100% found this document useful (1 vote)
330 views

Rowad - Installation Procedure For HDPE

This document provides a method statement for installing HDPE and LLDPE geomembrane. It discusses manufacturing quality control, delivery and handling procedures, subgrade preparation, panel installation, welding, and inspection/testing. The goal is to ensure the geomembrane is installed according to specifications to provide an effective barrier. Key steps include inspecting materials, laying out panels, welding seams, and performing non-destructive and destructive tests to identify and repair any defects.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
330 views

Rowad - Installation Procedure For HDPE

This document provides a method statement for installing HDPE and LLDPE geomembrane. It discusses manufacturing quality control, delivery and handling procedures, subgrade preparation, panel installation, welding, and inspection/testing. The goal is to ensure the geomembrane is installed according to specifications to provide an effective barrier. Key steps include inspecting materials, laying out panels, welding seams, and performing non-destructive and destructive tests to identify and repair any defects.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

METHOD STATEMENT

For the Installation of HDPE and LLDPE Geomembrane

Please Note : This document is generic only and for use only on projects where Rowad itself is directly
involved with the Installation work on site .
If the document is used as a reference by 3rd or other parties any comments herein which relate to Rowad
Obligations and actions strictly do not apply unless otherwise agreed to in writing.

Contacts :
Website: www.rowadgeo.com
Enquiries: [email protected]
Telephone: 00966 (0)13 812 1360

P. O. Box 14164 Dammam 31424. Kingdom of Saudi Arabia


Road No. 42, 2nd Industrial City, Dammam, Kingdom of Saudi Arabia

(DOC MS. Dated 01 October 2016 Version 05 )


Table of Contents
SECTION A - INTRODUCTION
Quality Statement........................................................................................................
Organization ................................................................................................................

SECTION B MANUFACTURING QUALITY CONTROL


HDPE and LLDPE Geomembrane Quality Control .....................................................
Raw Materials..............................................................................................................
Geomembrane Testing................................................................................................
Extrusion Rod ..............................................................................................................
Storage and Handling..................................................................................................
Flowchart Geomembrane Quality Control Program .................................................

SECTION C METHOD STATEMENT


HDPE and LLDPE Geomembrane Quality Control .....................................................
Delivery, Storage and Handling ..................................................................................
On-Site Material Inspection .........................................................................................
Panel Identification and Layout ...................................................................................
Equipment ...................................................................................................................
Subgrade Preparation .................................................................................................
Anchoring ....................................................................................................................
Deployment .................................................................................................................
Panel placement..........................................................................................................
Preparation for Welding...............................................................................................
Welding Procedures ....................................................................................................
Seam Inspection and Repair .......................................................................................

SECTION D INSTALLATION QUALITY ASSURANCE


Conformance Testing ..................................................................................................
Non-Destructive Testing..............................................................................................
Destructive Testing......................................................................................................
Defects and Repairs....................................................................................................
Geomembrane Acceptance ........................................................................................
Flowchart Geomembrane Welding and Installation .................................................

SECTION E ROWAD STANDARD MATERIAL SPECS & MANUFACTURING QC REQUIREMENTS

SECTION F ROWAD STANDARD INSTALLATION QC & QUALITY ASSURANCE REQUIREMENTS

SECTION G SITE SPECIFIC REQUIREMENTS

CONVERSIONS USED in this MANUAL:

40 mil = 1.0 mm

1 inch = 25.4 mm

1 foot = 304.8 mm

Degree Fahrenheit to Centigrade = (F-32) x 5/9 = C

1 Psi = 6.894 kPa~


SECTION A

INTRODUCTION

Qua lity S t a t e m e n t
Rowad Geo is dedicated to an objective of continuous commitment to quality. This
dedication begins with the manufacture of the geomembrane material and ends only
when our customer has accepted the liner. The employees of Rowad Geo, therefore,
endorse and require a policy of Total Quality. This policy is based on the principle that
quality is the fundamental responsibility of every department and is carried out by each
person in that department.
Programs and procedures designed to implement this quality principle are developed by
the Quality Control Department and are utilized by every employee of the Company.
Rowad Geo laboratories are accredited by the Geosynthetic Accreditation Institute Lab
Accreditation Program (GAI-LAP). Rowad Geo Manufacturing and Installation processes
are ISO 9001:2008 registered.

