Pipeline ROU
Pipeline ROU
VERLA
Rohrleitungssysteme
Piping Systems
International
Piping Engineering
R
Rohrleitungsbau
Rohrleitungsbau
Journall for
f r Piping,
P , Engineering,
E , Practice
P
Pipes
Special Steel Pipelines Technology
project comprise more than 11,000 Economical and social goals are 1,760 km (1,091 miles), is divided into
pages. • combustion emissions 445 km in Azerbaijan, 245 km in Georgia
All persons concerned have their own and 1,070 km in Turkey. Crossings in the
• no loading or offloading emissions pipeline path concern
ideas and regulations; to take them all
into account or to find compensation, • zero discharge of oil or chemicals to • rivers, canals and other inshore
often on a monetary base, is an land or surface waters waters
important step in the direction of • maximising efficiency of net energy • public roads and pathways
achieving the permission and exported
approvability of such a project. • railway tracks
• minimizing project footprint (including
At this stage of the project, it is already Right of way (ROW),temporary • underground lines of all kind
possible to minimise many technical and facilities and access roads) • special geological features (like active
economical risks by applying trenchless • no net damage to protected faults etc.)
technologies. Some examples for this ecological areas or archaeological As a result, Azerbaijan has 350, Georgia
are: sites 250 and Turkey 300 crossings beneath
• utilising the HDD technology for railways and roads, river crossings are
• no creation of access routes to
crossing sections of the bore path Azerbaijan 30, Georgia 200 and Turkey
otherwise inaccessible areas
which includes the risk of landslides to approx. 600. Of course this includes all
avoid destabilisation, which is to be • restoration of habitat and hydrological
inshore waters, from the rivulet to the
expected with the open cut method regimes
dried out wadi to the mountain stream in
• undergoing inaccessible path sections • no loss of containment of product flood.
with long distance installation, this • no resettlement of local population In most cases, namely in less sensitive
saves elaborate structural measures areas of minor importance, these
• no permanent disruption to the
for establishing access roads crossings are done with the open trench
livelihood of the local population
• crossing natural areas worth method. Figures from the BTC section in
Concrete effects of these principles can
protecting with the help of Azerbaijan clarify the relations between
be seen in the fact that an examination of
underground construction methods in open and trenchless installation: besides
the flora and fauna, above and below the
greater depths: time and money seven HDD- crossings, this section with
crossing area of the river, is carried out
consuming discussions with pressure 445 km in length requires the
before river crossings are established,
groups are avoided, the protection of performance of 21 auger borings. Here,
and the effects of construction and
nature can truly and constantly be the pipeline is installed inside the built-in
operation of the pipeline is drawn up in
guaranteed protection pipe, in order to avoid damage
an evaluated scale. The decision, in
• In an actual case, the utilisation of to roads and railway tracks and to
which way the pipeline installation and
private property and the payment of disturb sensitive river regions and natural
other measures taken during
compensation could be avoided by areas as little as possible.
construction and operation shall
applying the HDD method. commence, is based on these results. Definitely different relations can be seen
• The installation of a line with the HDD The crossing types and the manner of in the example of the 354 km long
technique in great depths helps to construction, for example, are defined in product pipeline from Stade to the DOW
avoid a limitation of the utilisation, this way. Chemical location in Teutschenthal. For
which would be the natural result of an this steel pipe, dimensions 273x5.6/8.8
open trench installation with the usual 2.3 Reflections on the trenchless part mm, with PE coating, 113 pressings, 9
cover of only a few metres. In pipeline construction, the installation protection steelpipe pressings and 203
of lines in populated areas is generally steered HDD drills were carried out, 24 of
All these points show clearly that it is
done underground, still mainly applying them were larger crossings of rivers and
possible to defuse environmentally
open trench methods. The trenchless, navigation canals.
