Reporting Quarterly Physical Progress of Works in 2017

This document summarizes the quarterly physical progress of works in 2017 for the Greater Dambulla Water Supply Project. It shows the planned and completed actions and work percentages for intake, water treatment plant, reservoirs, transmission system, and distribution system for each quarter. The overall completion percentage increased each quarter, reaching 90.5% by the fourth quarter.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views

Reporting Quarterly Physical Progress of Works in 2017

This document summarizes the quarterly physical progress of works in 2017 for the Greater Dambulla Water Supply Project. It shows the planned and completed actions and work percentages for intake, water treatment plant, reservoirs, transmission system, and distribution system for each quarter. The overall completion percentage increased each quarter, reaching 90.5% by the fourth quarter.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

REPORTING QUARTERLY PHYSICAL PROGRESS OF WORKS IN 2017

Ministry: Ministry of City Planning and Water Supply Accounting Head:


Department: National Water Supply and Drainage Board Accounting Head:
Programme No:
Project No:

Vote Name of the Q1 Q1 Q2 Q2 Q3 Q3 Q4 Q4


particulars Project Action planned Work Action planned Work Action planned Work Action planned Work
done done done done

% %

Intake-Partial Commissioning 89.90% Commissioning 95.60% Commissioning 95.70%


Greater Dambulla
Water Supply Water Treatment Plant-Partial Commissioning 86.80% Commissioning 92.20% Commissioning 92.60%
Project 81.20% 82.70%
Reservoirs-Partial Commissioning Commissioning Commissioning 87.40%
Transmission System-90% Completion 74.80% 100% Completion 80.80% 100% Completion 84.90%
Distribution System-80% Completion 65.20% 100% Completion 70.80% 100% Completion 75.70%
Overall 100% Completion 88.60% 100% Completion 90.50%