Method Statement For The Installation of Power and Lighting System Wiring
Method Statement For The Installation of Power and Lighting System Wiring
Method Statement For The Installation Of Power and Lighting System Wiring:
3. Location of Activity
Power and lighting system for the whole building
4. Operation
1. Material: Material used will be as approved by the engineer. The sizes and routes
routing will be as per the approved shop drawing.
2. Storage and Protection: Deliver components parts to site, completely identified in
accordance with shop and certified drawings prepared for this work. Store in
accordance with the manufacturers instructions, above ground, properly protected
from the weather and construction activities.
3. Wiring:
a. No wiring be carried out until the appropriate tests required or in the electrical
testing section have been done and the consultant has given his clearance for
wiring to commence.
b. A loop in form of wiring shall be used as far as practicable or unless otherwise
indicated. Joints in conductors shall be made using insulated terminal blocks
complying with requirements of this specification.
c. At expansion joints adequate slack shall be left in the cable.
d. Where conduits are installed for wiring by others, a draw wire shall be provided
between each draw in position.
e. Where three-phase circuits comprising single-core cables are installed in trunking,
all cables of a shall be tied together at intervals not exceeding 200mm.
f. Cables forming part of alarm, control, communication or monitoring circuits shall
have identification sleeves at their terminations. Identification shall be consistent
with the relevant wiring diagrams.
5. Responsibility
1. Project Manager
a. To ensure that all the preparation and application works are carried out according to
the Contract Specification and with the approved drawings.
b. To ensure that the progressing of work is carried out according to the planned
program and as per the approved method of statement.
c. To ensure that all the equipment and materials required to execute the work are
available according to the planned construction program.
d. To co ordinate with the Main contractor, MEP Coordinator and Safety Officer, for a
safe and proper execution of the works.
2. Site Engineer
a. To ensure that the works are carried out according to the Contract Specifications,
approved method statement and the shop drawings.
b. To provide all necessary information and distribute responsibilities to his
construction team.
c. To monitor the progress of work in relation with the work program and to report to
the Project Manager.
d. To co-ordinate with the safety officer and to ensure that the works are carried out in
safe practising methods.
3. Foreman
a. The foreman will carry out his duties by maintaining continuous coordination with
the site engineer on daily basis, and ensure proper distribution of the workforce in
the required and planned locations.
b. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties properly.
c. To ensure in consultation with the site engineer that the manpower involved in the
works are moving as agreed and planned for the work.
d. To ensure that the daily work is progressing as planned and advise the site
engineer of any requirement for additional resources. To control disposal of waste
materials according to the instructions received from the site engineer.
e. To ensure full coordination with the safety officer to maintain safe working and
proper house keeping of the site, following the approved safety measures and
further ensure that all his working team are aware of the same to prevent accident
and losses.
f. To inform the site engineer and of the areas ready for inspection.
g. Distribution and the control of material shall be monitored by foreman and store
keeper.
6. Equipment Requirements
The requirements that will be engaged for Power and lighting System Wiring works will
be as follows:
1. Measuring tape
2. Cutting plier
3. Box spanner set
4. Bending spring
5. Pipe Wrench
6. Drilling Machine
7. Crimping tool
8. Crew driver
9. Pulling spring
10. Hammer
11. Common tools
7. Health and Safety
Strictly followed as per the manufacturers Health and Safety recommendations for
handling and use of the materials. Ensure all involved personnel shall be aware of the
same.
Design Drawings
Design and Review of Design Authorities
1 All the Drawings
Drawings Documents Drawings Departments
Requirements
No damages, proper
Check the
moving of the wiring,
conduits and Approved
Visual and material should have Approved Drawin
3 trunking are Method
Puling spring minimum status of - No Method Statemen
cleared before Statement
Objection with comments
wiring
(2)
Visual
Raise inspection Approved NO obstructions height, Approved
4 Measurement
request Drawings Proper position Drawings
instrument