Electrical Works 35 Report

This document provides reports on the progress of various electrical works for the Arar Airport Development Project, including medium voltage cable installation, low voltage cable and duct installation, manhole installation, earthing systems, and lightning protection systems. It shows the percentage of work completed for excavation, material delivery, installation, testing and connection, backfilling, and total work done for each aspect of the project. Overall, installation works have progressed to 65-90% completion across cable, duct, and manhole works, while earthing and lightning protection systems are only 10% complete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
233 views6 pages

Electrical Works 35 Report

This document provides reports on the progress of various electrical works for the Arar Airport Development Project, including medium voltage cable installation, low voltage cable and duct installation, manhole installation, earthing systems, and lightning protection systems. It shows the percentage of work completed for excavation, material delivery, installation, testing and connection, backfilling, and total work done for each aspect of the project. Overall, installation works have progressed to 65-90% completion across cable, duct, and manhole works, while earthing and lightning protection systems are only 10% complete.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 6

ARAR AIRPORT DEVELOPMENT PROJECT

Ref No. : 113- EL. 01-12-2016 ELECTRICAL SECTION


Meduim Voltage Network Report
Cable
Total Installed Cable Excavation Deliveried Cable(30%)
Installed test& connection Backfilling Total Work Done
CABLE SIZE in mm2 in L.M (20%) (10%) (15%) 100%
( 25%)
300 6050 20% 25% 30% 0% 15% 90%

Low Voltage Network( Armoud cable direct buried in ground) Report


Cable
Total Installed Cable Excavation Deliveried Cable(30%)
Installed test& connection Backfilling Total Work Done
CABLE SIZE in mm2 in L.M (20%) (10%) (15%) 100%
( 25%)
MTB (15.3.10) 300 mm2 1900 20% 25% 30% 0% 15% 90%
CFR (15.3.1.8) 300 mm2 1250 20% 25% 30% 0% 15% 90%
ADM (15.03.6) 70 mm2 100 20% 25% 30% 0% 15% 90%
ADM (15.03.7) 300 mm2 100 20% 25% 30% 0% 15% 90%

Low Voltage Network Report

Total Installed Duct Excavation Warning tabe Backfilling Total Work Done
Duct bank Duct Bank Installed (65%)
Bank In L.M (15%) (5%) (15%) 100%

Duct bank (2x2), 4'' UPVC 780 15% 65% 0% 0% 80%


conduit
Duct bank (2x3), 6'' UPVC 0 0% 0% 0% 0% 0%
conduit
Duct bank (6x3), 6'' UPVC 0 0% 0% 0% 0% 0%
conduit
Duct bank (3x3), 6'' UPVC 0 0% 0% 0% 0% 0%
conduit
Duct bank (4x3), 6'' UPVC 0 0% 0% 0% 0% 0%
conduit

Low Voltage Manholes Report


Manholes Manholes
Total Installed Excavation Deliveried Manholes Backfilling Total Work Done
Manholes Types cover
Manholes In Qty (15%) Installed (25%) (15%) 100%
( 25%) (20%)
(I)Man hole class MH1 9 15% 25% 22% 0% 0% 62%
(L)Man hole class MH2 12 15% 25% 13% 0% 0% 53%
(T)Man hole class MH3 2 15% 25% 12% 0% 0% 52%

Low Current Network Report


Total Installed Duct Excavation Warning tabe Backfilling Total Work Done
Duct bank Duct Bank Installed (65%)
Bank In L.M (15%) (5%) (15%) 100%
Duct bank (2x3), 4'' UPVC 1850 15% 65% 0% 0% 80%
conduit

Low Current Manholes Report


Manholes Manholes
Total Installed Excavation Deliveried Manholes Backfilling Total Work Done
Manholes Types cover
Manholes In Qty (15%) Installed (25%) (15%) 100%
( 25%) (20%)
(I)Man hole class MH1 40 15% 25% 18% 5% 0% 63%
(L)Man hole class MH2 13 15% 25% 11% 5% 0% 56%
(T)Man hole class MH3 13 15% 25% 11% 5% 0% 56%

Earthing (power&communication) system


Materials
Deliveried test&
Excavation Ancillary works Backfilling Total Work Done
Building LUMPSUM (30%) connection
(15%) (20%) (15%) 100%
(20%)
Power Earthing (1) 5% 0% 0% 5% 0% 10%
MTB
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
ADM
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
CFR
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
CRB
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
MES
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
TS1
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
TS2
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 5% 0% 0% 5% 0% 10%
IRR
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%
Power Earthing (1) 0% 0% 0% 0% 0% 0%
GTB
Comm. Eaething(1) 0% 0% 0% 0% 0% 0%

