Steel Mill Industrial Training
Steel Mill Industrial Training
AT
NIGERIA
SUBMITTED BY:
OSUDE BENEDICT
SUBMITTED TO:
METIN BILIN
ABSTRACT
The Ajaokuta Steel Company is one of the steel mills, located I the western part
of Nigeria and it was established 1979 and charged with the task of constructing
and operating an integrated iron and steel plant. Ajaokuta Steel plant was
planned to be built in three stages. The first stage of 1.3 million tonnes to
produce long steel products was followed by immediate expansion to 3.6
million tonnes for the production of 1.3 million tons of flat products in addition
to the long products. The third stage is the expansion of the complex to produce
5.2 million tons of various types of finished and semi-finished steel products
including heavy plates and heavy sections. The plant is designed such that it can
be expanded up to 10 million tonnes eventually subject to demand. The steel
complex is almost completed.
2
ACKNOWLEDGEMENT
3
TABLE OF CONTENT
ABSTRACT………………………………………………………………2
ACKNOWLEDGEMENT……………………………………………….…….3
CHAPTER 1
INTRODUCTION………………………………………………………...…….5
CHAPTER 2
CHAPTER 3
PIG-IRON PRODUCTION…………………………………………………..16
ELECTRIC-FURNACE STEEL………………………………………………21
FINISHING PROCESSES…………………………………………………….22
PIPE……………………………………………………………………………22
RED-INGOT…………………………………………………………….……..23
TIN PLATE………………………………………………………………...….25
WROUGHT IRON…………………………………………………………....25
CLASSIFICATIONS OF STEEL……………………………………………..27
Carbon Steels…………………………………………………….……………27
Alloy Steels……………………………………………………………………27
4
High-Strength Low-Alloy Steels………………………………………………27
Stainless Steels………………………………………………………………....27
Tool Steels……………………………………………………………………..28
STRUCTURE OF STEEL………………………………………..……………28
CHAPTER 4
5
CHAPTER 1
INTRODUCTION
Planning for the Nigerian Steel Industry started around 1958 as earlier stated.
The starting point was the search for appropriate local inputs, the characteristics
of which determined the particular technologies that would be adopted. Iron ore
was located at Agbaja, Itakpe and Udi; suitable Limestone at Jakura, Mfamosin
and other parts of the country. Coal deposits were always there at Enugu while
potential coke-able coal was struck at Lafia.
Market surveys were commissioned and the construction of the Kainji Hydro-
electric Dam promised an abundant source of electrical energy. Between 1961
and 1965 many firms from the industrialized nations of the West submitted
proposals for the construction of an integrated Steel Plant in Nigeria. The view,
then, was that the available raw materials could not be used in conventional Iron
and Steel making technologies. The “Strategic Udy Process”, a direct reduction
(DR) process still in the pilot plant stage in the USA, was then considered by
Nigeria. The idea was accepted and a joint venture company, the Nigerian Steel
Associates was formed with Westinghouse and Koppers as the foreign Partners.
This programme failed because it did not prove capable of meeting commercial
scale requirements.
In 1967 a UNIDO survey identified Nigeria as a potential steel Market. This led
to the signing of a bilateral agreement between the defunct Soviet Union and
Nigeria, and, the arrival of Soviet steel experts in Nigeria to conduct a
feasibility study. The experts recommended the Blast Furnace/Basic Oxygen
Furnace (BF/BOF) process of 570,000 tonnes per annum capacity of rolled
products. They also confirmed the availability of raw materials and
recommended further geological surveys. In 1970 a contract was awarded to
TiajPromExport (TPE) of defunct USSR to conduct a study to identify sources
of feedstock, quality and quantity of materials for the proposed integrated iron
and steel plant. By this time the second National Development Plan (1970 –
1975) had envisaged the construction of a 750,000 tonnes per year capacity
Plant.
Apart from Government Ventures there were a few private initiatives in the
lesser capital-intensive steel industry of rolling mills coming up.