Organi zati on
Persons performing quality-related functions have sufficient authority and organizational
freedom to: (1) identify quality programs; (2) initiate, recommend or provide solutions
through designated channels; (3) verify implementation of solutions; (4) control further
work when required. The person responsible for defining and measuring the overall
effectiveness of the Quality Program is the Quality Control Manager.
Key personnel include the Chairman, General Manager Operations, Manufacturing
Manager, Quality Control Manager, Product Development Manager, Regional
Managers, Project Managers, and the Safety Manager. Resumes of key personnel are
provided when requested or required by project specifications.
SECTION B

M ANUFACTURING QUALITY CONTROL

1. HDPE and LLDPE Geomembrane Quality Control


1.1 Rowad Geo manufactures HDPE (High Density Polyethylene) and LLDPE (Linear Low
Density Polyethylene) liner material in rolls for specific projects. Rowad Geo standard
quality control specifications are documented in Section E. Site specific requirements, if
any, are documented in Section G.
1.2 The geomembrane shall consist of quality resins designed and manufactured specifically
for the purpose of this work, as satisfactorily demonstrated by prior use. The
geomembrane shall be high density polyethylene (HDPE) or linear low density
polyethylene (LLDPE). The geomembrane liner will be manufactured from first quality
resins containing no plasticizers, fillers, recycled polymers, or extenders. Carbon black is
normally added to provide ultraviolet resistance, and other additives to provide thermal
stability. If a color other than black is specified then color concentrates and other
ultraviolet inhibitors will be added in place of carbon black.
1.3 The geomembrane shall be manufactured as a continuous sheet 8m wide. The roll
length shall vary according to thickness. ( please note these lengths are indicative only
and may vary from project to project depending upon requirements)

Thickness 0.5mm 0.75mm 1.0mm 1.5mm 2.0mm 2.5mm 3.0mm


Length (Smooth ) 350m 225m 170m 110m 80m 70m 50
One side texture 200m 150m 100m 80m 60m 50
Double side texture 175m 125m 90m 70m 50m 40

All rolls shall be identified with a unique roll number printed on a label affixed to the inside
and outside of the roll showing manufacturer, thickness, and material type (HDPE or
LLDPE).
1.4 The geomembrane shall be either smooth-surface or textured surface material. Textured
surface geomembrane shall be manufactured so that the surface irregularities are on one
side or both sides of the sheet.
2. Raw Materials
2.1 The resin shall be designed and manufactured specifically for the intended purpose.
Tests shall be performed by the resin manufacturer and results provided to Rowad Geo.
When the resin is delivered, it shall be tested to verify that it meets the required
specification.
2.2 Test results shall be recorded on the relevant form.
2.3 The resin shall be a Rowad Geo. standard product or an approved equal.
3. Geomembrane Testing
3.1 Geomembrane is tested at the frequencies indicated on Rowads standard material
specification sheets (Section E) unless modified by site-specific project requirements
(Section G).
3.2 Test results are recorded on the relevant form. Test results shall refer to the relevant roll
number.
4. Extrusion Rod
4.1 Extrusion rod is tested at the frequencies indicated on Rowads standard material
specification sheets (Section E) unless modified by site-specific project requirements
(Section G).
SECTION B

4.2 Test results shall be recorded on the relevant form.


5. Storage and Handling
5.1 Rolls of material are handled with equipment that will not damage the membrane. Fabric
straps are attached to the rolls of material to be used for unloading at the job site.
5.2 The storage area shall be reasonably flat and free of sharp rocks or other objects that
could damage the material.
SECTION B

Geomembrane Quality Control Program

Review resin
vendor Certs

Meets No
specifications? reject resin!

Yes

Sample resin for


inspection/testing

No Meets
Reject resin! specifications?

Yes

Release resin for


sheet production

Monitor
Production

Forming Surface
Thickness
behavior appearanc
e

No
Acceptable? Reject sheet!

Yes

Sample sheet for


inspection/testing

Meets
No
Reject roll! specifications?

