Method Statement Scaffolding Draft
Method Statement Scaffolding Draft
METHOD
STATEMENT
BS
STANDARD
PROJECT:
CLIENT :
Page 1 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
INDEX
3 INTRODUCTION
4 SCOPE OF WORK
5 MANAGEMENT GUIDANCES
7 SCAFFOLDING DESIGN
8 SCAFFOLDING MATERIAL
10 SCAFFOLDING TYPES
11 INSPECTION
12 SCAFFOLDTAG SYSTEM
13 MODIFICATION
1 INTRODUCTION
2 SCOPE OF WORK
3 MANAGEMENT GUIDANCES
iii) Ensure that all its employees adhere to the recognized standard or code
of practice with respect
to the selection, erection and possible modifications of scaffolds.
iii) Provide proper training for its scaffolders and ensure that the
Scaffolding
Supervisor properly monitors the performance of scaffolders.
iii) Carry out regular quality control and safety checks on scaffolding
materials and on erected
scaffolds.
Page 3 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
CLIENT shall:
iii) Ensure at all times that scaffolding is safely used by users and
not modified without
authorization.
iii) Ensure that users inform the scaffolding supervisor when scaffolding
is no longer required
and is available for dismantling.
iii) BS EN 39: 2001 Loose steel tubes for tube and coupler scaffolds
technical delivery
conditions.
5 SCAFFOLDING DESIGN
The access and workings scaffolds listed in Table -1, with their construction
criteria, shall be designed
by SCAFFOLDING CONSTRUCTION (SC) in accordance with appropriate
BS Standards. All
other scaffolds, and all scaffolds which are the subject of a specific user
request outside the pre-
specified format of Table 1, shall be designed by SCAFFOLDING
CONSTRUCTION (SC) to
the requirements and approval of client.
3 SCAFFOLDING MATERIAL
When scaffolding is erected in areas where high levels of radiated heat are
unavoidable encountered,
e.g. where high temperature pipe work is in close proximity, timber scaffold
boards may be exposed
to the risk of burning or charring. In these
circumstances, the use
of pressed steel staging boards is an acceptable alternative.
Page 6 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
a) Planning
All scaffolds shall be braced and tied to form a rigid stable structure. There
are minimum requirements
for bracing and tying scaffold but these is a guide only to the scaffolder. A
priority concern of the
scaffolder is to provide a safe working platform free from movement.
If this priority is not
satisfied on completion of the minimum requirements for bracing and tying,
the scaffolder is bound
to include such extra ties and braces as in needed.
i) Braces.
With the exception of tower and single bay scaffolds, face braces shall be
provided that are attached
to the external row of standards of the scaffold as close to the junction of the
ledger and standard as
is practicable and extend to the full length and height of the scaffolding.
Transverse braces shall
be provided that are attached diagonally in every lift joining the internal and
external standards at both
ends of the scaffold and at intervals not exceeding 25 metres. Tower and
single bay scaffolding shall
be provided with braces diagonally in every face in every lift of the scaffold.
ii) Ties.
Ties shall be provided that are attached by 90 couplers to the outside and
inside standards or ledgers as
close as possible to the junction of ledgers and standards. They shall be
located horizontally no
further than one bay from the ends and at intervals not exceeding
3 bays. They shall be located vertically in the first lift and at intervals not
exceeding 4
metres.
c) Guard Rails
All working platform above a height of 2 metres or at any height less than 2
metres where a hazard
such as starter bars exists, shall be provided with double guard rails
and kickboards to all open
edges.
The guard rails shall consist of a top rail erected 1 metre above the working
platform and a midrail
erected midway between the top rail and the working platform.
Page 7 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
d) Scafftags
e) Dismantling
Prior to any dismantling of scaffolding taking place and during the dismantling
procedure, the following
safety precautions shall be observed:
The scafftag is to be changed from Complete status to Incomplete status.
The area at ground level is to be barricaded with general purpose bunting
and a sign displayed
stating Danger Men Working Above
All planks are to be turned to remove dust and dirt that may cause eye injuries.
Care shall be taken to
ensure personnel are not working below when plank cleaning is taking place.