6
The Nigerian Steel Development Authority
The Authority was to examine various process routes including natural gas-
based direct reduction processes that require high-grade iron ores, which were
not available in Nigeria. In 1973, the presence of good grade ore (though not of
high-grade quality) was confirmed at Itakpe that led to the NSDA
commissioning TPE to prepare a Preliminary Project Report (PPR) for the
proposed BF/BOF Plant. The PPR was submitted in 1974, scrutinized and
finally accepted in 1975. With the source of Iron Ore confirmed it was proposed
that coking coal would be imported and blended appropriately with local coals.
A three-phased development program (1st phase to produce 1.3 million tonnes,
which will be expanded to 2.6 million tonnes incorporating the flat sheet
production in the 2nd phase, and the third phase to increase capacity to 5.2
million tonnes) was accepted.
The initial product mix proposal suggested 50% long products and 50% flat
products. This was based on the product demand profile revealed by market
surveys. The Government decided that Ajaokuta Steel Plant should produce
only long products in the first stage of 1.3 million tonnes per year, and flat
products in the 2.6 million tonnes expansion which was planned to dove-tail the
first phase completion and this is to be followed by a third phase of 5.2 million
tonnes per annum. This decision was advised by the need to take advantage of
economy of scale since flat-product mills of capacity below 1 million tonnes
were considered uneconomical. An additional consideration was to use the
relatively simpler technology of long-products rolling to rain up an otherwise
virgin and inexperienced Nigerian Workforce of the time.
7
The NSDA was dissolved by the federal Government in 1979 and this
metamorphosed in to several organizations, thus:
The last three establishments are to be fully funded by the Government, through
the Ministry. The rest of the organizations are supposed to be companies that
should be self-funding, because at one time or the other, they had been
incorporated as limited liability companies.
capacity
(per year)
i. Ajaokuta Inter-grated Blast 3 no. 540,000 Bars, rods,
Steel Co. furnace, tons long light
(Public) 4-strand for
Ltd. capacity products sections
blooms
1.35m.ton
Ajaokuta
ii. Alliance Rolling - - 20,000 tons Bars
Steel Co., mill long
Ibadan products
iii. Allied Rolling - - 20,000 tons Bars
Steel Co., mill long
Onitsha products
8
iv. Asiastic Rolling - - 60,000 tons Bars;
Manarin mill long sections
Ind., Ikeja products
v. Continental Mini mill - - 150,000 Bars;
Iron & tons long sections
Steel Co., products
Ikeja
vi. Delta Steel Inter-grated 2 Midrex 3no. 320,000 Bars; rods;
Co., 600 series tons long sections
(Public) 6-strand for
Ovwien/Al Direct products
billets
adja, Reduction
furnaces;
capacity1.0
2 m.t
vii. Federated Mini mill - - 140,000 Bars;
Steel tons long sections
Industry, products
Otta
viii. General Mini-mill - - 50,000 tons Bars
Steel Mill, long
Asaba products
ix. Jos Steel Rolling - - 210,000 Bars, rods
Rolling mill tons long
Company, products
(Public)
Jos
x. Katsina Rolling - - 210,000 Bars, rods
Steel mill tons long
Rolling Co. products
(Public)
Katsina
xi. Kew Metal Mini-mill - - 20,000 tons Bars;
Industries, long sections
Ikorodu products
xii. Kwara Rolling - - 40,000 tons Bars
Commercia long
9
l, Metal mill products
and
Chemical
Industries,
Ilorin
xiii Mayor Rolling - - 220,000 Bars.
