Fencing Method Statement
Fencing Method Statement
PREPARATION BY:
Action Name Signature Role Company Date
Originator
Checked
Reviewed
Approved
B
C
2 Personnel
Project Manager shall be responsible for ensuring that the works comply with quality, HSE, and
other relevant project requirements
Project Engineer responsible for supervising the general installation work and liaises with relevant
authorities when required. Directly responsible for ensuring that the works are executed as per
project and authorities specifications.
Safety Officer- Monitors on-site safety issues, site safety induction, implement and ensure the
safety procedures at site.
Skilled Labour Performs installation/construction of all works in accordance with approved shop
drawings, specifications, standards, Method Statements with quality workmanship
Labour responsible for performing minor manual tasks
The machines and equipment will be deployed as required and necessary to meet the project
requirements and schedule.
4 Site Procedures
All necessary approval must be obtained from concern office before starting any construction
activities.
5 Sequence of Works
A. Fence Line Layout
B. Civil Works including Post and Bracing
C. Installation Fabric
The site of the fence shall be sufficiently cleared of obstructions, and surface irregularities
shall be graded so that the fence will confirm to the general contour of the ground. The fence
line shall be cleared on each side of the fence centreline. This clearing shall consist of rocks
or other obstructions that will interfere with proper construction of fence. Locate and marked
the fence alignment and elevation including the exact position of the fence post in accordance
with the details on the approved drawing plans.
Prior to excavation use detection device to pinpoint existing underground utilities in the area.
Excavate the location of the fence post for concrete foundation and the alignment of the fence
for the concrete terrain anchorage, refer to Appendix B for the detailed drawing plan for
dimensions and sizes of the concrete foundation and concrete terrain anchorage. All
excavation shall be carried out under strict supervision. Once the excavation activity is
completed the Engineer will inspect and approved the dimension of the excavated area as per
approved drawing plan. All excavated area shall be barricaded to prevent any person from
falling into the site.
The fence pipe post shall be set plumb, true to line and grade in the excavated trench and
shall have necessary support to fix the pipe post in place. Concrete will be poured in the
excavated trench for post footing, the post shall be stabilized until the concrete has cured, and
concrete terrain anchorage along the alignment of the fence. Distance of post shall according
to the approved drawing plans. Concrete works shall be in accordance with BS 1722 and shall
comply with provision of Section 5 Concrete of QCS 2014.
Attach winding bracket to the fence post on the level where the top and bottom rail will be
installed. Install the horizontal pipe for top and bottom, truss rod including the necessary
attachments to stabilize the fencing frames. Visually check and verify the height of the post
and other member after the framing members have been installed as per approved drawing.
a) Roll out chain link and stretched in one continuous length from one post to another post.
b) At the end of the chain link with the same length as the post spacing unbend the end of
the weave straight, do the same at the adjacent side until the chain link with desired length
is separated.
c) At the top of the fence or the bottom, spin the weave in counter clock wise direction as if
to unscrew it from the roll. Continue spinning and you will see the other end unweaving
from its adjacent weaves. Also check that it have bent the far end straight or it will snag
as it will be twisted.
d) After rolling out the chain link hook up one end near of the other post then stretch the
chain link to the opposite side of the post. Pull the chain link by hand or by stretching tools.
e) Pull as much stack out as possible before hooking up the chain link in the opposite post.
The fabric is stretched sufficiently when the diamond cannot be squeeze with one hand.
Do not overstretched or post will be damage. The top of the fence should snap back to
the post when pulled out a little.
Necessary safety plan, precautions and procedures shall be implemented prior to and during
execution of installation, which includes the following:
1. All personnel must attend project HSE induction prior to start works on site. (No Induction No
work on project site)
2. All staff and workers will wear mandatory PPE i.e. hard hat, safety boots, safety glasses, gloves
and vest.
3. All tools, Equipment must be in good condition and inspected on daily bases before the start
of any activity.
4. Follow site safety rules and regulation.
5. Necessary signs shall be provided.
6. Supervisors should give instruction and exercise supervision to ensure that workers follow
these plans and systems of work.
7. Keep site area clean and clear of obstacles.
8. Waste will be removed off site on regular basis.
8 Quality Assurance
The works shall be managed from start to completion to meet the project requirements and
specifications, project programme of works and project budget as per the quality management
documentations.
Management shall include the supply of all resources necessary for completion, monitoring of the
works as per the project program, and carrying out the works that meets the company and contract
quality requirement.
Monitoring shall be done on a daily basis and a regular progress meeting shall be implemented to
closely identify the status of each part of the works.
In carrying out the works, the management shall ensure progress to be delivered on time against
project program.
Public Provide the appropriate fencing and/or barricades as per site risk assessment.
Injury to public General site Apply appropriate signage and pedestrian control.
1
Unsecured site
General site workers
Vehicular accidents
workers
Site Visitors
3 3
09 Regular inspection of site barricades and signage to replace worn out or
damaged safety facilities.
PM 3 1
03
General site staff Security arrangements
General site
Conduct site inspection to ensure access/egress is adequate for the task
workers
2 Inadequate site access
Slips, trips and falls, abrasions,
strains and sprains. General site staff
Site Visitors
5 3
15 activities.
Maintain Safe Access & Aggress
PM 5 1
05
Traffic management shall be prepared
A site logistics plan shall be prepared. This shall detail the site boundary,
pedestrian and vehicle access and site roads
General site
workers Barriers shall be installed to separate pedestrians from vehicle traffic.
Failure to designate
Pedestrian routes shall be clearly marked and illuminated where necessary.
and separate external General site
Traffic accident fatality / damage /
3 traffic / pedestrian
routes
lost production
staff
Site visitors
5 3
15 Signage should be in a language understood by the majority of the labor
Traffic management signage and lighting shall be installed as necessary
Traffic management arrangements for labor drop off / collection shall be
PM 5 1
05
Neighbours
implemented. Labor shall not be put at risk from moving vehicles and machinery
General public
Traffic Marshalls or Flag men shall control heavy traffic routes and crossing
points. Flag men shall be suitably trained
Repetitive movements, When heavy or awkward items are being worked on or moved, mechanical
such as stooping, handling equipment or assistance should be provided..
twisting the trunk, Back Injury General site Avoid repetitive handling of loads.
stretching, twisting the
Other injuries Arrange the distribution of the work force in team lifting
12 wrist or neck, etc.
Property damage
Workers
General site
staff
3 3
09 Store heavier or frequently used items at a position where they can be easily
accessed. e.g. Store room, site offices.
PM 3 1
03
Inadequate grip on
heavy, awkward, hot, Use correct posture to lift or lower loads.
sharp or slippery Training shall be provided to all the work force
objects