relevant demands and other constraints
at an early stage with the trenchless closed installation part of the complete When the Alliance Gas Pipeline in North
installation method and to guarantee the bore path length may not be relevant, but America (length 1,900 miles, 36-inch in
feasability and viability of a project. it is of great importance to realise that diameter) was installed the relations were
many projects – particularly those with as follows: more than half of the road
2.2 Conceptional and aspects large crossings of any kind – could not be crossings were executed in the road bore
environmental carried out without the trenchless technique. 13 large river crossings had to
method at all. A dense settlement and be overcome additionally, the HDD
“Throughout the pipelines planning
valuable surfaces are disturbed in very crossing of the Peace Rivers, with 3,600
process we have worked to minimise
few places alone, emissions are reduced foot (1039 metres), being the most
negative impacts on the environment and
society”. This sentence in a BTC or occur only on a small scale and small challenging of them all; ramming and
document already marks the limitations of use are avoided. HDD technique were combined for this.
responsibility of all parties concerned at The following recent examples may back Microtunnelling machines were also used
the stage of conception. The basic up these statements. But even the for the project.
course for installation and operation of population in apparently unproblematic When comparing the Trans Alaska
the pipeline is already set at this stage, regions shows increasing sensitivity Pipeline System (TAPS) to the Sakhalin II
and this course suggests the trenchless towards the effects of above-ground Pipeline, we also get insight into
method for line installation. construction methods – as is made interesting figures. Both lines run through
Therefore, a few of the maximes shall be transparent by the ESIA transaction inhospitable arctic regions, but their
drawn up, following the plan and concerning the BTC pipeline. This modes of construction vary.
construction of the BTC pipeline and the development almost forces us to apply The TAPS is an oil pipeline, 1200 mm in
SCP following the same path some time the underground installation techniques. diameter, pressure 70 bar and 1,280 km
later on. The BTC pipeline, with its total length of long; 673 km of these run above the
ground, 602 km are built conventionally strain on the environment – the example 3.1.1 Open Crossings
underground, 6 km are equipped with of the Kamchatka Pipeline has already The crossings of roads, rivers, brooks
special freeze-protection devices. More shown this. and railway tracks is often performed
than 900 rivers and brooks, 70 of them Therefore HDD was applied for the river using the open trench method. Usually
significant, were crossed by 13 pipeline crossings, crossings in open trenches unpaved gravel roads are concerned,
bridges or open trenches of 2.3 to 4.8 were only allowed in the winter months, which are closed and crossed with the
metres, almost 15 metres deep in the when the soil was deeply frozen. open trench.
most extreme case. No HDD crossings
Tacking stock we can say that the HDD Minor roads and railway tracks are
were performed. At the beginning of the
technique, as it is today, is effective and crossed by working one half of the way
seventies this technique seemed
economical in its application, even in while maintaining the other half for the
unsuitable for such an extreme plan;
extreme conditions. traffic.
also, large rocky boulders obstruct the
area of the bore path. Dry open-cut crossings of small rivers or
Recent experience in the U.S. Arctic 3 Techniques Installation irrigation canals is carried by means of a
(ARCO Colville River Crossing) has only 3.1 Open trench construction by-pass of the water course into pipes;
now proved the technology in Permafrost otherwise, the flowing water is simply
Naturally, the open trench construction
conditions. This project was executed in crossed with an open trench. Decisive
takes the lion’s share of the total length.
1997/1998 and took seasons rather than factors are the amount of water, function
Figure 6 shows the typical situation.
the single season planned. The analysis of the water course, effects of the
Before the beginning of work, the future
of the crossing type (Bridge, trench, measure on the crossing and
path is determined and staked out. After
HDD) used similar methodology as used downstream area as well as the
this, the working area is cleared, which
by Sakhalin Energy. HDD was chosen as expenditure required for restoring the
means, the removal of any trees and
being least expensive (at the time, based bushes standing within this area which riverside and slope area.
on a single season construction. includes the ‘right of way’ area (ROW). Therefore, every crossing demands
The Sakhalin II Pipeline consists of an oil In the case of the BTC, the working thorough investigations to find out how
and a gas pipeline, 500 mm in diameter space is 32 meters because the SCP will to avoid too much disturbance for
each, 600 and 1200 mm in some parts, follow at a later date, but in the same residents and the environment, how to
100 bar operation pressure and a total corridor a further expansion of merely 12 carry out the measures as quickly as
length of 807 km. More than 1100 water m of the ‚right of way’ zone is necessary. possible and how to restore the
courses of all kinds, 63 of them Here, the principle of using the already disturbed surfaces to their original state
particularly sensitive, had to be crossed. existing corridor to protect humans and in the best possible way.
