Crashing Exercises Solution PDF
Crashing Exercises Solution PDF
Exercise 1, Part A.
You are given the following data about the project tasks, network, and crash times/costs. Cal-
culate the cost of the project at all time durations until you can no longer crash the project any
further.
Direct costs
Normal Crash Maximum
ID Time Cost Time Cost Slope Crash Time
Page 1 of 11
Exercise 1, Part B: Initial Network
Calculate the critical path(s) and the direct costs of this project:
Exercise 1, Part C.
If possible, calculate the critical path(s), and the additional costs of crashing this project by
another 1 day:
Normal Duration Direct Costs: $9700 Additional Costs of Crashing: $100 (A)
Page 2 of 11
If possible, calculate the critical path(s), and the additional costs of crashing this project by
another 1 day:
Normal Duration Direct Costs: $9700 Additional Costs of Crashing: $100 (A)+ $400 (E)
If possible, calculate the critical path(s), and the additional costs of crashing this project by
another 1 day:
Normal Duration Direct Costs: $9700 Additional Costs of Crashing: $100 (A)+ $400 (E) +
$600 (C)
Total Cost at this time period: $10,800
Page 3 of 11
If possible, calculate the critical path(s), and the additional costs of crashing this project by
another 1 day:
Normal Duration Direct Costs: $9700 Additional Costs of Crashing: $100 (A)+ $400 (E) +
$600 (C) + $600 (C)
Total Cost at this time period: $11,400
If possible, calculate the critical path(s), and the additional costs of crashing this project by
another 1 day:
Normal Duration Direct Costs: $9700 Additional Costs of Crashing: $100 (A)+ $400 (E) +
$600 (C) + $600 (C) + 1500 (F)
Total Cost at this time period: $12,900
Page 4 of 11
If possible, calculate the critical path(s), and the additional costs of crashing this project by
another 1 day::
Normal Duration Direct Costs: $9700 Additional Costs of Crashing: $100(A)+ $400(E) +
$600(C) + $600(C) + 1500(F) + 1500(F)
Total Cost at this time period: $14400
Exercise 1, Part D.
Tally the Direct Costs that you calculated at Each Duration in the table below. Calculate the in-
centive that you would have to complete the project at the various time periods.
Initial -1 -2 -3 -4 -5 -6 -7
Dur
Project Duration 38 37 36 35 34 33 32 NA
Total Direct Costs $9,700 $9,800 $10,200 $10,800 $11,400 $12,900 $14,400 NA
TOTAL PROJECT
$9,700 $9,300 $9,200 $9,300 $9,400 $10,400 $11,400 NA
COSTS
Page 5 of 11
Exercise 2, Part A.
You are given the following data about the project tasks, network, and crash times/costs. Cal-
culate the cost of the project at all time durations until you can no longer crash the project any
further.
Direct costs
Normal Crash Maximum
ID Time Cost Time Cost Slope Crash Time
A 10 $5000 10 $5000 $0 0
B 12 $1200 11 $1300 $100 1
C 11 $3600 9 $4800 $600 2
D 5 $300 4 $600 $300 1
E 8 $1000 6 $2000 $500 2
F 9 $2400 7 $5400 $1500 2
G 8 $700 7 $1000 $300 1
$14200
Page 6 of 11
Exercise 2, Part B: Initial Network
Calculate the critical path(s) and the direct costs of this project:
Exercise 2, Part C.
If possible, calculate the critical path(s) and the costs of crashing this project by 1 day:
Page 7 of 11
If possible, calculate the critical path(s) and the costs of crashing this project by 1 day:
Normal Duration Direct Costs: $14,200 Additional Costs of Crashing: $100(B) + $300 (G)
If possible, calculate the critical path(s) and the costs of crashing this project by 1 day:
Normal Duration Direct Costs: $14,200 Additional Costs of Crashing: $100(B) + $300(G) +
$600(C)
Page 8 of 11
If possible, calculate the critical path(s) and the costs of crashing this project by 1 day:
Normal Duration Direct Costs: $14,200 Additional Costs of Crashing: $100(B) + $300(G) +
$600(C) + $600(C)
If possible, calculate the critical path(s) and the costs of crashing this project by 1 day:
Normal Duration Direct Costs: $14,200 Additional Costs of Crashing: $100(B) + $300(G) +
$600(C) + $600(C) + $1500 (F)
Page 9 of 11
If possible, calculate the critical path(s) and the costs of crashing this project by 1 day:
Normal Duration Direct Costs: $14,200 Additional Costs of Crashing: $100(B) + $300(G) +
$600(C) + $600(C) + $1500(F) + $1500(F) +$500(E)
Page 10 of 11
Exercise 2, Part D.
Tally the Direct Costs that you calculated at Each Duration in the table below. You are given
the direct costs at each time period Calculate total project costs.
Initial -1 -2 -3 -4 -5 -6 -7
Dur
Project Duration 40 39 38 37 36 35 34 33
Total Direct Costs $14,200 $14,300 $14,600 $15,200 $15,800 $17,300 $19,300 NA
Page 11 of 11