SR - No Specification Description of Items Unit Qty Rate Amount

The document provides specifications and pricing for three solar systems: 1. A 40kW system for tube wells with 138 solar panels costing Rs. 4,706,840. 2. A 31.7kW system for feed pumps with 104 solar panels costing Rs. 4,054,720. 3. A 6.7kW system for 6 hours of daily utilities load plus 2 hours backup with 22 solar panels and batteries costing Rs. 1,619,960. The total cost of all three systems is Rs. 10,381,520.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
468 views4 pages

SR - No Specification Description of Items Unit Qty Rate Amount

The document provides specifications and pricing for three solar systems: 1. A 40kW system for tube wells with 138 solar panels costing Rs. 4,706,840. 2. A 31.7kW system for feed pumps with 104 solar panels costing Rs. 4,054,720. 3. A 6.7kW system for 6 hours of daily utilities load plus 2 hours backup with 22 solar panels and batteries costing Rs. 1,619,960. The total cost of all three systems is Rs. 10,381,520.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

LKP1

I. VFD BASED SOLAR SYSTEM FOR TUBE WELLS NIZAM ENERGY


Sr.No Specification Description of Items Unit Qty Rate Amount

1.00 3 Phase, 22 VFD/Solar Pump Inverter with MPPT -Dual Supply Mode -
KW ABB/Equivalent 1.00 No. 380,000.00 380,000.00
2.00 PV = 26 KW Solar Panels (Solar 305 Watts) as per specifications and
approved by the Engineer In-Charge 86.00 No. 23,180.00 1,993,480.00
3.00 GI/Concrete PV Mountings structure and civil works complete in all
respects 43.00 No. 7,000.00 301,000.00
4.00 Solar DC Wiring and DB Box and Accessories 1.00 Lump-Sump 190,000.00 190,000.00
Total Amount (Rs.) 2,864,480.00
5.00 Transportation For Punjab Lump-Sump 1.00 Lump-Sump 30,000.00 30,000.00
7.00 Installation charges 1.00 Lump-Sump 55,000.00 55,000.00
Total Amount (Rs.) Total 2,949,480.00
II. VFD BASED SOLAR SYSTEM FOR FEED PUMPS
1.00 3 Phase, 20 VFD/Solar Pump Inverter with MPPT -Dual Supply Mode -
KW ABB/Equivalent 2.00 No. 350,000.00 700,000.00
2.00 PV = 21 KW Solar Panels (Solar 305 Watts) as per specifications and
approved by the Engineer In-Charge 70.00 No. 23,180.00 1,622,600.00
3.00 GI/Concrete PV Mountings structure and civil works complete in all
respects 35.00 No. 7,000.00 245,000.00
4.00 Solar DC Wiring and DB Box and Accessories 1.00 Lump-Sump 135,000.00 135,000.00
Total Amount (Rs.) 2,702,600.00
5.00 Transportation For Punjab Lump-Sump 1.00 Lump-Sump 20,000.00
7.00 Installation charges 1.00 Lump-Sump 45,000.00
Total Amount (Rs.) Total 2,767,600.00
III. SOLAR SOLUTION FOR 6HRS DAYTIME OPERATION AND *2HRS OF BACKUP FOR 5 KW OF UTILITIES LOAD
1.00 6.7 KW, 24V Solar Panel: Poly Crysralline: AS per Specifications 22.00 No. 23,180.00 509,960.00
2.00 10KW, 48V, Hybrid Inverter: as per specification, approved by the
Three Phase engineer In charge 1.00 No. 400,000.00 400,000.00
3.00 200Ah, 12 V Dry Batteries: as per specification, approved by the
engineer in charge 8.00 No. 65,000.00 520,000.00
4.00 MS Powder Distribution box & Accessories (5 breakers): Legrand & Sez
Coated or Equivalent approved by the Engineer 1.00 No. 35,000.00 35,000.00
5.00 G/Iconcrete Panel Mounting structure and civil works complete in all
respects 11.00 No. 7,000.00 77,000.00
6.00 6 mm & Cables as per specification, complete in all respect
16mm 1.00 Lump-Sump 28,000.00 28,000.00
7.00 Installation charges 1.00 Lump-Sump 35,000.00 35,000.00
8.00 Transportation 1.00 Lump-Sump 15,000.00 15,000.00