All horizontal tubes, once
removed, shall be turned to the vertical to remove grit and metal flakes from
inside the tubes to
avoid eye injuries during lowering operation.
8 TYPES OF SCAFFOLD
In all cases, the following scaffold types are to be subject to specific design by
SCAFFOLDING
CONSTRUCTION (SC)
when the client may require to approve in detail prior to erection:
Page 8 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
a) Definition
b) Bay Sizes
c) Loadings
No more than two working platforms are to be fully loaded per bay but
this number may be
increased provided the total loading per bay does not exceed the total of
two fully loaded bays.
d) Erection
All gear to be used in the erection of an independent scaffold will be laid out
nearly and sorted into
sizes for easy access. It will be necessary to erect general purpose bunting
around the gear so as
not to create a trip hazard for other personnel. The area to be
scaffolded will have general
purpose bunting erected at ground level and a sign strating
caution men working above displayed prominently to protect personnel
from hazards involved in
the erection of the scaffold.
Page 9 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
plates may be placed directly on that surface without the use of timber sole
plate. The standards
may then be placed on the base plates as required.
Temporary raked tubes should be used to plumb the first two standards
and may be removed at
such time as the scaffold is self supporting through the fixing of addition
member.
Caution must be observed at this base lift of the scaffold to ensure joins do
not occur in adjacent
standards in the same lift and in adjacent ledgers in the same bay.
Appropriate tube sizes are
selected at the planning stage to satisfy these criteria. All horizontal
members are to be made
level and all standards made plumb with the use of an accurate spirit level.
During the erection of the scaffold, and while any alterations to the scaffold
are being carried out, a
scaffold incomplete sign is to be displayed prominently at the base of the
scaffold.
a) Definition
b) Bay Sizes
Standard spacing for modular scaffolding may vary from those set down
for tube and fitting
scaffolding provided approval has been granted but the
Department of
Occupational Health Safety and Welfare / An example of this variation is
the 2.4m transoms
available in the wedge lock system that enable the scaffolder to erect 2.4m x
2.4m medium duty bays.
Page 10 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
c) Loadings
No more than two working platforms are to be fully loaded per bay but
this number may be
increased provided the total loading per bay does not exceed the total
of two fully loaded
platforms.
d) Erection
General purpose bunting will be erected around the gear so as not to create
a trip hazard for other
personnel. The area to be scaffolded will have general purpose bunting
erected at ground level and a
sign stating caution men working above displayed prominently to protect
personnel from hazards
involved in the erection of the scaffold.
For ground surfaces other than concrete slabs, timber sole plates are to be
placed at the required
spacing for the scaffold to be erected, i.e. heavy duty, medium duty and
light duty. Adjustable base
plates or screw jacks are to be positioned on the sole plates to
accommodate the standards. If
the scaffold is to be erected on a concrete slab the adjustable base plates
may be placed directly
on that surface without the use of timber sole plates. Caution must be
observed at this base lift of the
scaffold to ensure joins do not occur in adjacent standards in the same lift.
Appropriate standard sizes
are selected at the planning stage to satisfy these criteria.
Legers, transoms and braces are fixed to the standards using the patented
fixing methods and each
member will be made level using the adjustable base plate and an accurate
spirit level. Bracing is to
be installed progressively at the required locations, not as an
afterthought at the completion of
the scaffold.
Page 11 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
Where hop-up brackets are used as an extension of the working platform width,
they must be restrained
from rotation by approved tie bars. A two board hop-up bracket will not be
used to accommodate
one board.
During the erection of the scaffold and while any alterations to the scaffold
are being carried out, a
scaffold incomplete sign is to be displayed prominently at the base of the
scaffold.
a) Definition
b) Bay Sizes
c) Height
The maximum height of a free standing tower is three times the least base
dimension measured
centre to centre of the standards.
d) Loadings
Not more than one working platform shall be erected on a tower scaffold
although intermediary
landing platforms may be erected for access to the working platform. The
working platform on a
tower scaffold shall not exceed the following loadings;
Heavy duty 625 kg.
Medium duty 430 kg.
Light duty 180 kg.