Eng. Co., mill tons long sections
Ikorodu products
xiv Metcombe Rolling - - 10,000 tons Bars;
Steel Co., mill long sections
Owerri products
xv. Nigerian Mini mill - - 100,000 Bars
Spanish tons long
Eng. Co., products
Kano
xvi. Nigersteel Mini mill - - 40,000 tons Bars;
Co., Enugu long sections
products
xvii. Oshogbo Rolling - - 210,000 Bars; rods
Steel Co., mill tons long
Oshogbo products
(Public)
xviii. Qua Steel Rolling - - 60,000 tons Bars,
Products, mill long sections
Eket products
xix. Selsametal, Rolling - - 100,000 Bars
Otta mill tons long
products
xx. Union Rolling - - 20,000 tons Bars
Steel Co., mill long
Ilorin products
10
xxi. Universal Mini mill - - 80,000 tons Bars,
Steel Co., long sections
Ikeja products
xxii. Baoyao Rolling - - 20,000 tons Bars
Futurelex, mill long
Abuja products
CHAPTER 2
11
Ariel view of the Ajaokuta steel mill
The Ajaokuta Steel Company is one of the steel mills that were born when the
NSDA was dissolved. This mill is located at the western part of Nigeria and it
was established 1979. The Ajaokuta Steel plant is built in three stages. The first
stage of 1.3 million tonnes to produce long steel products was followed by
immediate expansion to 3.6 million tonnes for the production of 1.3 million tons
of flat products in addition to the long products. The third stage is the expansion
of the complex to produce 5.2 million tons of various types of finished and
semi-finished steel products including heavy plates and heavy sections. The
plant is designed such that it can be expanded up to 10 million tonnes eventually
subject to demand. The Ajaokuta steel mill was tasked with producing services
such as;
(ii) Rods and bars (both high tensile and mild steel varieties),
(v) Flat sheet steels (plain, and galvanized, and also the entire spectrum
classified as flats),
12
INTERIOR VIEW OF THE STEEL MILL
The site of the Ajaokuta mill is like a small community (it is very gigantic). The
first day on site was very interesting and I was excited, I was given a tour of the
facility by my supervisor who is a senior staff of the company. I was to
13
accompany him while he was making his morning trip around the facility upon
an electrical mobile. He put me through a rough sketch of the facility and a bit
of history the rest of the day ended on a better note since I was the new guy
people were quite eager to help.
The company rule is that even if you are a working employee newly employee
to the facility you won’t operate any machinery or participate in the processing
of steel. You will go through six months of just observation and tutoring, it’s
more like a safety measure since every part of the facility is as dangerous as the
other. Every part of the main processing unit is hot!!!
The rest of my first month I was tagged with junior staffs that was tasked who
in turn is a newly employed staff and is presently at the last quarter of his
training period. I spent a great deal of the rest of my internship with him, and I
was to write a report on my weekly activities and submit to my supervisor at the
end of every week.
CHAPTER 3
14
3.1 INTRODUCTION TO STEEL PRODUCTION
Steel Production
Molten pig iron is poured into a basic oxygen furnace (BOF) for conversion to
steel. Steel is a form of iron produced from iron ore, coke, and limestone in a
blast furnace. Excess carbon and other impurities are removed to make strong
steel.
15
3.1.1 PIG-IRON PRODUCTION
Blast Furnace
In order to turn crude iron ore into usable pig iron, its impurities must be
removed. A blast furnace accomplishes this by forcing extremely hot air
through a mixture of ore, coke, and limestone, called the charge. Carts called
skips dump the charge into the top of the furnace, where it filters down through
bell-shaped containers called hoppers. Once in the furnace, the charge is
subjected to air blasts that may be as hot as 870° C (1600° F). (The furnace
must be lined with a layer of firebrick, called the refractory, in order to sustain
these temperatures.) Melted metal collects in the bottom of the furnace. The
waste metal, called slag, floats on top of the molten pig iron. Both of these
substances are drained, or tapped, periodically for further processing.
The basic materials used for the manufacture of pig iron are iron ore, coke, and
limestone. The coke is burned as a fuel to heat the furnace; as it burns, the coke
gives off carbon monoxide, which combines with the iron oxides in the ore,
reducing them to metallic iron. This is the basic chemical reaction in the blast
furnace; it has the equation: Fe2O3 + 3CO = 3CO2 + 2Fe. The limestone in the
furnace charge is used as an additional source of carbon monoxide and as a
“flux” to combine with the infusible silica present in the ore to form fusible
16
calcium silicate. Without the limestone, iron silicate would be formed, with a
resulting loss of metallic iron. Calcium silicate plus other impurities form a slag
that floats on top of the molten metal at the bottom of the furnace. Ordinary pig
iron as produced by blast furnaces contains iron, about 92 %; carbon, 3 or 4 %;
silicon, 0.5 - 3 %; manganese, 0.25 - 2.5%; phosphorus, 0.04 - 2 %; and a trace
of sulphur.