Total Amount (Rs) 1,619,960.00


Total Cost of Solar System 7,337,040.00

Note: Number of pannels has been calculated as per pump and utilities load seprately and not on inverter rating.
LKP2
SUB HEAD NO-9: SOLAR SYSTEM
I. VFD BASED SOLAR SYSTEM FOR TUBE WELLS
Sr.No Specification Description of Items Unit Qty Rate Amount

1.00 3 Phase, VFD/Solar Pump Inverter with MPPT -Dual Supply Mode -
40KW ABB/Equivalent 1.00 No. 600,000.00 600,000.00
2.00 PV = 40 KW Solar Panels (Solar 305 Watts) as per specifications and
approved by the Engineer In-Charge 138.00 No. 23,180.00 3,198,840.00
3.00 GI/Concrete PV Mountings structure and civil works complete in all
respects 69.00 No. 7,000.00 483,000.00
4.00 Solar DC Wiring and DB Box and Accessories 1.00 Lump-Sump 300,000.00 300,000.00
Total Amount (Rs.) 4,581,840.00
5.00 Transportation For Punjab Lump-Sump 1.00 Lump-Sump 40,000.00 40,000.00
7.00 Installation charges 1.00 Lump-Sump 85,000.00 85,000.00
Total Amount (Rs.) 4,706,840.00
II. VFD BASED SOLAR SYSTEM FOR FEED PUMPS
1.00 3 Phase, 30 VFD/Solar Pump Inverter with MPPT -Dual Supply Mode -
KW ABB/Equivalent 2.00 No. 500,000.00 1,000,000.00
2.00 PV = 31.7 KW Solar Panels (Solar 305 Watts) as per specifications and
approved by the Engineer In-Charge 104.00 No. 23,180.00 2,410,720.00
3.00 GI/Concrete PV Mountings structure and civil works complete in all
respects 52.00 No. 7,000.00 364,000.00
4.00 Solar DC Wiring and DB Box and Accessories 1.00 Lump-Sump 195,000.00 195,000.00
Total Amount (Rs.) 3,969,720.00
5.00 Transportation For Punjab Lump-Sump 1.00 Lump-Sump 30,000.00 30,000.00
7.00 Installation charges 1.00 Lump-Sump 55,000.00 55,000.00
Total Amount (Rs.) 4,054,720.00
III. SOLAR SOLUTION FOR 6HRS DAYTIME OPERATION AND *2HRS OF BACKUP FOR 5 KW OF UTILITIES LOAD
1.00 6.7 KW, 24V Solar Panel: Poly Crysralline: AS per Specifications 22.00 No. 23,180.00 509,960.00
2.00 10KW, 48V, Hybrid Inverter: as per specification, approved by the
Three Phase engineer In charge 1.00 No. 400,000.00 400,000.00
3.00 200Ah, 12 V Dry Batteries: as per specification, approved by the
engineer in charge 8.00 No. 65,000.00 520,000.00
4.00 MS Powder Distribution box & Accessories (5 breakers): Legrand & Sez
Coated or Equivalent approved by the Engineer 1.00 No. 35,000.00 35,000.00
5.00 G/Iconcrete Panel Mounting structure and civil works complete in all
respects 11.00 No. 7,000.00 77,000.00
6.00 6 mm & Cables as per specification, conplete in all respect
16mm 1.00 Lump-Sump 28,000.00 28,000.00
7.00 Installation charges 1.00 Lump-Sump 35,000.00 35,000.00
8.00 Transportation 1.00 Lump-Sump 15,000.00 15,000.00