Page 12 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
e) Erection
All gear to be used in the erection of a tower scaffold will be laid out neatly
and sorted into sizes for
easy access. It will be necessary to erect general purpose bunting around the
gear so as not to create a
trip hazard for other personnel. The area to be scaffolded will have general
purpose bunting erected
at ground level and a sign stating caution men working above displayed
prominently to protect
personnel from hazards involved in the erection of the scaffold.
The surface to support the scaffold should be checked to ensure it is even and
free from
obstructions. If required, level the ground surface at the points standards are to
be located.
For ground surfaces other than concrete slabs, timber sole plates are to be
placed at the required
spacing for the scaffold to be erected, i.e. heavy duty, medium duty or light
duty. Base plates of mild
steel with an area no less than 0.225m2 x 6mm thick are to be positioned
on the sole plates. If
the scaffold is to be erected on a concrete slab, the base plates may be
placed directly on that surface
without the use of timber sole plates.
Temporary raked tubes should be used to plumb the first two standards
and may be removed at
such time as the scaffold is self supporting through the fixing of addition
members.
Caution must be observed at the base lift of the scaffold to ensure joins do
not occur in adjacent
standards in the same lift. Appropriate tube sizes are selected at the
planning stage to satisfy these
criteria. All horizontal members are to be made level and all standards
are to be made plumb
using an accurate spirit level. A spreader may be used to accurately guage
the diagonals of the tower
to ensure the standards remain plumb and prevent corkscrewing
When the span of the putlogs supporting working platform exceed 1.5 metres,
they will be supported by
a puncheon to a lower member, or strutted to lower members.
During the erection of the scaffold, and while any alterations to the scaffold
are being carried out, a
scaffold incomplete sign is to be displayed prominently at the base of the
scaffold.
Page 13 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
f) Bracing
h) Access Towers
Where the tower scaffolding is erected to provide access to a work area above
6 metres in height, the
landing places for the ladders must be fully decked (except when access is
provided).
The platform shall have a safe means of access which shall always be on the
narrowest side of the
tower. Access may be achieved in the following ways:
Tools and heavy loads shall not be carried but hauled up or lowered down by a
person on the platform
within the confines of the tower.
Page 14 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
a) Definition
b) Application
d) Maximum Drop
The maximum distance that a working platform may be erected from overhead
supports is three lifts or
six metres. Single lengths of tube only, are to be used as drop tubes, there
are to be no joins or
dropping again from ledgers or transoms.
e) Loadings
One only working platform per bay of drop scaffolding shall be loaded at any
one time and such
working platform shall not be loaded in excess of the following:
All gear to be used in the erection of a hanging scaffold will be laid out nearly
and sorted into sizes for
easy access. The physical environment of the area to be scaffolded will
determine whether the gear
to be used in the erection of the scaffold will be passes up or
Page 15 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
passed down. This decision will be made during the job safety analysis
discussion between the
work supervisor and the licensed scaffolders.
All gear to be used in the erection of the scaffold will have general purpose
bunting erected
around the storage area to prevent trip hazards to other personnel.
Prior to raising or lowering the drop tubes into position a short tube
approximately
300mm shall be fixed with a 90 coupler to the lower end of the drop tubes.
This short tube affords the
scaffolder a degree of comfort when erecting the initial ledgers and
transoms and shall not be
substituted by a 90 coupler.
Scaffolders are permitted to access the lower end of the drop tube by sliding
sown the tube to the
T piece or by walking the steel beams if the former is not practicable.
It is paramount for the scaffolder to secure his lanyard to the drop tube prior
to descending to the T
piece. The lanyard will be given two full turns on the drop tube and secured
back to the second belt
ring, and shall only be removed to relocate to another member. As there
will be two scaffolders
involved in fixing the first lift, it will not be necessary for either to
traverse the longitudinal
spacing between the drop tubes. This negates the practice of moving
about during the initial
erection stage without anti-fall protection. As early as is practicable the
working platform planks and
guard rails shall be installed and only when this is complete may anti-fall
protection be removed.
The nature of the overhead supports will cause the scaffold to sway
considerably and must be eliminated
as early as possible by bracing all faces of the scaffold and where possible, by
the installation of ties.
