Excel Time Schedule Template

The document provides a 1 week look ahead schedule for the SH16 Causeway Upgrade Project from March 9-14, 2015. It includes 8 tasks such as removing preload material, installing gantry pilling, trimming batters, installing temporary lighting diversions, and installing stormwater drainage. The tasks have assigned resources, materials, quantities, and must be completed according to the target milestones and constraints listed to keep the project on schedule.

Uploaded by

Mukhlish Akhatar
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
257 views

Excel Time Schedule Template

The document provides a 1 week look ahead schedule for the SH16 Causeway Upgrade Project from March 9-14, 2015. It includes 8 tasks such as removing preload material, installing gantry pilling, trimming batters, installing temporary lighting diversions, and installing stormwater drainage. The tasks have assigned resources, materials, quantities, and must be completed according to the target milestones and constraints listed to keep the project on schedule.

Uploaded by

Mukhlish Akhatar
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

SH16 Causeway Upgrade Project (NZTA CA3685) Zone 1 :: Causeway (CH 1200 - 3060) Data Date: 04 March 2015

Zone 1 :: Causeway (CH 1200 - 3060) Data Date: 04 March 2015 - P6 Extracted

Please forward updated plan to Hassan Eliwa by 04:00 pm Friday - [email protected] Page 1 of 6

1 Week Look Ahead Programme


1 Weeks look ahead - W 63

Activity Status
M T W T F S
Constraints / Requirements from others - Work Target
Activity ID Location 1 Weeks Ahead - Task Description (Important Tasks for Upcoming Original Start Finish Resources Name Material Name Quantity Unit that must and can be performed prior to the Milestone Free Float &

10-Mar-15

11-Mar-15

12-Mar-15

13-Mar-15

14-Mar-15
9-Mar-15
weeks) Duration indicator
release of this task to production Ref.

Zone 1 - Causeway (CH 1200 - 3060) 199 10-Jun-14 30-May-15 1 1 1 1 1 1

Zone 1 - Stage 1 to Stage 3B 203 6-Mar-14 21-May-15 1 1 1 1 1 1

Zone 1 - East Bound Works 203 6-Mar-14 21-May-15 1 1 1 1 1 1

A42500 EB Area 9G (Z5-3 & Z1E) (CH 820 - Remove Preload to FL 8 2-Mar-15 10-Mar-15 Earthworks / Remove EWcrw, Type B Cut 1,944 m3 88 A39970 88 1 1 0 0 0 0

A43770 EB Area 9G (Z5-3 & Z1E) (CH 1000) Gantry Pilling (P8) @ 1000 8 9-Mar-15 18-Mar-15 Gantry 88 A39970 88 1 1 1 1 1 1

A42530 EB Area 9G (Z5-3 & Z1E) (CH 820 - Trim Batter 5 12-Mar-15 17-Mar-15 Earthworks EWcrw 88 A39970 88 0 0 0 1 1 1

A42520 EB Area 9G (Z5-3 & Z1E) (CH 820 - Temporary Lighting Diversions (6 No) 3 13-Mar-15 17-Mar-15 Lighting 88 A39970 88 0 0 0 0 1 1

A35900 EB Z1A (CH 2500 - 2740) Install SW drainage (1.24.1 - 1.25.3) + (TD1.5 - 1.26.3 part) 12 06-Mar-15 21-Mar-15 Stormwater SW Drainage, Dcrw 90 m 81 A39970 81 1 1 1 1 1 1

A37510 EB Z1B (CH 2020) Install Stormwater Drainage Outlet 1.48.1 - MH 1.48.2 2 09-Mar-15 10-Mar-15 Stormwater Dcrw 70 A39970 70 1 1 0 0 0 0

A36380 EB Z1C (CH 1340 - 1500) Settlement Period (5 Months - by design) (3 Months) 83 28-Feb-15 21-May-15 Settlement 17 A39970 17 1 1 1 1 1 1
Zone 1