Yes

Delivery
approval!
SECTION C

METHOD STATEMENT
(Generic Unless Otherwise Stated)

1. HDPE and LLDPE Geomembrane Quality Control


1.1 Rowad Geo installs HDPE (High Density Polyethylene) and LLDPE (Linear Low Density
Polyethylene) geomembranes.
2. Delivery, Storage and Handling
2.1 Prior to unloading, the handling equipment is inspected to verify that it will not damage
the material. Fabric straps or other approved apparatus are used for handling of material.
2.2 Rolls must be examined upon unloading to insure that there is no damage to the material
and to assure that the correct material for the job has been received.
2.2 The storage area must be secure to prevent vandalism and thefts and must be such that
rolls are not likely to be damaged by passing vehicles. The storage area shall be such
that continuous contact with water is minimized. The storage area shall be smooth, flat
and free of rocks or other objects that could cut or puncture the liner. Rolls of
geomembrane do not need protection from normal weather conditions.
3. On-site Material Inspection
3.1 Identification labels on material rolls shall be inspected and roll numbers recorded for
future documentation. The roll number is unique and shall be used to identify the roll in
QC testing and to determine which panels are cut from an individual roll.
4. Panel Identification and Layout
4.1 As part of the initial job planning a panel layout drawing shall be prepared that shows
how rolls of liner material may be assembled and joined to form the finished liner. Each
panel of liner shall be assigned a number for future reference.
4.2 Proposed Panel Layout Drawings are intended as a guideline, during Project Planning, to
indicate the basic layout concepts and allow for feedback between the Owner, Liner
Installer, Engineer, etc. Actual finished Panel Layout (i.e. As-Built) may differ from the
proposed panel layout due to field evaluations of actual site conditions. Such conditions
may include considerations for construction coordination between contractors, weather
(i.e. wind direction), minimization of field seaming and miscellaneous other factors.
5. Equipment
5.1. Welding Equipment: The Geomembrane Contractor shall provide welding equipment
showing extrudate temperature (extrusion welder), wedge temperature (wedge welder) or
nozzle temperature (hot air). Sufficient equipment shall available to avoid delaying work,
and shall be supplied by a power source capable of providing constant voltage under a
combined-line load. Generators with rubber tires are allowed on the geomembrane.
Prior to placement on the geomembrane, tires should be inspected to assure that there
are no sharp objects adhered to them that could result in damage to the geomembrane.
Scrap membrane should be placed under the generator to ensure that any spilled fluids
will not come into contact with the geomembrane.
5.2. Punch Press: The Geomembrane Contractor shall provide a punch press for the on-site
preparation of specimens for testing.
5.3. Field Tensiometer: The Geomembrane Contractor shall provide a tensiometer for on-site
shear and peel testing of geomembrane seams. The tensiometer shall be in good
working order, built to ASTM specs, and calibrated within one year. The tensiometer
shall be motor driven and capable of a 2 and 20 in/min jaw separation rate. It shall be
capable of measuring the force exerted between the jaws and have a digital readout.
SECTION C