Subsequent lifts may be installed in the scaffolding at maximum spacing of 2
metres and are erected
as for independent tube and fitting scaffolding. Where the scaffolder is in
a stationary position
during the erection of subsequent lifts, and guard rails are not
provided, he will secure his
lanyard to a member of the scaffold.
Page 16 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
The gap in the decking shall be fitted with guard rails and a swing rail to
define the open edge or an
approved trapdoor.
Drop tubes are fixed to the horizontal tubes that are fixed to the beams using
inverted 90
couplers and a check fitting positioned immediately adjacent to and above that
fitting.
The inboard structure is erected with the needles projecting the required
distance from the fulcrum
point and the purpose made counterweights positioned the required
distance inboard from the
fulcrum as per the calculations. The counterweights will have their mass
clearly stamped on them and
locked onto the standard so as not to become dislodged.
Page 17 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
Prior to any work commencing on the outboard section of the scaffold the
scaffolder will secure his
lanyard to the fulcrum or other substantial anchorage. Under no
circumstance is work to commence
outboard, without anti-fall protection. All permanent tension members are to
be in place and check
fittings fixed appropriately before descending the drop tubes to the T pieces.
When all members of the scaffolding have been removed the scaffolders
return to the overhead
supports by climbing up the drop tubes. Temporary tension members are
again fixing to the needles
and fulcrum to eliminate nay bending effect and the remainder of the scaffold
may be dismantled.
There are some general safety guidelines that must be considered when
erecting or dismantling
drop scaffolding;
The nature of the work to be performed from the working platform may
require the scaffold to
be fully enclosed with a fire retardant material to protect those personnel
working below.
Page 18 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
a) Definition
b) Bay Sizes
c) Loadings
Not more than one working platform shall be erected on a mobile scaffold
although intermediary
landing platforms may be erected for access to the working platform. The
working platform on a
mobile scaffold shall not exceed the following loadings;
d) Height
When the base of a mobile scaffold is extended, the centre of the working
platform must be located
vertically above the centre of the base, providing that;
When a wall, or the like, prevents the extension being used on one side, the
base on the opposite
shall be extended to give the required ratio.
e) Castors
f) Bracing
Page 20 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
Castors are to have the locking device engaged at all times when stationary
and only released for
the purpose of shifting location.
Personnel are not permitted to remain on the working platform when the
scaffold is being moved.
Access to the working platform shall only be gained via the ladder access
provided through the
centre of the scaffold.
Planks shall not span the working platforms of two mobile scaffolds unless
the mobile scaffold are
tied together with ledgers.
The maximum jacking adjustment on the castors shall not exceed 300mm.
i) Loading
The maximum load per platform unit shall not exceed 225kg. Not more than
two platform units shall
be loaded at any one time.
ii) Bracing
The height of the working platform shall not exceed two times the least base
measurement but in any
event the height of the working platform shall not exceed 9 meters.
Page 21 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
a) Definition
b) Bay Sizes
Heavy duty 1.8m x 1.5m
Medium duty 2.4m x 1.8m
Light duty 3.0m x 2.1m
c) Loadings
d) Bracing
Diagonal bracing is to be provided on all faces of the scaffold and where
necessary, internally to
ensure a rigid scaffold. Where a birdcage scaffold is erected within a
confined area, butt tubes
may be used in addition to, or in substitution of, other bracing or ties, if the
wall surface permits. In
some cases the ledgers and transoms can butt against the wall to give the
scaffold rigidity.
e) Working Platform
If there are insufficient planks to closely plank the whole area of the working
platform then the area
not covered shall be guard railed at the open edge.
Page 22 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
f) Erection
Care must be taken to ensure the working platform planks are placed to run at
right angle to the grade.
This will eliminate any tendency for the planks to slide off the putlogs.
Page 23 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
a) Definition
b) Bay Sizes
c) Loadings
Not more than two working platforms are to be erected and fully loaded
per bay of scaffolding
supported by cantilevered beams.
d) Erection
The basis of all cantilever scaffolds is the needle beams and as such is critical
to the safe erection of
the scaffold.
The job safety analysis discussion between the licensed scaffolder and
supervisor should cover the
following points regarding the beams;
Page 24 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
The beams are positioned the required distance apart according to the
standard spacings of the scaffold
and projected the required distance outboard from the building or structure.