Total Amount (Rs) 1,619,960.00


Total Cost of Solar System 10,381,520.00

Note: Number of pannels has been calculated as per pump and utilities load seprately and not on inverter rating.
LKP3
SUB HEAD NO-9: SOLAR SYSTEM
I. VFD BASED SOLAR SYSTEM FOR TUBE WELLS
Sr.No Specification Description of Items Unit Qty Rate Amount

1.00 3 Phase, 20 VFD/Solar Pump Inverter with MPPT -Dual Supply Mode -
KW ABB/Equivalent 1.00 No. 350,000.00 350,000.00
2.00 PV = 22 KW Solar Panels (Solar 305 Watts) as per specifications and
approved by the Engineer In-Charge 74.00 No. 23,180.00 1,715,320.00
3.00 GI/Concrete PV Mountings structure and civil works complete in all
respects 37.00 No. 7,000.00 259,000.00
4.00 Solar DC Wiring and DB Box and Accessories 1.00 Lump-Sump 135,000.00 135,000.00
Total Amount (Rs.) 2,459,320.00
5.00 Transportation For Punjab Lump-Sump 1.00 Lump-Sump 20,000.00 20,000.00
7.00 Installation charges 1.00 Lump-Sump 40,000.00 40,000.00
Total Amount (Rs.) 2,519,320.00
II. VFD BASED SOLAR SYSTEM FOR FEED PUMPS
1.00 3 Phase, 15 VFD/Solar Pump Inverter with MPPT -Dual Supply Mode -
KW ABB/Equivalent 2.00 No. 250,000.00 500,000.00
2.00 PV = 16 KW Solar Panels (Solar 305 Watts) as per specifications and
approved by the Engineer In-Charge 52.00 No. 23,180.00 1,205,360.00
3.00 GI/Concrete PV Mountings structure and civil works complete in all
respects 26.00 No. 7,000.00 182,000.00
4.00 Solar DC Wiring and DB Box and Accessories 1.00 Lump-Sump 120,000.00 120,000.00
Total Amount (Rs.) 2,007,360.00
5.00 Transportation For Punjab Lump-Sump 1.00 Lump-Sump 30,000.00 30,000.00
7.00 Installation charges 1.00 Lump-Sump 35,000.00 35,000.00
Total Amount (Rs.) 2,072,360.00
III. SOLAR SOLUTION FOR 6HRS DAYTIME OPERATION AND *2HRS OF BACKUP FOR 5 KW OF UTILITIES LOAD
1.00 6.7 KW, 24V Solar Panel: Poly Crysralline: AS per Specifications 22.00 No. 23,180.00 509,960.00
2.00 10KW, 48V, Hybrid Inverter: as per specification, approved by the
Three Phase engineer In charge 1.00 No. 400,000.00 400,000.00
3.00 200Ah, 12 V Dry Batteries: as per specification, approved by the
engineer in charge 8.00 No. 65,000.00 520,000.00
4.00 MS Powder Distribution box & Accessories (5 breakers): Legrand & Sez
Coated or Equivalent approved by the Engineer 1.00 No. 35,000.00 35,000.00
5.00 G/Iconcrete Panel Mounting structure and civil works complete in all
respects 11.00 No. 7,000.00 77,000.00
6.00 6 mm & Cables as per specification, conplete in all respect
16mm 1.00 Lump-Sump 28,000.00 28,000.00
7.00 Installation charges 1.00 Lump-Sump 35,000.00 35,000.00
8.00 Transportation 1.00 Lump-Sump 15,000.00 15,000.00

Total Amount (Rs) 1,619,960.00


Total Cost of Solar System 6,211,640.00

Note: Number of pannels has been calculated as per pump and utilities load seprately and not on inverter rating.
LKP4
SUB HEAD NO-9: SOLAR SYSTEM
I. VFD BASED SOLAR SYSTEM FOR TUBE WELLS
Sr.No Specification Description of Items Unit Qty Rate Amount

