Short Interval Control Template PDF

This document provides a template for short interval control to improve productivity over time. It includes sections to 1) look back at the last interval and identify the top 3 losses and potential countermeasures, 2) look forward to the next interval and identify upcoming events that could impact productivity, and 3) prioritize specific actions for the next interval assigned to individuals to either fix, stabilize, prepare for, or generally improve issues.

Uploaded by

senzo scholar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views

Short Interval Control Template PDF

This document provides a template for short interval control to improve productivity over time. It includes sections to 1) look back at the last interval and identify the top 3 losses and potential countermeasures, 2) look forward to the next interval and identify upcoming events that could impact productivity, and 3) prioritize specific actions for the next interval assigned to individuals to either fix, stabilize, prepare for, or generally improve issues.

Uploaded by

senzo scholar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

SHORT INTERVAL CONTROL TEMPLATE Line: Crew: Date: Time:

1 Look Back Top Losses Time Impact Potential Countermeasures Esc.


Look back at the last interval and list the TL1
three Top Losses.
Record the Time Impact (lost productive
time) for each loss.
TL2
Identify Potential Countermeasures to
fix or stabilize each loss.
If a countermeasure cant be completed
with existing plant-floor resources, mark TL3
it for Escalation.

2 Look Forward Upcoming Events Time Impact Potential Countermeasures


Look ahead to the next interval and UE1
identify Upcoming Events that may
adversely affect production.
Look for events such as:
Changeovers UE2
Shift handovers
Material changes
Record the estimated Time Impact
(estimated lost productive time). UE3
Identify Potential Countermeasures
(typically preparations) to reduce the
time impact.

3 Prioritize Specific Actions for Next Interval Fix Stabilize Prepare Improve Person
Select Specific Actions for Next
Interval. These are typically actions from
the most promising countermeasures.
Relate each action to a Loss or Event using
the small box (e.g., TL1). Or, an action may
be a more general improvement.
Mark whether the action will:
Fix
Stabilize
Prepare
Improve
Assign responsibility for the action to a
specific Person.