Pipeline bridges were not built, instead, nature alike, is also applied. This kind of application naturally has a
there were 8 HDD crossings with covers The next step is to excavate a trench, strong effect on all persons concerned
of up to 10 metres, the others were approx. 2.5 m deep, in which the already and the surroundings of the civil works.
mainly achieved using the open cut welded pipe string is lowered later on. Even under normal conditions elaborate
method. Approx. 15 km of open trench are always job site logistics for the parallel-running
No part of the line was installed above prepared at this stage. The trench should processes of excavation, installation,
the ground, as Permafrost is not a be backfilled with the same material, back-filling and restoring works as well
problem there, and the Russian especially the cover layer should be the as the required cross and longitudinal
understanding of security and nature same as before. Then the surface is transports in the area of the job site are
protection is contrary to open lines: landscaped and restored. indispensable. Heat, dust and, most of
Technical failure, or even sabotage, can In the way the building activities and all, precipitation aggravate the access to
lead to great damage and permanent regional transactions of this BTC pipeline the job site and turn work in deep terrain
interference, if oil emerges from the line. project should be organised, the building into a strain for man and equipment
The TSUREN (Russian Federal site claims no more than a length of 60 Appointed time schedules set everyone
Regulators) have also experienced, that km during the complete time. The under pressure, making additional
installations above the ground are building activities should last for 6 to 8 measures inevitable in order to ensure
subject to massive technical weeks in each region. During this time, all the completion of the job in time. Here,
maintenance and servicing, their possible efforts to minimise noise, dust trenchless technologies - assumed the
construction has proved an immense and job site traffic should be taken. job site is accessible – are considerably
less sensitive; additional equipment of
the machine technique allows work even
under extreme conditions, i.e. larger
cooling aggregates for great heat or
heated shelters built above the unit for
cold temperatures.
Therefore, the application of trenchless
techniques can prevent many negative
effects of the open-cut construction,
reduce the costs for restoring the original
condition and save additional
mobilisation of resources for completing
the project.
disturbance of the surface, very high installation have been examined was part installed than non-cohesive soils with
daily performance and economic of the dissertation mentioned above. their loose bedding, cast iron pipes with
efficiency. Particularly in rural regions, Result of this examination: the ideal soil protruding collar connections are
where often the distances are long, free for applying the plough technique is well therefore hardly suitable for loose, sandy
of obstacles and the geology is compactable and sufficiently stable. soils.
consistent, this method is unbeatable. Only slight lifting of the soil on the terrain
When applied under water, the plough is surface occurs , the required total pulling 3.2.2 Special Plough – mode of
pulled across the sea bed by ship, force is low and stress during installation operation
opening a trench in which the pipe is laid is not severe. Route sections containing Supported by the cable-pulled special
and then backfilled again. boulders, fractured rocks or stones are plough, the pipeline is laid directly into
The conventional pipe and cable plough unsuitable for this method. Soils of this the void created by the displacement
creates a V-shaped trench for installing kind can neither be displaced nor process, which is the advantage of this
the pipe, back-fill is performed in the compacted. Depending on the bedding, method. Here, we must differ between
next working step. Ploughs – made in unfavourable loads may occur, the static or dynamic plough method
USA - with a pulling force of 330 tons, influencing the functioning order or the with installation box – the line is lead
depths up to 6.5 ft can be achieved in service life of the pipe in a bad way. overhead to the plough share – and the
one single working step. The dimensions The investigation also proved, that the plough towing method. Plough towing
of this kind of plough: length 75 ft x width load on the cables and pipes is means that the line is inserted in the
40 ft; pipes up to 45 inches in diameter minimised in comparison to conventional starting pit and – as the word already
can be installed. suggests – is towed underground into the
building methods, because the soil is
Similar dimensions - approximately 70 only slightly disturbed. The application already created plough track.