17
increased 25 %by pressurizing. Experimental installations have also shown that
the output of blast furnaces can be increased by enriching the air blast with
oxygen.
The process of tapping consists of knocking out a clay plug from the iron hole
near the bottom of the bosh and allowing the molten metal to flow into a clay-
lined runner and then into a large, brick-lined metal container, which may be
either a ladle or a rail car capable of holding as much as 100 tons of metal. Any
slag that may flow from the furnace with the metal is skimmed off before it
reaches the container. The container of molten pig iron is then transported to the
steelmaking shop.
18
Steel Production at a Krupp Plant
19
(about 8 ft.). In front of the hearth a series of doors opens out onto a working
floor in front of the hearth. The entire hearth and working floor are one story
above ground level, and the space under the hearth is taken up by the heat-
regenerating chambers of the furnace. A furnace of this size produces about 100
metric tons of steel every 11 hr.
20
The oldest process for making steel in large quantities, the Bessemer process,
made use of a tall, pear-shaped furnace, called a Bessemer converter that could
be tilted sideways for charging and pouring. Great quantities of air were blown
through the molten metal; its oxygen united chemically with the impurities and
carried them off.
21
and other impurities that are present. The additional alloying element goes
either into the charge or, later, into the refined steel as it is poured into the ladle.
Continuous casting (right, red arrows) is a method of working steel that conveys
steel from its molten state to blooms, ingots, or slabs. The white-hot metal is
poured into open-ended moulds and continues on through rollers cooled by
water. A series of guide rollers further shapes the steel into the desired form.
However, hot rolling (left, blue arrows) is still the primary means of milling
steel. This process begins with pre-shaped steel slabs, which are reheated in a
soaking pit. The steel passes through a series of mills: the blooming mill, the
roughing mill, and the finishing mill, which make it progressively thinner.
Finally, the steel is wound into coils and transported elsewhere for further
processing.
22
Steel is marketed in a wide variety of sizes and shapes, such as rods, pipes,
railroad rails, tees, channels, and I-beams. These shapes are produced at steel
mills by rolling and otherwise forming heated ingots to the required shape. The
working of steel also improves the quality of the steel by refining its crystalline
structure and making the metal tougher.
A Hot Ingot
3.4.1 A RED-INGOT
An ingot, red-hot and malleable from the high temperature of the soaking pit, is
lifted out of the furnace for further processing. As the steel is worked and
reheated, it becomes stronger.
23
length from 4 m (13 ft.) to 370 m (1,210 ft.). Continuous mills are equipped
with a number of accessory devices including edging rollers, descaling devices,
and devices for coiling the sheet automatically when it reaches the end of the
mill. The edging rollers are sets of vertical rolls set opposite each other at either
side of the sheet to ensure that the width of the sheet is maintained. Descaling
apparatus removes the scale that forms on the surface of the sheet by knocking
it off mechanically, loosening it by means of an air blast, or bending the sheet
sharply at some point in its travel. The completed coils of sheet are dropped on
a conveyor and carried away to be annealed and cut into individual sheets. A
more efficient way to produce thin sheet steel is to feed thinner slabs through
the rollers. Using conventional casting methods, ingots must still be passed
through a blooming mill in order to produce slabs thin enough to enter a
continuous mill.