0 0 0 0 0 0

0 0 0 0 0 0

0 0 0 0 0 0

Zone 1 - West Bound Works 51 17-Feb-15 01-May-15 1 1 1 1 1 1

A38390 WB Z1G (CH 1270 - 2000) Earthworks Fill to Cycleway to 250mm below FL SPR (5251m3) @ 150m3/da 35 17-Feb-15 07-Apr-15 Earthworks EWcrw, Type B Fill 5,251 m3 ### A39420 109 1 1 1 1 1 1

A42830 WB Z1G (CH1560-1860) Bullk bag wall 300m (1560-1860) 13 02-Mar-15 17-Mar-15 Earthworks EWcrw, LWF Fill 216 ### A39420 109 1 1 1 1 1 1

0 0 0 0 0 0

0 0 0 0 0 0

0 0 0 0 0 0

Structures Works 18 9-Mar-15 27-Mar-15 0 1 1 1 1 1

Causeway Bridge (CB) 18 09-Mar-15 27-Mar-15 0 1 1 1 1 1

Causeway New Bridge (CNB) 18 09-Mar-15 27-Mar-15 0 1 1 1 1 1

A37530 EB Causeway New Bridge (CNB) (CHConstruct Bored Piles Piers (6 Piles @ 3d/Pile) 18 09-Mar-15 27-Mar-15 FH Civil - Crew 2 Piles 6 No 39 A39970 39 0 1 1 1 1 1

A37580 EB Causeway New Bridge (CNB) (CHFRP Abutment FF Insitu Headstock 6 09-Mar-15 13-Mar-15 Structures SCrew 39 A39970 39 0 1 1 1 1 0

Err:504 Err:504 Err:504 Err:504 Err:504 Err:504

NEXT TARGET MILESTONE / TRAFFIC STAGE 0 0 0 0 0 0

A39970 EB Zone 1 (CH 1100 - 2740) Stage 3B Traffic Switch - Rosebank On Ramp / install Gantries 23-Oct-15 34 Weeks Rem. 0 0 0 0 0 0

A39100 Zone 1 - Stage 4A Stage 4A - Divert Rosebank onramp Traffic 23-Oct-15 34 Weeks Rem. 0 0 0 0 0 0

A39420 WB Z1F Z1G (CH 1280 - 3050) Stage 5A Traffic Switch - Rosebank off-ramp WB 03-Nov-15 35 Weeks Rem. 0 0 0 0 0 0

Err:504 Err:504 Err:504 Err:504 Err:504 Err:504

End of April Target New Task due to breakdown/details New Tasks due to change in design
SH16 Causeway Upgrade Project (NZTA CA3685) Zone 1 :: Causeway (CH 1200 - 3060) Data Date: 04 March 2015 - P6 Extracted

Please forward updated plan to Hassan Eliwa by 04:00 pm Friday - [email protected] Page 4 of 6

5 Weeks Look Ahead Programme


5 Weeks look ahead
Constraint Type(s)
64 65 66 67 68

Free foat
5 Weeks Ahead - Task Description (Important Tasks for Upcoming Original Constraints / Requirements from others - Work Who will
Activity ID Location Start Finish Resources Name Material Name Quantity Unit that must and can be performed prior to the do the

16-Mar-15

23-Mar-15

30-Mar-15

13-Apr-15
weeks) Duration

6-Apr-15
release of this task to production RFO?

Pr
M
PI

A
L

I
Zone 1 - Causeway (CH 1200 - 3060) 199 10-Jun-14 30-May-15 1 1 1 1 1

Zone 1 - Stage 1 to Stage 3B 223 06-Mar-14 21-May-15 1 1 1 1 1

Zone 1 - East Bound Works 223 06-Mar-14 21-May-15 1 1 1 1 1

Area 9G Off Ramp Exit (CH 820 - 1140) (GNRI Area 3 + Zone 1 E) 143 01-Sep-14 23-Apr-15 1 1 1 1 1

A43770 EB Area 9G (Z5-3 & Z1E) (CH 1000) Gantry Pilling (P8) @ 1000 8 09-Mar-15 18-Mar-15 Gantry 88 1 0 0 0 0