feet wide, 70 feet long and 30 feet high – range comprises non-cohesive and Simply one little starting pit for setting
are the specifications of a marine cohesive soils. Depending on the and aligning the plough is required. The
pipeline plough, which was used for the consistency or ground compactness, the plough blade can be precisely adjusted
installation of a 24 inch pipeline with a ability to be displaced has an effect on in its height by hydraulics, allowing
total length of 35 miles in the Eastchester the pulling force during installation. The progressive adaptation of the ploughing
Extension Project. friction-reducing effects (which also depth to the current needs down to 2.0
These plough methods require rather reduce the power requirements) of a m. The towing winch with its pulling force
large working space to the sides, which Bentonite lubrication can also be of up to 140 t and a cable length of 130
require a lot of finishing work. The favourable for the installation procedure. m is mounted to an off-road vehicle and
company Georg Föckersperger GmbH, Cohesive soils with a soft consistency braces itself automatically when reaching
Aurachtal, has developed a basically new take longer to settle on the pipe being the target.
installation and pipe laying technique in
Germany 30 years ago and is improving
the method since then (Figure 7). Up to
now more than 50,000 km of pipeline,
including steel pipe s up to 350 mm OD
and casting lines up to ND 250, have
been installed.
A dissertation from the year 2003
determined the loads occurring during
installation and converted them into a
mathematical formula. Accordingly,
pipelines can be laid in a way that
eliminates damage to the pipe and near-
by lines, allowing great single lengths to
be pulled in. Fig. 8:
Rocket plow
3.2.1 Special Plough – soil conditions application in the
mud flats (Source:
The soil-mechanical processes affecting Föckersperger
cohesive and non-cohesive soils during GmbH)
Plough and plough blade are mounted to occur along the pipeline course, but also cutting head itself, to excavate the path
a rig with special tyres which can be when sensitive natural habitats need for the protection pipe.
adjusted in height and track width by crossing and damage has to be avoided. In reference to the size of drillable
means of hydraulics, therefore, The choice of the right method depends obstacles, the pipe diameter itself should
application is no problem even in mainly on pipe diameter, length of the be either small enough to bore through
inaccessible terrains or when crossing bore, geology and geo-technical without upsetting the position, or large
shallow offshore waters. In 2003, the conditions. The dimensions, depth, enough to recover these obstacles. The
most spectacular application took place excavating and set-up of the start and protection pipes have lengths of 6 – 12
across the north German mud-flats, target pits, the size (dimensions) of the metres and are welded together
when a 5 km long water line to the small required working space as well as the successively. You have to make sure of
island Nordstrandischmoor was measures for ground water drainage the roundness and a smooth surface of
ploughed in (Figure 8). differ from one method to the other. the pipe in order to keep the friction
Lines with small diameters are also The composition and structure of the down.
installed, even in bundles, with track ground in the geo-technical sense is the An overcut or the application of pipe
warning tape and a daily performance of decisive factor for the completion of any lubrication can reduce the pipe friction
up to 2000 – 3000 metres. The so-called drilling job, a fact, which has to be caused by forward thrust. In extreme
rocket plough is available for larger acknowledged by carrying out a cases, the friction forces and the jacking
pipelines, steel lines up to OD 350 and sufficient survey beforehand. forces may lead to deformation of the
cast iron pipelines up to ND 250 have
pipe and stop the forward thrust.
been ploughed in until this day. In 2003, a 3.3.1 Auger Boring
special ATV-DVWK-M139 leaflet was In the starting pit, the thrust pipe is
published, which documents all his bore technique uses a protection aligned exactly to the target and runs
application ranges, requirements and pipe which is pressed forward, while an relatively stable in its direction, if no outer
quality assurance. auger removes the spoil at the same forces affect the steel pipe. Any
time. This method can be used for occurring intercalations or hard layers
The plough method is particularly
almost any soil type. However, it is lying diagonally to the thrust direction
suitable for rural areas with a low
necessary to observe the stability of the can divert the installation from the
population density, great pipeline lengths
soil structure. Non-cohesive soils and desired direction. The installation takes
with only a few connections
larger stones cause problems; the first the course of the weakest resistance.
underground. Up to now, this method
has only been used for pressure lines. have a tendency to flowthe second must Especially sliding upward makes it hard
Crossing small shallow waters and be easily smashed to pieces to keep the to keep the direction.
installing pipes in slopes is no technical passages of the auger unblocked. A larger bore diameter may be helpful
problem due to the plough construction If the soil conditions are unstable, the because it maintains the exact position
with universally adjustable wheel auger flight must be pulled back behind of the medium pipe which is going to be
extensions. the cutting shoe in order to avoid installed, the remaining annulus is filled in
The utilisation of the plough method has breakage of the position front. Otherwise correspondingly. If the thrust pipe gets
proved its economic and eco-friendly the auger can work directly in the cutting stuck, however, over-boring in counter-
value for pipe installation below ground shoe area or even be equipped with a heading may help to complete the bore.
water level. Unpaved terrain is a pre-
condition and there should be no larger
obstacles in the track. Before the
Table 1: Soil type classification
installation can commence, the exact
position of crossing lines and the
underground conditions in the line path
must be determined.
The method is remarkably efficient, time-
saving and eco-friendly, because the
excavation of trenches is not necessary,
the track of the plough is simply
smoothed down. A very economical,
ecological, proven and versatile
technique with only minimal underground
impact is offered to the customer and
user.
Fig. 11: Slickbore application: 1. Bore pipe ramming Slickbore application: 2. Pipe pulling (Source: Tracto-Technik GmbH)
of the thrust pipes was measured. The function, they are mainly made of steel are required and the sewer pipe is the
evaluation proved that it is unnecessary concrete, stone ware, glass-fibre installation pipe at the same time. Within
to add any additional design loads or reinforced concrete, cast iron or steel. the range of large diameters, curved
precaution correction values to the Microtunnelling is the further deve- drives are possible.
calculation of the thrust pipes, the pipes lopment of conventional pipe driving to a With the suitable choice of cutting tools a
are not damaged by this method. We remotely controlled one. Originally it was wide soil spectrum can be excavated;
come to the following conclusion: under developed for the unmanned, on-target there are suitable working techniques
consideration of certain constructional driving for short distances of little more from sand and gravel to rock. Decisive
measures, this method is recom- than 100 metres, but meanwhile it results factor is the service life of the tools,
mendable for pipe installation on a large in the already mentioned diameters and which must be long enough to reach the
scale. In order to go easy on the gas distances of several hundred metres. target shaft or at least the next
pipes, a reusable impact pipe should be Typical driving lengths – without intermediate shaft. Long distance drives
placed between the product pipe and the intermediate jacking stations – are can be carried out by using intermediate
horizontal rammer. Furthermore, care between 100 and 250 metres. The jacking stations.
should be taken, not to impair lines or maximal driving lengths to be achieved Furthermore, there is little settlement
buildings in the neighbourhood by depend on the pipe type, bearable strain with this method. If handled properly, the
occuring vibrations. from the jacking propulsion forces, soil pressure at the cutting face can be build
Another variation of the ramming conditions, measures of possible friction up against standing soil and water
technique is the so-called slick boring. reduction and the thrust capacity of the pressure, the driven void is immediately
This technique utilises a horizontal main jacks. secured by the thrust pipe. Bentonite is
rammer to drive home a protection pipe. also used as a drilling fluid for this
At the beginning, the term micro-
After removing the soil, the medium pipe technique. Its task is to support the
tunnelling was used as the description of
is connected. With a winch, an excavator cutting face, lubricate the annulus
non-accessible pipe driving up to DN
or some other pulling facility, the bore between pipe and soil and transport the
800 / DN 900 in Germany; meanwhile,
pipe is pulled and then the product pipe suspension charged with the cuttings.
thanks to the further development of this
takes its place (Figure 11). technology, lines up to 4 metres in Thus characteristic project parameters
Decisive assets are the advantages of diameter can be driven with remote are the pipe diameter, driving length,
the ramming method mentioned above, control. The largest possible pipe topography, depth of the start and target
in connection with the reusability of the diameter to be transported along our shafts and the soil condition. With this
rammed pipes and the economical, streets is the upper limit of the diameter. method, even geologically difficult terrain
direct, exact and gentle installation of can be bored over long distances.
This development was made possible by
coated pipeline pipes. The job site set-up consists of the pipe
the application of highly sensitive
The pipe roofing method is another jacking equipment assembled in the
measuring instruments, the installation of
variety for crossing embankments. In this starting shaft, a container with power unit
reliable control devices and the
case, a protective roof and the contour and control container, settlement tank,
adaptation of technologies used for
recycling unit for the soil-slurry-
for the intended multi-pipe tunnel is excavating huge tunnel constructions
suspension and a pipe storage. The set-
created by pipe-to-pipe ramming. After with slurry and earth pressure balanced up can be flexibly adapted to the
the excavated soil is removed and the shields. It includes, among others, the available space on sites. The standard
site-mixed concrete vault is prepared, a exact detection of pressures, volumes, shaft is 3.20 m in diameter and can be
passage for laying several lines has been inclinations in the installation area and a used for driving pipes up to ND 800 with
created. precise control via computer-aided 2 m length; recovery of the unit makes a
regulation and control facilities. target shaft of 2.0 m in diameter
3.3.4 Microtunnelling Microtunnelling was developed for the necessary. If the jacking frame is turned
Microtunnelling is a trenchless method linear and exactly steerable course of the around, it can also be used as a two-
which is carried out as an unmanned pipe path in height and position, these sided driving shaft. Larger pipe
pipe installation with fully automatic properties are specially required within diameters require individual launch
control. The jacking pipes are also the the area of gravity lines, where often only shafts, they are built for pipe lengths up
product pipes; depending on their a smooth inclination of the open channel to 3.5 m.
Fig. 17:
Pipe ramming the building measures are involved, from
assisting pipe the highest national level down to any
pulling private association; maybe elsewhere the
(Source: Tracto- regional policy and compulsory approval
Technik GmbH) proceedings are not quite as intensive as
in Germany. Whether the project
executing organization is the government
or a company with private legal form,
may also be crucial.
compensation areas within the 5 Potentials of Trenchless surrounding nature suffer from dust,
accompanying space around the pipe Installation noise and other deragations for many
line path for inevitable impairment of the weeks? How much is an adequate
5.1 Comparative Reflections on
natural balance must be included in the compensation for frustration and
Construction Methods
plans. annoyance due to the lost quality of life?
When comparing different construction
Already existing lines in the path area are Without comparing exact figures or one
methods, the first aspect is always the
handled in a similar way. Previously working method directly to the other, we
financial one, namely the direct costs.
installed utility lines require a certain intuitively come to the immediate
Indirect costs which are generated by the
distance to the new line; co-ordination conclusion, that the trenchless
impact of humans, nature and
with the operator line owner is necessary. environment are often ignored. The construction method prevents many of
Access roads to the bore path and emission of dust, noise and exhaust gas the previously discussed disadvantages
driving possibilities on site have to be during the complete working time is the right from the start, also before
considered, also the space for pipe first great disturbance factor. commissioning the pipelines. Let us not
storage, mass balance, assembly and forget the fact, that often there is no
These costs are not economically alternative to trenchless installation.
disassembly of the machines; final check interesting for a project, but the effects
paths, landscaping and access to on the complete commercial life must not
compressing and monitoring stations are 5.2 Economical Aspects
be swept under the carpet; they toggle
included in the plan. mobility, cause delays, lead to loss in The crucial question, which method is
sales, reduce productivity or even more economical, often has no simple
endangering the earnings for a living. All answer. There are too many individual
4.3 Pre-Conditions for Final Checks
over the world, there are still regions with building projects, the marginal conditions
The more detailed determination of the are manifold.
bore path course should also include the inhabitants who depend completely on
an intact natural environment. For Basically, drawing a comparison
possibility for constant pipeline check.
farmers in barren regions, the between the different methods and their
Helicopter landing and constant pipeline
maintenance or unrestricted utilisation of costs for construction only makes sense
checks should be possible. Also, the
their few fertile fields is vital; fishermen for a concrete project. Still the few
preconditions for installing parallel data
rely on their intact fishing grounds. extensive examinations and attempts to
lines and control cables, i. e. for the
A further aspect are consequential costs make the costs more transparent by
operation and control of the stations,
due to the work itself, which often occur evaluating documents and numerals are
should be given from the beginning.
when operations are not carried out well appreciated. Without going into
correctly. Who is charged with the costs details or trying to evaluate the method,
4.4 Building-Technological for overhauling works on street surfaces, the results of such examinations shall be
Advantages and Specifications who pays for subsequent treatment due summarized in the following.
As soon as the parameters listed in point to settlement of unprofessional One example is the examination carried
4.1 to 4.4 have been clarified, the backfilling, when the guarantee periods out by NRC – the National Research
decision is made, whether the course is have run out and the enterprises can no Council in Canada. This examination
of poor surface quality and can be longer be made liable for damage. from June 2002 is based on 174 projects;
worked with open trench methods, or The open-cut construction method they all are projects of different lengths
whether their high-quality and causes consequential costs, because and diameters, carried out with different
demanding surface is predestined for the normally stable soil formations are construction methods. In reference to the
horizontal drilling technique. disturbed by the building measures; average costs per mm in diameter and
Usually this is valid for all water damaged slopes start moving, erosions metre in length of all projects, the
crossings, traffic way crossings, crossing lead to earth movings, surfaces without relations of the costs for HDD to pipe
of biotopes and nature conservation vegetation are generated. Consequential jacking to micro-tunnelling are 1 : 1.44 :
terrains, all tunnels and almost every costs due to the breakage of pipelines 3.2; compared with open trench
precipice track. The horizontal drilling already in operation are hard to calculate. methods, the costs for the projects
technique is also recommendable for all which have been carried out using the
Consequential costs are also caused by
terrains with a high ground water level HDD technique lie 23% below the costs
line operation: the Peace River was
and soils with a high settling behaviour, in for open trench methods. When only
crossed by a HDD bore of 3600 ft (1039
order to avoid unnecessary expenditure. m) in length and 36-in in diameter to diameters were compared, the
In karstic terrains and regions with install the Alliance Gas Pipeline - the trenchless projects up to 940 mm were
exposed rocks and poor vulnerable soils, difficulty degree was generally also always cheaper, but above 960 mm,
the horizontal drilling technique is also acknowledged; as a back-up option in some open trench projects were more
the best choice. case of a failure of the HDD bore, an economical.
The space requirements of the horizontal elaborate and extremely expensive The Final Report of the King County
drilling technique are usually smaller than suspension bridge (two pylons, main Project also shows the cost advantages
those of soil moving machines, but if spanning width 490 m, width of the two of the HDD – technique clearly, when
large drill rigs are used, the space for side spannings 245 m each ) for the compared to microtunnelling. When
drilling fluid recycling units, suspension reception of the pipeline was planned, single projects are compared, we come
material storage and sedimentation paired off with the costs for maintenance to the conclusion, that the HDD method
basin must also be regarded. The access and servicing for many years. dominates the installation of pressure
tracks (set-ups of the bore) for siphons When confronted with the decision for an and gradient lines, because the precision
and crossings must not be forgotten. installation using the open-cut or of position and height is not so important
Companies with exceptional drilling trenchless method, we must not for these lines. But don’t forgt there are
equipment naturally also offer planning compare the costs alone, sometimes it is also the consequential charges and long-
and calculation software for horizontal also a question of building culture. Is it lasting life cycle costs
drilling projects. really allowed to let residents and the Trenchless Technologies have proved
their value in practice; the methods are would make open-cut installation the consumer. A high-quality
up to the technical standard and have impossible. underground installation hardly disturbs
showed their economic advantages. In The economic aspect must not be the building ground stability, thus
order to apply these techniques forgotten – this installation method can preventing breakage and damage to the
successfully, their potentials but also actually save money while construction pipelines and making their operation
their limits have to be examined carefully and under operation. An determined bore relatively safe. Consequential damage of
for every new project. path is often only possible because of the surface or the environment is almost
trenchless installation, detours are unlikely.
5.3 A Contribution to the Availability of avoided, time and money consuming But not only large transportation
Energy discussions are prevented, the utilisation pipelines are important, further
Beside transportation by ship, pipelines of soil and grounds is only interrupted for distribution networks are required for
assure the supply for the consumer. the residents in certain spots or not at all urban regions and cities. With growing
Trenchless techniques play a big part in – expenditure for compensation is population, especially in urban regions,
pipeline construction; often they are the reduced. trenchless technologies become
focus of attention. They allow the Trenchless Technologies help to make essential for installing lines for gas, water
installation of paths in topographic, geo- pipeline installation more profitable and and other media quickly, economically
technical or technical conditions which enable the safe and economic supply for and safely.