1.00 3 Phase, 20VFD/Solar Pump Inverter with MPPT -Dual Supply Mode -
KW ABB/Equivalent 1.00 No. 350,000.00 350,000.00
2.00 PV = 22 KW Solar Panels (Solar 305 Watts) as per specifications and
approved by the Engineer In-Charge 74.00 No. 23,180.00 1,715,320.00
3.00 GI/Concrete PV Mountings structure and civil works complete in all
respects 37.00 No. 7,000.00 259,000.00
4.00 Solar DC Wiring and DB Box and Accessories 1.00 Lump-Sump 135,000.00 135,000.00
Total Amount (Rs.) 2,459,320.00
5.00 Transportation For Punjab Lump-Sump 1.00 Lump-Sump 20,000.00 20,000.00
7.00 Installation charges 1.00 Lump-Sump 45,000.00 45,000.00
Total Amount (Rs.) 2,524,320.00
II. VFD BASED SOLAR SYSTEM FOR FEED PUMPS
1.00 3 Phase, 15VFD/Solar Pump Inverter with MPPT -Dual Supply Mode -
KW ABB/Equivalent 2.00 No. 250,000.00 500,000.00
2.00 PV = 16 KW Solar Panels (Solar 305 Watts) as per specifications and
approved by the Engineer In-Charge 52.00 No. 23,180.00 1,205,360.00
3.00 GI/Concrete PV Mountings structure and civil works complete in all
respects 26.00 No. 7,000.00 182,000.00
4.00 Solar DC Wiring and DB Box and Accessories 1.00 Lump-Sump 120,000.00 120,000.00
Total Amount (Rs.) 2,007,360.00
5.00 Transportation For Punjab Lump-Sump 1.00 Lump-Sump 30,000.00 30,000.00
7.00 Installation charges 1.00 Lump-Sump 35,000.00 35,000.00
Total Amount (Rs.) 2,072,360.00
III. SOLAR SOLUTION FOR 6HRS DAYTIME OPERATION AND *2HRS OF BACKUP FOR 5 KW OF UTILITIES LOAD
1.00 6.7 KW, 24V Solar Panel: Poly Crysralline: AS per Specifications 22.00 No. 23,180.00 509,960.00
2.00 10KW, 48V, Hybrid Inverter: as per specification, approved by the
Three Phase engineer In charge 1.00 No. 400,000.00 400,000.00
3.00 200Ah, 12 V Dry Batteries: as per specification, approved by the
engineer in charge 8.00 No. 65,000.00 520,000.00
4.00 MS Powder Distribution box & Accessories (5 breakers): Legrand & Sez
Coated or Equivalent approved by the Engineer 1.00 No. 35,000.00 35,000.00
5.00 G/Iconcrete Panel Mounting structure and civil works complete in all
respects 11.00 No. 7,000.00 77,000.00
6.00 6 mm & Cables as per specification, conplete in all respect
16mm 1.00 Lump-Sump 28,000.00 28,000.00
7.00 Installation charges 1.00 Lump-Sump 35,000.00 35,000.00
8.00 Transportation 1.00 Lump-Sump 15,000.00 15,000.00

Total Amount (Rs) 1,619,960.00


Total Cost of Solar System 6,216,640.00

Note: Number of pannels has been calculated as per pump and utilities load seprately and not on inverter rating.

NIZAM ENERGY
Hybrid Solar Power system at Sahulat Center LPK 1- 11 Nizam
Sr.No. Description Specifications Quantity Amount (Rs.)
1 Solar Panel: Poly Crystalline:As per specifications 945KW, 24V 3 89775
2 Apxert Inverter: Voltronics or Equivalent as per specification 3KW, 24V, PWM 1 35000
3 Dry Batteries (Deep Cycle GEL): Sacred Sun or equivalent as per specification 200Ah, 12V 2 130000
4 Distribution box & Accessories (5 breakers): Legrand & Sez or Equivalent approved by the MS Powder coated 1 18000
Engineer
5 Panel Mounting structure and civil works complete in all respects GI/Concrete 1 10000
6 Cables 6mm & 16mm Lum Sum 18000
7 Installation charges Lum Sum 20000
8 Transportation Lum Sum 10000
9 Led Tube Rods 2 2800
Total Amount (Rs.) 333575