A42530 EB Area 9G (Z5-3 & Z1E) (CH 820 - Trim Batter 5 12-Mar-15 17-Mar-15 Earthworks EWcrw 88 1 0 0 0 0

A42520 EB Area 9G (Z5-3 & Z1E) (CH 820 - Temporary Lighting Diversions (6 No) 3 13-Mar-15 17-Mar-15 Lighting 88 1 0 0 0 0

A37150 EB Area 9G (Z5-3 & Z1E) (CH 820 - H6 Timber Edge Beam 4 19-Mar-15 23-Mar-15 Earthworks EWcrw 88 1 1 0 0 0

A37170 EB Area 9G (Z5-3 & Z1E) (CH 820 - Remove Stability Berm Wave Bund 2 19-Mar-15 20-Mar-15 Earthworks D50=240 Cut, EWcrw 270 m3 88 1 0 0 0 0

A42510 EB Area 9G (Z5-3 & Z1E) (CH 820 - Bench Into Preload / Fill to Existing Shoulder / Geofabric Wrap RHS (CH 920 10 19-Mar-15 31-Mar-15 Earthworks EWcrw, Type B Fill 2,557 m3 88 1 1 1 0 0

A43780 EB Area 9G (Z5-3 & Z1E) (CH 1000) Gantry Foundation (P8) and Plinths @ 1000 5 19-Mar-15 25-Mar-15 Gantry 88 1 1 0 0 0

A37210 EB Area 9G (Z5-3 & Z1E) (CH 820 - Remove Stability Berm (3150m3 Plugged amount) 7 21-Mar-15 30-Mar-15 Earthworks Type B Cut, EWcrw 3,150 m3 88 1 1 1 0 0

A37620 EB Area 9G (Z5-3 & Z1E) (CH 820 - Remove Stability Berm Coastal Rock D50=520 1 31-Mar-15 31-Mar-15 Earthworks D50=520 Cut, EWcrw 512 m3 88 0 0 1 0 0

A42540 EB Area 9G (Z5-3 & Z1E) (CH 820 - Place Filter Rock D50=240 2 02-Apr-15 07-Apr-15 Coastal Rock EWcrw, D50=240 893 m3 88 0 0 1 1 0

A42550 EB Area 9G (Z5-3 & Z1E) (CH 820 - Coastal Rock Place and Trim D50=520 4 09-Apr-15 13-Apr-15 Coastal Rock EWcrw, D50=520 2,305 m3 88 0 0 0 1 1

A37320 EB Area 9G (Z5-3 & Z1E) (CH 800 - SW Drainage (5.19.1 - 5.19.2) (5.20.1 - 5.20.2) (5.21.1 - 5.21.2) (5.22.1 - 5.2 8 14-Apr-15 23-Apr-15 Stormwater Dcrw 88 0 0 0 0 1

EB Z1A Earthworks and Preload (Ch 2250 - 2750) 30 25-Feb-15 16-Apr-15 1 1 1 1 1

A35900 EB Z1A (CH 2500 - 2740) Install SW drainage (1.24.1 - 1.25.3) + (TD1.5 - 1.26.3 part) 12 06-Mar-15 21-Mar-15 Stormwater SW Drainage, Dcrw 90 m 81 1 0 0 0 0

A35880 EB Z1A (CH 2500 - 2740) Trench and Install Lighting Power Service 3 23-Mar-15 26-Mar-15 Lighting / Utilities Trench 81 0 1 0 0 0

A35690 EB Z1A (CH 2250 - 2500) Trench and Install Lighting Power Service 3 27-Mar-15 30-Mar-15 Lighting / Utilities Trench 81 0 1 1 0 0

A43830 EB Z1A (CH 2500 - 2740) Timber Edging for Swale Works 3 31-Mar-15 02-Apr-15 Earthworks EWcrw 81 0 0 1 0 0