The outboard distance is calculatd from the desired width of the working
platform plus the
clearance required from the building or structure to the working platform,
plus
200mm.
The inboard restraint toms are installed the required distance inboard and
tied together and welded
or bolted to the beam to prevent any movement.
When calculating the outboard load the mass of the components of the
scaffold must be considered
as they make up part of the load. The outboard distance is calculate as
the clearance from the
pivot point to the inside standard of the scaffold plus 2/3 the width of the
scaffold.
f) Access
Page 25 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
a) Definition
The means of lowering or raising the stage, whether those means are operated
by hand or are power
driven
The overhead supports, attachments and tracks ; and
The means of suspension
b) Platforms
There are a variety of platforms available, some single units and some
component assemblies
that allow the length of the platform to be varied. However, there are some
basic requirements that
apply to all platforms;
c) Overhead Supports
The overhead supports of a light duty suspended stage will vary with
individual job applications
but can basically be divided into two categories. They are ;
The overhead supports must be prevented from moving laterally by being tied
together or in some
other way prevented from moving to the satisfaction of the Supervisor.
Have a weight not less than 3 time the weight necessary to balance the weight
of the load on the
projecting part of the needle when the platform is fully loaded.
Page 27 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
Scaffold tube needle supports may take the form of a spurred needle
arrangement or a double
needle arrangement as show in figure 10. They are to be counterbalanced
as in figure 10 or tied to
the building or structure capable of withstanding three times the force likely to
be imposed.
Prior to any light duty suspended stage being put into service for the first
time or being put into
service after a substantial period of non use, the light duty suspended
stage shall be inspected and
tested by a SAS Accident Prevention Advisor.
f) Load Calculation
the total outboard load is divided by two to determine the outboard load per
needle.
f) Winches
There are numerous climbing winches available, each with their own special
features. Prior to any
climbing winch being put into service on prior approval must be obtained.
Features common to all climbing winches approved for use on site are: Drive
up,
drive down
SWL clearly displayed
Dead man button operation
Manual operation in the event of power failure
Automatic fall stop rope
Page 28 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
g) Winch Ropes
Winch ropes are supplied with winches by the manufacturer and under no
circumstances should be
substituted for any other rope. The ropes are generally 8mm diameter, 6/24
or
6/31 steel core construction galvanized steel.
All the safety features of the climbing winch are to no avail should the rope
break so the correct
handling and inspection of the rope are critical.
h) General Safety
All personnel required to work from the platform of a light duty suspended
stage shall wear at all
times, approved anti-fall protection secured to the guard rail.
The area shall be barricaded with general purpose bunting and a sign
displayed prominently
stating Danger Men Working Above.
9 INSPECTION
iii) Complies with any design drawing and /or specification for that
particular scaffold
Page 29 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
iv) The Hand-over Certificate has been signed and dated on behalf of
SCAFFOLDING
CONSTRUCTION (SC)
10 SCAFFTAG System
Insert for the holder, one side white on green to indicate, when
showing, that the scaffold is
certified for use and giving details, the other side black on yellow to
indicate, when showing,
that the scaffold is under inspection and must not be used. An exact
duplicate of the insert is
retained in a SCAFFTAG rack in an appropriate location, e.g.
Authorities Office, Control
Room, etc.
11 MODIFICATIONS
Modifications to SCAFFTAG- certified scaffolds shall be undertaken only
by SCAFFOLDING
CONSTRUCTION (SC) with the authority of the worksite supervisor. After
a modification has
been made, inspection and recertification shall be carried out.
Page 30 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
All procedures and safety guidelines followed shall take into consideration the
following hazards.
iii) Overloading
The access area around a scaffold may need to be roped-off, to reduce the risk
of debris or equipment
falling on passer-by.
iii) No scaffolder shall work from a scaffold platform of less than three
scaffold boards all
properly supported.
Page 31 of 32
METHOD STATEMENT
GENERAL PROJECT SCAFFOLDING WORKS
iii) For exposed work at heights, scaffolders shall wear safety harnesses
and whenever practicable,
attach safety lanyards to a secure anchor point on an adjacent
structure.