5.4. Vacuum Box: The Geomembrane Contractor shall provide a vacuum box for on-site testing
of geomembrane seams. The vacuum box shall have a transparent viewing window on top
and a soft closed-cell neoprene gasket attached to the bottom. The housing shall be rigid
and equipped with a bleed valve and vacuum gauge. A separate vacuum source shall be
connected to the vacuum box. The equipment shall be capable of inducing and holding a
vacuum of 5 psi.
5.5. Gauge and Air Pump: The Geomembrane Contractor shall provide an air pump capable of
achieving a minimum of 35 psi. Gauges must be capable of registering at least 35 psi.
5.6. Miscellaneous Equipment: Small tools will include hook blade utility knives, scissors with
rounded points and silicone or rubber rollers. Step up transformer per generator will be used
to assure constant voltage to the welding equipment as necessary.
6. Subgrade Preparation
6.1 The subgrade is prepared by the owner or by the contractor according to the
specifications. The surface must be smooth, with no rapid changes of grade such as
steps or settlement next to concrete structures. All slopes and surfaces must be
compacted to ensure the integrity of the membrane. While the geomembrane is
designed to withstand some differential settlement, an analysis of these areas must be
made by the engineer to ensure that the stresses on the membrane are acceptable.
6.2 The surface of the subgrade must be free of sharp rocks, penetrating debris or other
appurtenances that could damage the membrane. Typically, finished subgrade is
achieved using a smooth steel drum roller or other method as approved by the Project
Engineer. Under certain conditions a cushion geotextile can be evaluated and approved
for use by the Project Engineer, to provide protection for the geomembrane.
6.3 After acceptance by the Owners Representative, Rowad shall perform a visual
inspection of the subgrade surface to determine that it is suitable to be lined. Rowads
acceptance of the finished subgrade surface shall be recorded on the relevant form.
7. Anchoring
7.1 The membrane is to be anchored as shown on the plans and approved drawings. The
anchor trench is excavated by the owner or by the contractor as shown on the approved
contract drawings. Attention must be paid to the stability of the soil being excavated.
Excavation of trenches should be coordinated with the geomembrane installation to avoid
excessive exposure to weathering prior to installation. Trenches that collapse,
deteriorate, or become saturated, may require rework by the contractor.
7.2 Upon placement of geomembrane panels, the anchor trench must be partially backfilled
by the contractor immediately to prevent panel slippage, wind uplift or blowout that could
result in liner damage. If immediate backfilling of trenches is not possible, sandbag
loading should be used to provide temporary ballast. Final backfilling and compaction, by
the Owner or contractor, should commence only after the geomembrane has had time to
dissipate manufacturing orientation and settle into its final position. Final backfilling of the
anchor trench shall be completed per the specification.
8. Deployment
8.1 Geomembrane panels shall be unrolled using methods that will not damage, stretch, or
crimp the geomembrane and shall protect the underlying subsurface from damage. The
methods used shall minimize wrinkles. If necessary a smooth piece of geomembrane may
be used as a rub sheet to facilitate deployment of geosynthetic layers. The rub sheet does
not need to run the entire length of the slope, only the top crest and first few feet of the
slope need to be covered to facilitate deployment. Ballast that will not damage the
geomembrane shall be used to prevent uplift due to wind.
SECTION C

8.2 Panels shall be oriented perpendicular to the line of the slope crest (i.e., down and not
across slope). If panels must be placed across slopes then they shall be shingled such
that the upper panel is overlapped above the lower panel. For slopes steeper than 10:1,
cross seams parallel to the crest or toe will be located at least 1 foot from the crest or the
toe of slope or at such a distance where a fully integrated weld can be performed in
restricted locations. Cross seams on slopes should be minimized, but are acceptable
when staggered throughout the slope.
8.3 Each panel deployed shall be assigned a simple and logical identifying code consistent
with the submitted panel layout drawings. No more panels shall be deployed in one day
than can be welded during that same day. Tack welding may be acceptable as a
temporary measure. However, when possible tack welded panels shall not be left
overnight.
8.4 Personnel walking on the geomembrane shall not wear types of shoes that could damage
the geomembrane. Smoking shall not be permitted on the geomembrane.
8.5 Vehicular traffic on the geomembrane shall be minimized. Equipment shall not damage
the geomembrane by handling, trafficking, leakage of hydrocarbons, or any other means.
The geomembrane surface shall not be used as a work area, for preparing patches,
storing tools and supplies, or other uses. A protective cover may be spread out as a
work surface.
8.6 Rowad uses low ground pressure devices such as ATVs and tractors to help facilitate
deployment over other geosynthetic layers and to reduce the potential for strain related
injuries among its field personnel. Low ground pressure devices are machines with less
than 7 psi per wheel when carrying a driver weighing approximately 150 lbs. The typical
specification for equipment working directly over the geosynthetics placing cover material
is 7 psi. Using low ground pressure machines also results in a safer work environment.
Utilizing low ground pressure machines also results in a safer work environment.
8.7 Sufficient material shall be provided to allow for geomembrane shrinkage and contraction
and to avoid bridging. The Superintendent shall determine the amount of additional
geomembrane required for compensation based on the weather conditions during
installation.
9. Panel Placement
9.1 When possible the geomembrane should be deployed according to the previously
approved panel layout drawing, when such drawings are available. Site conditions such
as wind and requirements of the owner or earthwork contractor may require changes to
the panel layout sequence. The installation should be started at the highest elevation so
that any rainfall runs off to the lower part of the impoundment, thus preventing water from
getting under the geomembrane. W hen possible liner should also begin at the upwind
side to minimize wind lift. When in position, panels shall be visually inspected to identify,
and to allow for subsequent repair, any damage that may have occurred during handling
or installation.
9.2 Geomembrane rolls are unrolled using a front-end loader or forklift, and specially
designed lifting apparatus that is attached to the bucket or forks of the equipment. This
enables the panels to be placed in position without heavy equipment running on
the material. Panels are deployed to allow a minimum overlap of three inches.
When possible, final overlap should be oriented to create a shingle effect in the
down slope/grade direction.
10. Preparation for Seaming
10.1 The seam numbering system shall be compatible with the panel coding system. During
welding operations, at least one Senior Technician shall be present and shall provide
supervision over other welders.
SECTION C