By far the most important coated product of the steel mill is tin plate for the
manufacture of containers. The “tin” can is actually more than 99 % steel. In
24
some mills steel sheets that have been hot-rolled and then cold-rolled are coated
by passing them through a bath of molten tin. The most common method of
coating is by the electrolytic process. Sheet steel is slowly unrolled from its coil
and passed through a chemical solution. Meanwhile, a current of electricity is
passing through a piece of pure tin into the same solution, causing the tin to
dissolve slowly and to be deposited on the steel. In electrolytic processing, less
than half a kilogram of tin will coat more than 18.6 sq. m (more than 200 sq. ft.)
of steel. For the product known as thin tin, sheet and strip are given a second
cold rolling before being coated with tin, a treatment that makes the steel plate
extra tough as well as extra thin. Cans made of thin tin are about as strong as
ordinary tin cans, yet they contain less steel, with a resultant saving in weight
and cost. Lightweight packaging containers are also being made of tin-plated
steel foil that has been laminated to paper or cardboard.
25
more iron oxide or mill scale to the charge, working the oxide into the iron with
a bent iron bar called a raddle. The silicon and most of the manganese in the
iron are oxidized and some sulphur and phosphorus are eliminated. The
temperature of the furnace is then raised slightly, and the carbon starts to burn
out as carbon-oxide gases. As the gas is evolved the slag puffs up and the level
of the charge rises. As the carbon is burned away the melting temperature of the
alloy increases and the charge becomes more and more pasty, and finally the
bath drops to its former level. As the iron increases in purity, the puddler stirs
the charge with the raddle to ensure uniform composition and proper cohesion
of the particles. The resulting pasty, sponge like mass is separated into lumps,
called balls, of about 80 to 90 kg (about 180 to 200 lb.) each. The balls are
withdrawn from the furnace with tongs and are placed directly in a squeezer, a
machine in which the greater part of the intermingled siliceous slag is expelled
from the ball and the grains of pure iron are thoroughly welded together. The
iron is then cut into flat pieces that are piled on one another, heated to welding
temperature, and then rolled into a single piece. This rolling process is
sometimes repeated to improve the quality of the product.
26
3.5.1 Carbon Steels
More than 90 % of all steels are carbon steels. They contain varying amounts of
carbon and not more than 1.65 % manganese, 0.60 % silicon, and 0.60 %
copper. Machines, automobile bodies, most structural steel for buildings, ship
hulls, bedsprings, and bobby pins are among the products made of carbon steels.
27
action of body fluids. In kitchens and in plants where food is prepared, handling
equipment is often made of stainless steel because it does not taint the food and
can be easily cleaned.
28
strains in the metal, and these are relieved by tempering, or annealing, which
consists of reheating the steel to a lower temperature. Tempering results in a
decrease in hardness and strength and an increase in ductility and toughness.
CHAPTER 4
29
STEEL MILL SAFETY REGULATIONS.
For construction crews working in steel plants, there are many hazards. The
following points summarize the main hazard areas.
1) Pinch points and moving equipment.
o Transportation equipment
Bulk material handling and transport is a major activity for a steel mill. There
are railroad systems with tracks all over the plant, hot metal cars, transfer cars,
buggies, charging cars, hopper cars, scrapers, coil carriers, slab carriers, and
many others.
o Overhead cranes
Overhead cranes form an integral part of operating and maintenance practice
throughout a steel mill. Many hazards are associated with their use, including
overhead loads, hot metal splash, equipment failure, communication
breakdown, and the fact that crane operators may not be aware of construction
workers in unexpected locations.
o Operating equipment
Production equipment may operate on a timed basis, it may be remote-
controlled, or operators may not expect non-operating personnel on site.
Construction personnel must learn plant safety practices, alarms, access
requirements and limitations, and emergency procedures for whichever section
of the mill they must enter. They must follow these procedures.
30
o Chemical Hazards
The following is a list of the major chemical hazards present in steel mills
identified in the table and their effects. It is not intended to be comprehensive.
Chemicals and chemical processes may vary from plant to plant.
Acids
• pickling and tinning lines and acid regeneration plants (hydrochloric)
• Hydrochloric acid or sulphuric acid
• Highly corrosive, can be dangerously reactive in high concentrations
Ammonia
• Very irritating to the eyes, nose and throat
• High exposure can cause choking and breathing difficulties
• Coke oven by-products plant.