Lightning Protection System


Connect
Materials Materials Ancillary works test& connection with Total Work Done
Building LUMPSUM Deliveried Installed (20%) (20%) earthing 100%
(30%) (25%) sys.(5%)
MTB 1 0% 0% 0% 0% 0% 0%
ADM 1 5% 0% 0% 0% 5% 10%
CFR 1 5% 0% 0% 0% 5% 10%
CRB 1 5% 0% 0% 0% 5% 10%
MES 1 5% 0% 0% 0% 5% 10%
TS1 1 5% 0% 0% 0% 5% 10%
TS2 1 5% 0% 0% 0% 5% 10%
1RR 1 5% 0% 0% 0% 5% 10%
GTB 1 0% 0% 0% 0% 0% 0%

Lighting Outlets
Materials Materials test&
Total Outlet
Building Deliveried Installed connection Total Work Done 100%
Installed (40%) (30%) (30%)
E & T Rooms 36 30% 20% 0% 50%
4+8+32+17+
CFR(15.4.1- +23+9+93+26+24+6
1,2,3,4,5,6,7,8,9,10,12,15,1 +1+2+27+14+79+29 35% 25% 0% 60%
8,19,20,21,22,23,25) +25+32+31=464
TS1(15.4.1-1,2,3,4,5) 8+19+20+6+1=54 35% 25% 0% 60%
ADM (15-4-1- 9+52+19+3+30+6+ 30% 20% 0% 50%
1,4,5,6,11,13,14) 50=169
CRB(15-4-1- 42+46+4+8+2+1+10
1,2,3,4,5,6,7,8,9,10,11,12,1 +10+4+3+4+3+7= 30% 20% 0% 50%
5) 123

MES( 15-4-1-
3,4,5,6,7,8,9,10,11,12,13, 22+45+24+2+7+7+3 30% 20% 0% 50%
+3+3+3+28+3=100
15)

Lighting Switch Outlets


Materials Materials test&
Total Outlet
Building Deliveried Installed connection Total Work Done 100%
Installed (40%) (30%) (30%)
E & T Rooms 2 20% 20% 0% 40%
CFR(15.4.2.1,2,3,4) 25+5+2+8=40 20% 20% 0% 40%
TS1 9 30% 25% 0% 55%
ADM (15-4-2-1,2,3,4) 25+3+2+5=35 20% 20% 0% 40%
CRB(15-4-2-1,3,4,5,6,7,8) 3+4+4+2+1+1+2=17 20% 20% 0% 40%
MES(15-4-2-1,2,3,4,5,7) 5+2+3+1+1+2=14 15% 15% 0% 30%
Socket Outlets
Materials Materials test&
Total Outlet
Building Deliveried Installed connection Total Work Done 100%
Installed (40%) (30%) (30%)
E & T Rooms 49 10% 10% 0% 20%
CFR 25 10% 10% 0% 20%

32 Outler for
single phase duplex 20% 15% 0% 35%
socket 16 A.
TS1
3 Outler for three
phase socket 16 A. 10% 10% 0% 20%
(Weather Proof)

Switch Disconnectors (Isolators) Outlets


Materials Materials test&
Total Outlet
Building Deliveried Installed connection Total Work Done 100%
Installed (40%) (30%) (30%)
E & T Rooms 8 10% 10% 0% 20%
CFR 8 5% 5% 0% 10%

2 Outlet for 220 V,


20 A, disconnect 10% 10% 0% 20%
switch

4 Outlet for 380 V,


32 A, disconnect 20% 10% 0% 30%
TS1 switch
TS1

3 Outlet for 380 V, 20% 10% 0% 30%


32 A, disconnect
switch (explosion
Proof)
ADM (15-4-4-1) 10 5% 5% 0% 10%

Road Lighting Poles


Excavation Materials test&
Type Total Install (Num) &Backfilling( Foundation Materials Total Work Done
Deliveried connection
(Electrical Network) (15%) Installed (30%) (15%) 100%
10%) (30%)
LP1 (07-07-01) 100 8% 15% 15% 5% 0% 43%
LP2 (07-07-02) 12 5% 5%