100% found this document useful (2 votes)
1K views

Dry Wall Partition-Method Statement

This document provides an inspection and test plan for dry wall partition works for a construction project in Qatar. It outlines the objectives, scope, references, procedures, and records for inspecting and testing the installation of dry wall partitions. The key steps include: (1) obtaining approval for framework and board materials, (2) setting out the partition areas, (3) installing framework per drawings and specifications, (4) completing preceding work, (5) inspecting and approving the installation of boards, (6) applying joint filler and decorative coatings. Records of material approvals, inspections, and checklists will be maintained.

Uploaded by

TAHER AMMAR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views

Dry Wall Partition-Method Statement

This document provides an inspection and test plan for dry wall partition works for a construction project in Qatar. It outlines the objectives, scope, references, procedures, and records for inspecting and testing the installation of dry wall partitions. The key steps include: (1) obtaining approval for framework and board materials, (2) setting out the partition areas, (3) installing framework per drawings and specifications, (4) completing preceding work, (5) inspecting and approving the installation of boards, (6) applying joint filler and decorative coatings. Records of material approvals, inspections, and checklists will be maintained.

Uploaded by

TAHER AMMAR
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 4

QATAR BUILDING ENGINEERING COMPANY

INSPECTION AND TEST PLAN Doc. No. ITP.CS.15


Department QA/QC Rev. 0
Title Dry Wall Partition Works Date 11.11.01

INSPECTION AND TEST PLAN


ITP.CS.15
DRY WALL PARTITION WORKS

REVISION HISTORY

0 Original Issue 11.11.01

Rev. Revision information Date

Originated by Reviewed by Approved by

Swaminathan Ganesan K.Kunhappan Hassan Sahli

Sign: Sign: Sign:

Owner: QBEC Page 1 of 6


QATAR BUILDING ENGINEERING COMPANY
INSPECTION AND TEST PLAN Doc. No. ITP.CS.15
Department QA/QC Rev. 0
Title Dry Wall Partition Works Date 11.11.01

Owner: QBEC Page 2 of 6


QATAR BUILDING ENGINEERING COMPANY
INSPECTION AND TEST PLAN Doc. No. ITP.CS.15
Department QA/QC Rev. 0
Title Dry Wall Partition Works Date 11.11.01

DRY WALL PARTITION WORK

1.0 OBJECTIVE

1.1 To describe the inspection and test procedure for erection of dry wall partition
works for the contract no GTC.101/ED/01 Engineering, Procurement,
Installation and Commissioning (EPIC) of Ras Laffan Utilization Project
Buildings and utilities and support service Phase 1-Utilities.

2.0 SCOPE

2.1 Applicable to the dry wall partition work in office buildings at Service Base Area,
Service Berth Area.

3.0 REFERENCE

3.1 Architectural requirements


3.2 Manufacturers recommendations
3.3 Project Approved Drawings

4.0 PROCEDURE

4.1 Approval for the materials like framework, partition boards, including fixtures
have to be taken from QP prior to proceed for actual work.

4.2 Setting out of the areas where dry wall partitions have to be erected has to be
done and the approval from QP has to be obtained to proceed further.

4.3 Framework material has to be selected based on approved drawings,


Architectural specifications and should be fixed as per manufacturers
recommendations.

4.4 All the succeeding activities like electrical & telephone conduiting wiring and
other M&E recess are to be completed successively.

4.5 QP clearance has to be obtained before proceeding with fixing of partition


boards.

4.6 Based on architectural requirement the selection of the boards are to be made.
They must be damage free and have required thickness.

4.7 The boards are to be fixed to the frame in position, true to line and level.

Owner: QBEC Page 3 of 6


QATAR BUILDING ENGINEERING COMPANY
INSPECTION AND TEST PLAN Doc. No. ITP.CS.15
Department QA/QC Rev. 0
Title Dry Wall Partition Works Date 11.11.01

4.8 All the joints are to be filled with approved sealer tapes, putty and the
decorative coat to be applied.

5.0 Records :

5.1 Material approval report.

5.2 Inspection reports.

5.3 Checklist.

Owner: QBEC Page 4 of 6

You might also like