A35890 EB Z1A (CH 2500 - 2740) Form and Complete Drainage Channel 4 07-Apr-15 11-Apr-15 Earthworks EWcrw, SW Drainage 240 m 81 0 0 0 1 0

A43620 EB Z1A (CH 2510) Install New Traffic Signals (CH 2510) 2 07-Apr-15 08-Apr-15 Signals 81 0 0 0 1 0

A43860 EB Z1A (CH 2620) Install Relocated Traffic Sign (16-EB-120A) @ CH 2620 1 13-Apr-15 13-Apr-15 Traffic Sign 81 0 0 0 0 1

A43870 EB Z1A (CH 2500) Install Traffic Sign (16-EB-124A) @ CH 2500 1 14-Apr-15 14-Apr-15 Traffic Sign 81 0 0 0 0 1

A43880 EB Z1A (CH 2460) Install Traffic Signs 3No @ CH 2460 1 15-Apr-15 15-Apr-15 Traffic Sign 81 0 0 0 0 1

A43890 EB Z1A (CH 2410) Install Traffic Sign 1No @ CH 2410 1 16-Apr-15 16-Apr-15 Traffic Sign 81 0 0 0 0 1

EB Z1A Pavement and Traffic Works 4 30-Mar-15 07-Apr-15 0 0 1 1 0

A35720 EB Z1A (CH 2250 - 2500) Cut Pavement Box for Formation (1163m3 Cut 0.410m) 4 30-Mar-15 07-Apr-15 Earthworks Type B Cut, EWcrw 1,163 m3 81 0 0 1 1 0

EB Z1B Trial Embankment (Ch 1770 - 1868) 223 06-Mar-14 16-Apr-15 1 1 1 1 1

A36030 EB Z1B (CH 1770 - 1868) Settlement Period Over Concrete Slab (Ch 1852-1840) and (Ch 1798-1786) - 389 06-Mar-14 29-Mar-15 Settlement 70 1 1 0 0 0

A42860 EB Z1B (CH 1770 - 1868) Geotech Team to confirm Settlement Period 123 27-Nov-14 29-Mar-15 Settlement 70 1 1 0 0 0

A36040 EB Z1B (CH 1770 - 1868) Remove Preload 3 30-Mar-15 02-Apr-15 Earthworks / Remove EWcrw 70 0 0 1 0 0

A36240 EB Z1B (CH 1760 - 1800) Remove Preload of Coastal Rock 4 30-Mar-15 07-Apr-15 Coastal Rock / RemovD50=520 Cut, EWcrw 1,760 m3 70 0 0 1 1 0

A36450 EB Z1B (CH 1770 - 1868) Remove Wave Bund of Coastal Rock 2 30-Mar-15 31-Mar-15 Coastal Rock D50=520 Cut, EWcrw 820 m3 70 0 0 1 0 0

A36050 EB Z1B (CH 1770 - 1868) Form and Pour Concrete Slab 4 07-Apr-15 11-Apr-15 Earthworks 70 0 0 0 1 0
Zone 1

A36060 EB Z1B (CH 1770 - 1868) Curing Time 3 13-Apr-15 16-Apr-15 Earthworks 70 0 0 0 0 1

EB Z1B Earthworks and Preload (Ch 2080 - 2250) 12 23-Mar-15 11-Apr-15 0 1 1 1 0

A36241 EB Z1B (CH 2080 - 2250) Install Stormwater Drainage Outlet 1.22.1 - 1.22.2 and 1.23.1 - 1.23.2 4 23-Mar-15 27-Mar-15 Stormwater Dcrw 70 0 1 0 0 0

A37520 EB Z1B (CH 1900) Install Stormwater Drainage Outlet 1.49.1 - MH 1.49.2 2 28-Mar-15 30-Mar-15 Stormwater Dcrw 70 0 1 1 0 0

A36220 EB Z1B (CH 2080 - 2250) Trench and Install Lighting Power Service 3 31-Mar-15 07-Apr-15 Lighting / Utilities Trench 70 0 0 1 1 0

