
would develop customer service and Simply Order software training for telephone
operators as phase one of this project.
Project Purpose
Business Objectives
The improvements in customer service as well as the efficiency of the new order
entry system will result in reduced customer complaints related to telephone
operator etiquette and long wait times. Customer satisfaction will increase sales
and help A-Z achieve the target goal of $23 million in total sales ($8 million in
catalog sales and $15 million in internet sales) and a net profit of $5 million.
Exclusions
This project will be complete when all the deliverables and sub-documents listed
above have been signed off on by the project sponsor, Jane MacKenzie, and
delivered to A-Z Specialties by WoE. Prior to delivery of all deliverables, A-Z
Specialties and WoE will reach an agreement on ownership of and further use of
deliverables.
This project includes several formal plans to carry out a smooth development and
implementation of the Using Simply Order Software and Customer Service
Training. These plans include a schedule, course design document, change
management plan, target milestones, and project plan approvals.
Scheduled Meetings
WoE Project Manager, Mary DuQuaine will provide a status report every Monday
to the team in writing via Basecamp Project Management software.
Team 3: Module 5-Project Management Plan 3
9/2/2017
Assumptions
Constraints
The following situations will constrain the ability of A-Z Specialties to complete
the project:
Training time will be constrained by the shifts of the trainees and SMEs.
External Dependencies
The development of the Telephone Operator Training for A-Z Specialties will
follow the ADDIE method of course development, wherein:
(A)nalyze - WoE will partner with subject matter experts within A-Z to gather
and assess data surrounding telephone operations and the training of
employees.
(D)esign - WoE will use its findings to design instructor-led training that
addresses improved customer service and phone etiquette as well as navigation
and use of the new Simply Order product database and order system.
Milestones
Below is a Work Breakdown Structure (WBS) showing the project broken into its
component sections of the telephone operator training being designed and
developed by WoE. A readable PDF is submitted as a separate document.
Below is a project schedule based on the WBS but with the addition of start and
due dates as well as responsible parties. A readable PDF is submitted as a separate
document.
The Gantt chart provides a visual representation of the schedule showing the
highest-level categories including dates and responsible parties. A readable PDF is
submitted as a separate document.
Purpose
The purpose of the Change Management Plan will help manage change requests to
the project, while insuring control of the schedule, scope, budget, and
resources. This plan will minimize the impact a change can have on both A-Z and
WoE.
Goals
Approved by: