EMGT 835 FIELD PROJECT:
Front End Loading (FEL) and
Process Engineering Workflow
By
Ryan C. Spangler, P.E.
Master of Science
The University of Kansas
Spring Semester, 2005
An EMGT Field Project report submitted to the Engineering Management Program and
the Faculty of the Graduate School of ‘The University of Kansas in partial fulfillment of the
requirements for the degree of Master of Science.
Rett fet “falos
Dr. Robert Zerwekh Date
Committee Chair
~\ > :
Jn nr Dg SEES
Annette Tetmeyer Date
Committee Member
4
Kenda Caskey
Committee MemberFront End Loading (FEL) and
Process Engineering Workflow
TABLE OF CONTENTS
Executive Summary
|. Introduction 1
A. Historical Perspective
B. Definition of FEL
C. Value of FEL in Project Development
Ul, Project Scope 5
A. Objectives
B. Review Approach
C. Selection of Sample Projects
lil. Review of FEL Deliverables 8
A. Definition of FEL Deliverables
B. Scope of Deliverables
IV. Process Engineering Workflow 21
FEL Deliverables and Responsibilities
FEL1 Activities
FEL2 Activities
FELS Activities
Development of Sample Report
mMoOOD>
V. Recommendations& Conclusions 27
A. Effective Management of FEL
B. Execution of FEL Engineering
C. Transition from FEL to Detailed Design
D. Additional Work
Appendices
| References
Il Project Team Abbreviations
Il Sample FEL Report
ENGT 835 ~ Spring 2005
F:\Report Documents\Table of Contents. dos
yan Spangler
rspangler@ gmail.comFront End Loading (FEL) and
Process Engineering Workflow
LIST OF TABLES AND FIGURES
Page
Figure 1 — Project Timetine 3
Table 1 ~ FEL Projects List 7
Table 2 - Standard FEL Deliverables 8
Table 3 - FEL Deliverables and Responsibilities at
Table 4 ~ FEL 1 Workflow — Activities and Responsibilities 23
Table 5 - FEL 2 Workflow — Activities and Responsibilities 24
Table 6 - FEL 3 Worktlow — Activities and Responsibilities 25
EMGT 835 ~ Spring 2005 yan Spangler
F \Report Documents\Tables and Figures.doc ‘spangler@ gmail.comExecutive Summary
Project development for the oil refining industry is typically performed through a
process called Front End Loading (FEL). In recent years, the Process and Industrial
Division of Burns and McDonnell has performed several FEL efforts for various
refining industry clients. A review of past FEL efforts indicates significant variation in
the FEL deliverables provided, the content of these deliverables, and the overall
quality. The primary objective of this field project report was to perform a review of
past projects, and develop a comprehensive list of “standard” FEL deliverables.
‘Once these deliverables were defined, a review of engineering workflow activities for
each stage of the FEL process was performed. The list of deliverables and the
engineering workflow activities provide a solid basis for the planning and execution of
future FEL efforts.
As a byproduct to this report, a standard FEL sample report was also developed.
This sample report is intended to benefit the division in three areas; 1) as a training
tool for the introduction of FEL to new employees, 2) as a template or guide for future
FEL efforts, and 3) as a sales tool for the demonstration of an FEL document to
potential clients.
Finally, several recommendations were made regarding the management of an FEL,
effort, execution of FEL engineering, and the transition of FEL to detailed design
For management of FEL, four key recommendations have been identified:
* Use of a 3-Phase FEL approach.
‘* Managing and maintaining consistent client “buy-in” throughout the FEL
process.
EMGT 895 ~ Spring 2005 Ryan Spangler
F \Report Documents\Executive Summary.doc rspangler@ gmail.com* Utilizing early involvement of individual design disciplines and construction,
* Conducting PDRI reviews following each stage of FEL to measure progress.
‘* Use independent FEL benchmarking for larger or more complex projects.
For execution of FEL engineering, four key recommendations were identified:
+ Emphasis on the development of a written Process Design Basis in early
FEL.
* Focus on thorough documentation of design assumptions by individual
engineering disciplines.
‘+ Obtain operations input from the client in early FEL.
+ Improve quality review procedures specifically for FEL projects.
Finally,
ive recommendations were made for transition of FEL to detailed design.
‘+ Maintain strong continuity of project team, specifically with lead engineers
and piping designers.
* Improve format standard for FEL data to streamline communication of data in
detail design,
* Maintain adherence to FEL design assumptions were at all possible to
minimize scope creep.
‘* Limit unresolved issues from FEL by conducting a final open items review to
track ail uncertain or outstanding issues prior to start of detailed design.
* Implement management of change process in FEL to ease transition to detail
design.
EMGT 835 - Spring 2005 yan Spangier
F\Report Documents\Exceutive Summary. doc rspangler@ gmail.comIntroduction
A. Historical Perspective
The oil refining industry is one of the largest and most dynamic industries in the
world. In the United States, the oil refining industry has grown out of necessity
since the late 1800's, producing the fuels required to drive the economical
expansion of the 20" century. The products of a modern day refinery include
gasoline, diesel, jet fuel, home heating oil, and petroleum based lubricants. Also
produced are various petrochemical byproducts, used as raw materials to make
numerous products from plastics and synthetic fibers, to beauty products and
pharmaceuticals,
There are currently 149 operating refineries in the United States, processing
more than 16.9 million barrels per day (BPD) of raw crude oil (NPRA, 2004).
Many of the companies that own and operate the modern day refineries are
descendents of the country’s first oil companies, who started in the early days of
oil field exploration, and developed refining and product marketing capabilities as
the industry grew. These companies are typically referred to as the “fully
integrated” or “major” refiners, reflecting their capability to compete in all aspects
of the oil and gas industry including exploration, transportation (pipeline), refining,
and product marketing. These companies tend to be the largest oil refiners due
to their established assets and infrastructure, and are the product of long, storied
histories, steady growth, and strategic mergers and consolidation, In the U.S.,
these companies primarily include six major oil companies; ConocoPhillips,
Exxon Mobil, BP Amoco, ChevronTexaco, Marathon Oil, and Royal Dutch/Shell
Oil. Each of these companies have total U.S. refining capacity (in terms of total
EMGT 835 - Spring 2005 yan Spangler
F Report Documents Introduction doe rspangler@ gmail.comcrude oil processing capacity) of more than 500K BPD. Together, the six
“majors” process more than 9.0 million BPD of crude oil (roughly 55% of the
market).
The balance of the industry is controlled by the “independent” refining
companies. These companies generally have little or no exploration or
transportation capability, and therefore must purchase crude oil on the open
market, and refine this oil to finished products. Some independent refiners own
wholesale or retail marketing outlets, while others sell their products to
independent marketing companies. There is a wide range of processing
capabilities within the independent refiners. Some of the largest independents
include Valero Energy, Sunoco, Premcor, Tesoro, and Koch Industries. Each of
these companies process more than 500K BPD of crude oil. There are also
dozens of smaller independents, which process anywhere from a few thousand
barrels to 100K BPD or more. The smaller independents include those such as.
Sinclair Oil, Frontier Oil, NCRA/Cenex, Coffeyville Resources (formerly
Farmland), Ergon/Lion Oil, Western Refining, Suncor Energy, and Hunt Refining.
B. Definition of FEL
‘The FEL (Front End Loading) process is a common strategy in the development
of capital projects for the oil refining industry. For other process industries, this
may also be referred to as FED (Front End Design), or FEED (Front End
Engineering Design). However, in all cases, the overall idea of an FEL process
is the same, and includes all project development activities from early project,
conceptualization to project authorization and funding. The FEL process is
typically broken down into two or three project development phases. Figure 1
2
EMGTT 835 - Spring 2005 yan Spangler
Report Documental Introduction doc rspangler@ gmail.comillustrates a typical FEL timeline, assuming a three-phase approach (FEL 1, FEL
2, and FEL 3).
FIGURE 1 — Project Development and Execution Timeline
Front End Loading (FEL) Project Execution
SS
FEL raz reus F
: ‘cousraucrion
Business Planning = Review of Atemates |- Class "A" Design | PETAL DESIGN, 7m
Matter Stes” “Pretmnary Design | Hazards Arayss Detaled Engnorng | Mobizaon
Feetnotogy *Prtminay Exits |-Detinave Estate |"ETwBMeN Purchase | Cenarion
Evaluation “Proje Ecopomics "Project onemce | SubEENIBELSK | Comm
|- Conceptual Design |- Risk Analysis. - Risk Analysis: e
= Project Econonice
[Risk Anais
TIMELINE, >
C. Value of FEL in Project Development
For an engineering contractor in the oil refining business, it is critical to develop
effective FEL processes and procedures for working with both the major and
independent refiners. For the major refiners, it is essential for all engineering
contractors who bid on the development and execution of large capital projects to.
demonstrate a complete understanding of the FEL process. In general, the
major refiners tend to have established and structured methods to project
development. These companies are committed to the FEL process and
recognize the value of FEL in developing successful projects.
When working for a major refining company, the engineering contractor must be
flexible enough to tailor their FEL process to the needs of the client. Typically, a
major refiner will have specific expectations regarding the type of FEL
deliverables required and the quality of such deliverables. It is up to the
3
EMT 835 - Spring 2005 yan Spangler
F \Report Documents - Introduction doe ‘[email protected]engineering contractor to demonstrate an understanding of the critical elements
of a thorough FEL package, and be willing to provide this information in a way
that meets the expectations of the client.
For the independent refiner, project development is often a greater challenge.
These operating companies typically have limited engineering resources and less
corporate structure in the execution of capital projects. Nevertheless, this does
not make FEL any less important when working for an independent. In fact,
working for an independent often requires the engineering contractor to have an
even better understanding of the FEL process. Many independent refiners tend
to spend less in FEL engineering, opting to skip over some of the later FEL
activities and award directly to an EPC contractor on a lump sum basis, This
strategy is based on the perception that this minimizes up-front investment,
streamlines the process of project funding, and shifts the project responsibilty
and risk to an EPC contractor. However, perception is not always reality, and it
is up to the engineering contractor in this scenario to sell the benefits of a good
FEL process to a client who may not appreciate the advantages of such an
approach. An incomplete FEL process inevitably results in poor scope definition.
If the scope is poorly defined, there is a greater chance for major scope changes
or surprises in detailed design. This creates added costs, project delays and
engineering rework, which could often be avoided with a thorough FEL approach.
ENGT 835 - Spring 2005 Ryan Spangler
F:\Report Documental - Introduction. doc rspangler@ gmail.comIl, Project Scope
A. Objective
The objective of this field project report is to perform a review of recent FEL
efforts in the Process and Industrial Division of Burns & McDonnell, with a focus
on developing a standard list of FEL deliverables, and a complete definition of
the Process Engineering Workflow required to support these deliverables. It is
intended that this report will benefit the division in several areas:
+ Training
Provide an introduction to the FEL process for new process department
employees.
* Benchmarking
Provide a starting point for development of future FEL efforts, and a standard
by which to measure and evaluate FEL performance.
* Sales Tool
Provide a sample document to demonstrate the value of a structured FEL
approach for potential clients.
As a byproduct to this report, a “standard” FEL template report will be developed,
which can function as a guide for future FEL efforts, and/or demonstration
document for sales of the FEL process to potential clients.
EMGTT 836 ~ Spring 2008, yan Spangler
F.\Report Documentsill - Project Scope.doc sspangler@ gmail.comB. Review Approach
This report focuses only on the FEL process from the initial stages of project.
development, to the release of engineering for detailed design (point at which
project funds are approved to initiate detailed design). Process workflow
activities during detailed design and construction are outside the scope of this
report. However, proper execution of an FEL package must be developed with
an eye to the final end product (a fully functional process plant, built on schedule
and on budget). Therefore, the review of FEL deliverables and any
recommendations proposed will be made in the context of promoting effective
transition from the FEL stage to detailed design and construction.
C. Selection of Sample Projects
A thorough discussion of the workflow required to effectively execute an FEL
project requires definition of a proper set of FEL deliverables, To achieve this
objective, a search of recent projects was performed to identify a sample of
significant FEL efforts completed by the division over the past 4 years. The
selected project list is shown in Table 1, and includes FEL projects for one major
refiner and two independent refiners. These FEL efforts provide the basis for this
report.
EMGT 835 — Spring 2005, yan Spangler
F\Report Documents\l- Project Scope. doc rspangler@ gmail.comTABLE 1 - FEL Projects List - (Selected sample from Jan 2001 to Dec 2004)
Client FEL Scope Proceed to Detail
Project Design?
ConocoPhillips
ULSG - Ponca FELS Yes
Crude Unit Revamp FELI/FELO/FELS Yes
Coker Revamp FELO/FELS No
NOx Reduction Project FEL1/FEL2/FELS No.
ULSD — Denver FEL1/FEL2/FEL3 No
Coker Project FELI/FEL2/FELS Yes
ULSD — Ponca FEL1/FEL2/FEL3 Yes
ULSG = Lake Charles FEL1/FEL2/FEL3 Yes
ULSD = Lake Charles FELI/FEL2/FELS Yes
Sinclair Oil Corporation
HTU Revamp FEL/FEL2FEL3 Yes
NHDS Project FEL1/FEL2/FEL3 Yes
Sulfur Block Project FELi/FEL2/FEL3 Yes.
‘CRU Revamp FEL3 Yes
National Cooperative
Refinery Assoc. (NCRA)
‘Amine Regenerator FELS Yes
‘Sour Water Stripper FEL3 Yes
EMGT 695 — Spring 2008 yan Spangler
F\Report Documents\l- Project Scope.doc
rspangler@ gmail.comIll. Review of FEL Deliverables
A. Definition of FEL Deliverables
The list of sample projects identified in Table 1 covers a wide range of project,
types and scope. A review was performed to evaluate the FEL deliverables
provided for each of these projects. The result of this review was the
development of a comprehensive list of FEL deliverables for each phase of FEL.
Table 2 lists the FEL deliverables identified, and indicates in which phase or
phases a specific deliverable is typically issued. For documents to be issued in
more than one FEL phase, these documents are issued in multiple revisions as
project information is better defined from one phase to the next.
TABLE 2 ~ Standard FEL Deliverables
Deliverable Phase
FEL1 | FEL2 | FEL3
Project Scope Documents
Project Description X
>!
>><]
Project Execution Plan
Design Basis Documents
Process Design Basis X
Material and Energy Balance
Utility Summary
Emissions Summary
><]><|><|><]><
Equipment Design Basis
Piping Design Basis
Civil/Structural Design Basis
Electrical Design Basis
Instrument and Controls Design Basis
Fire Protection Design Basis
Insulation Design Basis
Protective Coatings Design Basis
>| ><|><|>]><}>| ><>] ><] ><>} >< ><]
Cost Estimate Basis x x
Key Drawings
Block Flow Diagrams x
Process Flow Diagrams x
Piping and Instrumentation Diagrams
>|><|>¢|
Materials of Construction Diagrams
8
EMGT 835 - Spring 2005 yan Spangler
F\Report Documentsll- Review of FEL Delverables.coc rspangler @ gmail.comSite Plan’ x
General Arrangements x
Piping One-Line Drawings
><|><]><| >
Electrical One-Line Diagrams
Specifications
Equipment Specifications
Piping Specifications
Instrument Specifications
Motor Specifications
|><|><)><]><
Insulation Specifications
Lists/Summaries
Line List
Tie-in List
Equipment List x x
>]><]><|><] ><}><|>«!
Instrument Data Sheets
‘Schedules
Overall Project Schedule x x
x!
Estimates
Factored Cost Estimate x
Preliminary Estimate x
Definitive Estimate x
Project Definition Reports
PDRI Summary Xx
B. Scope of Deliverables
A review of deliverables trom the sample projects indicates significant variation,
both in the content of the deliverables and the overall quality. In many cases,
some variation is required due to the different types of projects defined.
However, all FEL reports should follow the same general outline, providing the
‘same basic types of information. In general, the deliverables provided in a
9
EMGT 835 - Spring 2008 yan Spangler
FAReport Documentslll- Review of FEL Deliverables. doo spangler@ gmail.comcomplete FEL package should include the following:
1, Project Scope Documents
The Project Scope Documents include the Project Description and Project
Execution Plan. The purpose of these documents is to provide the overall
‘summary of the project scope and intent, and to outline the key factors to
successful project execution, including key assumptions, limitations and
challenges.
In general, the Project Description must include the general scope (what),
location (where), purpose (why), and the infrastructure and utilities required
(how).
The Project Execution Plan describes the key activities required for project
completion. The execution plan must consider requirements and limitations
based on engineering, equipment deliveries, and construction duration. This
document should also evaluate the contracting and procurement strategies
for the project, and interface responsibilities between the owner and various
contractors/sub-contractors.
2. Design Basis Documents
The design basis documents define the overall engineering basis of design
for each specific discipline required for execution of the project. For most
process plant design projects, this would typically include:
10
EMGT 835 - Spring 2005 yan Spangler
F\Report Documentsill- Review of FEL Deliverables.doc [email protected]- Process Design Basis
The Process Design Basis is the most important design basis document
in early FEL. This document defines the unit operations required, the
characteristics and quality of available feed stocks, the minimum
performance criteria or product quality standards, and the assumed
conditions for any supporting utlities. The Process Design Basis also
includes the project Material and Energy Balance, Utility Summary, and
Emissions Summary.
- Equipment Design Basis
The Equipment Design Basis describes the key parameters required for
all critical process equipment, including the sizing basis, performance
requirements, materials of construction, spare equipment philosophies,
over-design margin, and future expandability. The Equipment Design
Basis also identifies specific design codes or standards, as well as client-
specific specifications and preferences required.
- Civil/Structural Design Basis
The Civil/Structural Design Basis describes the overall general site
conditions, structural design codes and standards, special geotechnical or
foundation requirements, and region-specific wind, snow and earthquake
design requirements. This section also defines the style or type of
facilities that will be provided based on the client’s requirements. This
can include design features such as special access, landscaping, types of
paving, fireproofing, building materials, and architectural requirements.
in
MGT 635 ~ Spring 2005 yan Spangler
F.\Ropor Documientsill - Review of FEL Deliverables doc rspanglor@ grallcom- Electrical Design Basis
The Electrical Design Basis defines the requirements for design of new
electrical power systems, including a summary of new power loads
required, the electric distribution systems needed to support these new
loads, major electrical equipment required, such as substations or
transformers, and low voltage distribution requirements for
instrumentation and controls. This section also identifies any electrical
requirements related to general lighting, grounding, lightning or cathodic
protection, and heat tracing systems for piping. Finally, this section
defines the required design codes and standards, electrical area
classifications for equipment, and physical design requirements and
philosophies to be followed in regard to wiring, conduit, cable tray, electric
motors, design redundancy, emergency power, and utility power (welding
and general purpose receptacles).
- Instrument and Controls Design Basis
The Instrument and Controls Design Basis defines the type of instruments
to be installed (manufacturer, technology, materials of construction) for
each process service and function, including control valves, process
instrumentation (flow, level, pressure and temperature), and any special
analyzers. This document also defines control philosophy (DCS, PLC, or
other), applicable codes and standards, client preferences, acceptable
manufacturers, units of measure, calibration requirements, and
winterization (freeze protection) philosophy.
2
EMGT 695 ~ Spring 2005 yan Spangler
F\Repont Documental - Review of FEL Deliverables. doc rspangler@ gmail.com3. Key Drawings
There are several key drawings that must be developed during FEL. In early
FEL, these drawings are generally preliminary in nature, with the purpose of
illustrating options or assumptions. In late FEL, these drawings should be
issued for review and approval, and provide the basis for the start of detailed
design. The key drawing documents include:
- Block Flow Diagram
The Block Flow Diagram is a simplified drawing that illustrates the major
process steps required for the overall process design. This drawing
indicates the major feed stocks required (inputs), the process steps to be
Performed (unit operations), and the resulting products created (outputs).
The Block Flow Diagram may be issued as an independent drawing, or
incorporated into the written Process Design Basis for reference.
- Process Flow Diagrams (PFDs)
The Process Flow Diagrams illustrate the overall process flow scheme in
order to define all unit operations required and their relative sequence in
the overall process operation. This drawing is typically used as a
reference document for the Material and Energy Balance to provide
overall flow data and process conditions for all major process and utility
streams.
- Piping and Instrumentation Diagrams (P&IDs)
In the FEL process, the P&lDs are the most important single document
used to illustrate the process design required and the overall scope of
13
EMGT 835 ~ Spring 2005 Fyan Spangler
F \Report Documerts\ll- Reviow of FEL Deliverables. doo rspangler@ grai.com‘equipment, instrumentation and piping for the project. The P&IDs are
based on the same flow scheme illustrated by the PFDs, but with
significantly more detail. At the end of FEL, the P&iDs should contain ail
information required for the start of detailed design and should illustrate
all equipment, piping, valves, special fittings, instruments and safety
devices required to construct a complete, safe, and operable refinery
Process plant.
- Materials of Construction Diagrams (MSDs)
‘The Materials of Construction Diagrams (MSDs) are very similar to the
PFDs, with added information to define the equipment and piping
metallurgy requirements for the project. These requirements are based
on client preferences, required corrosion resistance, and the economic
plant lite expectancy.
Site Plan
The Site Plan Drawing illustrates the overall layout of the new process
unit in relation to the overall facility and any key infrastructure and access
features of the site (roads, railways, sewer and fire water systems, etc.)..
This drawing is also used to illustrate the availability of major utility
streams (cooling water, service water, instrument air, plant air, ete.) when
required to be obtained from locations outside the scope boundaries
(battery limits) of the new process unit.
14
EMGTT 895 — Spring 2005 yan Spangler
F.\Report Documentsill - Review of FEL Deliverables doc sspangler@ gmail.com- General Arrangements
‘The General Arrangement Drawings illustrate the relative layout of
‘equipment within the process unit boundaries of the project. This drawing
shows the outline dimensions and orientation of all equipment in the
project, as well as any major buildings or structures. The General
Arrangement drawings are used to evaluate access issues associated
with safety, operability, maintenance, and constructability.
- Piping One-Line Drawings
The Piping One-Line Drawings provide a simplified one-line illustration of
all major pipe runs required for the project. This drawing is typically
produced with the General Arrangement or Site Layout as the
background for consistency. The Piping One-Line Drawings are critical in
the development of a thorough FEL project cost estimate, because they
are often used in the tabulation of piping material take-offs and
preliminary design of major support structures and piperacks.
- Electrical One-Line Drawings
The Electrical One-Line Drawings illustrate the overall electricat
interconnects required for the project in a simplified, one-line format. This
drawing illustrates the power feed to all electric motors, and shows all
major electrical equipment including main power feeders, generators,
transformers, switches, contactors and motor control centers (MCCs).
15
EMGT 895 ~ Spring 2005 Ryan Spangler
F:\Ropon Dacumentslll- Review of FEL Deliverables dac rspanglar@ gmail.com4. Specifications
The specification documents define the quality of design, fabrication, and
installation required for equipment and materials in the project. The extent
and type of specifications developed in FEL may vary significantly based on
the type of project being considered. However, the specification documents
typically include:
- Major Equipment Specifications
Includes written specifications for major equipment such as storage tanks,
pressure vessels, fired heaters, heat exchangers, pumps and
compressors. These specifications may be based on standard in-house
specifications, client specifications, and/or industry standard
specifications (such as PIP (Process Industry Practices) or other).
Piping Specifications
The piping specifications define the design and installation requirements
for all piping materials on the project. The full compliment of piping
specifications for a typical project covers a wide range of metallurgy and
pressure classifications to cover the various types of piping services
required.
- _ Instrument Specifications
The instrument specifications define the specific design and installation
requirements for process instrumentation, control valves and relief
devices on the project. The instrument specifications may be in a written
format to cover general requirements, or may be communicated via
16
EMGT 895 ~ Spring 2005 yan Spangier
F\Report Documentsll- Review of FEL Delverables.coc repangler@ gmail.comindividual instrument datasheets for each required device (discussed
further below).
Motor Specifications
‘The motor specifications define the general sizing, selection, and
performance requirements for electric motors on the project. These
specifications are typically broken down based on motor voltage and
horsepower, and typically identity enclosure types, service factors,
acceptable manufacturers, minimum efficiencies, and other client
preferences as required.
- Insulation Specifications
The insulation specifications define insulation materials, types and design
criteria for piping and equipment insulation on the project. These
specifications are typically based on client specific preferences or industry
standards, and vary based on process specific requirements and local
environmental conditions.
5. Engineering Lists
The engineering list documents include the key project tabulations for
identifying and quantifying equipment items (Equipment List), as well as,
material commodities such as piping and insulation (Line List), process
instrumentation (Instrument List), motors (Motor List), and control system
components (VO List). The engineering lists may be issued in preliminary
format in early FEL, but are typically most valuable at the end of FEL for use
in development of the definitive cost estimate.
7
EMT 895 - Spring 2005 yan Spangler
FAReport Documents - Review of FEL Deliverabies. doc rspanglor@ gmail.com6. Data Sheets
Includes individual datasheets for equipment and critical instrumentation
(analyzers, control valves and relief devices). In early FEL, these datasheets
typically only include key process data (capacity, flow, temperature, pressure)
and general metallurgy requirements. In late FEL, additional information may
be specified, such as model numbers, connection sizes, and special features.
7. Schedules
The project schedule is a key reference document throughout the entire
process of FEL. In early FEL, a preliminary schedule should be developed to
analyze requirements for engineering workload, long lead equipment
deliveries, and general construction schedule requirements (key completion
dates, milestones, shut-down durations, etc.) At the end of FEL, a
comprehensive overall schedule should be prepared, which will serve as the
basis for project execution through detailed design and construction.
8. Cost Estimates
‘Overall project cost estimates should be prepared at the end of each phase
of FEL. Assuming a three-phase FEL process, the cost estimates to be
prepared include:
- FEL 1 Estimate
Typically referred to as an “Order of Magnitude” or “Factored Cost
Estimate.” There are several methods by which an FEL 1 estimate can
be developed. One method is to prepare an order of magnitude estimate
18
EMGT 835 — Spring 2005 yan Spanger
FAReport Documerts\ll- Review of FEL Deliverables. doc repangler@ gmail.combased on published project data (literature search) or through comparison
to similar projects executed by the client or engineering company. This
method may be sufficient for certain types of well understood projects, A
second method is based on utilizing assumed installation factors, which
are multiplied by budgetary cost estimates of equipment to obtain the total
installed cost. The cost factors used are typically based on industry
standard cost factors with adjustments based on in-house experience,
comparison to similar projects, and special project conditions, Depending
on the method used, and the quality of the reference data available, the
overall accuracy for this type of estimate is typically +/- 30 to 70%.
- FEL 2 Estimate
Typically referred to as a “Preliminary Estimate.” This type of estimate
requires additional engineering effort to develop sufficient scope definition
to allow preliminary quantities of basic materials to be estimated. This
includes piping, insulation, instrumentation, steel, concrete, etc,
Typically, equipment costs are based on budgetary vendor quotes and
preliminary sizing. The overall accuracy for this type of estimate is
typically +/- 15 to 30%.
- FEL3 Estimate
Typically referred to as a “Definitive Estimate.” The key differences
between an FEL 2 estimate and an FEL 3 estimate are improved
equipment pricing, and sharpened take-off quantities for all bulk
materials. Equipment costs for an FEL 3 estimate are based on multiple
vendor quotations, with sufficient bid conditioning to ensure firm pricing
19
EMGT 886 ~ Spring 2005 yan Spangler
F \Report Documental Review of FEL Deliverables doo rspangler@ gmail.comon all major equipment items. Take-off quantities are improved through
additional engineering, including one-line piping studies, preliminary
design of foundations and structures, and vendor quotations on control
valves, major instrumentation and control systems. The overall accuracy
for this type of estimate is typically +/- 5 to 10%. The FEL 3 estimate is
typically the basis used for the final application for project funding.
9. Project Definition Rating Index (PDR!) Reports
The Project Definition Rating Index (PDRI) is a method for evaluating whether
the FEL process has been performed with sufficient detail and effort to
provide a reasonable level of confidence that the project will be successful.
This is a technique that was originally developed by John Hackney (Hackney,
1992), and is endorsed by the Construction Industry Institute (Cll),
Determination of a PDRI score requires working through a list of typical
project topics and issues, and assigning points based on the level of
definition accomplished in FEL. The PDRI rating is typically developed
through a joint effort of all major project participants and should be done at
multiple points in the FEL process. For a three phase approach (FEL 1, FEL
2, FEL 3) it is recommended to perform a PDRI review at the end of each
FEL phase.
20
EMGT 835 ~ Spring 2005 yan Spangler
F \Report Documentslll Fleview of FEL Deliverables. doc rspanglor@gmalicomIV. Process Engineering Workflow
A. FEL Deliverables and Responsibilities
A review of Process Engineering Workflow activities for FEL requires a definition
of the responsibilities for each of the FEL deliverables defined in Section III —
Review of FEL Deliverables. Table 3 lists each of the identified FEL deliverables
and indicates the responsible project team member for each deliverable. The
process engineering responsibilities are indicated by “PE”. The other project,
team abbreviations are provided in Appendix Il.
TABLE 3 — FEL Deliverables and Responsibilities
Deliverables FELT FEL2 FEL3
Project Scope Documents
Project Description PE PM PM
Project Execution Plan PM PM PM
Design Basis Documents
Process Design Basis PE PE PE
Material and Energy Balance PE PE
Utility Summary PE PE
Emissions Summary PE PE
‘Equipment Design Basis PET ME,
Piping Design Basis PL
GiviStructural Design Basis CE
Electrical Design Basis EE
Instrument and Controls Design Basis iE
Fire Protection Design Basis ME
Insulation Design Basis ME
Protective Coatings Design Basis. ME
Cost Estimate Basis PM. PM PM
Key Drawings
Block Flow Diagrams PE
Process Flow Diagrams PE PE,
Piping and Instrumentation Diagrams PE PE
Materials of Construction Diagrams PE PE
Site Plan CE CE
‘General Arrangements PL. PL
Piping One-Line Drawings PL
Electrical One-Line Diagrams EE
2
EMGT 835 ~ Spring 2005 yan Spangler
F:\Report Documents\lV Process Engineering Worktiow doe rspangler@ gmail.com[Specifications
Equipment Specifications ME
Piping Specifications PL
Instrument Specifications rE
Motor Specifications EE
Insulation Specifications ME
Lists/Summaries
Tine List PE" RL
Tie-in List PET/PL
Equipment List Pew ME
Instrument List PEv IE
VO List 1
[Datasheets
Process Data Sheets PE
Equipment Data Sheets PET ME
Control Vaive Data Sheets PETE
Relief Valve Data Sheets PEM IE
Instrument Data Sheets PETE
[Schedule
Overall Project Schedule PM PM PS
Estimate
Factored Cost Estimate ES
Preliminary Estimate ES
Definitive Estimate Ey
Project Definition Reports
PDRI Summary PM
FEL.
'"" Initiated by Process Engineering. To be completed by the lead discipline at the end of
B. FEL1 Activities
The purpose of FEL 1 is the economic and feasibility review of a process design
scenario, proposed as a potential solution to a specific business objective. For
‘an engineering contractor, the customer typically performs the earliest stages of
FEL 1. The customer is the operating company (refiner) who continually reviews
their own position in the market, and identifies potential projects that will provide
MGT 835 - Spring 2005
22
F\Report DocumentstlV - Process Engineering Workflow doc
yan Spangler
‘spangler@ gmail.comsome economic advantage. Once the business objective is identified, it is at that
Point that an engineering contractor is often hired to perform many of the FEL 1
activities. Table 4 highlights the major activities that must be performed for a
typical FEL 1 effort.
TABLE 4 ~ FEL 1 Workflow - Activities and Responsibilities
Workilow Activity Description [Responsible]
Code Lead
7.1 [Business Planning
1.1.1 Identify Business Need or Opportunity ‘Owner
1.1.2 Assess Economic Factors for Success ‘Owner,
1.1.3 Review General Feasibility With Engineoring ‘Owner
72 [Market Studies
1.2.1 Perform Market Review ‘Owner,
1.2.2 Evaluate Availability of Critical Feedstocks ‘Owner
1.2.3 Evaluate Marketabilily of Products/By-products ‘Owner
1.2.4 Identify Market Risk Factors (Le. - Competitors, Market | Owner
Variability, Emerging Technologies, Regulations)
1.3 [Technology Evaluation
1.3.1 Perform Literature Search / industry Survey PE
1.3.2 List Potential Process Alternatives PE
1.3.3 Identity Technology Providers/Licensers PE
1.3.4 Perform Preliminary Screening of Alternatives PE
1.3.5 Finalize List of Potential Alternatives PE
14 [Conceptual Design
1.4.1 Prepare Preliminary Process Design Basis PE
1.4.2 Develop Preliminary Block Flow Diagram(s) PE
43 Prepare Preliminary Project Description PE/PM
1.4.4 Develop Milestone Project Schedule ‘Owner/PM
1.45 Develop Preliminary Cost Estimate Basis PMIES
15___ [Project Economics and Risk Analysis
1.5.1 Develop Order-of- Magnitude/Factored Cost Estimate | _PM/ES
1.5.2 Prepare Preliminary Economic Scenario ‘Owner
1.5.3 Run Economic Model to Check Project Benefit ‘Owner
1.5.4 Identify Risk Factors / Uncertain Variables ‘Owner
1.5.5 Run Economie Mode! With Variation (Monte Carlo) ‘Owner
1.5.6 Make Go / No-Go Decision on FEL 2 ‘Owner
1.5.7 Perform PORI Analysis for FEL Measurement ‘Team
2B
EMGT 635 ~ Spring 2005 yan Spangler
F:\Report DocumentsilV - Process Engineering Workilow.doc rspangler@ gmail.comC. FEL 2 Activities
The purpose of FEL 2 is the continuation of project development, with the
objective of selecting the most appropriate technology and overall design
approach. Table 5 highlights the major activities that must be performed for a
typical FEL 2 effort.
TABLE 5 - FEL 2 Workflow — Activities and Responsibi
Workllow Activity Description Responsible
Code Lead
2.1 [Review of Alternates
2.1.1 List Alternate Technologies/Methods from FEL 1 PE
2.1.2 Collect Additional Data / Research Altematives PE
2.2 [Preliminary Design
2.2.1 Revise Process Design Basis PE
2.2.2 Revise Block Fiow Diagram(s) PE
2.2.3 Develop Preliminary Process Flow Diagram(s) PE
2.2.4 Prepare Material and Energy Balance(s) PE,
2.2.5 Prepare Utility Summary PE
2.2.6 Prepare Emissions Summary PE,
2.2.7 Develop Preliminary Plot Plan CE
2.2.8 Develop Preliminary General Arrangement(s) PE/ME
2.2.9 Prepare Process Data Sheets on Equipment PE
22.10 Prepare Preliminary Equipment List PE
2.2.11 Revise Project Description PM
2.2.12 Prepare Project Execution Plan PM
2.3 [Preliminary Estimates
2.3.1 Obtain Budget Quotations on Equipment PEIME
2.32 Develop Preliminary Take-ofis on Long Run PE/PL
Piping
2.3.3 Develop Preliminary Quantities of Materials for Major CE
Foundations and Structures
2.3.4 Revise Preliminary Cost Estimate Basis PMES
2.4 [Review Project Economics and Risk Analysis
2.4.4 Develop Preliminary Estimate PMES
Revise Economic Scenarios ‘Owner
Revise Economic Model ‘Owner
Update Risk Factors / Uncertain Variables ‘Owner
Run Economic Model With Variation (Monte Carlo) ‘Owner
‘Select Preferred Project Alternative ‘Owner
Make Go/No-Go on FEL 3 ‘Owner
Perform PDAI Analysis for FEL Measurement Team
EMGT 895 ~ Spring 2005
FAReport Documents\lV - Procass Engineering Werkllow.doc
24
‘Ryan Spangler
‘spangler@ gmail.comD. FEL 3 Activities
The purpose of FEL 3 is the continuation of project development, with the
objective of developing a full definition of the project scope based on the process
alternative selected in FEL 2. At the end of FEL 3, the project should have a
definitive cost estimate, which is sufficient for application of project funding.
Table 6 highlights the major activities that must be performed for a typical FEL 3
effort.
TABLE 6 ~ FEL 3 Workflow - Activities and Responsibilities
Workflow Activity Description Responsible
Code Lead
3.1 [Class “A” Design
3.1.1 Revise Process Design Basis PE
3.1.2 Revise Block Fiow Diagram PE
3.1.3 Revise Process Flow Diagram(s) PE
3.1.4 Prepare Materials of Construction Diagram(s) PE
3.1.5 Finalize Material and Energy Balance(s) PE
3.1.6 Revise Utiity Summary PE
3.1.7_Revise Emissions Summary PE
3.1.8 Revise Piot Plan CE
Revise General Arrangement(s) MEICE
Revise Equipment Design Basis ME
Prepare Equipment Data Sheets ME
Revise Equipment List ME
Develop Piping One-Line Drawings PUPE
Develop Electrical One-Line Diagrams EE
Develop Equipment Specifications ME
Develop Piping Specifications PL
Develop Instrument Specifications TE
Develop Motor Specifications EE
Develop Insulation Specifications PL
Prepare Line List PE/PL
Prepare Tie-in List PEPL
Prepare Instrument List PEE
Prepare VO List TE
Prepare Control Valve Data Sheets PEVE
Prepare Relief Vaive Data Sheets PEE
Prepare Instrument Data Sheets PENE
Develop Piping Design Basis PL
[— Develop CivilStructural Design Basis CE
Develop Electrical Design Basis EE
Develop Instrument and Controls Design Basis iE
Develop Fire Protection Design Basis ME
25
EMATT 835 ~ Spring 2005 yan Spanglor
Report Documents\lV - Process Engineering Workflow.doc
rspangler@ gmailcom3.1.32 Develop Insulation Design Basis MEPL
3.1.33 Develop Protective Coatings Design Basis MEIPL
3.1.34 Revise Project Description PM
3.1.35 Revise Project Execution Plan PM
| 3.2 [Hazards Analysis
3.2.1 Issue P&iDs for HAZOP Review PE
3.22 Conduct HAZOP Review Team
3.2.3 Implement HAZOP Recommendations in Design PE
33 Definitive Estimate.
3.3.1_Obtain Multiple, Firm Quotations on Equipment PEME
3.3.2 Condition Bids to Ensure Firm Pricing PM/ME
3.3.3 Develop Refined Take-offs on Long Run Piping PL.
3.3.4 Develop Refined Quantities of Materials for Major CE
Foundations and Structures
3.3.5 Revise Cost Estimate Basis PM/IES
3.3.6 Develop Overall Project Definitive Estimate ES
34 Review Project Economics and Risk Analysis
3.4.1 Finalize Economic Scenarios Owner.
3.4.2 Finalize Economic Mode! Owner
3.4.3 Update Risk Factors / Uncertain Variables Owner
3.4.4 Run Economic Model With Variation (Monte Carlo) ‘Owner
3.4.5 Make Go/No-Go on Project Funding to Detail Design Owner,
3.4.6 Perform PDRI Analysis for FEL Measurement Team
E. Development of Sample Report
This report has developed a comprehensive list of FEL deliverables based on a
review of past FEL efforts. This report also defines the activities required to
‘support these deliverables in the actual execution of an FEL effort. Using this
information as a basis, an FEL sample report has been developed, and is
included as Appendix Ill. This report is intended to further illustrate the type of
information required for a complete FEL package, and may serve as a guide for
future FEL efforts, and/or demonstration document for sales of the FEL process
to potential clients,
ENGT 835 - Spring 2008,
FAReport Documents\V - Process Engineering Workflow.dec
26
Ryan Spangler
rspangler@ gmail.comV. Recommendations
‘Several recommendations can be made, based on the review of past FEL efforts.
‘These recommendations are classified as one of three types; 1) recommendations
for effective management of FEL, 2) recommendations for execution of FEL
engineering or 3) recommendations for transition from FEL to detailed design.
A. Effective Management of FEL
Management plays a significant role in the execution of a successful FEL effort.
‘Some critical recommendations that should be emphasized for effective
management of FEL include:
1.
‘Three-Phase Approach
‘The recommended FEL strategy described in this report focuses on FEL
management through a three-phase approach. The three-phase FEL is a
common method used by many refining companies in the development of
projects. The three phases each have a specific objective and should not be
combined or skipped if at all possible. Following each phase, a documented
package of deliverables should be prepared, and project economics should
be evaluated to provide justification for moving to the next FEL phase.
Glient “Buy-In”
All phases of a successful FEL effort must be performed with close contact to
the client to ensure 100% “buy-in” to all FEL decisions and assumptions. In
the development of any project, many assumptions must be made in the early
phases where information is either not available or will require further work to
21
EMGT 835 ~ Spring 2005 yan Spangler
F.\Report Documents\V - Recommendations. doc ‘spangler@ gmail.comdefine. Often times these assumptions will make or break a project, and
therefore all key assumptions shouid be clearly stated, documented, and
reviewed with the client to ensure the best available information is being
considered. Interface between the client and the FEL team to maintain client
“buy-in” is one of the most important tasks of FEL management.
3. Early Involvement of Design Disciplines and Construction
Typically, the process engineering group leads FEL 1 and 2, utilizing a small
project team with direct interface to the client. This is due to the fact that
‘most engineering activities in early FEL are related to early conceptual
design, and technology evaluation. By FEL 3, the project development starts
to become more focused, and additional discipline engineers (mechanical,
piping, electrical, structural) are required. However, by this time, many of the
key project decisions may have already been made, and the project suffers
due to a lack of early input from the key disciplines. To avoid this missed
opportunity for value added input, it is recommended that periodic design
reviews be performed with project leads from all disciplines, starting at the
end of FEL 1. Additionally, these reviews should also include representatives
from construction to receive early input on constructability issues and safety,
Inclusion of these project team members as early as possible will maximize
design efficiency in the later stages of project development and will help to
avoid costly design changes and/or rework in detail design.
4, PDRI (Project Development Rating Index) Reviews
One common way to measure FEL progress from a managerial perspective is
the use of PDRI reviews. At a minimum, it is recommended that PDRI
28
EMGT 895 - Spring 2005 yan Spangler
F.\Report Documents\¥ - Recommendations doc ‘spangler@ gmail comreviews be performed at the end of each FEL phase. This provides a gauge
by which the overall FEL progress can be measured. At the end of FEL 3,
the PDRI analysis is used to indicate whether the overall FEL effort is
‘Sufficiently complete to provide a reasonable probability of success. The
Construction Industry Institute (Cll) indicates that projects that score a 200 or
less in the PDRI index are significantly more likely to succeed based on
‘overall cost, schedule and scope creep. For the Process and Industrial
Division it is recommended that all FEL 3 efforts should score 175 or less.
before being considered complete. In cases where a significantly higher
score is obtained, the weak areas of scope definition should be identified and
improved. If FEL cannot be extended to improve the PDRI score, the final
score obtained should be a consideration in the analysis of project risk and
the establishment of project contingency for detailed design and construction.
5. FEL Benchmarking
In addition to PDRI scoring, which is an internal measurement activity, there
are several companies that specialize in performing independent project
reviews and analysis for FEL efforts. One such company is IPA (Independent
Project Analysis), based in Ashburn, VA. IPA specializes in providing FEL
project evaluations, and can provide empirical statistics based on a database
of past projects to analyze a project's probability of success, This type of
independent analysis may not be required for all projects, but should be
strongly considered for the larger and more complex capital projects.
EMGT 835 ~ Spring 2008, yan Spangler
F.\Report Documents\v - Recommendations. dee ‘spanglor@ gmail.comB. Execution of FEL Engineering
Besides the managerial aspects of FEL, the other key component to a successful
FEL effort is the execution of FEL engineering. Several recommendations can
be made regarding FEL engineering. Some of the more critical
recommendations that should be emphasized include:
1. Process Design Basis
One of the earliest and most critical activities of an FEL effort is development
of the process design basis. The information contained in the process design
basis will significantly impact the type of process developed, the technologies
considered, and the overall project economics. Too often the process design
basis is developed based on preliminary information or poorly defined
assumptions. Any information considered preliminary or tentative in nature
should be noted within the process design basis, and a plan should be
developed for improving the certainty of such data (pilot piant testing, lab
analysis, literature search, etc). Significant effort should be taken to ensure
that the process design basis is as complete and accurate as possible before
any additional FEL activities are performed.
2. Documentation of Discipline Design Assumptions
While the process design basis is the most critical in early FEL, the other
discipline design basis documents are essential in the complete definition of
the project scope. Typically, the design basis assumptions are documented
in the Design Basis section of the FEL report. It is critical that these
documents include sutficient detail to define ail key design parameters
required for the project.
30
ENGT 835 — Spring 2005 yan Spangler
FAReport Documents - Recommendations doc ‘spangler@ gmail.com