A38620 EB Z1B (CH 2080 - 2250) Gantry Foundation (P6) @ CH 2080 EB 5 31-Mar-15 08-Apr-15 Gantry 70 0 0 1 1 0

A36230 EB Z1B (CH 2080 - 2250) Form and Complete Drainage Channel 3 09-Apr-15 11-Apr-15 Earthworks EWcrw 70 0 0 0 1 0

EB Z1C Earthworks and Preload (Ch 1340 - 1500) 83 19-Jan-15 21-May-15 1 1 1 1 1

A36380 EB Z1C (CH 1340 - 1500) Settlement Period (5 Months - by design) (3 Months) 83 28-Feb-15 21-May-15 Settlement 17 1 1 1 1 1

EB Z1C Earthworks and Preload (Ch 1650 - 1750) Slip Area 26 20-Feb-15 24-Mar-15 1 1 0 0 0

A39040 EB Z1C (CH 1600 - 1770) Shoulder Fill to Existing Shoulder LWF (~7.0m x 0.9m) (1071m3) @ 250m3/day 5 19-Mar-15 24-Mar-15 Earthworks Type B Fill, EWcrw 1,071 m3 17 1 1 0 0 0

A39050 EB Z1C (CH 1600 - 1770) Shoulder Cap Sand 3 with SPR (~7.0m x 0.6m) (714m3) 5 19-Mar-15 24-Mar-15 Earthworks Type B Fill, EWcrw 714 m3 17 1 1 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

Zone 1 - West Bound Works 51 17-Feb-15 01-May-15 1 1 1 1 1

WB Z1G (Ch 1270 - 2000) South Causeway 51 17-Feb-15 01-May-15 1 1 1 1 1

A38390 WB Z1G (CH 1270 - 2000) Earthworks Fill to Cycleway to 250mm below FL SPR (5251m3) @ 150m3/da 35 17-Feb-15 07-Apr-15 Earthworks EWcrw, Type B Fill 5,251 m3 109 1 1 1 1 0

A42830 WB Z1G (CH1560-1860) Bullk bag wall 300m (1560-1860) 13 02-Mar-15 17-Mar-15 Earthworks EWcrw, LWF Fill 216 109 1 0 0 0 0

A38400 WB Z1G (CH 1270 - 2000) Coastal Rock Place and Trim (D50=320) 18 09-Apr-15 01-May-15 Coastal Rock D50=320, EWcrw 1,100 m3 109 0 0 0 1 1

A38406 WB Z1G (CH 1270 - 2000) Fill to cycleway FL (700m3) @ 150m3/day 6 09-Apr-15 17-Apr-15 Earthworks Type B Fill, EWcrw 700 109 0 0 0 1 1

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

Structures Works 22 9-Mar-15 29-Apr-15 1 1 1 1 1

Causeway Bridge (CB) 22 09-Mar-15 29-Apr-15 1 1 1 1 1

Causeway New Bridge (CNB) 22 09-Mar-15 29-Apr-15 1 1 1 1 1

A37530 EB Causeway New Bridge (CNB) (CHConstruct Bored Piles Piers (6 Piles @ 3d/Pile) 18 09-Mar-15 27-Mar-15 FH Civil - Crew 2 Piles 6 No 39 1 1 0 0 0

A37580 EB Causeway New Bridge (CNB) (CHFRP Abutment FF Insitu Headstock 6 09-Mar-15 13-Mar-15 Structures SCrew 39 0 0 0 0 0

A37560 EB Causeway New Bridge (CNB) (CHFRP Pier CC Insitu Headstock - inc Temporary Support Install 15 31-Mar-15 29-Apr-15 Structures SCrew 39 0 0 1 1 1

0 0 0 0 0

0 0 0 0 0

0 0 0 0 0

Err:504 Err:504 Err:504 Err:504 Err:504 Err:504

Please forward updated plan to Hassan Eliwa by 04:00 pm Friday - [email protected]

Major Milestone / Stage Note that free float to the main traffic switch not to end of April target
End of April Target New Task due to breakdown/details New Tasks due to change in design