Asbestos
• can be present in blast furnace and stoves, by-products plant, steam,
generation (either central or waste heat boilers)
• Asbestosis, mesothelioma, lung cancer
By-product plant light oil
• containing chemicals such as benzene and naphthalene and minor amounts of
toluene and xylene
• Coke oven by-products
• Acute effects - typical solvent effects, central nervous system depression
• Chronic effects - carcinogens (cancer-causing agents); some cause liver and
kidney damage.
Carbon monoxide (CO)
• Odourless, colourless, poisonous gas
• makes up a large part of fuel gases (22-30% of blast furnace gas, 5-10% of
coke oven gas)
• Many hazardous locations, especially around blast furnaces – also coke ovens
and steelmaking
• can leak out from tops of blast furnaces, around hot stoves, pipelines; can
occur due to sudden shutdown of blowing engines, boiler rooms, ventilation
fans, and from insufficient gas removal during electrostatic precipitator
cleaning.
Coal tar pitch volatiles
• Coke oven by-products plant
• Skin irritant, cancer of the lung, skin, and scrotum
• Photosensitive dermatitis.
Coke oven emissions
• In the vicinity of the coke oven batteries
• A “designated substance” in Ontario, carcinogenic
• There must be a control/monitoring program.
Coke oven gas
• High in carbon monoxide and may contain trace amounts of carcinogens
31
• Contents can include benzene (0.4%), H2S, and hydrogen cyanide.
Dusts
• Iron oxide: (found in sinter plant, before blast furnace, and around
steelmaking) in addition to being irritating to eyes, this causes ciderosis, which
is a specifically named type of pneumoconiosis or obstructive lung disease; i.e.,
dust build-up, not fibrosis
• Coal:
- Irritant to the eyes, etc.
- Pulmonary fibrosis, pneumoconiosis
• Coke:
- There is some suspicion that coke is a carcinogen
• Silica:
- Silicosis
- Refractory brick lined furnaces and ladles
- may occur as dust at sinter plant,
Primarily during furnace repair
• iron chloride- around hydrochloric acid regeneration
•dust: plant
- Respiratory tract irritant to some people.
Hydrogen Sulphide (H2S)
• Around coke oven batteries
• Toxic gas (500-700 ppm can be instantly fatal)
• Rotten egg smell at very low concentrations - below 100 ppm
• Explosive at high concentrations.
Sodium hydroxide (NaOH)
- cleaning lines (tinning)
- Corrosive.
Sulphur dioxide (SO2)
• Blast furnace slag pits
• gas irritating to eyes, nose, and throat
• Overexposure can cause choking and breathing difficulties
• Delayed reaction to overexposure can be fluid build-up in the lungs.
32
be done in hot locations. Heat stroke can be a constant risk, especially during
warm weather. See the chapter on Heat Stress in this manual.
o Noise
Noise is a hazard at many locations in a steel mill. Hearing protection is often
required and warning signs are posted. High noise levels exist, for example,
around the tuyeres in the blast furnaces or any rolling mills. For guidelines on
noise exposure and hearing protection, refer to the chapter on Personal
Protective Equipment in this manual.
o General
Before work begins, crews should receive training in the hazards existing in the
work area and obtain and review the material safety data sheets for any
hazardous materials to which they may be exposed. These should be readily
available from the client or owner and, in fact, should be obtained at the time of
bidding to facilitate job planning. Any protective equipment used should at least
equal that worn by the client's workers in the area.
o Piping systems
The contents of piping systems, storage bins, and tanks should be known and
identified. Know the system of identification and warning used by the owner.
These may vary from one plant to another.
o Confined spaces
Special attention must always be paid to confined space entry. Always comply
with the Construction Regulation (Ontario Regulation 213/91) as a minimum.
The steel mill will usually have an entry permit system and requirements for
entry and work in confined spaces. Welding in any confined space must be done
with precautions. Pay special attention in cases where welding is being done on
stainless steel, since the chromium released is a possible cause of lung cancer.
The steel mill has an emergency procedure in place. All workers are expected to
know the warning alarm signals and follow the procedures.
33
REFERENCE
34