10.2 The surface of the geomembrane shall be wiped with a clean cloth to remove moisture,
dust, dirt, debris, or other foreign material. Solvents or adhesives shall not be used.
Panels shall overlap by a minimum of three inches for all welds.
10.3 Fish mouths or wrinkles at seam overlaps shall be cut to achieve a flat overlap. The cut
fish mouths or wrinkles shall be welded where the overlap is more than three (3) inches.
When there is less than three inches overlap, an oval or round patch extending a
minimum of three inches beyond the cut in each direction shall be used.
10.4 Seams shall be welded only when ambient temperature is between 32F and 110F as
measured six inches above the geomembrane surface unless other limits are approved,
in writing, by the Engineer (see Section G for site-specific requirements, if any). For
temperatures below 32F, the following procedures shall be utilized:
10.4.1 When the weather is clear and sunny with gentle winds (10 mph or less) wedge
welding can normally be performed at an ambient temperature between 15F and
32F (liner temperature is usually warmer than ambient due to the sun) without
additional provisions other than adjusting the welding machine. Welding
temperatures and machine speeds are adjusted to compensate for cloudy
weather and higher winds.
10.4.2 For temperatures between 5F and 15F some means of preheating the liner
other than that provided by the welding machine is needed. Types of preheating
(space heaters, temporary shelters and combinations of the two) will be
determined by the individual job conditions.
10.4.3 The following variables are measured and recorded:
Liner Temperature (surface contact thermometer)
Ambient Temperature (6 above liner)
Wedge Temperature During W elding
Wedge Speed
Temperature Set Point of Wedge
10.4.4 The wedge temperature during welding must be monitored by the machine
operator to insure temperature consistency. 10.4.5 No welding can take
place when it is snowing, sleeting, or raining. Snow and ice must be removed from the
liner prior to welding. Snow removal from the site area is the responsibility of the owner or
contractor.
10.5 Trial Welds: Trial welds shall be performed on geomembrane samples to verify welding
equipment operations and performance of seaming methods and conditions. Minimum of
two trial welds per day or shift per welding apparatus will be made, one made prior to the
start of work and one completed mid shift. Additional trial welds shall be made as
necessary when air temperature changes by more than 10F or winds change by more
than 8 mph or in accordance with site-specific requirements, if any (see Section G).
Welds shall be made under the same surface and environmental conditions as the
production welds (i.e., in contact with geomembrane subsurface and similar ambient
temperature).
10.6 Trial Weld Testing: Samples shall be at least five feet long and one foot wide with the
seam centered lengthwise. Five, one inch wide tests strips shall be cut from the trial
weld. Each of the specimens shall be tested in the field for peel. A trial weld specimen is
considered to pass when the peel test results meet or exceed the project specifications.
For double-wedge welding, both welds shall be individually tested and both shall be
required to pass in peel. The trial seam tests must pass before welding on the
geomembrane is started. Remaining samples shall be retained for future testing.
10.7 The primary method of welding shall be wedge welding and extrusion welding. Hot air
seaming shall be used for repairs and detailing.
SECTION C

11. Welding Procedures


11.1 Fusion (Wedge) Welding:
11.1.1 Fusion (wedge) welding utilizes a metallic wedge heated to the required
temperature and guided between the lapped edges of adjacent panels. The
welding machine is aligned and set to the required temperature (typically 325
to 400C depending on the material thickness and site conditions), and the
machine travel speed is set to the required setting for the applicable material
thickness. The wedge heats the area of the two panels to be joined to the
required temperature. Rollers immediately following the wedge exert the
required pressure on the heated area to obtain fusion between the adjoining
panels.
11.1.2 Welding apparatus shall be automated, vehicular-mounted, and equipped with
devices giving applicable temperatures and pressures.
11.1.3 As the welding progresses, the welding operator takes care to assure correct
machine speed and alignment.
11.2 Extrusion Welding:
11.2.1 Adjacent panels shall be tack bonded together using procedures that do not
damage the geomembrane, allow required tests to be performed, and are not
detrimental to final seaming. Welding apparatus shall be free of heat-degraded
extrudate before welding. The geomembrane surface shall be abraded to a
maximum inch beyond the weld bead area, using a disc grinder, or equivalent,
not more than hour before welding. The top edges of geomembrane 60 mil or
greater shall be beveled 45 using a hand held grinder. The ends of all seams,
which are more than five minutes old, shall be ground when restarting the weld.
Grinding depth shall not exceed ten percent of the liner thickness.
11.2.2 Extrusion welding entails placing a hot extrudate on top of the preheated lap of
two adjoining panels while simultaneously applying pressure, and utilizes a
welding rod made from the same type of resin as the membrane. The welding
rod is melted inside the extrusion welding machine to form the hot extrudate.
Preheating of the sheet in the weld area is performed by the extrusion welding
machine.
11.2.3 The Teflon shoe (that determines the profile of the molten extrudate) is checked
for correct dimensions. The temperature controllers are then set to appropriate
temperatures and the machines are allowed to heat to the machine temperature
set point.
11.2.4 When the seam area is prepared, the welding machine is positioned so the
nozzle and the shoe are flat on the seam. As the machine is moved forward,
care is taken to assure that the point of the preheat nozzle is centered on the
edge of the top sheet and is as close to the sheet as possible.
11.2.5 As the welding progresses, the welding operator takes care to assure correct
machine speed and alignment.
11.3 Hot Air Seaming:
11.3.1 Hot air seaming utilizes a resistance heater, blower and temperature controller to
force hot air between the lapped edges of the adjoining geomembranes. The hot
air melts the opposing sheet surfaces. Pressure is immediately applied to bond
the two sheets.
11.3.2 Hot air seaming is commonly used for repairs and detailing tasks.
SECTION C

12. Seam Inspection and Repair


12.1 After welding, a close visual inspection of the seam is made. This is done as soon as
possible after the weld has been completed. The inspection is to include weld alignment.
For extrusion welding, the weld thickness and profile is inspected.
12.2 Defective areas are marked and repaired then the repairs are inspected and approved.
This inspection/repair process is carried out in a systematic manner as soon as possible
to ensure that no defective area goes unrepaired.
SECTION D

CONSTRUCTION QUALITY ASSURANCE


1. Conformance Testing (By CQA Consultant)
1.1 When conformance testing of the geomembrane material is required and the samples
have not been taken in the plant, samples shall be obtained in the field at a frequency
defined in the project specifications. The CQA Consultant shall obtain samples and
forward them to their laboratory. Care shall be taken not to damage the geomembrane
during sampling. The sample shall be cut three feet long (excluding the first three feet of
the roll) by width of roll. The machine direction shall be marked on the samples with an
arrow.
2. Non-Destructive Testing
2.1 Non-destructively test all field seams over their full length using vacuum box testing, air
pressure testing for fusion (wedge) welded seams only, or spark testing. Generally non-
destructive testing is carried out as the seaming progresses.
2.2 Rowad standard testing parameters and requirements are documented in Section F.
Site-specific requirements, if any, are documented in Section G.
2.2 Vacuum box testing shall conform to the following requirements:
2.2.1 The equipment shall include two vacuum box assemblies consisting of the
following: a rigid housing, a transparent viewing window, a soft neoprene gasket
attached to the bottom, a vacuum gauge, a vacuum device equipped with
pressure control, a rubber pressure/vacuum hose with fittings and connections, a
soapy solution and an applicator.
2.2.2 Testing shall conform to the following procedure: Brush soapy solution on seam.
Place vacuum box over the wetted area. Ensure that a leak-tight seal is created.
Apply a vacuum of approximately 5 psi. Examine the geomembrane through the
viewing window for the presence of soap bubbles for not less than ten seconds.
All areas where soap bubbles appear shall be marked and repaired as described
in this section.
2.3 Air pressure testing for fusion (wedge) welded seam with an enclosed space,
shall conform to the following requirements:
2.3.1 The equipment shall consist of the following: an air pump (manual or motor
driven) equipped with pressure gauge capable of achieving pressure over 35 psi,
a rubber hose with fittings and connections, a sharp hollow needle and a
pressure gauge. Sufficient cushioning (i.e. rubsheet, wheels, padding, etc.)
should be provided under the air pump equipment to protect the geomembrane.
2.3.2 Testing shall conform to the following procedure: Seal both ends of the seam to
be tested. Insert needle into the channel created by the double-wedge weld.
Energize the air pump to a minimum pressure as indicated in Section F, close the
valve, and sustain the pressure for five minutes. If pressure loss exceeds the
allowable drop or does not stabilize, locate faulty area and repair as described in
this section. After test completion, the air channel at the opposite end of the
seam from the air insertion point should be punctured to release the air. This will
assure there is no channel blockage and that the seam has been tested along its
entire length. If blockage is present, locate and test seam on both sides of
blockage. Remove needle and repair penetration holes by extrusion welding as
necessary.
SECTION D

2.4 Spark testing shall be used for those extrusion seams that are unable to be tested by
a vacuum box.
2.4.1 The spark test method consists of placing 24 gauge copper wire at the edge or just
under the top sheet overlap of the two sheets, prior to extrusion welding. After
welding, a spark detector operating at 20,000 volts is run along the weld. If any
pinholes are present, a circuit will be completed through the copper wire and the
spark detector. This will sound an alarm in the detector alerting the operator to the
presence of a defective area. The spark test is typically used for extrusion welded
seams where there is no hazard anticipated from a spark and where there is no
chance of creating a vacuum seal.
2.4.2 There is no immediate danger to human or animal life if a circuit is made through the
spark detector. However, the spark detector should not be used in the presence of
water or excessive moisture.
3. Destructive Testing
3.1 As the welding of the geomembrane progresses, test samples shall be cut from the
finished liner. Defective areas identified by visual inspection such as appearance of
excessive heating, contamination, offset weld, etc. should be marked for subsequent
repair. The owners representative or Rowad shall determine the location of the
destructive samples (see Section F for Rowad standard frequency and Section G for site-
specific frequency, if any). When reasonable, destructive samples should be taken at the
beginning or end of a seam, preferably from areas that will be buried in the trench.
Based upon successful test results and Engineers approval the frequency of testing may
be decreased (see Section G for site-specific requirements, if any). It is in the owners
interest to minimize the number of destructive holes in the liner.
3.2 Both destructive and trial weld samples shall be labeled with the following information:
a) destructive (red label) or trial weld (green label) sample
b) job name and number
c) date sample was welded
d) membrane thickness
e) sample or seam number, if applicable
f) welders name
g) welding machine number
h) ambient temperature at time of welding
3.3 Laboratory Testing (performed by the CQA laboratory): Samples shall be tested in peel
and shear. Minimum acceptable strength to be obtained for these tests shall be in
compliance with Rowads standard testing values (see Section F). If the project
specifications are not in agreement, special considerations will be made between Rowad
and the CQA consultant/owners representative in order to agree upon destructive values
for each individual project (See Section G).
3.4 At least five specimens shall be tested by each test method. Specimens from each
sample shall be selected alternately for testing (i.e., peel, shear, peel, shear, . . .). For
double wedge seam samples, both welds shall be tested in peel. Test results shall be
provided verbally within 24 hours after receiving samples, and in written form within
seven days.
3.5 Failing samples shall be bounded by two locations where samples have passed
destructive tests. For reconstructed seams exceeding 150 feet, a sample taken from
within the reconstructed seam shall also pass destructive testing.
3.6 Prior to the geomembrane being covered by the next layer of geosynthetics or soil,
seams shall exhibit passing results in laboratory testing.
SECTION D

3.7 Immediately repair all holes in the geomembrane resulting from destructive samples.
The continuity of the repair shall be vacuum tested in accordance with this section.
4. Defects and Repairs
4.1 The geomembrane shall be examined for defects, holes, blisters, undispersed raw
materials, and any sign of contamination by foreign matter. The geomembrane surface
shall be clean at the time of examination. Each suspect location shall be repaired and
non-destructively tested. Geomembrane shall not be covered at locations that have not
been repaired.
4.2 Damaged geomembrane shall be removed and replaced with acceptable geomembrane
if damage cannot be satisfactorily repaired.
4.3 Any portion of the geomembrane exhibiting a flaw or failing a destructive or non-
destructive test shall be repaired. Procedures available include:
4.3.1 Patching used to repair large holes (over 3/8 diameter) and tears (over 2 long),
and contamination by foreign matter.
4.3.2 Abrading and re-welding: used to repair small seam sections (less than 12 long).
4.3.3 Spot welding: used to repair small tears (less than 2 long), pinholes, or other
minor, localized flaws.
4.3.4 Capping used to repair large lengths of failed seams.
4.3.5 Removing the unsatisfactory material or seam and replacing with new material.
4.4 Patches or caps shall extend at least 3 beyond the edge of the defect, and all corners of
material to be patched and these shall be rounded to a radius of at least 1. The
geomembrane below caps shall be cut to avoid water or gas collection between the two
sheets.
4.5 Repairs shall be non-destructively tested using methods specified in this section.
Geomembrane Acceptance
Rowad shall retain all ownership and responsibility for the geomembrane until final acceptance by the
owner. Owner will accept the geomembrane installation when the installation is complete and verification
of the adequacy of all field seams and repairs, including associated testing, is complete.
SECTION D

Geomembrane Welding & Installation

Inspect
Subgrade

Inspect Rolls

Test Startup Samples

Meet No
Specifications? Reset Welder

Yes

Test Welds

Destructive Non-Destructive
Testing Testing

Tensile Peel & Spark/Air


Shear Pressure/Vacuum

Meet
No
Repair Specifications?

Yes

Visual Inspection

Quality
Approval!
SECTION E

MATERIAL SPECIFICATIONS AND MANUFACTURING QUALITY


CONTROL REQUIREMENTS

This section contains Rowad Geo, standard material specification sheets. These
sheets include minimum physical property requirements and manufacturing quality
control testing frequencies. Which can be down load from our website?

Rowads manufacturing division will provide material meeting the following requirements
unless superseded by site-specific project requirements (see Section G)
SECTION F

INSTALLATION QUALITY CONTROL AND


QUALITY ASSURANCE REQUIREMENTS

This section contains Rowad Geo, standard values for seam quality and non-destructive
testing parameters
Rowads Construction Division will install material as per the following requirements
unless superseded by site-specific project requirements (see Section G).
Air Pressure Testing
Nondestructive air pressure testing of fusion welded seams shall conform to the following parameters:
Maximum Acceptable Pressure and Pressure Loss

HDPE LLDPE
Thickness Max. Pressure Allowable Loss Max. Pressure Allowable Loss
20-mil 20 psi 5 psi 20 psi 5 psi
30-mil 25 psi 5 psi 25 psi 5 psi
40-mil 30 psi 4 psi 30 psi 4 psi
60-mil 30 psi 3 psi 30 psi 3 psi
80-mil 35 psi 2 psi 35 psi 2 psi
100-mil 35 psi 2 psi 35 psi 2 psi

Destructive Testing
Destructive test samples shall be taken nominally every 500 feet of seam.
The destructive sample shall be 12 wide by 48 long with the seam centered lengthwise. The
sample shall be cut into four (4) parts for Rowads on-site archives, the Owners archives, the CQA
laboratory for testing, and field testing.
Five specimens shall be tested for shear strength and five for peel adhesion. 4 out of 5 specimens
must meet the following minimum requirements to be considered passing.

HDPE Minimum Acceptable Strength (lbs / in. width)

Thickness Shear Strength Peel Adhesion Strength


Wedge Weld Extrusion W eld
40-mil 80 52 45
60-mil 120 78 72
80-mil 160 104 90
100-mil 200 130 120

LLDPE Minimum Acceptable Strength (lbs / in. width)

Thickness Shear Strength Peel Adhesion Strength


Wedge Weld Extrusion W eld
40-mil 44 40 40
60-mil 66 60 60
80-mil 88 75 70
100-mil 110 94 88
SECTION G

SITE-SPECIFIC REQUIREMENTS

This section contains site-specific project requirements including material specifications,


seam quality criteria and non-destructive testing and welding parameters.

These requirements supersede Rowad Geo, standard requirements found in Section E


and Section F.

You might also like